W29-MoM Piping Weekly Meeting

The Weekly Piping Coordination Meeting on July 15, 2025, addressed HSE concerns, manpower status, and material procurement updates. Key actions included improving housekeeping, planning for missing spools, and ensuring communication between teams. The next meeting is scheduled for July 22, 2025, to follow up on outstanding issues and progress.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
8 views3 pages

W29-MoM Piping Weekly Meeting

The Weekly Piping Coordination Meeting on July 15, 2025, addressed HSE concerns, manpower status, and material procurement updates. Key actions included improving housekeeping, planning for missing spools, and ensuring communication between teams. The next meeting is scheduled for July 22, 2025, to follow up on outstanding issues and progress.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Minutes of Meeting (MoM)

Date: 15 July 2025


Subject: Weekly Piping Coordination Meeting
Week: W29

Attendees: Valtteri, Renzo, Jaziel, Abdulraheem, Bruno, Ludovit, Venkata, Abolfazl, Andrew, Jose

1. HSE:
o Rain protection kits, keep dry & intact working clothes
o check weather before planning activities
o Housekeeping needs to improve on going
o Loose materials to be taken control by logistic / material management. Till completion

2. Manpower Status:

• General Manpower
o Manning 113
o Transition phase dia inch to test pack target works.? Ongoing and need to improve
for better results.
 BKS:
o 12 personnel currently on site out of 16, working on Oschatz/Boiler lines.
 OCT Team:
o 6 direct workers on day shift and 3 on night shift. Total 9 Mans.
 Boiler Pre-Commissioning Preparation
o Action: Enersense to plan and assign required resources.
 IKM Team:
o 16 direct, in 2 teams for FRP and the rest.
 Odda Plast
o No workers Email notified by Espen stating on summer holidays will notify when they
have time.
 PIMS administration
o Dedicated person requested for full control on the checklist & Punchlist part ->
waiting from Finland office response.
• QC Manpower
1 Doc. control starting today. waiting from Finland office response.
Alexandras replacement is still missing. waiting from Finland office response.
3. Planning and Coordination:
 Priority Lines
o All piping priorities are fully clarified & acknowledged by ENE.
o The APL line MC still forecasted end of WEEK 29, ENE shall share daily wise punch
closure status.
o Updated schedule shared. Escalated to management meeting.
o Material delivery forecast by be shared by ENE according to the priorities given-
>Today in the shared folder. >> this topic is twice, refer point4 material section.
o Schedule should be prioritized during the week 28 to revise the schedule integrating
delivery dates for remaining Material. Escalated to management meeting.

 Supervisor Visibility and Communication


o Daily walkdowns between ENE/Metso ongoing where daily concerns are discussed
and solved. Shall continue & improve more to get detailed information on Test pack
readiness.
o Supervisors’ names should be filled in the live progress file to enhance
communication between Metso and Enersense, update the organisation chart with
contact & email details. Will be checked in next meeting (ENE will share by tomorrow
16-Jul-25)
4. Material Procurement:
o ENE shall communicate the outstanding materials which are under procurement
status with deliveries. Updated file to be shared on share point. By today, COB
o Ludo email for material status to reply->Today COB, by Andrew>> again by today,
COB

5. Mechanical Completion & Piping Status:


• TP10 Missing Spool
o The missing spool for TP10 will be handled by ENE.
o Action: ENE started pre fabrication->end of W28>> 60% fabricated
 Touch-Up Painting and Pickling
o Action: Enersense to start aligning with OCT team by giving required test pack which are
scheduled for re-instatement. Ongoing
o TG Part of painting to be started, details to be shared to OCT for action> Today COB>>
again today, COB.
o Multiserwis must be consider for touch-up paint of supports for carbon steel lines. (Arild
BOL)
o Shrouded boxes lines handover from ENE to KBS, dates shall be provided as handover
to work front for KBS. construction completion, waiting forecast from ENE> ENE by today
COB.
o Missing spool between MOG and Espoo connection. to be confirmed if SX material.->to
be confirmed by Metso, confirmed not SX, its SS, ENE to provide work forecast by today
COB
 NDT Schedule
o Additional information was requested. Reports to be provided. Minimum 10 days window
o Action: Responsible teams to provide an updated NDT plan. ENE confirmed NO
BACKLOGS. W29
 TP Changes and Modifications
o All changes must be validated by Mr. DAN (ENE) and (Metso) Mr. Abdul Raheem/ Mr.
Abolfazl prior to execution.
o Metso will share Test pack details for the priority wise of commissioning. Done
• Line walkdowns
o All priorities line walkdowns completed, very few lines to walk & uninstall part of lines to
cover.
o Commissioning priorities added to the line walkdowns. Checks ongoing and ENE will
update internally.
o Odda Plast: One repaired spool will be returned to site, ENE will co-ordinate, other spool
with T piece, NCR 71 raised, waiting with follow up of corrective actions / BOL / Mecwide-
Amiblu response. Next failure of lines NCR generated, BOL will provide 2 man’s available
to attend the repairs, Espen is the focal point of communication.
o Repair procedure shared by Amiblu to odda plast, odda plast is on summer vacation,
waiting for resources by BOL.->Boliden
• Piping tasks list effecting other disciplines
o ENE agreed to allocate 2 mans for closing of the listed items shared by email. Need
weekly update of closure points. Started, ENE will update by today COB.

6. RFIs:

o No Open RFIs

7. Documents:
o Waiting for Weekly Report W28.
o TG Test packs documentation is outstanding. (Quality) Topic closed, transferred to
Quality MoM.

Next meeting Date: 22-Jul-2025 at 11:00 AM Lothe Meeting Room