Construction of Tourist Assistance Center Building Phase (II)

The project involves constructing a new Tourist Assistance Center in Bislig City to enhance tourist services and experiences, with an estimated cost of 3 million. Key components include site preparation, building construction, utility installation, and landscaping. The project aims to benefit tourists and local businesses while promoting economic growth in the region, with a timeline from April 19, 2025, to June 10, 2025.

Uploaded by

Ed Decatoria
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
42 views1 page

Construction of Tourist Assistance Center Building Phase (II)

The project involves constructing a new Tourist Assistance Center in Bislig City to enhance tourist services and experiences, with an estimated cost of 3 million. Key components include site preparation, building construction, utility installation, and landscaping. The project aims to benefit tourists and local businesses while promoting economic growth in the region, with a timeline from April 19, 2025, to June 10, 2025.

Uploaded by

Ed Decatoria
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Name of Program or Project Construction of Tourist Assistance Center Building Phase (II)

This project involves the construction of a new building to serve as a Tourist Assistance Center. This will expand the capacity to serve tourists and improve
Brief Description the overall tourist experience.

*Site preparation and groundwork


*Building construction (including foundation, structure, and finishing)
Program or Project Components *Installation of necessary utilities (electricity, water, sewage)
*Furnishing and equipping the center
*Landscaping and external works

Proponents LGU Bislig City, Tourism Devision, Tourist

Estimated Cost 3,000,000.00

The current Tourist Assistance Center is inadequate to meet the growing needs of tourists. This new building will provide a larger, more modern, and more
Justification efficient facility to better serve tourists and promote tourism in the area. The improved facility will enhance the overall tourist experience, leading to increased
tourism revenue and economic benefits for the region.

Intended Beneficiaries Tourists visiting the area, local businesses, and the local economy.

Program or Project Term April 19, 2025 to June 10, 2025

Target Output(s) and Success


Output: A fully functional and modern Tourist Assistance Center.
Indicator(s) Success Indicators: Number of tourists served, positive feedback from tourists, increased tourism revenue in the area.

Construction delays due to weather or material shortages.


Possible Risks Cost overruns.
Unexpected site conditions.

Develop a detailed project schedule with contingency plans for potential delays.
Risk Mitigation Secure funding and establish a robust budget control system.
Conduct thorough site investigations before construction begins.

Expected Stakeholder's Response Positive feedback from tourists and local businesses, increased tourism revenue, and overall economic growth in the area.