Evaluation of The Requirements For Battery Energy Storage System To Postpone The Investment of Distribution System
Evaluation of The Requirements For Battery Energy Storage System To Postpone The Investment of Distribution System
Translated by
by Google
Google
50 Phaholyothin Road, Chatuchak, Bangkok 10900, Thailand. Goal. 0-2797-0999 Ext. 1577
E-mail: 1 2
[email protected], [email protected]
Abstract—This paper proposes the application of the battery energy storage VSPPs to postpone the investment for the new distribution line construction
system (BESS) to be installed in the distribution system for the purpose of
and to improve the efficiency of electricity usage by allowing the BESS to
postponing the investment of the distribution reinforcement in the short term
power distribution planning. A case study of the distribution system including store excessive the power during the period of the generated power greater
the photovoltaic system and the BESS obtained from the Provincial Electricity than the power demand and to release the power to the power system during
Authority (PEA) is used to evaluate the requirements of the BESS to be installed in
the period of the generated power less than the power demand. By this
the distribution system by considering four types of loads which are household,
small enterprise, industry and other types. It reveals from the study that the installation of the
strategy, it is possible for PEA to accommodate in time with the increased
BESS can effectively extend the time of the new distribution line construction. number of connected
VSPPs.
I. INTRODUCTION and can store the large amount of energy but slow response and short life
time. Therefore, they are suitable for the provisional power supply in case of
At present, the global energy crisis and related issues become critically
the interruption of electricity. The differences between various types of
important Many current researches are focusing on energy management
batteries can be shown in Table I [3]. In this study, the lead-acid battery is
issues and smart grid technologies. Due to the continuously increasing of
chosen due to its general availability and inexpensive price. The installation
electricity demand and the promotion of renewable energy sources connected
of the battery into the power system with DG can extend the investment
to the power systems, many electric utilities are urged to pay more attention
period of the construction of the new distribution power system such as
to analyze, to design and to improve the existing power system suitable for
extending the investment period of changing to the larger sizes of the
the future change [1]. In Thailand, the Provincial Electricity Authority (PEA)
distribution feeders by which the battery will store the excessive power during
is one of the authorized bureaus realizing the importance of the smart grid.
the light load and release the power to the power system during the peak
Recently, PEA constantly endeavors to adopt the smart grid by creating the
load [4].
PEA smart grid roadmap having the implementation project for 15 years [2].
In the first period (2012-2017), there are many pilot projects such as the
smart grid development, the smart meter installation, the microgrid
TABLE I
development and the connecting plan of very small power producers (VSPPs).
THE PROPERTIES OF EACH TYPE OF BATTERIES.
Being focused on VSPPs, PEA needs to plan for extendable distribution
Battery Rated Power Price Life Time Efficiency
systems in order to accommodate the increased power generated from
VSPPs in the future satisfying both funding and the installation setup period Types (kW) (USD/kWh) (Times) (%)
for long term and short term. Lead Acid 1– 50,000 13 1,500 85
MW
978-1-4799-0545-4/13/$31.00©2013IEEE
Authorized licensed use limited to: CONACYT NATIONAL COUNCIL OF SCIENCE AND TECHNOLOGY. Downloaded on January 12, 2025 at 21:40:09 UTC from IEEE Xplore. Restrictions apply.
Machine Translated
Translated by
by Google
Google
This paper considers the energy consumption of the electricity It can be noticed that the equation does not depend on the
customers by using the demand forecast in the PEA small area load temperature as in the two previous cases.
forecast in order to comply with the short term distribution planning in four D. Other type
years [5]. The loads of electricity customers can be divided into four types The simulation model of this type of user can be expressed
ace:
as follows: 1) household, 2) small enterprise, 3) industry and 4) other type.
yy++=ÿ ÿ ÿ11 ttt
and
(3)
++= + + + ÿt
and
Tty 13412312max,1 and t and you
and
and you
and
and yt and
(1)
IV. SAMPLE SYSTEM
Where The distribution system shown in Fig. 1 is used for the evaluation. This
th
ty is the power demand in the t month, power system consists of the following
th
components:
t Tmax, is the average maximum temperature in t
month,
PV1 PV2
and is the constant that can be calculated from:
22 kV
( m 1 +ÿÿ121121 ,
ÿÿÿÿ ÿÿÿÿ ÿ ÿÿ 1
) substation
0
es
and
3
12 , Fig. 1. A study distribution system.
and
4
is ÿ 121 ,
A. Distribution system
and
t is the tolerance error of the simulation model.
The grid power can be calculated from the following
C. Industry
The simulation model of this type of electricity customers can be
Where
expressed as:
Authorized licensed use limited to: CONACYT NATIONAL COUNCIL OF SCIENCE AND TECHNOLOGY. Downloaded on January 12, 2025 at 21:40:09 UTC from IEEE Xplore. Restrictions apply.
Machine Translated
Translated by
by Google
Google
construction of the PV power plant has the capacity from 1,000 kW to However, if the PEA decides to construct the new distribution line
8,000 kW. Fig. 2 shows the PV power profile based on the forecasting
to solve the problem of excessive power that is the new construction of
result.
the 2nd circuit on the same pole, the cost will be 43,333 USD/circuit
km. If the line length is 18 km, the total cost will be 780,000 USD and it
requires one year for the construction. On the other hand, if the BESS
8,000
7,000 is adopted instead, in 2012-2015, the size of 3,500 kWh having the cost
6,000 of 45,500 USD can be used to solve the same problem in the short
5,000
term. Therefore, the adoption of the BESS is cheaper
kW4,000
3,000
2,000
than the new construction of the new distribution line. Table II
1,000
summarizes the evaluation results of the power and energy required for
0 h
BESS.
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
00:00
01:00
02:00
03:00
04:00
05:00
06:00
07:00
08:00
09:00
20:00
21:00
22:00
23:00
24:00
500
Fig. 2. PV power profile.
400
The load analysis of the 5th feeder of the Pattaya substation is 200
carried out and is adjusted according to the load growth in the central 100
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
00:00
01:00
02:00
03:00
04:00
05:00
06:00
07:00
08:00
09:00
20:00
21:00
22:00
23:00
24:00
plotted as shown in Fig. 3-6. 2012 2013 2014 2015
to solve the problem of over ratting of the distribution lines in short term 250
h
From the PEA's planning criteria, it is found that the 22- 0
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
01:00
02:00
03:00
04:00
05:00
06:00
07:00
08:00
09:00
20:00
21:00
22:00
23:00
24:00
power up to 16,000 kW. From Fig. 7, it is obvious that in 2014, 10:00 2012 2013 2014 2015
am-11:00 am, 1:00 pm-2:00 pm, and 3:00 pm-4:00 pm, the distribution
Fig. 4. The forecasting load profile for small enterprise customers.
line must be able to accommodate
Authorized licensed use limited to: CONACYT NATIONAL COUNCIL OF SCIENCE AND TECHNOLOGY. Downloaded on January 12, 2025 at 21:40:09 UTC from IEEE Xplore. Restrictions apply.
Machine Translated
Translated by
by Google
Google
TABLE II
2,000
THE EVALUATION RESULTS OF POWER AND ENERGY REQUIRED FOR BESS.
1,800
1,600
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
00:00
01:00
02:00
03:00
04:00
05:00
06:00
07:00
08:00
09:00
20:00
21:00
22:00
23:00
24:00
1,196 3,536
VI. CONCLUSIONS
expensive solution since the excessive power may occur only in 1-6 hours in a
300 day. The installation of the BESS can be used to postpone the new distribution line
construction so as to solve the short term planning problem and save the cost of
250
investment. However, this paper does not consider the optimal location of the
200
installation of the BESS.
kW150
100
Finally, in order to bring the analysis results more complete, the future work should
50
be done by considering the optimal location and the power flow analysis for all
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
00:00
01:00
02:00
03:00
04:00
05:00
06:00
07:00
08:00
09:00
20:00
21:00
22:00
23:00
24:00
package.
REFERENCES
Fig. 6. The forecasting of load profile for other types of customers. [1] Z. Xue-song, C. Li-qiang and M. You-jie, "Research on smart grid technology", Proc. of the
2010 International Conference on Computer Application and System Modeling (ICCASM),
vol.3, pp. 599-603, Oct. 22-24, 2010.
20,000
[2] Website: http://www.pea.co.th, "PEA smart grid roadmap", 2012.
18,000
16,000 [3] H. Liang, M. Fan, J. Li, "Research on optimal configuration for combined
14,000
storage in microgrid", Proc. of CIGRE 2011 Bologna Symposium, 13
12,000
10,000 Sep. 2011.
kW 8,000
[4] A. Oudalov, D.Chartouni, C. Ohler, G.Linhofer, "Value analysis of
6,000
4,000 battery energy storage applications in power systems", Proc. of Power
2,000
Systems Conference and Exposition (PSCE'06), pp. 2206-2211,
0 h
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
01:00
02:00
03:00
04:00
05:00
06:00
07:00
08:00
09:00
20:00
21:00
22:00
23:00
24:00
2012 2013 2014 2015 [5] Technical Report, "Study on small area load forecast", Provincial
Authorized licensed use limited to: CONACYT NATIONAL COUNCIL OF SCIENCE AND TECHNOLOGY. Downloaded on January 12, 2025 at 21:40:09 UTC from IEEE Xplore. Restrictions apply.