Pro 4.5 0001 1 02
Pro 4.5 0001 1 02
M&C-M Procedure
PRO-4.5-0001-1-02
Energy Isolation
HSE Manager – Midstream, Network
Document Owner: Janelle Shackley
Solutions & OMS
HSE Manager – Midstream, Network
Approved By: Janelle Shackley
Solutions & OMS
HSE Specialist - Control of Work and
Prepared By: Adrian Connolly
Contractor Management
Document Status: Active Version 5
Approved Date: 15-Dec-23 Review By: 15-Dec-28
Purpose
Whenever BP conducts construction, maintenance, demolition, remediation and other similar work
that are typical of our industry, there is the potential for harm to people and the environment and for
damage to equipment. This document provides requirements for the isolation of energy systems in
support of PRO 4.5-0001-0-01 Control of Work. Energy Isolation is a key component of the system of
work that allows tasks to be completed safely and without unplanned loss of containment with the
potential to cause environmental damage or to damage a plant or equipment.
This procedure sets out a required approach to isolation of energy systems in accordance the Life
Saving Rules, and the requirements of GDP 4.5-0001 Control of Work.
Contents
Purpose .......................................................................................................................................... 1
Relevant OMS element(s) ........................................................................................................ 1
1. Scope .................................................................................................................................... 5
2. Methodology ........................................................................................................................ 5
2.1. General ............................................................................................................................ 5
2.2. Mechanical Isolation ....................................................................................................... 6
2.2.1. Positive Isolation 6
2.2.2. Valve Isolation 7
2.2.2.1. Double Block and Bleed 7
2.2.2.2. Single Valve 7
2.2.2.3. Valve Actuators 8
2.2.2.4. Isolation of other Energy Sources 8
2.2.3. Steps in Performing Mechanical Isolations 8
2.2.3.1. Identify 9
2.2.3.2. Isolate 9
2.2.3.3. Secure 9
2.2.3.4. Discharge 9
2.2.3.5. Test 9
2.3. Electrical Isolation ......................................................................................................... 10
2.3.1. Key Considerations 10
2.3.2. Steps Performing Electrical Isolation 10
2.3.2.1. Identify 10
2.3.2.2. Isolate 10
2.3.2.3. Secure 11
2.3.2.4. Discharge 12
2.3.2.5. Test 12
2.3.3. Interlocks and Automatic Starting of Equipment 12
2.3.4. ‘Try’ Step 13
2.3.5. Cutting of Electrical Cables 13
2.3.6. Opening of Enclosures 13
2.4. Working On or Near Live Electrical Equipment ........................................................... 14
2.4.1. Key Considerations 14
2.4.1.1. High Energy Installations 14
2.4.2. Safeguards 14
2.4.2.1. Assessment 14
2.4.2.2. Stand-by Person 15
2.4.2.3. Competency 15
2.4.2.4. Precautions 15
2.4.2.5. Safety Apparel (PPE) for Electrical Work 15
2.4.2.6. Earthing 16
1. Scope
The requirement specified in this procedure applies equally to BP employees, contractors and visitors
engaged in the ANZ MC&M business.
Specific sites, areas and activities may have more detailed OMS requirements and where these exist the
requirements will be specified in local procedures, safe work instructions, manuals, handbooks or
specific standards.
2. Methodology
2.1. General
Isolations may be recorded on the Work Permit, Work Clearance, Lock out Tag out (LOTO) document or
other associated document for the work such the safe work procedure or risk assessment. Once
isolations have been performed, they shall be checked by the worker to confirm effectiveness before
commencing work.
Where capable of being locked, the lockout device is a lock with a tag to secure the isolation. If not
capable of being locked, tags only may be used along with other measures to provide an equivalent
protection to applying locks.
and drains are checked to be free from blockage during discharge of stored energy, and
prior to testing the isolation is effective.
g) Test conducted to confirm that equipment is isolated and that plant / equipment is de-
energized / depressurized and / or cannot be started.
The method of isolation and discharge of stored energy shall be authorised in accordance with PRO4.5-
0001-1-01 Permit to Work (NZ) and WPCG-PRO-01 Worth Authorisation (Australia), and executed by the
responsible person(s).
Positive Isolation is regarded as the most secure method and should be considered in the development
of all LOTO Plans.
Positive isolation is defined as:
a) Spool removal - removal of a pipework section or spool piece and blanking the live end,
also called ‘air gapping’.
b) Blind isolation - insertion between flanges of a blind (spade); the swinging closed of a
spectacle blind (plate); or replacement of a spacer (slip-ring) with a line blind (spade).
Where spool removal cannot be achieved, isolation by a valve and line rated spade provides the next
highest quality and security. The valve shall be locked and the spade inserted for that particular
isolation. The valve and spade shall be tagged in their secure position to prevent inadvertent operation
and removal.
Spectacle blinds, blank flanges, bolting, and gaskets shall be adequate thickness for the line rating. New,
correctly rated gaskets shall be installed and all correctly sized bolts shall be installed and tightened.
Positive isolation by spool removal or air gapping shall be considered as the minimum sole means of
isolation for Confined Space Entry - exception for the use of line rated blind only as authorised by the bp
engineering authority for the business. When a spool or valve is removed, (air gapped) the ‘live’
pipework side should be fitted with a blank flange. In most circumstances the isolated equipment (vessel
or pipe-work) flange should be left open to allow the vessel or pipe-work to "breathe". Positive isolation
by spool removal shall be performed for any positive isolation for confined space entry lasting longer
than one month.
Positive isolation is required for hot work on pipelines or equipment containing hydrocarbons (or other
flammable or combustible dangerous goods) that involves burning, welding, grinding, air arcing,
soldering, open flame or other similar type of activities. Isolation by valve and line rated spade is
acceptable for positive isolations involving this work. Positive isolation by spool removal shall be
performed for any positive isolation for hot work lasting longer than one month. Note that positive
isolation is not mandatory when performing hot taps, electrofusion welding of UPP, the Fitsafe technique
or other similar work.
Double block and bleed is the most secure form of valve isolation, but should only be used if the valve(s)
can provide a reliable seal under the particular conditions of service. The main valve shall be locked and
tagged closed and the bleed shall be wired and tagged open to prevent inadvertent operation.
Double block and bleed valve isolations may be considered as the minimum sole means of isolation for
routine short duration cold work for moderate and high pressures. This type of isolation shall only be
used if the duration of the work is short (less than 4 hours) and the immediate work site shall not be left
unattended.
In single valve isolations the integrity of the isolation is critically dependent upon the reliability of the seal
under the particular conditions of service and the security of the single valve operating stem.
Isolation against a tested single valve may be used for the purpose of swinging a spectacle blind,
inserting a line rated spade or fitting a blind flange to achieve higher integrity isolation.
Single valve isolations may be considered as the sole means of isolation for routine, short duration, cold
work where pressures on the active side are less than 200 kPa g. The duration of work shall be short
(less than 4 hours) and the immediate work site shall not be left unattended.
Other energy sources can include heat, gas, steam, gravity and pressure. These shall be isolated by a
physical break which is identified by a tag and secured by a lock or an equivalent mechanical means that
cannot be neutralized without the use of tools. Open ends shall be blanked or capped. Persons
performing the work shall test the operation of equipment before work commences to ensure effective
isolation.
The following key steps shall be applied when making safe mechanical installations.
a) Identify
b) Isolate
c) Secure
d) Discharge
e) Test
2.2.3.1. Identify
The equipment to be worked on and all isolation points shall be clearly identified. For Complex
Isolations, a copy of the plant P&ID’s should be marked showing which items are isolated and attached
to the LOTO plan.
2.2.3.2. Isolate
The equipment to be worked on shall be isolated from all sources of energy by the highest method of
isolation as reasonably practical and meeting the minimum isolation requirements of this procedure for
the type of work. Consideration should also be given to locking out and tagging any originating sources
of energy (e.g. pump motor circuit breakers) of the system.
2.2.3.3. Secure
All isolation points shall be locked out to ensure energy control devices, such as valves, are secured in a
safe position from inadvertent operation.
Appropriate warning tags shall be placed at all isolation points, which forbids the operation of the energy
control device and associated equipment, communicates the reason for lockout, the name of the person
who applied the tag and the date the tag was applied. Consideration should also be given to locking out
and tagging any originating sources of energy (e.g. pump motor circuit breakers) of the system.
2.2.3.4. Discharge
Once isolations have been made, all stored energy shall be discharged so far as is reasonably
practicable. Prior to breaking containment of a pipeline or piece of equipment (e.g. filter vessel), it shall
be de-pressurised to atmospheric pressure by means of a vent or drain to atmosphere. Any product or
contaminated water shall be captured. Product or contaminated water shall not be allowed to drain to
ground or be directed into open drains. It is critical that all bleeds, vents and drains are checked to be
free from blockage prior to testing.
2.2.3.5. Test
The energy control devices (e.g. valves,) as well as plant and equipment which is isolated, shall be tested
prior to conducting work to prove effective energy isolation
Electrical equipment shall be considered to be energised (i.e. live) until proven de-energised.
The following key steps shall be applied when making safe electrical installations.
a) Identify
b) Isolate
c) Secure
d) Discharge
e) Test
2.3.2.1. Identify
Electrical equipment to be worked on and the appropriate point of supply shall be clearly identified.
Identification of equipment should include labelling that is both consistent and clear at the equipment to
be worked on and all points of possible isolation, e.g. control isolator and main point of supply.
2.3.2.2. Isolate
The electrical equipment to be worked on shall be isolated from all sources of supply (e.g. mains,
generator, battery or solar) either by opening switches, removing fuses or switching circuit breaker /
RCD/ RCBO. Where isolation is performed at a removable or rack-out circuit breaker or combined fuse
switch or a removable fuse the device should be racked out or removed to provide a visible break for
isolation verification.
Where isolation is provided by the removal of fuses in a distribution board or motor starter the following
shall apply:
a) Removed fuses shall not be stored in the same panel as the fuse holder.
b) Fuses shall be tagged and stored in a secure location during the period in which
equipment is isolated.
c) Blank or empty fuse cartridges, preferably painted yellow and tagged ‘for isolation
purposes’ shall be inserted into the fuse holder to prevent inadvertent contact with
exposed conductors and to clearly identify that equipment is under isolation.
Confirmation shall be made that all required isolations are in place. For complex isolations, this
confirmation may be by a nominated second person if deemed necessary to manage the risk of incorrect
isolation.
2.3.2.3. Secure
a) Tagging
Tags shall be placed at all points of switching, isolation or disconnection. Such tags shall be
clearly understandable and signed and dated by the person placing the tag or by the
supervisor in charge of the work party. Identification labels should also include warnings for
any abnormal hazards, e.g. multiple points of supply, etc.
b) Lock Out
Where a facility exists to lock an isolation point, it shall be used. All points of isolation for
the work (e.g. circuit breakers, switches and combined fuse switch units forming part of the
power or control circuit) should be locked out. Where locking facilities are not available,
temporary securing devices should be used. Securing devices shall be able to withstand any
disrupting environment, e.g. not become ineffective due to vibration.
If lock out facilities do not exist at the isolation point, other measures shall be implemented
to ensure the isolation is secure for the safety of personnel conducting the work. This may
include locking out the switchboard cabinet door, the room door, or a spotter to remain in
attendance. The need to implement alternative measure should be reported to the bp
representative.
Where fitted, all fuses in the power and control circuits requiring isolation for the work shall
be removed.
Where fitted, three phase field isolators in the power circuit requiring isolation for the work
shall be tagged in the off position and should be locked off.
Local field isolators for equipment shall be tagged in the off position and should be locked
out.
Where an isolation is secured (lock out) a padlock should be used and should be uniquely
keyed to prevent inadvertent removal by others. The use of a multi-lock device should be
employed where more than one person is to attach a personal lock to an isolator.
Figure 2 shows a typical method for tagging and locking out circuit breakers on a distribution
board.
Figure 2: Electrical Circuit Breaker with Multiple Lock hasp, Single Lock and Tag
2.3.2.4. Discharge
2.3.2.5. Test
During the isolation consideration shall be given to the possibility of circuit wiring or electrical equipment
becoming live due to the operation of automatic control devices, e.g. thermostats, float switches, PLCs
and other interface and interlock devices.
To prevent the inadvertent or automatic starting of equipment from remote locations the respective
output from a PLC or DCS to equipment being isolated shall be disconnected as part of the isolation
process. This includes connections to motor starters, valve solenoids, motorised valves, instrument
power etc.
Disconnection of the PLC/DCS output may be achieved by one of the following;
a) Physically disconnecting wiring at the output module,
b) Physically disconnecting wiring or removal of a fuse at a terminal strip in a wiring
enclosure,
c) Physically disconnecting wiring at the field device; or,
d) Through the use of a disconnect switch on the PLC/DCS or at the equipment.
Where practicable, persons performing the work shall try to start the equipment via the field isolator or
PLC once the isolations are in place. This step is sometimes referred to as the ‘try’ step.
When carrying out work which involves cutting existing cables, the cable shall be treated as live until
positive tests proving the cable is de-energised can be made at the point where the cable is to be cut.
Opening of enclosures while circuits remain energised is often required to facilitate inspections,
troubleshooting and maintenance activities. However, consideration shall be given to the potential for
hazardous atmospheres. This shall be considered in the risk assessment for the task and a gas test shall
be conducted by a competent person for all such work in hazardous areas - as per WPCG-PRO-01 Work
Authorisation (Australia) and PRO4.5-0001-1-01 Permit to Work (NZ).
Opening of enclosures or cabinets where there is the presence of exposed voltage higher than 32Vac
shall only be permitted by qualified persons i.e. electrical engineer, electrical worker.
While there is low risk for a competent person when opening a panel to observe the status of wiring or to
inspect components as part of troubleshooting or maintenance activities, a safe approach distance of
500mm to exposed and live conductors shall be observed.
Placing hands or any part of the body within 500mm of live and exposed conductors shall be considered
live work and additional safeguards shall be in place to protect the person from direct or indirect contact
with energised conductors.
Working on live electrical equipment shall only be considered as a last resort and when an adequate risk
process has been undertaken and documented in accordance with the risk assessment for the task.
The recommended safe guards, as listed in section 5.4.2, should be identified on risk assessment for the
task.
When working in the vicinity of live exposed electrical conductors consideration shall be given to the
potential arc flash hazards and level of PPE required.
Note: electrical work on switchboards with fully enclosed busbar chassis assemblies with integrated
isolation switch for each individual tee-off is permitted provided that:
a) All the spare poles are isolated at the busbar,
b) The circuit or tee-off which is being worked on is isolated at the busbar, and
c) The circuits immediately adjacent the circuit being worked on are isolated at the busbar.
When working, testing or fault finding on energised electrical equipment, a fault current of up to 20 times
the rated current of the supply transformer can flow for short duration during fault conditions. Arcs that
are produced under these conditions have the energy to cause an explosion and/or melt metallic
switchboard cubicles. Arcs can cause severe burns to the skin and/or flash burns to the face and eyes.
Inhaled hot gases and molten particles can cause serious internal burns to the throat and lungs. Injury
can also occur through the impact from flying debris and dislodged components. Overcurrent circuit
protection may not operate in such circumstances.
For installations rated above 800A or where the fault currents exceed 2000A special precautions are
required.
2.4.2. Safeguards
When working on live electrical equipment the safeguards outlined in 5.4.2.1 through 5.4.2.8 (inclusive)
shall apply.
2.4.2.1. Assessment
Prior to commencing any work on live electrical equipment an assessment of the associated risks shall
be undertaken. This assessment shall include a consideration to the available fault current and the
requirement for appropriate PPE based on the arc flash hazard.
Where in the judgment of the person doing the work, it cannot be carried out safely without assistance or
a safety observer, that person shall be provided with the assistance required. If assistance is not
provided, work shall be delayed until isolation can be arranged.
When troubleshooting involves the use of approved test equipment and the measuring of voltages by
direct contact with exposed conductors exceeding 32Vac or 50Vdc the person undertaking the work shall
be supported by a safety observer of stand-by person.
2.4.2.3. Competency
Any persons undertaking work on live electrical equipment shall be skilled and competent in the work to
be carried out.
2.4.2.4. Precautions
The person responsible for authorising work to be carried out live shall specify any particular precautions
to be taken to eliminate hazards and to prevent injury.
Electrical workers and assisting personnel shall wear protective clothing suitable for the task when
working on, or in close proximity to, live (energised) electrical equipment.
a) PPE for Low Energy Installations:
1. The minimum PPE requirements that shall be followed for working in close
proximity to live low voltage exposed electrical equipment in low energy systems
are;
i. Safety glasses
ii. Long sleeve cotton shirt
iii. Long cotton pants
iv. Leather safety shoes
v. Leather gloves
Note: the above is the minimum PPE requirement for low voltage, low energy work.
2.4.2.6. Earthing
When working on live electrical equipment having earthed metal, precautions shall be taken to ensure
earthing continuity is maintained to any component part of the equipment at all times.
Bonding conductors may be required to be installed when removing electrical equipment from earthed
metal, e.g. live component part separated from its connected earthing medium. Bonding conductors
shall be rated to withstand the ‘let through’ energy of the primary protection without failing.
Particular care should be taken when removing neutral connections as tests may have indicated a de-
energised situation. However, when these connections are removed, a voltage may be present between
conductors or between conductors and earth.
Only conductors at one potential should be worked on at any one time and insulated barriers should be
utilised in the work area between conductors of different phases or voltage potentials.
Insulating mats or barriers should be used between electrical workers and conductors and between
electrical workers and earth including building structures such as concrete and steel which may be
earthed.
Isolation of power shall always be the first choice when undertaking electrical work.
However consideration shall be given that there may be instances when fault finding, commissioning or
testing is only possible while equipment is live and in these instances other safety precautions are
required to be taken.
The electrical worker shall be competent in the work being undertaken and be familiar with the
equipment involved and the safeguards for requirements for working on live electrical equipment shall
be applied.
All test equipment, including leads and probes, shall be suitable for its intended purpose and periodically
inspected to ensure that it remains operational and safe.
Before carrying out any tests, equipment shall be checked to ensure that it is correctly set, functional and
in good condition.
Testing equipment used for detecting a live (energised) source should undergo trial operation on a
known live circuit to prove that it is functioning correctly immediately before and after the test has taken
place.
Electrical test equipment (including test leads) used for direct contact on low voltage systems shall
comply with the requirements of AS 61010.1 or an equivalent standard and shall be a minimum of CAT
III 600V design.
Contact probes and leads shall be checked for damage to insulated parts, ensure continuity and verify
connections prior to use.
Insulation resistance testers shall be able to maintain a terminal voltage within +20% and -10% of the
nominal open-circuit terminal voltage, when measuring a resistance of 1 MOhm on the 500 V range or 10
MOhm on the1000 V range.
Voltage indicators such as high impedance volt meters shall only be used to verify the presence of a
voltage.
They shall not be used to verify the conductivity of a cable, as they will operate satisfactorily with high
resistances within the circuit under test.
Voltage indicating neon type devices shall not be used as the only means to verify the presence of a
voltage.
Test equipment that has the potential to generate a spark and is intended for use within a hazardous area
shall be certified for use within that hazardous area. If equipment is not hazardous area certified and has
a spark potential, the normal requirements of WPCG-PRO-01 Work Authorisation (in Australia) and PRO-
4.5-0001-1-01 Permit to Work (in New Zealand) shall be followed.
Neon or LED test ‘pencil’ devices, similar to those shown in Figure 3 below, requiring the user to form
part of the test circuit shall not be used as electrical test devices.
Electrically powered equipment shall be isolated, locked and tagged out from its power supply in
accordance with the requirements of this local procedure.
Diesel driven equipment shall be positively isolated by removal and tagging out of ignition key, securing
of electrical isolation switch and consideration to disconnection of the battery, which has its own risks of
generating sparks and damage to circuit boards.
Steam, hydraulic or pneumatic equipment shall be positively isolated from its energy source by positive
isolation of its motive force. Further isolation will depend on the type of equipment and may include pipe
and additional physical isolation.
Persons performing the work shall test the operation of equipment before work commences to ensure
effective isolation.
The following procedure should be followed to lock out / tag out any vehicle to conduct work on the
vehicle or any equipment on the vehicle;
a) Park the vehicle safely; if possible at the maintenance workshop.
b) Turn off the vehicle ignition, remove the vehicle keys and turn the master battery isolation
switch OFF.
c) Install a lock out tag on the steering wheel, with the fleet number of the vehicle, the date
and time and name and signature. If possible install a lock out tag on the master battery
isolation switch.
d) Inform all who may be affected.
e) Follow the isolation requirement in this procedureError! Reference source not found. to
undertake the necessary repair works.
f) The lock out tag shall only be removed by the maintenance fitter or the manager,
following repair work and test driving / operation has been conducted.
Plant isolations shall be approved by the Permit Officer (to approve the work as safe to do under the
isolation) and Site Representative (to approve any business operational impact) and executed by the
responsible person(s). All isolations shall be viewed and tested the isolations to confirm they are in
place prior to work under the isolation.
If the work is covered by a task breakdown the isolations shall be specified within the procedure.
The work area shall be clearly identified and cordoned off to ensure that there is no risk from traffic,
personnel not associated with the work, or other external sources.
Isolation of the highest quality and security which is reasonably practicable shall always be used.
Positive isolation shall be provided for all work other than cold work. Vessel Isolations (e.g. filter
changes) for routine, short duration, cold work which are not positive isolation shall be subject to a risk
assessment. This shall only be allowed where the work duration is short (less than four hours) and the
immediate work site shall not be left unattended.
Given the specific hazards of Confined Space Entry, LOTO Plans shall be risk assessed.
Isolations shall be made to prevent the accidental introduction into the confined space of materials,
through equipment such as piping, ducts, vents, drains, conveyors, service pipes or firefighting systems.
The method of isolation shall be by Positive Isolation. The preferred method of isolation is air gapping.
Isolations should be made as near as possible to the Confined Space to be entered. Where isolation at
the vessel cannot be achieved due to the size of a piping connection, or where piping connections are
welded to the vessel / equipment, the isolation should be made at the nearest available place to the
vessel / equipment. The interconnecting piping between the vessel / equipment then becomes an
integral part of the Confined Space and shall be taken into account when preparing for entry and issuing
Confined Space Entry Permits.
b) The effects of winds to create a low pressure area downwind of manways and other
openings which could result in an airflow and contaminants moving inside a vessel /
equipment in the reverse direction to that expected,
c) Connecting piping can contain harmful materials not removed from the systems during
purging and gas freeing, which can be subsequently released due to airflow and / or solar
heating, or Hot Work.
Positive isolation of all sources of energy is mandatory for confined space entry into tanks. Valves and/or
sections of pipe from each connecting pipeline including foam pipelines (where installed) shall be
removed from as near to the shell as possible and the open end of the pipelines shall be sealed with an
appropriately line rated blank flange.
All electrical connections other than extra low voltage equipment complying with AS/NZS 3000 Electrical
installations (known as the Wiring Rules) shall be positively isolated.
Potential energy sources shall also be discharged e.g. floating suctions, by landing these onto solid
supports.
2.7.5. Confined Space Entry Isolation (valve chambers and tank turrets)
Positive isolation of all external sources of energy is often not practically achievable for pipeline valve
chambers and tank turrets. The highest level of isolation practically achievable shall be determined in
the risk assessment with appropriate controls and monitoring of isolation detailed and response to the
loss or containment detailed in emergency response plans.
It is often not practically achievable to fully drain down and gas free pipework associated with aviation
refuelling vehicles. If entry into aviation vehicle compartments is required, pipework shall be
disconnected and isolated from compartments, pipework sealed and external vapour sources from
refuelling equipment controlled. The risk of vapour migration into vehicle confined spaces shall be
determined in the risk assessment with appropriate controls and monitoring of isolation detailed.
Equipment that has been removed from service for maintenance (whether routine or non-routine) shall
on completion of maintenance, be tested in service to confirm the integrity of the system. If this is not
possible at the time the maintenance is completed, then maintenance shall be deemed incomplete and
the equipment shall remain locked out / tagged out until testing in service can be undertaken.
On completion of the work, removal of locks and tags, de-isolation and recommissioning of the system
shall be performed with the same care as used during the isolation, locking and tagging. For example,
integrity testing of the point of isolation shall precede the removal of any blank flanges, swinging of
spectacle blinds or reinstatement of pipework to test for the presence of stored energy or product which
could be released.
Lockout locks and tags shall only be removed by the person who applied them.
Exceptions
Only under exceptional circumstances, locks and or tags may be removed by the site manager (authority
not to be delegated) according to the following procedure:
a) Verify that the person who placed the Lock and Tag is not on site.
b) Make all reasonable efforts to contact the person.
c) Ensure that the plant is in a safe and operable condition, by inspection by a competent
person.
d) Remove lockout and tag.
e) Re-commission plant.
f) Ensure that the person who applied the tag and lock is informed that the plant has been
returned to service and the documentation has been signed off by the site representative.
2.9. Commissioning
Equipment that has been removed from service for maintenance (whether routine or non-routine) shall
on completion of maintenance, be tested in service to confirm the integrity of the system. Pressure, leak
and functional testing of the reinstated system shall be performed as required for the equipment.
Particular care should be taken of electrically, pneumatically or hydraulically operated valves which may
open or close on reinstatement of the energy source. If this is not possible at the time the maintenance
is completed, then maintenance shall be deemed incomplete and the equipment shall remain locked out
/ tagged out until testing in service can be undertaken.
The roles and responsibilities associated with this procedure are listed in the following table.
Site Representative The Site Representative shall be the site manager or delegate, or if the
site is unmanned it may be the Permit Officer or Work Clearance Issuer.
The Site Representative is responsible for the overall safety of the site.
The Site Representative shall be aware of all planned operations of the
site that may interact with the work. Therefore no work shall be
undertaken before the Site Representative countersigns the work
authorisation. The Site Representative may stop or defer work at any
time.
Worker performing isolation Only performing isolations they are competent and authorised to
perform.
Completing isolations in accordance with bp and regulatory
requirements.
The key process steps outlined in this procedure are included in a Self-Verification Programme.
6. Associated Documents
7. External References
This This procedure was prepared with reference to relevant legislation/regulations including but not
limited to, relevant Acts, Regulations, AS/NZ Standards and industry codes and practices.
Details of current legislation/regulations can be provided by the HSE Team on request.
8. Version Summary.
9. Disclaimer
Page of
LOTO Plan Prepared by: Description of work:
Instructions
1 Review Site Procedure for the Isolation of Equipment (Lock Out / Tag Out).
2 Note lock out points in left column (attach P&ID or equipment drawing indicating isolation points).
3 Install Plant Locks at points outlined in left column.
4 Record lock number(s) beside corresponding lockout point.
5 Complete “Installed by” and “Date Installed”.
6 Confirm all isolations, locks and tags installed, and stored energy discharged.
7 Attach copies of LOTO PLAN to permit.
8 When locks are removed, complete “Removed by” and “Date Removed” columns.
9 Confirm all isolations, locks and tags removed and to confirm system integrity.
10 File completed copy of LOTO PLAN with completed Work Permit.
# Identification of Electrical Disconnect, Site lock Installed by: Date Removed Date
Valve, or other energy source to be Number: Installed: by: Removed:
Locked Out
Diagram
Isolation Both block valves are now closed, the bleed valve is open and all three are secured. Any
Summary fluid passing via the upstream valve is vented through the intermediate bleed valve and
no pressure builds up against the downstream valve.
Diagram
Diagram
Annex C - Tagging
All energy control devices (e.g. valves,) as well as plant and equipment which is isolated, shall have an
identification tag attached. For Lock Out Tag Out, “DANGER - DO NOT OPERATE” or equivalent tags
shall be used. Additional “Out of Service” or “Information” tags may be attached to equipment, but
these tags do not form part of the isolation for the protection of workers performing work under the
isolation.
NOTE: AS1319 specifies requirements for the design and use of safety signs.
End of Document