Financial & Physical Target
Financial & Physical Target
1.1.2 Establish, Equipment and run site L. Sum 1 1000000 1000000.00 272727.27 27.27
laboratory and provide test laboratory
equipment and service during construction
1.1.3 The contractor shall provide and maintain L. Sum 1 300000 300000.00 225000.00 75.00
temporary sheds for the storage of
materials, tools, and tackle and the use of
all persons employed on the Site. Those
1.1.4 Establishment of Contractor's offices, L. Sum 1 1000000 1000000.00 500000.00 50.00
stores, canteens and other facilities;
mobilization of equipment, plant and
manpower etc. and removal and
demobilization after completion of the
project
1.1.5 Insurance of works P. Sum 1 100000 100000.00 27272.73 27.27
1.1.7 Insurance covering liability for industrial P. Sum 1 100000 100000.00 27272.73 27.27
accidents etc
1.1.8 Insurance covering liability for P. Sum 1 100000 100000.00 27272.73 27.27
contractor's acts or omissions
1.1.9 Insurance for accident or injury to P. Sum 1 100000 100000.00 27272.73 27.27
workmen.
0.00
1.2 Services 0.00
1.2.1 The Contractor shall safeguard the works, Months 12 50000 600000.00 163636.36 27.27
materials and plant against damage, loss
or injury, including all necessary watching
and lighting for the safety and security of
the works
1.2.2 Provision and maintenance of safety P. Sum 1 100000 100000.00 33333.33 33.33
equipment for the engineer like safety
shoes, helmet, glove and any necessary
which ordered by the engineer
1.2.3 Provision of surveying equipment three Months 12 76500 918000.00 306000.00 33.33
total station and six leveling with
surveying team. The equipment to be used
shall be appropriate to the work and as per
the instruction of the Engineer
1.2.4 Provide survey control and setting out L. Sum 1 60000 60000.00 20000.00 33.33
work for construction.
1.2.5 Provide operation and maintenance data L. Sum 1 50000 50000.00 0.00 0.00
manuals
1.2.6 Provisional sum for miscellaneous work L. Sum 1 1000000 1000000.00 272727.27 27.27
ordered by the Engineer
1.2.7 Maintain office and equipment for Months 12 50000 600000.00 163636.36 27.27
supervisor's representative including
utilities and services
1.2.8 Accommodation and services for the P. Sum 1 14133455.4 14133455.44 10600091.58 75.00
engineer's staffs
1.2.9 Concrete and soil testing to be carried out L. Sum 1 100000 100000.00 27272.73 27.27
in accordance with the specification
1.2.10 Allow for supplying temporary electricity, Months 12 100000 1200000.00 400000.00 33.33
water and other utility bills for the
supervisor's office for the Works and
1.2.11 Provide,
facilities maintain and keepincluding
of the contractor in a clean Months 12 30000 360000.00 120000.00 33.33
condition adequate temporary sanitary
accommodation and facilities in
accordance with local regulations for all
1.3 Miscellaneous
1.3.1 Provide Geo-Technical investigation to L. Sum 1 680000 680000.00 680000.00 100.00
confirm design bearing capacity and soil
properties
1.3.2 Provide As-built drawings as specified Set 3 30000 90000.00 0.00 0.00
1.3.3 Day work as per the instruction of the P. Sum 1 1000000 1000000.00 333333.33 33.33
Engineer, detail of the day work schedule
is given in the appendix of the tender
document.
1.3.4 Provision of Security Months 12 50000 600000.00 200000.00 33.33
5.2 Drawn pipe 50mm diameter to hand rail m 679.28 200.00 135,855.00 -
2.5.2 Drawn pipe 50mm diameter to hand rail m 1,766.75 200.00 353,350.00 282,680.00 80.00 -
2.5.3 Steel plate for t=5mm m2 445.10 57.00 25,370.70 20,296.56 80.00 -
2.7 RID Protection Works 11,064,457.05 11,064,457.05 100.00 - -
1 Earth work
1.1 Excavation m3 11,087.44 149.00 1,652,029.04 1,652,029.04 100.00
1.2 Fill & Compacting m3 3,326.18 282.00 937,983.60 937,983.60 100.00
2 Main work -
2.1 50 thick concrete class C-10, m3 14.87 1,903.95 28,313.38 28,313.38 100.00
2.2 Masonry 400mm thick m3 1,247.19 2,000.00 2,494,383.90 2,494,383.90 100.00
Reinforcement concrete class RC-25 to
2.3 m3 1,342.58 2,936.70 3,942,740.14 3,942,740.14 100.00
drop wall, Basin
2.4 Wrought formwork m2 2,148.12 464.15 997,049.93 997,049.93 100.00
2.5 Reinforcement 10,12mm Diameter Kg 14,456.53 70.00 1,011,957.06 1,011,957.06 100.00
2.8 Clearing & Excavation for SMD 39,776,458.15 39,100,000.00 98.30 12,548,822.60 31.55
1 Site clearing m2 199,869.63 13.10 2,618,292.18 2,618,292.18 100.00 1,522,822.60 58.16
2 Excavation m3 249,383.66 149.00 37,158,165.97 36,481,707.82 98.18 11,026,000.00 29.67
2.9 Gates 73439798.00 0.00
25,050,065.92
3,682,788.75
45,808,661
8.04
0.71
155,043.38
46,296,512.88
0.334892134104939
46,296,512.88
229,468,885.44
5.53
5.56
155,043.38
Bill. No Activity Unit Contact Unit rate To date Plan To date Executed
Quantity
Physical % Physical %
1 General Item
2 Structures and associated
works
2.1 Cross Regulator & Head
Regulators (HR & CR )
1 Earth work
N1.1 Clearing & Stripping m2 3,032.19 13.10 3,032.19 1.00 - -
1.1 Excavation m3 46,563.94 149.00 33,526.40 0.72 722.19 1.55
1.2 Backfill & Compacting m3 14,994.93 282.00 11,083.67 0.74 - -
2 Structure Work
2.1 Stone Work
2.1.1 Stone Masonry wall m3 11,541.07 2,000.00 3,053.48 0.26 - -
2.1.2 Dry stone Riprap m3 1,487.98 705.70 469.70 0.32 - -
2.1.3 Spreading & compacting m3 1,045.95 727.50 547.04 0.52 - -
2.1.4 Pipe diameter Φ-50mm pvc m 115.07 108.85 - - - -
2.2 Form Work
Smooth finish form work Type "F3" m2
5,132.18 464.15 - - - -
1 Earth work
1.1 Clearing m2 27,393.95 13.10 26,217.96 0.96 15,691.92 57.28
1.2 Excavation m3 128,595.24 149.00 124,916.10 0.97 48,931.66 38.05
1.3 Fill & Compacting m3 49,758.28 282.00 30,397.61 0.61 -
2 Structure Work
2.1 Stone Work
2.1.1 Stone Masonry wall m3 6,611.38 2,000.00 5,017.86 0.76 133.87 2.02
2.1.2 Mixed sand & gravel bedding m3 2,532.23 727.50 1,846.55 0.73 25.01 0.99
2.1.3 Cemented stone pitching m3 5,553.30 1,226.27 1,096.82 0.20 - -
2.2 Form Work
Smooth finish form work Type "F3" m2
37,633.55 464.15 17,894.35 0.48 48.40 0.13
1 Earth work
1.1 Clearing and stripping m2 4,695.69 13.10 - - -
1.2 Excavate of ordinary soil m3 5,539.72 149.00 - - -
1.3 Provided, fill and compact selected m3
granular material 3,139.71 282.00 - - -
1.4 Fill the soil over the Slab m3 654.12 282.00 - - -
2 Structural works
2.1 Stone works
2.1.1 Stone Pinching works m3 1,883.82 1,226.27 - - -
2.1.2 stone masonry wall m3 3,366.00 2,000.00 - - -
2.2 Sand and gravel
2.2.1 Spreading and compacting m3 3,140.66 727.50 - - -
2.3 Form Work -
2.3.1 Smooth finish form work Type "F2" m2 7,623.86 464.15 - - -
2.4 Concrete Work
2.4.1 Reinforced concrete class C-30 m3 2,783.07 3,588.35 - - -
2.4.2 Reinforced concrete class C-25 m3 220.53 2,936.70 - - -
2.4.3 Blinding layer concrete class C-10, m3
100mm 93.38 1,903.95 - - -
2.4.4 Mass concrete class C-20 m3 65.00 2,936.70 - - -
2.4.5 Cyclopean Mass Concrete m3 1,257.95 3,588.35 - - -
2.4.6 Bituminous (t=20mm) Kg 409.67 50.00 - - -
2.5 Steel Work
5.1 Reinforcement steel bar kg 229,902.95 70.00 - - -
5.2 Drawn pipe 50mm diameter to hand rail m
679.28 200.00 - - -
5.3 Steel plate for t=5mm m2 12.12 57.00 - - -
5.4 Elastomeric Bearings as specified on the Nr
drawing 60.00 2,000.00 - - -
5.5 ∅100mm pvc weep holes m 81.30 450.00 - - -
5.6 Drainage pipes m 18.00 1,500.00 - - -
2.6 Community Bridge
1 Earth work
1.1 Excavate of ordinary soil m3 6,716.51 149.00 6,716.51 1.00 396.29 5.90
1.2 Provided, fill and compact selected m3
granular material 2,011.96 282.00 2,011.96 1.00 - -
2 Structural works -
2.1 Stone pitching works m3 5,762.33 1,226.27 5,762.33 1.00 49.85 0.87
2.2 Sand and gravel -
2.2.1 Spreading and compacting 200mm mixed m3
sand and gravel bedding 1,990.92 727.50 1,990.92 1.00 - -
2.3 Form Work -
2.3.1 Smooth finish form work Type "F2" m2 3,182.25 464.15 2,970.10 0.93 23.74 0.75
2.4 Concrete Work -
2.4.1 Reinforced concrete class C-30 to all m3
concrete as shown the drawing 1,988.90 3,588.35 1,532.44 0.77 - -
N2.4.1.1 CC-20 Mass Concrete m3 116.25 2,936.70 93.00 0.80 - -
N2.4.1.2 Blinding layer concrete class C-10, m3
100mm thick under reinforced concrete 47.25 1,903.95 37.80 0.80 6.28 13.29
2.4.4 Bituminous (t=20mm) Kg 2,910.60 50.00 2,910.60 1.00 - -
2.5 Steel Work -
2.5.1 Provide, cut, bend and fix in position kg
reinforcement steel bar between 8mm 190,704.70 68.70 190,704.70 1.00 8,083.18 4.24
and 32mm diameter to all concrete
2.5.2 Drawn pipe 50mm diameter to hand rail m
1,766.75 200.00 1,413.40 0.80 - -
2.5.3 Steel plate for t=5mm m2 445.10 57.00 356.08 0.80 - -
2.7 RID Protection Works
1 Earth work
1.1 Excavation m3 11,087.44 149.00 11,087.44 1.00 -
1.2 Fill & Compacting m3 3,326.18 282.00 3,326.18 1.00 -
2 Main work
2.1 50 thick concrete class C-10, m3 14.87 1,903.95 14.87 1.00 -
2.2 Masonry 400mm thick m3 1,247.19 2,000.00 1,247.19 1.00 -
2.3 Reinforcement concrete class RC-25 m3
to drop wall, Basin 1,342.58 2,936.70 1,342.58 1.00 -
3032.19
33526.40
11083.67
3053.48
469.70
547.04
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
4804.98
1646.11
0.00
0.00
906.19
251.71
230.94
0.00
128.57
0.00
70.20
40.99
39.42
3.98
0.00
0.00
33.00
56.42
12.54
0.00
367.31
5.35
12.61
26217.96
124916.10
30397.61
0.00
0.00
5017.86
1846.55
1096.82
0.00
17894.35
0.00
7072.75
899.49
576.68
928.74
15251.60
0.00
361812.37
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
6716.51
2011.96
5762.33
0.00
1990.92
2970.10
1532.44
93.00
37.80
2910.60
190704.70
1413.40
356.08
11087.44
3326.18
0.00
14.87
1247.19
1342.58
2148.12
14456.53
199869.63
244843.68
0.00
20
60
20
20
20
10
15
15
15
5
5
10
20
10
12 month
No Description Test /Work Test /work Specification
Planned Conducted Requirement
1 Surveying works
1.1 Checking of as-built BM 20 10
1.2 Bench Mark Establishment 42 36
1.3 Topographic Survey 40 12
1.4 Survey Setting Out 20 8
1.5 As-built Reading 20 8
Remark
Remark
Remark
Project Progress
TO DATE PLANNED TO DATE EXECUTED
44.40%
35.44%
26.58%
18.11%
10.68%
4.98% 4.61% 4.85% 5.53% 5.56%
3.48% 3.58%
0.25% 1.57%
0.09% 0.25%
0.09% 1.57%
0 Dec-20
4 -1 3
Arithmetic OMMITTE
BILL ADDITION TOTAL REVISED
DESCRIPTION CONTRACT D
NO. Err AMOUNT AMOUNT
AMOUNT
1 General Item 26,291,455 26,291,455
Structures and associated
2
works
Main canal Cross regulator
2.1 and Primary canal Head 75,861,024 75,861,024
regulator
Community Bridges on
2.5 5,161,573 27,592,054.00 32,753,627
RBMC
2.6 RID Protection Works 11,064,457.05 11,064,457.05
Clearing & excavation for
2.7 39,776,458.15 39,776,458.15
SMD
2.8 Gate 77,711,570 (4,271,772.00) 77,711,570
TOTAL TO SUMMARY OF
494,977,299 36,363,823.30 531,341,123
CONTRACT
CONTINGENCY 10% 49497729.899879 53134112.33
VAT 15%
GRAND TOTAL 544,475,028.90 584,475,235.67
27,592,054
3663967.27827501
45,730,554
(37.25)
77.74 0.00 0
19.7692219911971 0.00
55.11 0.00
51.38 0.00
0.00 0.00
94.20 0.00
0.00 0.00
Project
2020 - 2021
S.No. Description plan Total
No Apr May. Jun July Aug Sep Oct Nov Dec Jan Feb Mar Apr
I Management Product
M.1 Project Brief 1 1
M.2 Project Approach 1 1
M.3 Risk Log 10
M.4 Highlight Reports 10
M.5 Project Initiation Doc. 1 1
M.6 Project Board Records 10
M.7 Project Board Sign-offs 5
M.8 Project File 1 1
M.9 Design Revision Doc. 2
M.10 Payment Certificate 10
M.11 Correspondence 100 2 5 5 5 5 10 13 5 50
Borrow Area Investigation
M.12 10
Report
II Quality Products
Q.1 Site Request 100
Q.2 Work Permit 100
Q.3 Survey Report 40 6 6 6 6 2 4 30
Q.4 Lab Report 40 2 2 2 2 2 1 11
Q.5 Product Descriptions 2 1
Quality Review
Q.6 4
Documentation
Project Issues/Change
Q.7 10
Control