TFC-OT3 (DS6) Project Execution Schedule - Rev.00
TFC-OT3 (DS6) Project Execution Schedule - Rev.00
Activity ID Activity Name Original Start Finish December 2022 January 2023 February 2023 March 2023
Duration 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26
OT3 Temporary Construction Facilities Construction Work (TCF) 96 15-Dec-22 20-Mar-23 20-Mar-23, OT3 Temporary Constructi on Facil ities C onstruction Work (TCF)
MOT3.1015 Agreement with local tribes 20 15-Dec-22 03-Jan-23 Agreement with local tribes
MOT3.1025 HSE Training & Issuance of Gate Pass 10 04-Jan-23 13-Jan-23 HSE Training & Issuance of Gate Pass
MOT3.1035 Method of Statement Submission and approval 10 04-Jan-23 13-Jan-23 Method of Statement Submission and approval
COT3.1420 Precast ConcreteT-Wall instal ation 7 22-Jan-23 28-Jan-23 Precast ConcreteT-Wall instal ation
Septic Tank and Soak Aw ay Pit 2mx2m x 1.5m 18 29-Jan-23 15-Feb-23 15-Feb-23, Septic Tank and Soak Away Pit 2m x2m x 1.5m
COT3.1440 Concrete works for base 4 31-Jan-23 03-Feb-23 Concrete works for base
COT3.1450 Brickwall works for walls 4 04-Feb-23 07-Feb-23 Brickwall works for walls
COT3.1470 Cement plastering all around 3 08-Feb-23 10-Feb-23 Cement plastering all around
COT3.1650 Concret cover with 3m ht ventline. 5 11-Feb-23 15-Feb-23 Concret cover with 3m ht ventline.
COT3.1480 Porta Cabins for EMIL Team installation 6 10-Mar-23* 15-Mar-23 Porta Cabins for EMIL Team installation
COT3.1490 Porta Cabins for Pantry/Meeting Room installation 6 10-Mar-23 15-Mar-23 Porta Cabins for Pantry/Meeting Room installation
COT3.1510 Driver Rest Room/Prayer Room installation 6 10-Mar-23 15-Mar-23 Driver Rest Room/Prayer Room installation
COT3.1520 Leveling and compaction for the soil 3 29-Jan-23 31-Jan-23 Leveling and compaction for the soil
COT3.1530 Rebar, Formwork and Concrete Pouring for Foundation 7 01-Feb-23 07-Feb-23 Rebar, Formwork and Concrete Pouring for Foundation
COT3.1540 Leveling and compaction for the soil 3 18-Feb-23 20-Feb-23 Leveling and compaction for the soil
COT3.1570 Rebar, Formwork and Concrete Pouring for Foundation 5 21-Feb-23 25-Feb-23 Rebar, Formwork and Concrete Pouring for Foundation
COT3.1550 Leveling and compaction for the soil 3 18-Feb-23 20-Feb-23 Leveling and compaction for the soil
COT3.1560 Concrete pouring for the warehouse 7 21-Feb-23 27-Feb-23 Concrete pouring for the warehouse
COT3.1640 Leveling and compaction for the soil 5 18-Feb-23 22-Feb-23 Leveling and compaction for the soil
COT3.1670 Leveling and compaction for the subgarde 7 23-Feb-23 01-Mar-23 Leveling and compaction for the subgarde
COT3.1680 Subbase filling and compaction 7 28-Feb-23 06-Mar-23 Subbase filling and compaction
EOT3.1080 Power cables Laying, Terminati on and Testing 24 20-Feb-23* 15-Mar-23 Power cables Laying, Terminati on and Testing
EOT3.1090 Diesel Generator Installation and Termination 7 25-Feb-23 03-Mar-23 Diesel Generator Installation and Termination
EOT3.1100 Power Distribution Panel Installation and Termination 12 25-Feb-23 08-Mar-23 Power Distribution Panel Installation and Termination
EOT3.1110 Switch over panel installation Installation and Termination 12 25-Feb-23 08-Mar-23 Switch over panel installation Installation and Termination
EOT3.1120 Street Light Panel Installation and Termination 7 09-Mar-23 15-Mar-23 Street Light Panel Installation and Termination
MOT3.1060 Piping works (Water Supply and Drainage System) 15 23-Feb-23 09-Mar-23 Piping works (Water Supply and Drainage System)
MOT3.1090 Oil Pump Installation,Tightening & Assembly 8 02-Mar-23 09-Mar-23 Oil Pump Installation,Tightening & Assembly
MOT3.1100 Water Pump Installation, Tightening & Assembly 6 10-Mar-23 15-Mar-23 Water Pump Installation, Tightening & Assembly