0
IN THE KARNATAKA REAL ESTATE APPELLATE TRIBUNAL,
BENGALURU
DATED THIS THE 30TH DAY OF JUNE, 2025
PRESENT
HON’BLE SRI SANTHOSH KUMAR SHETTY N.
JUDICIAL MEMBER
AND
HON’BLE SRI MAHENDRA JAIN,
ADMINISTRATIVE MEMBER
APPEAL NO. (K-REAT) 61/2023
BETWEEN:
M/S. Sobha Limited,
A Company incorporated
under the provisions of
the Companies Act, 1956,
Having it s Registered Office
at: “Sobha” Devarabisanahlli,
Sarjapur-Marathalli Outer Ring Road,
Bellandur Post, Bengaluru-560 103.
Karnataka State, India.
Represented by its Authorized Signatory
Sri Prasad M.S, …APPELLANT
(By Sri. Vinayaka S Pandit, Advocate)
AND
1. Karnataka Real Estate
Regulatory Authority,
No.1/14, 2nd Floor, Silver Jubilee Block,
Unity Building Backside, CSI Compound,
3rd Cross, Mission Road,
Bengaluru-560 027.
Represented by its Secretary.
1
2. Mr. Sudhir Pillai,
3. Mrs. Rama Pillai,
Both are
Residing at 3037,
Casa Paradiso, Block-3, Sobha City,
Bengaluru-560 064. : RESPONDENTS
(By Sri. I.S Devaiah, Advocate for 1st Respondent-RERA
By Smt Niharika Mallan, Advocate for R2 & R3)
This Appeal is filed under Section 44 of the Real Estate
(Regulation and Development) Act, 2016, praying to set aside the
impugned order dated 24.03.2023, passed by the 1st Respondent-
RERA in Complaint No.CMP/190112/0001852.
This appeal having been heard and reserved for Judgment,
coming up for pronouncement of Judgment, this day, the Hon'ble
Administrative Member delivered the following:
JUDGMENT
As averred in the Memorandum of Appeal, the 2nd & 3rd
Respondents-Allottees (hereinafter referred to as 'the Allottees' for
short) had entered into an Agreement of Sale/Construction
Agreement dated 21.07.2015 with the Appellant-Promoter
(hereinafter referred to as 'the Promoter' for short) to purchase a
residential apartment bearing No.A-2-4071, Block-4 (Block-16), in
a real estate project known as ‘Sobha City-Casa Paradiso Block 4’,
developed by the Promoter for total Sale Consideration of
Rs.1,40,60,180/-, and paid an amount of Rs.1,57,43,001/-. As per
the terms contained in Clause-5 of the Construction Agreement,
the Promoter agreed to complete the project and handover
possession of the Apartment by the end of 31.05.2018. Since, the
promoter has failed to complete the project and handover
2
possession of the flat within the stipulated time, the Allottees filed
a complaint under Section-31 of the Real Estate (Regulation and
Development) Act, 2016 (hereinafter referred to as 'the Act' for
short) before the Karnataka Real Estate Regulatory Authority ('the
Authority' for short), seeking compensation by way of interest for
every month delay. By the impugned order, the Authority allowed
the complaint filed by the Allottees and directed the Promoter to
pay a sum of Rs.23,28,599/- towards delay period interest,
calculated at the rate of SBI MCLR + 2% for the period from
01.12.2018 till 23.06.2020. Being aggrieved by the same, the
Promoter has preferred this appeal.
2. We have heard Sri. Vinayak S Pandit, learned counsel for the
Promoter, Sri. I.S Devaiah, Advocate for 1st Respondent-RERA and
Smt Niharika Mallan, Advocate for Respondents No. 2 & 3, and
perused the materials on record.
3. It is relevant to note that, the Authority on an earlier
occasion, by its order dated 16.03.2020 allowed the complaint filed
by the allottee and the operative portion of the earlier order is
extracted hereunder:-
“The complaint bearing No.CMP/190112/0001852 is
hereby allowed under Sec.31 of the Real Estate
(Regulation and Development) Act, 2016.
1. Registration of Sale Agreement: The promoter is
directed to register the sale agreement forthwith at the
cost of the promoter and no recovery shall be made from
3
the allottee since the delay in registration of the sale
agreement is entirely attributable to the promoter. Since
this relief was sought in the initial stage of the hearing of
the complaint, the same is allowed to recognize the right
of an allottee to get the sale agreement registered even at
a later date.
2. Handing over Possession: Promoter is hereby
directed to handover possession of the apartment to the
allottee within two weeks from the date of this order, since
the Occupancy Certificate is obtained.
3. Registration of the Apartment: Promoter is hereby
directed to register the apartment in favour of the allottees
within four weeks from the date of this order.
4. Compensation: i) The allottee/s has furnished a
statement of computation of compensation on the basis of
which it is evident that the allottee/s are entitled for
compensation on the payments made by them, on account
of the fact that the apartment was not delivered for
possession for occupation as per the date committed by
the promoter in the sale agreement which is 31st May
2018.
ii) The interest payable by promoter to the
allottee/s is regulated in accordance with the Rule 16 of
the Karnataka Real Estate (Regulation and Development)
Rules, 2017. The submission of the allottee/s that the
respondent promoter has charged 11% interest on the
final payment due from the allottee is found to be
arbitrary. The allottee is liable to make the final payment
only at the time of the delivery of possession for
occupation and therefore any levy of interest and any
deduction/recovery of any such amount from the
compensation payable to the complainant allottee is not
permissible. It is evident from the Memo submitted by the
complainant allottee that the final payment of
st
Rs.10,07,076/- has also been made by 1 February, 2020
itself without waiting for handing over possession of the
apartment. Having regard to the facts and circumstances
of the case, the promoter of the project is hereby ordered
to pay compensation in accordance with Rule 16 of the
Karnataka Real Estate (Regulation and Development)
Rules, 2017. Accordingly, the respondent is directed to
pay interest to the complainant-allottees @ State Bank of
India highest marginal cost of lending rate plus two per
cent computed from 01.06.2018 till the date of handing
over possession of the apartment. For the purpose of
4
calculating the interest payable, the aggregate amount
paid by the allottee upto 31.05.2018 shall be considered as
the principal amount and the final payment of
Rs.10,07,074/- paid on 1st February, 2020 shall be added
to the principal amount, so as to consider the said amount
also eligible for interest w.e.f. 2nd February, 2020.
5. Completion of all Development works and
Amenities: The Respondent-Promoter is further directed to
ensure that all the pending development works are
completed as per the specifications and representations
made in the sale agreement; all the internal and external
developmental works are completed in accordance with the
approved plan of the project and all the requisite amenities
are provided and are functioning satisfactorily.”
4. Challenging the said order, on earlier occasion, the promoter
has preferred an appeal No. 259/2020 before this Tribunal and by
the judgment dated 06.12.2022, this Tribunal allowed the appeal,
set-aside the earlier order dated 16.03.2020, and remanded the
matter to the Authority for fresh consideration. The operative
portion of the earlier judgment dated 06.12.2022 reads as under:
(i) The reliefs granted at paragraphs 1, 2, 3 and 5 of the
operative portion of the impugned order have become
infructuous and they do not arise survive for
consideration;
(ii) The appeal is allowed and the impugned order dated
16.03.2020 passed by the Karnataka Real Estate
Regulatory Authority, Bengaluru in complaint
No.CMP/190112/0001852, insofar as to paragraph-4(i)
and (ii) of the operative portion of the impugned order is
hereby set aside and the matter is remitted to the
Authority only to the said extent, for fresh consideration,
in accordance with law and in the light of the
observations made herein above, after affording
opportunity to both the parties;
(iii) All the contentions of the parties are kept open to be
urged before the Regulatory Authority;
5
(iv) As the matter pertains to the year 2015, the
Authority shall make an endeavor to dispose of the
complaint as expeditiously as possible and at any rate
within the outer limit of 45 days from the date of parties
entering appearance;
(v) Since the appellant-promoter and allottees-
respondents have appeared before this Tribunal through
their counsel, they are directed to appear before the
RERA on 19.12.2022 without expecting further notice
from RERA;
(vi) In the event if there is no sitting of the authority on
the said date, the matter may be taken up immediately
on the next date of sitting;
(vii) The Registry is hereby directed to release the
amount deposited by the appellant with this Tribunal
while preferring the Appeal in compliance of proviso to
Section 43(5) of the Act, along with interest, if any,
accrued thereon, by issuing either a cheque or DD in the
name of the appellant-company and shall hand over the
cheque or DD to the Authorized signatory of the
appellant-company who has signed the vakalath and
appeal memo, on furnishing necessary documents and by
following due procedure;
(viii) In view of disposal of the Appeal, all pending I.As. if
any, stand rejected, as they do not survive for
consideration;
(ix) The Registry shall comply with the provisions of
Section 44 (4) of the Act and return the records to RERA,
if any.
There is no order as to costs.”
After remand, the Authority passed the impugned order dated
24.03.2023, against which, the Promoter is before this Tribunal in
the present appeal in the second round of litigation.
6
5. As urged in the Memorandum of Appeal, the learned counsel
for the Promoter contended that the Authority has failed to
consider the directions issued by this Tribunal in the earlier
Judgment passed in Appeal No.259/2020. Although there was no
fault on the part of the Promoter, the Authority awarded delay
compensation in favour of the Allottees without assigning proper
reasons. The Promoter received Occupancy Certificate on
24.01.2020 and sent offer of possession letter on 28.01.2020 and
hence, the Authority was not justified in awarding compensation
till 23.06.2020; As per Section-19(10) of the Act, the Allottees are
bound to take possession within two months from the date of
issuance of Occupancy Certificate and in fact, the Promoter had
offered possession through E-mail dated 28.01.2020. While
awarding compensation, the Authority failed to take note of
outbreak of COVID-19 which is a force majeure. The copy of the
Memo of Calculation filed by the Allottees has not been furnished
to the Promoter to refute the calculation made by the Allottees and
thereby the allottees have violated the principles of natural justice.
Further, as per terms contained in Clause-5.4 of the Construction
agreement, the time consumed by the statutory authorities for
issuance of clearances is required to be excluded. Though an
application for Occupancy Certificate was made to the BBMP on
23.10.2018 (02.11.2019 as noted in Occupancy Certificate issued
by BBMP), and the BBMP was required to consider or reject the
7
application within 30 days, but the BBMP kept quiet for a period of
one year and hence, the delay in obtaining Occupancy Certificate
comes within Clause-5.4(c) of the Construction Agreement and
such delay was beyond the control of the Promoter and, therefore,
the Allottees are not entitled for compensation for the delay
caused by the BBMP. In spite of receipt of offer of possession letter
through e-mail on 28.11.2018, the allottees sent email dated
04.12.2018 stating that they do not intend to take possession prior
to issuance of Occupancy Certificate by Competent Authority. The
Allottees were also in default in payment of Sale Consideration as
per the Schedule of payments in the construction agreement and
the allottees were yet to pay a sum of Rs.1,06,037/-. The
Promoter, in fact gave discount of Rs.127 per sq.ft to the Allottees
and the Authority has failed to take note of these factors while
passing the impugned order. The Authority has failed to take note
of the provisions of Section-72 of the Act which spells out the
factors to be taken into account while adjudging the quantum of
compensation or interest under Section-71. On these grounds, the
Promoter prays for dismissal of the Appeal.
6. Per contra, learned counsel for the Allottees, filed their
Statement of Objections on 09.01.2025 and contended that the
Promoter has not approached this Tribunal with clean hands and
made false, misleading and vexatious averments in the Appeal by
suppressing various material facts and selectively placed a few
8
documents which is nothing but abusing the process of law.
Indisputably, there was a delay in completing the project and
handing over possession as per the time stipulated in the
agreement. In response to the email dated 28.11.2018 of the
Promoter, the allottees responded to the same by email dated
04.12.2018 stating that without Occupancy Certificate they are
reluctant to take possession of the apartment. There was no
restriction on account of pandemic COVID-19 for the period from
28.01.2020 to 22.03.2020. Vide email dated 05.02.2020, the
Promoter put an undue pressure on the allottees, directing them to
withdraw the complaint No.1852 filed before the Authority that too
after receipt of entire payment. The request made by the Allottees
through email dated 05.02.2020 and 10.02.2020 for handing over
apartment went in vain, hence, the contention of the Promoter
that delay in handing over possession was on account of force
majeure cannot be accepted. The complaint filed by the allottees
was decided by the Authority on merits strictly with reference to
terms of direction issued by this Tribunal in Appeal No.259/2020
and there is no miscarriage of justice as alleged by the Promoter in
Paragraph-18 of the Appeal Memo. The Occupancy Certificate by
the Competent Authority was received only on 24.01.2020, the
Promoter sent an offer letter on 28.01.2020 for which, the
allottees replied through their mails dated 04.2.2020, 05.02.2020
and 10.02.2020 and hence, the Authority, considering the delay on
9
the part of the Promoter to handover possession of the apartment,
rightly awarded compensation and no fault can be found with the
said order. Immediately after receipt of offer letter on 28.01.2020,
the allottees have paid the final payments within two days i.e., on
30.01.2020 and 01.02.2020 but it was the Promoter who
intentionally pressurised the allottees to withdraw the complaint
No.1852 and delayed handing over possession of the apartment
from 01.02.2020, the date on which the final payment was made
till 23.03.2020. The grounds urged by the Promoter at paragraphs-
23 to 48 are only based on assumption and does not stand legal
scrutiny. The allottees have invested their life time savings to
peacefully enjoy their retirement life in their permanent home and
the promoter, knowing the fragility of the health of the retired
persons and their financial capacity to withstand to long litigation,
is exercising a mind game and psychological stress on them only
with a view to indefinitely harass the allottees with an ulterior
motive. The Authority, after evaluating the materials on record and
after following due process of law, passed the impugned order
which does not call for interference from this Hon’ble Tribunal. The
allottees filed a memo dated 09.01.2025, 12.03.2025 along with
several documents, including the Statement of Accounts, to
substantiate the total amount paid by them and order dated
21.01.2023 passed by the BBMP, by which the Occupancy
Certificate issued in respect of the project has been cancelled by
10
the BBMP on the ground that the Occupancy Certificate has been
obtained by furnishing false documents. Apart from this, the
Allottees filed written synopsis/arguments on 25.04.2025, inter
alia urging the same grounds as urged in the statement of
objections. On these grounds, the allottees pray for dismissal of
the appeal.
Oral arguments made by the Appellant/Promoter
7. In the oral arguments made by the counsel for the
Appellant/Promoter on 12.03.2025, they argued that the Sale
Agreement was signed on 21.07.2015 and the due date for
possession was 31.05.2018, with a rider in Clause-5.4 of the
Construction Agreement, the due date for delivery of the
apartment will be further subject to variation on account of various
factors narrated in Clause-(a) to (h) of Clause-5.4 of the
Construction Agreement, important one being delay in issue of
NOC/permission, Occupancy Certificate, sanction by the
Government and Statutory Authorities and also delay in providing
utility connections by various Authorities. The Completion
Certificate by the registered Architect was issued on 16.10.2018
and the Promoter submitted an application on 23.10.2018 for
issuance of Occupancy Certificate. An offer letter was sent by the
Promoter to the allottee on 28.11.2018 to which the Allottees
replied, that they do not wish to takeover possession prior to
issuance of Occupancy Certificate.
11
8. The counsel for Promoter argued that, the Promoter wrote a
letter to BBMP on 25.10.2019 reminding about the issuance of
Occupancy Certificate and the Occupancy Certificate was
eventually issued on 24.01.2020. After the issuance of Occupancy
Certificate, the Promoter wrote a letter to the Allottees, along with
enclosing a copy of the Occupancy Certificate on 28.01.2020
asking for balance payment and to take over possession.
9. The Allottees still went ahead and filed complaint before the
Authority, which was allowed by the Authority on 16.03.2020,
against which the Promoter preferred an appeal in Appeal
No.259/2020 as per which the matter was remitted to the
Authority, insofar as, it relates to para-4(i) and (ii) of the operative
portion of the impugned order dated 16.03.2020 for fresh
consideration in accordance with law.
10. The Occupancy Certificate issued by the BBMP was cancelled
on 21.01.2023 on the grounds of false information,
misrepresentation of facts etc against which the Promoter
preferred an Appeal before the Karnataka Administrative Tribunal,
which is still pending for final adjudication.
11. The Authority passed the impugned order on 24.03.2023 in
which, rather than adjudicating upon the issues returned by the
Tribunal, they directed the Promoter to pay a sum of
Rs.23,28,599/- towards delay period interest. The interest
12
calculation in the impugned order is incorrect, since from
28.01.2020, being the date on which Promoter sent offer letter for
taking over possession, the Promoter is not liable to pay any
interest, even if it is decided by Tribunal to pay for delay, if any.
12. The counsel further argued that the fact of COVID-19
pandemic will apply to the Promoter from March, 2020 onwards as
per Clause-5.4 of the Sale Agreement, since, these were factors
beyond the control of the Promoter.
13. Since, the Promoter had applied for the Occupancy
Certificate before the due date, under Section-310 of Municipal
Co-operation Act, he is entitled for the date of application being
considered as deemed Occupancy Certificate from one month after
the date of application of Occupancy Certificate being on
15.10.2018. The Authority has erred in awarding delay
compensation even after the Occupancy Certificate was issued on
the basis of Memo of Calculation given by the Allottees, without
considering the objections made by the Promoter. The Promoter
has been penalized for no fault of his and therefore, the impugned
order deserves to be set aside.
Oral arguments made by the Respondents/Allottees
14. The counsel for the Allottees argued that the Promoter has
only mentioned the dates which are convenient to suit his case and
13
to give an example, he said that in the Occupancy Certificate
granted on 24.01.2020, the application for issuance of Occupancy
Certificate in the “Reference” part of the documents is shown as
02.11.2019, and there is no reference to the date of 23.10.2018
on which the Promoter has claimed to have even made an
application for issue of Occupancy Certificate. Further, the
Occupancy Certificate was cancelled by the Competent Authority
on 21.01.2023 on account of the documents submitted along with
the application for Occupancy Certificate containing false
information, misrepresentation of facts etc.
15. Counsel for the Allottees further argued that it was patently
illegal on the part of the Promoter to being everything under
Clause-5.4 of Construction Agreement for delay in completion of
the project, including things such as approvals and sanctions by
the Government and Statutory Authorities, non-availability of
construction material, labour etc., short supply of material, rain fall
above 25 mm, any other reasons beyond the control of the
Promoter, under the pretext of which the Promoter is claiming to
seek shelter for any amount of delay due to these factors which
are primarily the responsibility of the Promoter. Only the delay on
account of force majeure as defined in the Explanation Section-6
of the Act, for factors such as war, flood, drought, fire, cyclone,
earthquake or any other calamity caused by nature can be the
permissible grounds for delay in completion of the project.
14
16. Insofar as, the Promoter’s claim the deemed Occupancy
Certificate is concerned, the Promoter, in his email dated
13.03.2019 to the Allottees, has himself stated that Occupancy
Certificate by BBMP for block-16 & 17 was pending due to new
guideline given by NGT and that the Supreme Court has passed an
order on 05.03.2019 for setting aside a portion of the condition
prescribed by NGT and therefore, they will follow up with the BBMP
for receiving the Occupancy Certificate. It clearly confirms that as
on March, 2019 there was no Occupancy Certificate in place. The
application for Occupancy Certificate was initiated by the Promoter
only after obtaining the consent order from KSPCB on 21.09.2019
which is much after the due date for giving possession.
17. The Promoter had also written a letter to Joint Director of
Town Planning of BBMP for issuance of Occupancy Certificate in
which they referred to the final Fire clearance certificate dated
01.10.2018, and the Consent for Operation dated 21.09.2019
requesting for issuance of Occupancy Certificate on the basis of
these documents. While the Promoter had applied for Occupancy
Certificate on 18.04.2017 for Partial Occupancy Certificate, it was
for Block-9, 10 & 12 and another application for Partial Occupancy
Certificate was submitted by the Promoter on 16.05.2016, but this
was for Block-2 to 6, 8 & 13. The application for Occupancy
Certificate for Block-16, in which the Allottees had purchased the
apartment, was filed only on 02.11.2019. This shows that the
15
Promoter was actually not completed on the day submitted first
application for issuance of Occupancy Certificate on 23.10.2018
and the Occupancy Certificate issued by the Competent Authority
was not available with Promoter.
18. The allottees also submitted a memo on 09.01.2025 in which
they have submitted a copy of letter addressed to the Promoter
requesting to honour the provisions of Section-18 of the Act for
having failed to handover possession in terms of the Sale
Agreement. They have also submitted a copy of an email sent by
the Promoter to the Allottees on 05.02.2020 advising the Allottees
to take possession and get the Sale Deed registered subject to
withdrawal of the Complaint in 1852 filed by the allottees before
the Authority. This email was an attempt to exert pressure tactics
upon allottees that unless they withdrew the complaint, the Sale
Deed will not be registered. The Allottees stated that since their
request for possession was still pending, they did not withdraw
their complaint before the Authority and therefore, such
communication by the Promoter amounts to an unfair trade
practice on their part. The Allottees replied on the same date on
05.02.2020 to the Promoter saying that the Promoter had agreed
to process the handover of the apartment after the allottees makes
full payment and that in spite of this the allottees having made the
full payment, the Promoter has changed the stand and imposed
the condition of withdrawing the complaint before the RERA, as a
16
condition precedent before handing over the possession, which is
blatantly illegal.
19. The Allottees stated that they are willing to accept interest
till 28.01.2020 being the date of offer letter sent from the
Promoter after issuance of Occupancy Certificate, in the interest of
amicable resolution of the dispute.
20. The Authority has rightly taken the relevant factors into
account while adjudging the quantum of compensation or interest
for the amount of loss caused as a result of the default by the
Promoter since, the allottees had to pay interest on the home loan
taken and also had to incur expenses for rent from 01.06.2018 till
the date of Sale Deed which was on 30.06.2021. The allottees
rented an apartment for Rs.35,000/- per month in the same block
for this period for which he had to shell out for Rs.22.23 lakhs
approximately.
21. He also argued that the photographs that he has produced in
his memo dated 12.03.2025 shows that the project was not
completed as on 07.11.2018.
22. He further stated that the Occupancy Certificate and all other
approvals were cancelled by the Authority in January, 2023 and all
the matter is still pending before the KAT, but the fact that the
Occupancy Certificate was cancelled by BBMP is undisputable.
17
23. The allottees completed their arguments stating that the
appeal filed by the Promoter may be dismissed and the impugned
order may be confirmed in light of all these facts.
24. In view of the submissions made by the respective parties, the
points that would arise for our consideration are:
(i) Whether the Authority was justified in passing the
impugned order?
ii) What order?
25. We answer the above point No.(i) partly in the affirmative
for the following:
REASONS
26. To appreciate the nuances of the issues of this matter, it
would be relevant to recapitulate important facts of the case, and
grounds urged by the respective parties leading to the present
appeal. It is the case of the allottees that, they have entered into
Agreement for Sale/Construction Agreement dated 21.07.2015
with the Appellant-Promoter to purchase a residential apartment
bearing No.A-2-4071, Block-4 (Block-16), in a real estate project
known as ‘Sobha City-Casa Paradiso’, developed by the Promoter
for total Sale Consideration of Rs.1,40,60,180/-, and paid an
amount of Rs.1,57,43,001/- and the final installment of
Rs.10,07,074/- has been paid on 31.1.2020 and 03.02.2020
respectively. As per the terms contained in Clause-5 of the
18
Construction Agreement, the Promoter agreed to complete the
project and handover possession of the Apartment by the end of
31.05.2018. The Promoter, without furnishing copy of the
Occupancy Certificate issued by the Competent Authority, sent
email to the Allottees to pay the balance amount through email
dated 28.11.2018 to which the allottees replied on 04.12.2018
stating that they are not ready to takeover possession of the
apartment without Occupancy Certificate and thereafter filed
complaint against the Promoter seeking delay period interest.
27. After receipt of Occupancy Certificate by the Competent
Authority on 24.01.2020, the Promoter again offered to hand over
possession to the Allottees subject to withdrawal of the complaint
filed by the Allottees, before registration of the Sale Deed. The said
complaint came to be allowed on 16.03.2020, granting delay
compensation at the rate of MRCR of SBI+2% for the period from
01.06.2018 till the date of handing over of possession.
(underlined for emphasis)
28. The Promoter, challenged the said order and filed Appeal No.
259/2020 before this Tribunal and by the Judgment dated
06.12.2022, the matter was remanded back to the Authority for
fresh consideration. After remand, the Authority, by order dated
24.03.2023, allowed the complaint and directed the Promoter to
19
pay compensation of Rs.23,28,599/- towards delay period interest
from 01.12.2018 till 23.06.2020.
29. On the contrary, it is the case of the Promoter that the
project in question was completed on 01.10.2018 and after
securing Completion Certificate from the Architect on 16.10.2018,
they made an application for issuance of Occupancy Certificate
with the BBMP on 23.10.2018 which is required to be either
considered or refused by the BBMP within 30 days from the date of
application. Since, the BBMP has not considered the same, it
should be presumed that there was a deemed Occupancy
Certificate as per Section-310 of KMC Act.
30. Thereafter, based on the deemed Occupancy Certificate, the
Promoter sent communication to the Allottees on 28.11.2018
requesting them to take possession of the apartment. But the
Allottees failed to take possession and filed complaint before the
Authority. Since, the Promoter issued letter of offer on 28.11.2018,
they are not required to pay delay compensation to the Allottees.
However, after issuance of Occupancy Certificate on 24.01.2020,
the Sale Deed was executed in favour of the Allottees on
23.06.2020 and possession of the Apartment was handed over.
The Promoter contended that the Authority has failed to consider
the observations made by this Tribunal in the earlier Judgment
dated 06.12.2022, while passing the impugned order.
20
31. The Allottees filed a complaint seeking compensation by way
of interest for every month delay, since the Promoter failed to
complete the project and hand over possession within the
stipulated period. By the impugned order, the Authority allowed
the complaint filed by the Allottees and directed the Promoter to
pay a sum of Rs.23,28,599/- towards delay period interest,
calculated at the rate of SBI MCLR + 2% for the period from
01.12.2018 till 23.06.2020. Being aggrieved by the same, the
Promoter has preferred this appeal.
32. It would be appropriate for this Tribunal to look into the
main grounds urged by the counsel for the Promoter against the
impugned order. The Promoter has argued mainly along the
following grounds:-
33. Firstly, he contended that the Promoter obtained Completion
Certificate from the registered Architect on 16.10.2018 and applied
for issuance of Occupancy Certificate which was received by the
Authorities on 23.10.2018, but the Authorities issued the
certificate only on 24.01.2020 and hence, it should be presumed
that there was a deemed Occupancy Certificate from the date of
application for issuance of Occupancy Certificate, as contemplated
under Section-310 of the KMC Act.
21
34. Secondly, he contended that the delay in handing over
possession is on account of force majeure factors, as noted in (a)
to (h) of Clause-5.4 of the Construction Agreement and hence, the
Promoter is not liable to pay compensation by way of interest for
every month delay to the Allottees.
35. Thirdly, he contended that since the grace period of six
month is added, the Promoter is required to pay interest with
effect from 01.12.2018 and not from 01.06.2018, as contended by
the Allottees. Now, we proceed to determine the main issue
involved in the appeal,
36. Point No.(i):- Before adverting to the main points for
consideration formulated by us, it would be appropriate for us to
consider the three primary grounds urged by the learned counsel
for the Promoter. Insofar as, the first ground urged by the
Promoter, regarding “Deemed Occupancy Certificate” in the
case on hand, it is evident that as far as
“Sobha City Casa Paradiso-2” is concerned, the Promoter claims
that the Completion Certificate was issued by the Engineer/
Architect on 16.10.2018 and the first application for issuance of
Occupancy Certificate has been made on 23.10.2018. According to
the Promoter, the so-called ‘Deemed Occupancy Certificate’ will
take effect after one month of making the application for
Occupancy Certificate i.e. on 02.02.2019 and whereas the final
22
Occupancy Certificate has been issued by the BBMP, the
Competent Authority as per Section-2 (zf) of the Act, on
24.01.2020. The only Occupancy Certificate pertaining to Block-16
which is available in the records was issued by the BBMP only on
24.01.2020. Apart from this, the Promoter, in his email dated
13.03.2019 to the Allottees, has himself stated as under:-
“As you are aware, BBMP were pending Occupancy
Certificate for Block-16 & 17 (Sobha City CP3 & CP4)
due to new set of guidelines defined by NGT. We are
glad to inform you that Supreme Court has passed order
(dated 5th March, 2019) by setting aside portion of
condition defined by NGT, the status quo ante is
restored as per the existing RMP 2015.
Please find enclosed the high Lights of the
Supreme Court Order in this regard. Sobha Limited will
follow up with KSPCB & BBMP for receiving the
Occupancy Certificate ASAP.”
37. The above admission of the Promoter clearly indicates that
the Occupancy Certificate by BBMP for block-16 & 17 was pending
due to new guidelines given by NGT and that the Supreme Court
has passed an order on 05.03.2019 for setting aside a portion of
the condition prescribed by NGT and therefore, they will follow up
with the BBMP for receiving the Occupancy Certificate. Added to
this, the NOC for fire clearance for Block No. 2 to 8 was given on
01.07.2020 with a caveat that for other Blocks, namely, 1, 9, 10,
11, 16 & 17, the Promoter shall apply for NOC after the installation
of necessary equipments. The NOC clearance for occupation of
Block-9, 10, 16 & 17 has been issued by the Competent Authority
23
on 15.04.2021. These factors clearly confirm that as on March,
2019 there was no fire clearance or Occupancy Certificate in place.
The application for Occupancy Certificate was initiated by the
Promoter only after obtaining the consent order from KSPCB on
21.09.2019 which is much after the due date for giving possession.
The claim that the Promoter is entitled to seek the benefit of a
deemed Occupancy Certificate on 02.02.2019 is not backed by any
substantive argument to this effect.
38. At this juncture, it would be appropriate to bring some clarity
regarding the ambiguity pertaining to the issue of Completion
Certificate vis-a-vis Occupancy Certificate, Competent Agency vis-
a-vis Competent Authority which can issue the certificates. Before
the introduction of the concept of Occupancy Certificate, the
certificate issued by the Competent Authority, which necessarily
would have to be a Government established Authority, would
permit occupation of any building as provided under local laws,
would be the Completion Certificate.
39. This is perhaps the reason as to why under Section-2(zf) of
the Act, the definition itself says that ‘Occupancy Certificate’ means
the occupancy Certificate or such other certificate by whatever
name called, issued by the Competent Authority which permits
occupation of any building etc.
24
40. In the Rule-4(1)(iv), a distinction seems to have been made
between a Competent Authority and Competent Agency. The
Completion certificate issued by the Competent Agency can be in
the form of a self certification by a registered Architect/Engineer,
but it cannot be considered as Completion Certificate as defined
under Section 2(q) of the Act, since, the Completion Certificate
which certifies that the Real Estate project has been developed
according to the sanctioned plan etc can only be issued by the
Competent Authority which as per Section-2(p) would be the
Competent Authority created or established by the Government,
which has powers to give the necessary permission for
development of such immovable property.
41. When such a Completion Certificate is issued by an Architect
or an Engineer, the Competent Agency for this purpose, it is by
way of a self certification. It has to be submitted to the
Government established Competent Authority, which has to inspect
the project and certify that indeed the project has been completed
as per the sanctioned plan and only then the certificate issued by
Competent Authority take the form of an ‘Occupancy Certificate’,
as defined in Section-2 (zf). Under Section 310 of Karnataka
Municipal Corporations Act, if a person applies for permission to
occupy the building upon completion of all works, and provides
necessary formalities for inspection of such building, and if the
Commissioner fails to intimate his refusal of the said permission
25
within 30 days, he may occupy or permit to be occupied such
building. The onus of completing all the development works, and
having submitting the application with necessary documents, rests
with the applicant.
42. At this stage, it is relevant to note that the ‘Competent
Authority’, as defined under Section 2(p) is an Authority created or
established under any law in force by the Government. For ready
reference, the above two definitions are extracted hereunder:
2(p) “competent authority” means the local authority or
any authority created or established under any law for
the time being in force by the appropriate Government
which exercises authority over land under its
jurisdiction, and has powers to give permission for
development of such immovable property;
(q) “completion certificate” means the completion
certificate, or such other certificate, by whatever name
called, issued by the competent authority certifying
that the real estate project has been developed
according to the sanctioned plan, layout plan and
specifications, as approved by the competent authority
under the local laws;
43. From the BBMP Bye-Laws also, it is evident that after
completion of the project, a Completion Certificate or such other
Certificate by whatever name called, will be given by a Registered
Architect etc certifying that the project has been developed as per
the sanctioned plan and specifications, as approved by the
Competent Authority under the local laws, and the Competent
Authority, upon inspection of the project shall issue the Occupancy
26
Certificate if the project is in accordance with the sanctioned plan.
The Completion Certificate as defined under Section 2(q) is
required to be issued only by an Authority created or established
by the appropriate Government and not by an Architect or by
Engineer or by any other similar non-Government Authority.
44. If indeed the Promoter seeks protection under Section-310 of
the Karnataka Municipal Co-operation Act, regarding ‘Deemed
Occupancy Certificate’ provision if the Competent Authority does
not issue the Occupancy Certificate within one month of filing of
the application, the Promoter is required by law under Section-19
(1) & (2) of the RERA Act, to disclose all material facts pertaining
to the project to the Allottee, including under Section-11(4)(b) of
the Act, specifically to make available the copies of Completion
Certificate, Occupancy Certificate etc., to the Allottees or to the
Association of Allottees as the case may be.
45. The Promoter in this case, has not even written to the
Competent Authority stating that since, they had filed an
application for issuance of Occupancy Certificate on 23.10.2018
and the Competent Authority has failed to either refuse or issue
the Occupancy Certificate and, therefore, they are proceeding with
the execution of the Sale Deeds on the basis of the provisions of
Section-310 of the Corporation Act, which provides for deemed
Occupancy Certificate. This amounts to suppression of material
27
facts and information to the allottee, as the Promoter is duty
bound under Section-11(4)(b) of the Act, to disclose all relevant
information and documents to the allottees from time to time. The
said provisions reads as under:-
“11(4) The promoter shall—
(b) be responsible to obtain the completion certificate
or the occupancy certificate, or both, as applicable,
from the relevant competent authority as per local
laws or other laws for the time being in force and to
make it available to the allottees individually or to
the association of allottees, as the case may be.”
Similarly, under Section-19 (1) & (2) of the Act, the allottee is
entitled to know all information pertaining to sanctioned plan,
approvals, stage wise completion of the project and so on.
46. In response to the email dated 28.11.2018 of the Promoter,
referred supra, by which the Promoter requested the allottees to
take possession based on the deemed Occupancy Certificate, the
allottees responded to the same by email dated 04.12.2018 stating
that:-
“Please intimate date by which Occupancy Certificate
is expected such that I can pay balance due and
takeover the apartment. It is reiterated that I was
originally promised delivery in a sales pitch by Sept
2017. However, the date was deffered to 31 May
2018 in the Sale and Construction Agreement. The
grace period for delivery (and as registered under
RERA) has since expired on 01 Dec 2018. With
Occupancy Certificate not yet available (thus not
permitting takeover and occupation), I would request
that FPRL be issued only on receipt of Occupancy
Certificate i.e certification of project completion the
28
authorities. I do not intend to takeover prior issue of
Occupancy Certificate.”
47. It is crystal clear that without the “Occupancy Certificate”
issued by the Competent Authority, it is improper on the part of
the Promoter to execute the registered Sale Deed in favour of the
Allottees. As such, the Allottees were well within their right to get
the Sale Deed registered only after issuance of Occupancy
Certificate issued by the Competent Authority and accordingly,
they rightly expressed their unwillingness to take possession of the
apartment. Hence, viewed from any angle, there is no substance
in the submission made by the learned counsel for the Promoter as
regards existence of the deemed Occupancy Certificate.
48. Insofar as, the second primary ground regarding the delay in
completion of the project due to Force Majeure factors is
concerned, it is just and necessary for this Tribunal to refer to the
terms/covenants contained in clause-5.1, 5.4 and 5.5 of the
Construction Agreement dated 21.07.2015 entered into between
the parties which are relevant to consider as to the existence of
‘Force Majeure’ conditions and also to reckon the date from which
the allottees are entitled to claim interest for the delay in handing
over possession. The said Clauses are extracted hereunder:
“5.1 The First Party shall complete and deliver
possession of the Schedule ‘B’ apartment to the
Second Party by the end of 31.05.2018. The date of
29
completion of construction means the date declared
by the First Party as the date for completion.
5.4 The date stipulated for the delivery of the
Schedule ‘B’ Apartment (as per clause 5.1 of this
agreement) is subject to variation on account of
a) Force Majeure/Act of God
b) Government Orders/restriction/control
c) Delay in issue of NOC/ permissions,
Occupancy certificate sanction by
Government and Statutory Authorities
/Local Bodies.
d) Delay in providing electrical, water and
sewerage connections by various
authorities.
e) Non-availability, non-supply of
construction materials/labour etc,
f) Short supply of materials (viz, sand,
aggregates etc.)
g) Delay/default in payments but the Second
Party.
h) Any other reason beyond the control of
the First Party.
i) Rainfall of 25mm or above
j) Riots, Transportation strikes, Labour
strike etc.,
On happening of any of the above events, the
date of delivery of the apartment by the First
party to the Second Party may be varied to any
future date and the Second Party is not entitled
for any compensation for delay in
completion/delivery of the apartment due to
above reasons.
30
5.5 In the event of there being any delay in
handing over the Schedule ‘B’ Apartment to the
Second Party for the reasons otherwise
than stated in clause 5.4 above the second
party is entitled to claim Rs 4/sft per
month on SBA as compensation from
01.12.2018 for such delay effective from
six months (grace period) from the date of
completion as per clause 5.1 herein above.
The calculation of compensation shall be
subject to the reason cited in clause 5.4 above
if the Second Party is entitled for any
compensation, the First party shall pay the
compensation to the Second Party at the time
of the Second party taking possession of the
apartment and registering the Sale Deed after
appropriating the amount due to the First Party
towards the said apartment/property. The
compensation payable under this clause is a
comprehensive final amount payable by the
First Party to the Second Party. The parties
hereto agree that the Second Party is not
entitled for any other claims of whatsoever
nature under this agreement.”
On careful perusal of the terms contained in Clause-5.5 of the
Construction agreement, there was no specific covenant as regards
a general grace period of six months for handing over possession.
49. As per the terms specified in Clause-5.5 of the Construction
Agreement, the allottees are entitled to claim Rs.4/-per square feet
per month on SBA as compensation from 01.12.2018 only in the
event of any delay in handing over possession of the flat for the
reasons otherwise than stated in clause-5.4 of the
construction agreement. On perusal of the above terms and
conditions, it appears that there is no clause/term contained in the
construction agreement regarding/about a general grace period of
31
six months. The right conferred on the allottees to claim interest
for every month of delay, as provided under the proviso to sub-
section (1) of Section-18 is a statutory right, without prejudice to
any other remedy available to the allottees under the Act. The
promoter has failed to produce any cogent evidence either before
the Authority or before this Tribunal to establish that the delay in
completion of the project within the time stipulated under the
Construction Agreement was on account of the reasons otherwise
than stated in Clause-5.4 of the construction agreement. As noted
in the Explanation to Section-6 of the Act, the ‘Force Majeure’
means “a case of war, flood, drought, fire, cyclone, earthquake or
any other calamity caused by nature affecting the regular
development of the real estate project”. In view of the above, the
factors noted in (a) to (h) of Clause-5.4 cannot be
construed/termed as ‘Force Majeure’.
50. It is undisputed fact that the Promoter received the
Occupancy Certificate from the Competent Authority only on
24.01.2020. While it is a fact that various restrictions were
imposed by the Government of Karnataka on account of pandemic
COVID-19, it was only with effect from 24.03.2020, which is after
the due date for completion. There was no restriction on account
of pandemic COVID-19 for the period upto 28.01.2020, the date
on which offer of possession was made to the allottee. Despite the
same, vide email dated 05.02.2020, the Promoter offered to get
32
the Sale Deed registered but put undue pressure on the Allottees,
directing them to first withdraw the complaint No.1852 filed before
the Authority by the allottees, that too after receipt of entire
payment before registration of the Sale Deed. The emails sent by
the Allottees through email dated 05.02.2020 and 10.02.2020
agreeing to withdraw the complaint if he is compensated as
required under the law went in vain, hence, the contention of the
Promoter that the delay in handing over possession was on
account of force majeure cannot be accepted. Under such
circumstances, the promoter cannot contend that the delay in
completion of the project was on account of ‘Force Majeure’.
51. It is also pertinent to note that, the counsel for the Allottees
filed a Memo dated 12.03.2025 along with the copy of the order
dated 21.01.2023 passed by the Joint Commissioner (Town
Planning-North) BBMP, by which the Occupancy Certificate dated
24.01.2020 and modified sanctioned plan issued in respect of the
project in question, has been cancelled on the ground that
Promoter had submitted false documents at the time of
application. The ‘Occupancy Certificate’ issued in respect of the
project was cancelled by the concerned Authority on 21.01.2023
and while the said order has been stayed by the Karnataka
Appellate Tribunal in Appeal No. 32/2023 vide interim order dated
01.02.2023, and the said interim order is in operation, hence, it
can be inferred that the Promoter had indeed tried to rush the
33
Occupancy Certificate without necessary approvals. Still, one can
say that the Promoter had valid Occupancy Certificate as on the
date of registration of Sale Deed in favour of the Allottees, at least
till the final disposal of the matter in KAT, whenever that happens.
(Underlined for emphasis)
52. Now we proceed to deal with the third contention urged by
the learned counsel for the Promoter relating to entitlement of six
months grace period. As per Clause-5.1 of the Agreement of
Construction dated 21.07.2015, the due date for handing over
possession was on 31.05.2018, subject to variation on account of
the events mentioned at (a) to (h) of Clause-5.4 of the
Agreement. But there was no mention about the grace period of
six months either in Clause-5.1 or 5.4 of the Agreement. Apart
from this, while passing the previous/earlier order dated
16.03.2020, the Authority computed the interest payable to the
Allottees with effect from 01.06.2018. At paragraph-4 (ii) of the
said order, the Authority held as under:
“For the purpose of calculating the interest payable, the
aggregate amount paid by the allottee up to 31.05.2018
shall be considered as the principal amount and the final
payment of Rs.10,07,074/- paid on 1st February, 2020
shall be added to the Principal amount, so as to consider
the said amount also eligible for interest w.e.f. 2nd
February, 2020.”
53. However, after remand by this Tribunal, the Authority, at
Paragraph-17 of the impugned order has recorded the finding to
the effect that as per the agreement of sale dated 21.07.2015, the
34
respondent-promoter was supposed to handover the said flat on or
before 31.05.2018 with six months grace period i.e., 01.12.2018.
In the absence of any specific covenant/terms either in the
Agreement for Sale or in the Agreement of Construction with
regard to the grace period of six months for handing over of
possession, the Authority, contrary to the terms contained in the
Agreement for Sale and Construction Agreement, allowed such six
months grace period while computing the compensation payable to
the Allottees. As such, we are of the considered view that the
Authority was not justified in allowing six months grace period
while passing the impugned order and we are constrained to hold
that there was no substance in the submissions made by the
learned counsel for the Promoter in this regard. Thus, it takes us
to the main issue relating to computation of compensation payable
to the Allottees.
54. Indisputably, the allottees and the promoter have entered
into a Construction Agreement on 21.07.2015. Under the said
Construction Agreement, the time stipulated for completion of
construction and handing over of the possession of the flat was on
31.05.2018. Admittedly, the promoter obtained the completion
certificate from the registered Architect on 16.10.2018 and applied
for Occupancy Certificate on 23.10.2018. But, in the Occupancy
Certificate issued by the Competent Authority (BBMP) on
22/24.01.2020, the date of application has been mentioned as
35
02.11.2019 which was issued by the Competent Authority (BBMP)
on 22/24.01.2020 and thereafter, the promoter intimated to the
allottees on 28.01.2020 and executed a registered sale deed in
favour of the allottees and handed over the possession of the flat
on 23.06.2020. The due date for completion was 31.05.2018, the
Occupancy Certificate was issued on 24.01.2020 and the Sale Deed
was executed on 23.06.2020, hence, there is clear delay in
completion of the project and handing over possession.
55. Thus it takes us to the main issue with regard to the
computation of compensation payable to the Allottees and
reckoning of the starting and ending date for computation of
compensation.
56. At this juncture, it would be relevant for this Tribunal to refer
to the provisions of Section-18 and 19(10) of the which reads as
under:-
Section-18. Return of amount and
compensation.—
(1) If the promoter fails to complete or is unable to
give possession of an apartment, plot or building,—
(a) in accordance with the terms of the
agreement for sale or, as the case may be, duly
completed by the date specified therein; or
xxxx
xxxx
Provided that where an allottees does not
intend to withdraw from the project, he shall be
paid, by the promoter, interest for every month of
36
delay, till the handing over of the possession, at
such rate as may be prescribed.
(3) If the promoter fails to discharge any other
obligations imposed on him under this Act or the rules
or regulations made thereunder or in accordance
with the terms and conditions of the agreement
for sale, he shall be liable to pay such
compensation to the allottees, in the manner as
provided under this Act.
19 xxxx
(10): Every allottees shall take physical
possession of the apartment, plot or building as the
case may be, within a period of two months of the
occupancy certificate issued for the said
apartment, plot or building, as the case may be.
Rule-16. Rate of interest payable by the
promoter and the allottees.- The rate of
interest payable by the promoter to the
allottees or by the allottees to the promoter,
as the case may be, shall be the State Bank of
India highest marginal cost of lending rate plus
two percent.
57. The important dates and events of the case on hand which
are noted in the table below:
Dates events
21.07.2015 Parties have entered into agreement for sale
and construction.
31.05.2018 Due date for delivery of possession of the flat.
16.10.2018 Promoter received completion certificate from
the Architect.
23.10.2018 Initially Promoter applied for occupancy
certificate on the basis of Completion
Certificate by Architect
02.11.2019 As noted in the Reference No.1 of Occupancy
Certificate dated 24.01.2020, the Promoter
made application for issuance of Occupancy
37
Certificate.
22/24.01.2020 Promoter obtained occupancy certificate.
28.01.2020 Promoter intimated to the allottees along with
occupancy certificate and requested the
allottees to get the sale deed registered.
19.03.2020 Government imposed lockdown on account of
COVID-19
31.01.2020 & The allottees paid final installment of
03.02.2020 Rs.10,07,076/- (10,00,000+7,074)
23.06.2020 The promoter executed registered sale deed
in favour of the allottees and handed over
possession of the flat.
01.12.2018 The Authority computed the payment of
interest payable to the allottees for every
month delay in handing over possession of
the flat.
21.01.2023 The BBMP passed order, cancelling the earlier
‘Occupation Certificate’ on the ground that
the same was obtained by the Promoter by
furnishing false document.
01.02.2023 The Karnataka Appellate Tribunal in appeal
No. 32/2023 filed by the Promoter, granted
an interim order of stay, staying the
execution and operation of the order dated
21.01.2023 passed by the BBMP.
58. The provisions of sub-section (1) (a) of Section-18 of the Act
which have been extracted supra contemplates that if the
Promoter fails to complete or is unable to give possession of an
apartment, plot or building in accordance with the terms of the
agreement for sale or, as the case may be, duly completed by the
date specified therein and in the event of the allottee does not
intend/wishes to withdraw from the project, he shall be paid by the
Promoter, interest for every month of delay, till the handing over of
the possession, at such rate as may be prescribed. Sub-section
(10) of Section-19 of the RERA Act, contemplates that the allottees
38
shall take physical possession of the apartment within a period of
two months from the date of issuance of Occupancy Certificate
issued for the said apartment. In the instant case, admittedly, the
Promoter had obtained the Occupancy Certificate on 22/24.01.2020
and conveyed/intimated to the Allottees along with the occupancy
certificate on 28.01.2020 and the allottees have paid the last
installment of Sale Consideration of Rs.10,07,074/- on 31.01.2020
and 03.02.2020 respectively which was payable at the time of
registration of Sale Deed on 01.02.2020. If two months time
stipulated under sub-section (10) of Section-19 for registration of
sale deed is excluded, the allottee is required to get the sale deed
executed on or before 28.03.2020. As there was lockdown imposed
by the Government with effect from 19.03.2020 up to the end of
May, 2020, the allottees have got the sale deed registered on
23.06.2020, which is understandable due to the lockdown.
59. Indisputably, the Occupancy Certificate by the Competent
Authority was received only on 24.01.2020, the Promoter sent an
offer letter on 28.01.2020 for which, the allottees replied through
their mails dated 04.2.2020, 05.02.2020 and 10.02.2020 and
hence, the Authority, considering the delay on the part of the
Promoter to handover possession of the apartment, rightly
awarded compensation and no fault can be found with the said
order. Immediately after receipt of offer letter on 28.01.2020, the
allottees have paid the final payments within two days i.e., on
39
30.01.2020 and 01.02.2020 but it was the Promoter who
unnecessarily imposed the condition upon the allottees to withdraw
the complaint No.1852 and in the process, delayed handing over
possession of the apartment from 01.02.2020, the date on which
the final payment was made till 23.06.2020, the actual date of
execution of the Sale Deed.
60. At this stage, it would also be relevant for this Tribunal to
refer to the law laid down by the Hon’ble Supreme Court in the
case of M/S. Newtech Promoters and Developers Pvt. Ltd., -
vs- State of Uttar Pradesh and others (2021 SCC OnLine SC-
1044), the provisions of Section-18 (1) and 19 (4) of the Act
recognize right of an allottee two distinct remedies viz., refund of
the amount together with interest or interest for delayed handing
over possession and compensation. In paragraph-25 of the said
Judgment, the Hon’ble Supreme Court held as under:
“25. The unqualified right of the allottee to seek refund
referred under Section 18(1)(a) and Section 19(4) of the
Act is not dependent on any contingencies or stipulations
thereof. It appears that the legislature has consciously
provided this right of refund on demand as an
unconditional absolute right to the allottee, if the
promoter fails to give possession of the apartment, plot
or building within the time stipulated under the terms of
the agreement regardless of unforeseen events or stay
orders of the Court/Tribunal, which is in either way not
attributable to the allottee/home buyer, the promoter is
under an obligation to refund the amount on demand
with interest at the rate prescribed by the State
Government including compensation in the manner
provided under the Act with the proviso that if the
allottee does not wish to withdraw from the project, he
40
shall be entitled for interest for the period of delay till
handing over possession at the rate prescribed”.
61. As regards the issue relating to the date from which the
allottee will be entitled to receive interest under Section-18, it is
clear that the Promoter has to pay interest for every month of
delay from the due date of hand over possession as per the
Sale/Construction Agreement till the date of actual hand over
possession of the Promoter. In this case, the due date for handing
over possession as per Sale Agreement is 31.05.2018 and the
actual possession was handed over on 23.06.2020. However it is
also an undisputed fact that the Promoter, after receiving the
Occupancy Certificate from the Competent Authority on
24.01.2020, sent the letter of offer to the allottees on 28.01.2020.
62. Therefore, this Tribunal is of the considered view that the
interest for delay in handing over possession may be computed
from the due date for handing over possession being on
31.05.2018, until 28.01.2020 being the date on which the
Promoter offered possession of the apartment, after receiving
necessary clearance from the Competent Authority. The interest
from the date of making the offer to the allottees on 28.01.2020 till
the date of possession was handed over on 23.06.2020 may not be
considered to be awarded to the allottees, as it was not due to the
fault of the Promoter.
41
63. Thus, the date to be reckoned for calculation of interest for
every month delay in handing over possession of the flat is
immediately after the due date for delivery of possession i.e.,
01.06.2018 and not 01.12.2018, as determined by the Authority,
since there is no grace period of additional six months in the
Agreement. Having regard to the totality of the facts and
circumstance of the case, interest of justice would be met if the
compensation by way of interest for every month delay is awarded
from 01.06.2018 to till 28.01.2020 the date on which offer was
made to the allottees after receipt of Occupancy Certificate by the
Promoter, and the impugned order is liable to be modified to that
extent.
64. Further, as an additional ground, the Promoter contended
that as per the terms of the Construction Agreement dated
21.07.2015, the allottees are required to make payments
depending upon the progress of each stage of the construction of
the building. On perusal of the Statement of Objections filed by the
promoter before the Authority on 21.10.2019, it is seen that the
promoter has not specifically pleaded in which of the payments
made by the allottees, there was a delay and how much was the
delay in making such payment and there was no claim made by the
promoter seeking penal interest for alleged delay in making
payment of sale consideration. In view of that perhaps, the
Authority, in its impugned order dated 24.03.2023, also has not
42
addressed this issue at all. Under such circumstances, the
contention of the learned counsel for the Promoter before this
Tribunal that there was a delay on the part of the allottees in
making payment of sale consideration is not sustainable.
,
65. For the foregoing reasons, we answer point No (i) partly in
the affirmative holding that the Authority was not justified in
reckoning the date 01.12.2018 as starting period for determining
the interest for every month of delay in handing over possession
and proceed to pass the following:
ORDER
(a) The appeal is partly allowed;
(b) The impugned order dated 24.03.2023 passed by the
1st Respondent-the Karnataka Real Estate Regulatory
Authority in complaint No. CMP/190112/0001852 is
hereby modified;
(c) In view of our finding recorded at Paragraph- 61 to
63, in modification of the impugned order it is
ordered that the Allottees are entitled to claim
interest for every month delay for the period from
01.06.2018 till 28.01.2020, the date on which offer
of possession was made;
(d) Both the parties are directed to file Memo of
Calculation determining the amount payable to the
allottees for the period from 01.06.2018 to
28.01.2020;
43
(e) After filing the Memo of Calculation, the Registry is
directed to release the amount in favour of the 2nd
and 3rd Respondents-Allottees, including interest
accrued thereon by issuing the bankers cheque/DD
after the expiry of the appeal period and by following
the due procedure;
(f) The remaining amount, if any, shall be released in
favour of the Appellant-Promoter by issuing the
bankers cheque/DD in favour of the Appellant-
Company after the expiry of the appeal period and
by following the due procedure;
(g) In view of disposal of the main appeal, pending I.As.,
if any, shall stand disposed of, as they do not survive
for consideration;
(h) Registry is directed to comply with the provisions of
Section 44(4) of the Act and to return the records to
RERA, if any received.
There is no order as to costs.
Sd/-
HON’BLE JUDICIAL MEMBER
Sd/-
HON’BLE ADMINISTRATIVE MEMBER