TOTAL UPAH
NO JOB DESCRIPTON PANJANG LEBAR TINGGI QUANTITY UNIT UPAH KERJA
KERJA
Structure Work
A Demolish Work
1. Wall Demolish (Bobok Dinding) 30.48 m2 Rp80,000 Rp2,438,400
2. Tile Demolish (Bobok Lantai 236.00 m2 Rp70,000 Rp16,520,000
3. Screed Paint (Haluskan permukaan tembok lama) 1174.00 m 2
Rp20,000 Rp23,480,000
4. Glass box remove (Bongkar Glassbox) 632.00 m2 Rp20,000 Rp12,640,000
B STRUCTURE PORTAL ROOFTOP FLOOR
1. Roof Clearing (Bersihkan Atap Genteng) 214.25 m2 Rp20,000 Rp4,285,000
2. Roof Waterproof Paint (Cat Waterproof Atap Genteng) 214.25 m2 Rp20,000 Rp4,285,000
3. Roof Gutter (Pasang Talang Air) 105.61 m' Rp42,500 Rp4,488,425
C FINISHING GROUND FLOOR WORK
1. Wall Work
Interior Paint (Cat Interior) 4.00 6.50 3.00 262.00 m2 Rp27,000 Rp7,074,000
4.00 8.00 3.00 298.00 m2 Rp64,000 Rp19,072,000
Exterior paint with waterproof 1 m (Cat luar, bagian bawah 1 meter waterproofing
2. Floor Work
128.00 m2 Rp75,000 Rp9,600,000
Install "Tiles Type 1" 120x60 cm use auto level system &ready cement for floor (MU 380)
(Pasang keramik ukuran 120x60 menggunakan MU 380)
Skriting floor with granite tile (matching with floor) WITH U LIST ALUMUNIUM 1 CM 9 57.80 m2 Rp95,000 Rp5,491,000
pasang skring lebar 10 cm dan list alumunium 1 cm)
3. Door and Window Work
W. Ventilation 2000 x 900 Fixed window with wood frame 4.00 unit Rp5,800,000 Rp23,200,000
(Perbaikan jendela dan pasang kusen jendela ukuran 2 m x 0,9 m)
W. Room 1800 x2500 Fixed window with wood frame 1.00 unit Rp7,200,000 Rp7,200,000
(Perbaikan jendela dan pasang kusen jendela ukuran 1,8 m x 2,5 m)
W. Kitchen 3000 x 1000 Fixed window with wood frame 1.00 unit Rp10,800,000 Rp10,800,000
(Perbaikan jendela dan pasang kusen jendela ukuran 1,8 m x 2,5 m)
4. Glass Railing (Railing Kaca) 15.00 m2 Rp750,000 Rp11,250,000
D. FINISHING FIRST FLOOR WORK
1. Wall Work
Interior Paint (Cat Interior)
Exterior Paint with waterproof 1 m 4.00 6.80 3.00 334.00 m2 Rp27,000 Rp9,018,000
2. Floor Work
Install "Tiles Type 1" 120 x 60 cm use auto levels system & ready cement floor (MU 380) 108.00 m 2
Rp75,000 Rp8,100,000
Skriting floor with granite tile (matching with floor) WITH U LIST ALUMUNIUM 1 CM 48.54 m2 Rp95,000 Rp4,611,300
3. Door and Window Work
W. Ventilation 2000 x 900 Fixed window with wood frame 5.00 unit Rp5,800,000 Rp29,000,000
W.Room 1800 x 2500 Fixed window with wood frame 2.00 unit Rp10,800,000 Rp21,600,000
4. Wood Railing Refinish (Finish Railing Kayu) 50.00 m2 Rp500,000 Rp25,000,000
E. ELECTRICAL GROUND & FIRST FLOOR WORK
1. Electrical Work
Cabling for lighting installation NYM 2 x 2,5 mm2 in HIC Clipsal 20 mm. 24.00 point Rp160,000 Rp3,840,000
Cabling for socket installation NYM 3 x 2,5 mm2 in HIC Clipsal 20 mm. 46.00 point Rp160,000 Rp7,360,000
Cabling for exhaust fan installation NYM 3 x 2,5 mm2 in HIC Clipsal 20 mm. 9.00 point Rp160,000 Rp1,440,000
Cabling for double switch installation NYM 2 x 2,5 mm 2 in HIC Clipsal 20 mm. 2.00 point Rp160,000 Rp320,000
2. Lighting fixture (Supply, install and testing)
Bra Light Outdoor 18.00 m Rp160,000 Rp2,880,000
Spotlight 7 W 4000K 27.00 nos Rp160,000 Rp4,320,000
Garden Light 15.00 nos Rp160,000 Rp2,400,000
3. Amarture Work (Supply, install and testing)
Double Switch
Socket 44.00 set Rp85,000 Rp3,740,000
Exhaust Fan 5w/220v (Supply & install) 91.00 set Rp160,000 Rp14,560,000
9.00 set Rp160,000 Rp1,440,000
F. OUTDOOR AREA
1. Paving Pathway (Pasang pathway pakai batu alam) 24.00 m2 Rp185,000 Rp4,440,000
TOTAL COST Rp305,893,125