Feeder/Substation
Order no Work details ZSO Vehicle Contact Person Start Time End time Start date Duration ISOLATION
Details
Sagar
DT Augmentation from 100 to BWN-4 grid to I-90 sec Panel no. 2 at I-90 sec 3
30445747 to be cancelled by Breakdown Lovenish + Vipin 08:30:00 14:30:00 23.08.2025 6
250 KVA with 1 Pole D&I 3 DSIIDC Bawana DSIIDC Bawana
Sandeep
DT Augmentation from 400 to BWN 6 grid to I-Block Panel no 3 at I Block sec 3
30445746 Sandeep NCC 1,3 Lovenish + Vipin 09:30:00 15:30:00 23.08.2025 6
500 with 1 Pole D&I and sec 3 S/s
PSD for zonal maintenance(AR
Hot spot attend, Tree trimming, BAWANA-1 GRID TO FG- VCB rack out panel no. 28
30445152 Arun 5th vehicle Gaurav/Arif 10:00:00 16:00:00 23.08.2025 6
HT jumperreplaced,Damaged 27 SEC-3 Bawana 1 Grid
GO replaced, creeper removed)
PSD for 1 Way RMU Gas filling BAWANA-4 GRID TO B- A/R & Go open HT521-
30444137 Arun 5th vehicle Arun + Mahabir 11:15:00 13:15:00 23.08.2025 2
at B-242 sec 3 BLOCK SEC-3 53/44/35/3
PSD for MMG work I-30 sec 4
HT521-33/6 and AR Hot spot BAWANA-4 GRID TO I VCB rack out panel no.31
30445749 Pawan NCC 2,4,5 MMG + Zone 10:30:00 12:30:00 23.08.2025 2
attend at HT521-33/18 I-64/4 ( BLOCK SEC-4 from BWN 4 Grid
GO 'B" I/C-80°C, "Y" O/G-135°C
PSD for consumer request J-
BAWANA-7 GRID TO J- 1 way RMU open at J-61 sec-
30445212 127 & 128 sec 5. 9350041545 Amit Breakdown Zone 11:00:00 13:00:00 23.08.2025 2
32 SEC-5 S/S O/D 5 DSIIDC Bawana S/s O/D
Banshi Dhar
Amit- Breakdown + PSD
Pawan- PSD + NCC 2,4,5 + RO + PSD
Arun Verma - 5th Vehicle- PSD + Maintenance work
Shiv Charan- 4th vehicle - RO + ESD to MMG team
Sandeep- PSD + NCC 1,3 + RO
Mahabir- GO Installation at B blk sec 3 + RMU Gas filling
Vipin- Maintenance work, HOT Spot attend on GO and DD