PLOTTING KERJA PT.
TRI KARYA CEMERLANG
MANDIRI INHEALTH TOWER
HARI/TANGGAL : Selasa, 17 Juni 2025
NO AREA SHIFT WANITA PRIA JAM ISTIRAHAT P3C/EXTRA JOB
1 EXTERNAL ISKANDAR
2 BASEMENT DIDIK
1. Iskandar :
3 LOBBY ADE - Swepping Sampah External Ring Luar dan Dalam
- Stripping Sampah All Floor 29-GF
4 GF TOILET 2. Didik :
SADIYAH - General Cleaning Pump Room
LANTAI 2
SURYADI - General Cleaning Ruang Fan P1
5 LANTAI 3 - General Ceaning Ruang Fan P2
LANTAI 5 3. Ade :
- Polishing Planter Pot
LANTAI 6 4. Suryadi Dan Sadiyah :
NUR
LANTAI 7 - Wall cleaning dinding dan partisi cubical Toilet Lantai GF-05
6 LANTAI 8 ALFINESA - Spotting Floor Drain Toilet Lantai GF-05
- ROC Ceilling (Exhaust Fan, AC Grill, Speaker & Kap Lampu) Koridor Lantai GF-05
LANTAI 9
5. Alfinesa, Nur, yuni :
LANTAI 10 1 12:00 - 13:00 - Wall cleaning dinding dan partisi cubical Toilet Lantai 06-10
YUNI
LANTAI 11 - Spotting Floor Drain Toilet Lantai 06-10
LANTAI 12 - ROC Ceilling (Exhaust Fan, AC Grill, Speaker & Kap Lampu) Koridor Lantai 06-10
6. Yudi dan Revita :
LANTAI 15 YUDI
- Wall cleaning dinding dan partisi cubical Toilet Lantai 11-17
LANTAI 16 - Spotting Floor Drain Toilet Lantai 11-17
7 REVITA
LANTAI 17 - ROC Ceilling (Exhaust Fan, AC Grill, Speaker & Kap Lampu) Koridor Lantai 11-17
LANTAI 18 7. Rahmat dan Rizka :
- Wall cleaning dinding dan partisi cubical Toilet Lantai 18-22
LANTAI 19
- Spotting Floor Drain Toilet Lantai 18-22
LANTAI 20 RAHMAT - ROC Ceilling (Exhaust Fan, AC Grill, Speaker & Kap Lampu) Koridor Lantai18-22
LANTAI 21 RIZKA 8. Dandi dan Popy :
LANTAI 22 - Wall cleaning dinding dan partisi cubical Toilet Lantai 23-29
- Spotting Floor Drain Toilet Lantai 23-29
LANTAI 23
- ROC Ceilling (Exhaust Fan, AC Grill, Speaker & Kap Lampu) Koridor Lantai 23-29
LANTAI 25
8
LANTAI 26
DANDI
LANTAI 27 POPY
LANTAI 28
LANTAI 29
1. Handi 1. On Air PH 2 Utara
9 GONDOLA 1 12:00 - 13:00
2. Rifki 2. Glass cleaning canopy pos 2
10 ADMIN 1 Renie Mustika 11:00 - 12:00
11 TEAM LEADER 1 Sarwinah 12:00 - 13:00
All Area
12 SITE MANAGER 1 Dede Setiawan 12:00 - 13:00
TOTAL KEHADIRAN
KONTRAK SHIFT
REALISASI SHIFT KETERANGAN
SHIFT 1 SHIFT 2
SITE MANAGER 1 - 1
TEAM LEADER 1 2 3
ADMIN 1 - 1
GONDOLA 2 - 2
CSO 14 16 30
19 18
TOTAL
37
DIBUAT OLEH, DISETUJUI OLEH,
DEDE SETIAWAN NANING
SITE MANAGER - PT. TRI KARYA CEMERLANG