8B8000Confidential Internal - )مقيد (داخلي
BID FORM
PRICING ATTACHMENT "I"
Renovation of Emergyncy & control center aEOA(ECC)
RFQ No.6500000292
Item Breakdown Long Description Unit Qty Unit Price Total payment
1 Breakdown supply & install ceiling gypsum board EA 5 157,568.40 787,842.00 Lump Sum
2 Breakdown supply & apply paint wall with all accessories EA 5 16,558.40 82,792.00 Lump Sum
3 Breakdown supply & install wall wood cladding upon apoved drawing EA 5 19,286.60 96,433.00 Lump Sum
4 Breakdown supply & install all electical items ( ciling light - power & I.T. outlet ) LOT 5 156,330.60 781,653.00 Lump Sum
5 Breakdown Modify the duct with the new ceiling with all accessories EA 5 32,298.20 161,491.00 Lump Sum
6 Breakdown modify FIRE SYSTEM with the new ceiling EA 5 12,363.60 61,818.00 Lump Sum
7 Breakdown Provide and install of MEETING TABLES for 12 person AS PER SCOPE AND catalog EA 5 13,038.00 65,190.00 Unite rate
8 Breakdown Provide and install of SIDE TABLE AS PER SCOPE AND catalog EA 5 7,418.20 37,091.00 Unite rate
9 Breakdown Provide and install of SHELVES AS PER SCOPE AND catalog EA 5 4,945.60 24,728.00 Unite rate
10 Breakdown Provide and install of CARPET AS PER SCOPE AND catalog M2 275 337.19 92,727.00 Unite rate
11 Breakdown Provide and install of Chairs AS PER SCOPE AND catalog EA 90 1,303.80 117,342.00 Unite rate
Sub-Total 1 2,309,107
Total Amount 2,309,107.00
Name in print and Signature Bidder's
8B8000Classified as Confidential Internal by SEC - )الشركة السعودية للكهرباء مصنف مقيد (داخلي
8B8000Confidential Internal - )مقيد (داخلي
BID FORM
PRICING ATTACHMENT "I"
Renovation of Emergency & control center aEOA(ECC)
RFQ No.6500000292
Duration Manpower Total Total CONTINGENCI COST PROFIT TOTAL BID
Manpower No. Equip. Duration (days) Equip. rate Total Base Cost UNIT PRICE
Item Long Description Qty Unit Unit Price Total (month) Rate/month Manpower Equipment ES OVERHEAD MARGIN PRICE
4 months 100.00% 690,580.80 2.50% 2.50% 10.00%
1 supply & install ceiling gypsum board 5 EA 46,594.52 6.44% 44,484.62 594,000.00 685,079.15 17,126.98 17,126.98 68,507.91 157,568.40 787,842.00
Safety Signages and Barricades 1 LOT 2,500.00 2,500.00 15.00 120.00 300.00 540,000.00
Remove the existing ceiling tiles. 224.19 M2 15.00 3,362.85 5.00 120.00 90.00 54,000.00
Supply & apply paint with all Ceiling Gypsum Board 104.775 M2 35.00 3,667.12
Supply & install gypsum ceiling board with all accessories upon
approved design. (Comply with Fire Resistance Ratings as
required by UBC Codes. Provide materials, accessories and
systems listed by UL and have been tested and approved by UL
and according to ASTM E119 for type of construction shown- Fire
Rated Suspension System gypsum board painted wh-2101)
Supply & Install Ceiling Tiles 119.415 M2 170.00 20,300.55
Supply & Install Ceiling Gypsum Board 104.775 M2 160.00 16,764.00
2 supply & apply paint wall with all accessories 5 EA 36,830.40 5.09% 35,162.64 0.00 71,993.04 1,799.83 1,799.83 7,199.30 16,558.40 82,792.00
Removal of Existing Paint 306.92 M2 60.00 18,415.20 300.00 0.00
Surface Preparation & apply paint with all required material 306.92 M2 60.00 18,415.20
3 supply & install wall wood cladding upon apoved drawing 5 EA 42,898.40 5.93% 40,955.87 0.00 83,854.27 2,096.36 2,096.36 8,385.43 19,286.60 96,433.00
Supple & install all required in surface preparation, priming, and
painting, staining and applying finishes to surfaces scheduled in
this section and as shown on the drawings.
Supply & install wood wall cladding with all accessories upon
approved design (MDF with ebony veneer finish as per the 88.56 m2 140.00 12,398.40
approved sample (ebony 32+ dark; brown 17)
Comply wood with water proof as required Provide materials,
accessories and have been tested upon required
Gypsum wallboard shall be taped and floated 130 m2 100.00 13,000.00 300.00 0.00
Gypsum wallboard Painting 0 m2 70.00 0.00 300.00 0.00
Entrance Glass Door 5 nos 3,500.00 17,500.00 300.00 0.00
supply & install all electical items ( ceiling light - power & I.T.
4 outlet ) 5 EA 347,721.81 48.07% 331,976.21 0.00 679,698.01 16,992.45 16,992.45 67,969.80 156,330.60 781,653.00
Supply & install all light fixture with all required electrical work
upon approved design 300.00 0.00
Supply and installation lighting system with all required
accessories as per drawing designed 90.00 0.00
Specify & design lighting lumen requirement upon as per SEC
standard
Spot light - 4000K - Daylight - anti-glow 120 nos 150.00 18,000.00
60 x 60 cm LED - 4000K. 65 nos 350.00 22,652.21
LED hidden light - 4000K (strip Lights) 140 LM 10.00 1,400.00
Emergency Light 5 nos 350.00 1,750.00
Emergency Exit Light 5 nos 500.00 2,500.00
CU/XLPE/PVC 3Cx 16mm 452.2 LM 33.00 14,922.60
Electrical Conduits 452.2 LM 10.00 4,522.00
Provide and install all electrical outlets as per sec representative
requirements (Legrand grounded electrical outlets including data
outlets)
Pull data cables to the server room using Cat6A cable (IT and
Communication) 1000 LM 250.00 250,000.00
Floor Box (IT, Electrical and Telephone) 30 nos 850.00 25,500.00
Wall Sockets 40 nos 45.00 1,800.00
Data Outlet (wall) 20 nos 200.00 4,000.00
Installation of New Switches 15 nos 45.00 675.00
5 Modify the duct with the new ceiling with all accessories 5 EA 71,839.85 9.93% 68,586.79 0.00 140,426.64 3,510.67 3,510.67 14,042.66 32,298.20 161,491.00
Modify A/C Air Ducting with applicable insulation as required 77.66 m2 550.00 42,715.59 300.00 0.00
Supply & install A/C liner grill (supply – return) with all
accessories upon ceiling design 65 nos 450.00 29,124.26
6 modify FIRE SYSTEM with the new ceiling 5 EA 27,500.00 3.80% 26,254.74 0.00 53,754.74 1,343.87 1,343.87 5,375.47 12,363.60 61,818.00
Modify and relocate Fire Fighting & Fire Safety equipment’s as
required (Sprinkler System, smoke detector, flasher) 5 lot 4,000.00 20,000.00 300.00 0.00
Testing and commissioning 5 lot 1,500.00 7,500.00
Provide and install of MEETING TABLES for 12 person AS
7 PER SCOPE AND catalog 5 EA 29,000.00 4.01% 27,686.82 0.00 56,686.82 1,417.17 1,417.17 5,668.68 13,038.00 65,190.00
Provide and install a Conference table as per design in catalog
for 12 person for each ECC room 5 nos 5,800.00 29,000.00 0.00
Provide and install of SIDE TABLE AS PER SCOPE AND
8 catalog 5 EA 16,500.00 2.28% 15,752.84 0.00 32,252.84 806.32 806.32 3,225.28 7,418.20 37,091.00
Provide and install a complete set of table and upper and lower
side support cabinets according to the design, including all
accessories, cabinets and according to the approved design and 5 set 3,300.00 16,500.00 0.00
specifications.
Provide and install of SHELVES AS PER SCOPE AND
9 catalog 5 EA 11,000.00 1.52% 10,501.90 0.00 21,501.90 537.55 537.55 2,150.19 4,945.60 24,728.00
Provide and install storage shelves according to the approved
design and specifications. 5 ea 2,200.00 11,000.00 0.00
10 Provide and install of CARPET AS PER SCOPE AND catalog 275 M2 41,250.00 5.70% 39,382.11 0.00 80,632.11 2,015.80 2,015.80 8,063.21 337.19 92,727.00
Provide carpet as per specification and design in the catalog 275 m2 150.00 41,250.00 0.00
11 Provide and install of Chairs AS PER SCOPE AND catalog 90 EA 52,200.00 7.22% 49,836.27 0.00 102,036.27 2,550.91 2,550.91 10,203.63 1,303.80 117,342.00
Provide 18 Chaires for each ECC room as catalog specification 90 nos 580.00 52,200.00 0.00
Sub-Total 1
Total Amount 723,334.98 690,580.80 594,000.00 2,007,915.78 50,197.89 50,197.89 200,791.58 2,309,107.00
Name in print and Signature Bidder's
8B8000Classified as Confidential Internal by SEC - )الشركة السعودية للكهرباء مصنف مقيد (داخلي
CITY SITE Width (M)
1 DAMMAM Dammam Services Office 4
2 JUBAIL Northern Electricity Admin Bldg 5.7
3 JOUF AlJouf Electricity Admin Bldg 4.8
4 NORTHERN BORDER Northern Border Electricity Admin Bldg 5
5 ALHASSA Al-Ahsa Electricity Admin Bldg 7.8
27.3
Length (M) Height (M) Total Floor Area Total Wall Area Wall cladding Gypsum Wall
6 3 24 60 12 18
10 2.8 57 87.92 15.96 28
7.3 3 35.04 72.6 14.4 21.9
15 3 75 120 15 45
4.25 4 33.15 96.4 31.2 17
42.55 15.8 224.19 436.92 88.56 130
44.838
50
Lighting Fixtures (60 x
Diffuser Spotlight (every 1 meter) Sockets switches
60)
6 6 16 10 2
18 18 27.4 15.7 2
9 9 20.2 12.1 2
24 24 36 20 2
8 8 20.1 12.05 2
65 65
120 69.85 10
Total Duration
120
120
120
120
120
MANPOWER RATE AS PER MANPOWER RENTAL COMPANY
Manpower Rates Hourly Rate
1 Engineer 1 40
2 Foreman 1 27
3 Safety Officer 1 35
4 Electrician 1 22
5 Plumber 1 22
6 Welder 1 28
7 specialized manpower (Gypsum) 1 21
8 specialized manpower (Door Install 1 21
9 labor 1 13
10 Driver 1 16
Equipment Rate Hourly Rate
1 Manlift 1
2 Crane 1
3 Backhoe / excavator/ boom truck 1
4 Forklift 1
5 Scaffolding 1
6 Manual Compactor 1
7 Lugger bucket 1
8 Pneumatic air demolition compress 1
9 Welding Machine 1
10 Demolition Equipment 1
11 Concrete Cuting machine 1
12 Sand blasting equipment 1
13 Compressor machine 1
Accommodation
1 Manpower Accommodation 1
2 Service Vehicle 1
WER RENTAL COMPANY Quantity Duration
Daily Rate (Hours) Monthly Rate (Hours)
10.00 209.00
400.00 8,360.00 1 4
270.00 5,643.00 5 4
350.00 7,315.00 5 4
220.00 4,598.00 5 4
220.00 4,598.00 4
280.00 5,852.00 4
210.00 4,389.00 4
210.00 4,389.00 4
130.00 2,717.00 25 4
160.00 3,344.00 5 4
46
Daily Rate Monthly Rate
350.00
1,500.00
800.00
500.00
300.00
250.00
90.00
200.00
200.00
1,000.00
350.00
350.00
200.00
Monthly Rate
3,500.00 10 4
4,000.00 6 4
Total
Total
33,440.00
112,860.00
146,300.00
91,960.00
0.00
0.00
0.00
0.00
271,700.00
66,880.00
723,140.00
140,000.00
96,000.00
863,226.00
690,580.80