TFC-OT3 (DS6) Project Execution Schedule - Rev.00

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views1 page

TFC-OT3 (DS6) Project Execution Schedule - Rev.00

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

OT3 Temporary Construction Facilities Construction Work (TCF)

Activity ID Activity Name Original Start Finish December 2022 January 2023 February 2023 March 2023
Duration 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26

OT3 Temporary Construction Facilities Construction Work (TCF) 96 15-Dec-22 20-Mar-23 20-Mar-23, OT3 Temporary Constructi on Facil ities C onstruction Work (TCF)

Project Milestone 96 15-Dec-22 20-Mar-23 20-Mar-23, Project Milestone

M1000 Contract Effective 0 15-Dec-22* Contract Effective

M1010 Mobilization Completion 0 14-Jan-23 Mobilization Completion

M1020 Civil Works Completion 0 11-Mar-23 Civil Works Completion

M1040 Completion of TCF works 0 18-Mar-23 Completion of TCF works

M1060 Handover 0 20-Mar-23 Handover

Construction 91 15-Dec-22 15-Mar-23 15-Mar-23, Construction

Oil Train 3 (OT3) 91 15-Dec-22 15-Mar-23 15-Mar-23, Oil Train 3 (OT3)

Preparation Works 31 15-Dec-22 14-Jan-23 14-Jan-23, Preparation Works

MOT3.1015 Agreement with local tribes 20 15-Dec-22 03-Jan-23 Agreement with local tribes

MOT3.1020 Manpower Mobilization 10 04-Jan-23 13-Jan-23 Manpower Mobilization

MOT3.1025 HSE Training & Issuance of Gate Pass 10 04-Jan-23 13-Jan-23 HSE Training & Issuance of Gate Pass

MOT3.1030 Mobilization of Equipment 4 11-Jan-23 14-Jan-23 Mobilization of Equipment

MOT3.1035 Method of Statement Submission and approval 10 04-Jan-23 13-Jan-23 Method of Statement Submission and approval

MOT3.1040 Survey work 4 11-Jan-23 14-Jan-23 Survey work

MOT3.1045 Site Mobilization 4 11-Jan-23 14-Jan-23 Site Mobilization

Civil Works 60 15-Jan-23 15-Mar-23 15-Mar-23, Civil Works

Site Grading 7 15-Jan-23 21-Jan-23 21-Jan-23, Site Grading

COT3.1350 Site Grading 7 15-Jan-23 21-Jan-23 Site Grading

Boundary Ditch 9 22-Jan-23 30-Jan-23 30-Jan-23, Boundary Ditch

COT3.1360 Excavation 7 22-Jan-23 28-Jan-23 Excavation

COT3.1370 Side Slopes Preparation 7 24-Jan-23 30-Jan-23 Side Slopes Preparation

Soil Embankment 10 31-Jan-23 09-Feb-23 09-Feb-23, Soil Embankment

COT3.1380 Soil Embankment 10 31-Jan-23 09-Feb-23 Soil Embankment

Fence & Gate 25 29-Jan-23 22-Feb-23 22-Feb-23, Fence & Gate

COT3.1390 Fence Foundation 10 29-Jan-23 07-Feb-23 Fence Foundation

COT3.1400 Fence Installation 15 03-Feb-23 17-Feb-23 Fence Installation

COT3.1410 Gate Installation 5 18-Feb-23 22-Feb-23 Gate Installation

T-Wall 7 22-Jan-23 28-Jan-23 28-Jan-23, T-Wall

COT3.1420 Precast ConcreteT-Wall instal ation 7 22-Jan-23 28-Jan-23 Precast ConcreteT-Wall instal ation

Septic Tank and Soak Aw ay Pit 2mx2m x 1.5m 18 29-Jan-23 15-Feb-23 15-Feb-23, Septic Tank and Soak Away Pit 2m x2m x 1.5m

COT3.1430 Excavation 2 29-Jan-23 30-Jan-23 Excavation

COT3.1440 Concrete works for base 4 31-Jan-23 03-Feb-23 Concrete works for base

COT3.1450 Brickwall works for walls 4 04-Feb-23 07-Feb-23 Brickwall works for walls

COT3.1470 Cement plastering all around 3 08-Feb-23 10-Feb-23 Cement plastering all around

COT3.1650 Concret cover with 3m ht ventline. 5 11-Feb-23 15-Feb-23 Concret cover with 3m ht ventline.

Porta Cabins 46 29-Jan-23 15-Mar-23 15-Mar-23, Porta Cabins

COT3.1460 Cabins Supporter works 20 29-Jan-23 17-Feb-23 Cabins Supporter works

COT3.1480 Porta Cabins for EMIL Team installation 6 10-Mar-23* 15-Mar-23 Porta Cabins for EMIL Team installation

COT3.1490 Porta Cabins for Pantry/Meeting Room installation 6 10-Mar-23 15-Mar-23 Porta Cabins for Pantry/Meeting Room installation

COT3.1500 Wash/Toilets installation 6 10-Mar-23 15-Mar-23 Wash/Toilets installation

COT3.1510 Driver Rest Room/Prayer Room installation 6 10-Mar-23 15-Mar-23 Driver Rest Room/Prayer Room installation

Watch Tower 20 29-Jan-23 17-Feb-23 17-Feb-23, Watch Tower

COT3.1520 Leveling and compaction for the soil 3 29-Jan-23 31-Jan-23 Leveling and compaction for the soil

COT3.1530 Rebar, Formwork and Concrete Pouring for Foundation 7 01-Feb-23 07-Feb-23 Rebar, Formwork and Concrete Pouring for Foundation

COT3.1580 Watch Tower Installation 10 08-Feb-23 17-Feb-23 Watch Tower Installation

Tank Foundation 8 18-Feb-23 25-Feb-23 25-Feb-23, Tank Foundation

COT3.1540 Leveling and compaction for the soil 3 18-Feb-23 20-Feb-23 Leveling and compaction for the soil

COT3.1570 Rebar, Formwork and Concrete Pouring for Foundation 5 21-Feb-23 25-Feb-23 Rebar, Formwork and Concrete Pouring for Foundation

Warehouse 15 18-Feb-23 04-Mar-23 04-Mar-23, Warehouse

COT3.1550 Leveling and compaction for the soil 3 18-Feb-23 20-Feb-23 Leveling and compaction for the soil

COT3.1560 Concrete pouring for the warehouse 7 21-Feb-23 27-Feb-23 Concrete pouring for the warehouse

COT3.1630 Containers installation 5 28-Feb-23 04-Mar-23 Containers installation

Shelters 22 29-Jan-23 19-Feb-23 19-Feb-23, Shelters

COT3.1600 Shelters Foundation 7 29-Jan-23 04-Feb-23 Shelters Foundation

COT3.1610 Smoker Shelter Installation 15 05-Feb-23 19-Feb-23 Smoker Shelter Installation

COT3.1620 Generator shelter Installation 15 05-Feb-23 19-Feb-23 Generator shelter Installation

Pavement 13 18-Feb-23 02-Mar-23 02-Mar-23, Pavement

COT3.1640 Leveling and compaction for the soil 5 18-Feb-23 22-Feb-23 Leveling and compaction for the soil

COT3.1660 Concrete Pavement 10 21-Feb-23 02-Mar-23 Concrete Pavement

Road 17 23-Feb-23 11-Mar-23 11-Mar-23, Road

COT3.1670 Leveling and compaction for the subgarde 7 23-Feb-23 01-Mar-23 Leveling and compaction for the subgarde

COT3.1680 Subbase filling and compaction 7 28-Feb-23 06-Mar-23 Subbase filling and compaction

COT3.1690 Gravel Filling 7 05-Mar-23 11-Mar-23 Gravel Filling

Lamp Pole 5 03-Mar-23 07-Mar-23 07-Mar-23, Lamp Pole

COT3.1590 Lamp Pole Foundation 5 03-Mar-23 07-Mar-23 Lamp Pole Foundation

Electrical System 26 18-Feb-23 15-Mar-23 15-Mar-23, Electrical System

EOT3.1070 Earthing System Installation 7 18-Feb-23 24-Feb-23 Earthing System Installation

EOT3.1080 Power cables Laying, Terminati on and Testing 24 20-Feb-23* 15-Mar-23 Power cables Laying, Terminati on and Testing

EOT3.1090 Diesel Generator Installation and Termination 7 25-Feb-23 03-Mar-23 Diesel Generator Installation and Termination

EOT3.1100 Power Distribution Panel Installation and Termination 12 25-Feb-23 08-Mar-23 Power Distribution Panel Installation and Termination

EOT3.1110 Switch over panel installation Installation and Termination 12 25-Feb-23 08-Mar-23 Switch over panel installation Installation and Termination

EOT3.1120 Street Light Panel Installation and Termination 7 09-Mar-23 15-Mar-23 Street Light Panel Installation and Termination

Mechanical Works 24 20-Feb-23 15-Mar-23 15-Mar-23, Mechanical Works

MOT3.1060 Piping works (Water Supply and Drainage System) 15 23-Feb-23 09-Mar-23 Piping works (Water Supply and Drainage System)

MOT3.1070 Diesel Tank Installation 10 20-Feb-23* 01-Mar-23 Diesel Tank Installation

MOT3.1080 Water Tank Installation 10 02-Mar-23 11-Mar-23 Water Tank Installation

MOT3.1090 Oil Pump Installation,Tightening & Assembly 8 02-Mar-23 09-Mar-23 Oil Pump Installation,Tightening & Assembly

MOT3.1100 Water Pump Installation, Tightening & Assembly 6 10-Mar-23 15-Mar-23 Water Pump Installation, Tightening & Assembly

Commissioning 5 16-Mar-23 20-Mar-23 20-Mar-23, Commissioning

COMOT3.1000 Provisional Acceptance 3 16-Mar-23 18-Mar-23 Provisional Acceptance

COMOT3.1010 Handover 2 19-Mar-23 20-Mar-23 Handover

Actual Work Critical Remaining Work Summary Page 1 of 1


Remaining Work Milestone