An Analytical Technique For Failure Analysis and Reliability Assessment of Grid Daily Outage Performance in Distributed Power System
An Analytical Technique For Failure Analysis and Reliability Assessment of Grid Daily Outage Performance in Distributed Power System
Corresponding Author:
Jacob Kehinde Ogunjuyigbe
Department of Electrical and Electronic Engineering, University of Abuja
Federal Capital Territory (F.C.T.), Abuja, Nigeria
Email: [email protected]
1. INTRODUCTION
The power system network is vulnerable to random faults caused by component failure,
transmission problems, and weather conditions. As a result, the critical task of a power network is to supply
energy to customers in a cost-effective and reliable approach, even when exposed to random faults. The
analysis of power system reliability usually considers several functional zones, including the Transmission
network, generation network, distribution network, interconnected system, industrial systems, protection
systems, and commercial systems [1]. Thus, system reliability can be expressed as the probability of a
component executing a given task satisfactorily in the designated operational circumstances over time [2].
One of the methods for ensuring that a distribution network can consistently provide uninterrupted power for
consumers is reliability evaluation. This is especially necessary because the power system is complicated and
made up of many parts of machinery and equipment that are prone to malfunction while being used in the
system, resulting in significant financial losses for the nation [3], [4]. About 80% of power outage failures,
according to experts, are caused by the equipment and components of the distribution system [5], [6]. The
two major techniques used in reliability distribution network analysis are Analytical methods and simulation
(Monte Carlo) methods. The analytical method deals with statistical distributions of failure rate and time
required to restore it to normal service conditions. The Monte Carlo method usually requires much time due
to the large inference number needed to converge to precise outcomes. The analytical method applied failure
modes assessment, parallel, and series networks methods for the reliability indices evaluation [6].
Franklin and Gabriel [7] assessed the dependability of Nigeria's power distribution system by
conducting a monthly evaluation of the Ekpoma Network feeders in Edo State from January to December
2012, using feeder load data acquired from the power holding company of Nigeria (PHCN). Their studies
indicated that daily feeder failures were caused by intermittent electrical problems in the distribution system.
Uhunmwangho and Eseosa [8] applied the NEPLAN software to forecast the Port Harcourt distribution
systems reliability through the data collected from the PHCN for the Choba distribution network and
discovered that the use of NEPLAN revealed much about the network's performance and made predicting
easierfor the potential outages in the system. The study also found it difficult to get critical data for network
research and advised that the Utility guarantee complete recording of all data (operational and maintenance)
to improve research in the Port Harcourt power distribution network. Adefarati et al. [9] examined the
various subsystem components of the Ayede 330/132 KV injection substation, which supply the Jericho,
Ijebu ode, Ibadan North, Sagamu, Ayede, and Iseyin substations, and discovered that the substation's
reliability can be increased by lowering the component failure rate and improving the mean time between
failures (MTBF). Ogheneovo [10] compared the reliability of the Onitsha distribution network between 2009
and 2011 before and after the installation of some photovoltaic (PV) systems at the injection substations
using ETAP software. Researcher found that the PV system's inclusion significantly improved the
substation's performance and the utility's revenue.
Gazijahani and Salehi [11] developed dynamic reconfiguration and incentive-based demand
response to determine the cost-reliability using the exchange market algorithm (EMA). Ghiasi et al. [12]
focused on the management risk of metro structures for economic assessment and risk evaluation in
transmission network problem expansion using the probability technique. Hu et al. [13] classified outage
time load points from 4 types to 7 types and identified different types of corresponding reliability parameters.
Rocha et al. [14] analyzed reliability for the distribution networks that involved islanding dynamics using
Non-sequential Carlo Monte models and stability transient simulation with a complete synchronous machine
model which includes a voltage regulator and speed. Šnipas et al. [15] applied a stochastic automatic network
to evaluate the reliability and failure rate of power system substations. The [16], [17] applied novel prediction
models that focus on hybrid engine forecasts for energy cost and energy not used. Gazijahani and Salehi [18]
developed an integrated technique that depends on time rate smart demand response operation and distributed
heterogeneous energy sources for multi-microgrids-oriented reliability planning.
Teera-achariyakul and Rerkpreedapong [19] proposed a technique to determine the failure rate time
variation of each feeder's future interruptions using customer interruption time, interruption energy rates, and
total service areas KVA. The game theory method is applied to balance preventive maintenance costs and the
importance of reliability enhancement. Mirhosseini et al. [20] developed an analytical novel method for the
distribution network through the development of a new reliability-weighted cumulative diagnostic factor.
Abbasghorbani et al. [21] developed reliability-centered maintenance for power system networks through the
preventive maintenance mechanism. The application of the proposed technique was validated in the
Khorasan substation transmission network of Iran. Mahdavi et al. [22] determined the importance of
maintenance in the expansion of the generation-transmission network considering the generation and
transmission reliability. The research focuses on generation and transmission expansion, reliability
availability, and failure rate with network maintenance. The optimal value of a cooling tower's functional
availability in a steam turbine generator was predicted by Kumar et al. [23] using metaheuristic algorithms.
In order to estimate the availability of the hydroelectric generator, Maan et al. [24] used an adaptive neural
fuzzy inference system. The configuration is made of four elements which comprise hydropower systems:
turbine, turbine governor, generator converter, and generator. The system's availability is also affected by
human error and the lack of water, which are connected in series. Kumar et al. [25] developed an effective
stochastic model for generators through the principles of cold reserve reliability, geometrically dispersed
failure, and maintenance guidelines.
In automatic distribution grids with potential customer outage cost estimation in the presence of DG
units, the authors of the paper [26] presented a reliability optimization method. Gazijahani and Salehi [27]
presented a reliability survey for electrical energy systems. An evolution economic algorithm (EMA) was
employed to solve the suggested cost-reliability-based framework in Ghiasi et al. [28], which proposes a unified
An analytical technique for failure analysis and reliability assessment … (Jacob Kehinde Ogunjuyigbe)
1854 ISSN: 2088-8694
incentive-based demand-management (DR) and adaptive reconfiguration approach. Jayappa et al. [29] address
risk management in metropolitan structures, which offered a probabilistic method of evaluating risks and
assessing the economics of transmission network development planning issues.
Whenever a fault occurs in a distribution line, it is important to act quickly, isolate the fault part,
allow the operation of non-fault parts, and minimize the area of the power outage. The combination of
recloser and switch devices may successfully isolate more than 95% of the fault area, improving not only the
social and economic but also the dependability of the power supply and establishing the groundwork for
distribution automation.
This research paper applied the analytical model method in the assessment of the reliability of the
APO 132/33 KV power substation in Abuja, Nigeria through the historical data collected from the APO
substation from 2009 to 2018. To increase the value of system average interruption duration index (SAIDI),
system average interruption frequency index (SAIFI), customer average interruption duration (CAIDI), and
average service availability index (ASAI) of the substation, there is a need to apply interconnections between
different feeders through proper configuration of switches or reclosers, to reduce failure occurrence in the
network which other researcher in literature did not considered. Also, the paper recommends a proper control
mechanism to monitor the state of MTBF and downtime for reliability and availability improvement in the
network. Artificial intelligence is also recommended to ascertain the effectiveness of the network.
2. METHOD
The study analyzed the reliability of the APO 132/33 KV substation in the Abuja electricity
distribution network between January 2009 to December 2018 using the probability distribution models. The
substation has two incoming lines that link to the National grid at the 330/132 KV Katampe and Kukwaba
(Gwagwalada) stations with a capacity of 250 MVA. The 132/33 kV Apo Substation is a feeder station that is
part of the Federal Capital Territory (FCT) in Abuja, Nigeria. The substation has 10 by 33kV and 1 spare
outgoing feeder line, which is as follows: H37, H35, H33, H31, H3, H7, H11, H13, H15, H21, & H23. The
study carries out the models on MATLAB software for fast real-time performance operations. The collected
data failure comprises downtime and outages of each feeder. After that, the probability approach was applied
to determine the daily outage feeder’s reliability using reliability, availability, mean time to repair (MTTR),
Failure rate, Distribution indices, and MTBF.
2.2. Availability
Availability is the probability that the system will be in a functional state within the specific period
of operation. It is usually expressed as the ratio of the expected value of operational time to the sum of the
expected values of operational time and downtime. Availability (A) is given in (1) to (6) [26].
𝑋[𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑜𝑛𝑎𝑙𝑡𝑖𝑚𝑒]
𝐴= (1)
𝑋[𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑜𝑛𝑎𝑙𝑡𝑖𝑚𝑒]+ 𝑋[𝑑𝑜𝑤𝑛𝑡𝑖𝑚𝑒]
Int J Pow Elec & Dri Syst, Vol. 16, No. 3, September 2025: 1852-1864
Int J Pow Elec & Dri Syst ISSN: 2088-8694 1855
Given a state function of the system Y(t), it can thus be expressed as (2).
Define the average availability based on real line intervals with an assumption of an arbitrary constant c > 0,
then, average availability is given by (4).
1 𝑐
𝐴𝑐 = ∫0 𝐴(𝑡)𝑑𝑡 (4)
𝑐
𝐴 = lim 𝐴𝑐 (5)
𝑐→∞
∞
MTBF = ∫𝑡 𝑡𝑓(𝑡)𝑑𝑡 (9)
where:
𝑓(𝑡) is the failure density function and t is the time until failure;
The discrete failure rate can be determined by substituting (7) with (9); and
Thus, MTBF is given by (10).
∞
MTBF = ∫𝑡 𝑡𝜆𝑒 −𝜆𝑡 𝑑𝑡 (10)
An analytical technique for failure analysis and reliability assessment … (Jacob Kehinde Ogunjuyigbe)
1856 ISSN: 2088-8694
system, in case of interruption, I, there are several customers not affected for a duration of interruption d. The
total customer duration of interruption CDI for any given interruption is given in (12) to (13) [28]:
CDI = d ∗ N (12)
So, for a total number of faults for n = 1, 2, 3, …, n, the CDI is given by:
CDI = d1N1 + d2N2 + d3N3 + …. + dnNn
Therefore CDI = ∑𝑛𝑖=1 𝑑𝑖 𝑁𝑖
Thus, SAIDI is given by:
∑𝑛
𝑖=1 𝑑𝑖 𝑁𝑖
SAIDI = (13)
𝑁𝑇
where,
di = the duration of the interruption
Ni = the number of customers interrupted
NT = the total number of customers
∑𝑛
𝑖=1 𝑑𝑖 𝑁𝑖
CAIDI = (14)
𝑁𝑖
where,
di = the duration of the interruption
Ni = the number of customers interrupted
2.4.3. SAIFI
This is the average number of times a customer is affected by a power outage during the year (or
period). The SAIFI is the ratio of the total number of customers interrupted to the total number of customers
served. The formula to calculate SAIFI is given in (15), (16) [28]. It provides the fraction of the time
customers are without electricity throughout the predefined interval of time. It is expressed as:
∑𝑛
𝑖=1 𝑁𝑖
SAIFI = (15)
𝑁𝑇
∑𝑛
𝑖=1 𝑁0
CAIFI = ∑𝑛
(17)
𝑖=1 𝑁𝑖
Int J Pow Elec & Dri Syst, Vol. 16, No. 3, September 2025: 1852-1864
Int J Pow Elec & Dri Syst ISSN: 2088-8694 1857
where,
di = the duration of the interruption
Ni = the number of customers interrupted
NT = the total number of customers.
Where,
di = the duration of the interruption
Ni = the number of customers interrupted
NT = the total number of customers
T = Time period under study
An analytical technique for failure analysis and reliability assessment … (Jacob Kehinde Ogunjuyigbe)
1858 ISSN: 2088-8694
Table 1 shows the MTTR of each feeder in the distribution network. Feeder 11 has the highest
MTTR with a value of 8.9551 hours, while feeder 3 has the least MTTR with 6.1477 hours. In other words,
feeder 3 is the fastest to be fixed in any case of fault occurrence in the distribution system. This may be due
to factors that include the distance of the feeder from the substation, the time to fault discovery, the nature of
the fault, and logistical issues. Feeder 9 is the most available, having an availability value of 0.9878 for the
10-year duration of the distribution system. Feeder 1 has the least availability of 0.9552. Other feeders with
relatively low availability are feeders 2, 3, 4, and 6, each with 0.9592, 0.9678, 0.9688, and 0.9683,
respectively.
The average time of operation between two consecutive failures is recorded to be highest in feeders
9 and 10, while feeder 1 shows the least mean duration of operation between failures. Feeders 5, 7, and 8 also
show a considerable duration of operation before a failure occurs. It can be deduced that the feeders with
relatively high MTBF are fairly stable in operation, that is, they have a reduced frequency of failure
compared to the feeders with low MTBF. The result shows that the MTTR of feeder 3 is relatively quickly
restored compared to the other feeders. Feeder 11 has the highest MTTR value, which makes it the slowest to
be restored to operation mode after the occurrence of a failure.
Int J Pow Elec & Dri Syst, Vol. 16, No. 3, September 2025: 1852-1864
Int J Pow Elec & Dri Syst ISSN: 2088-8694 1859
4. INFERENCE
The practical implications of a high MTBF of an electric feeder are:
− Increased Reliability: The probability of the feeder failing is extremely low, which reduces the frequency
of outages and disruptions.
− High MTBF leads to lower cost of maintenance of the grid and vice versa.
An analytical technique for failure analysis and reliability assessment … (Jacob Kehinde Ogunjuyigbe)
1860 ISSN: 2088-8694
− Increased uptime: the feeder remains operational for longer periods, ensuring a consistent power supply to
connected loads.
− Improved grid stability: the failure rate reduction contributes to a more reliable and stable power grid.
− Increased customer satisfaction: fewer outages and disruptions result in higher customer satisfaction.
Therefore, feeders 9 and 11 performed better than the other feeders. Also, the practical implications of
MTTR are discussed below:
− Longer duration of outages: when a failure occurs, it takes longer to repair, leading to extended
downtime.
− Increased downtime costs: the longer the repair time, the more the quantity of undelivered energy and
hence, lost productivity, replacement power costs, and revenue loss.
− Reduced grid resilience: A high MTTR means the feeder remains forced out of service for an extended
period, potentially triggering cascading failures or straining the grid.
− Decreased customer satisfaction: Longer outages lead to frustrated customers, which could damage the
reputation of utilities and strain the relationship between the stakeholders.
− Reduced overall efficiency: High MTTR can indicate inefficiencies in the repair process, either through
the use of a quality workforce, potentially impacting the overall performance of the grid.
Therefore, feeder 3 performed better than the other feeders.
5. CONCLUSION
This paper analyzed the reliability performance of the 132/33 KV Transmission substation in Abuja,
Nigeria, through the historical data collected from the APO substation from 2009 to 2018. The probability
approach was applied to determine the daily outage feeder’s reliability using Reliability, availability, MTTR,
Failure rate, Distribution indices, and MTBF. There were more forced failures in the distribution system from
the year 2013, which caused a reduction in the number of interruptions with the increased number of
customers connected to the distribution network. Due to the application of smart energy meters, the use of
prepaid energy meters has helped to regulate energy demand, reduce network overloading, especially during
peak hours, and minimize the cost of energy consumed. The system interruption duration is extremely high,
which causes feeder 1 to have the highest failure rate of the APO 132 kV/33 KV distribution network. There
are more forced failures in the distribution system due to switchgear and transformer failures. The result
shows that the system was most available in the year 2015 with an ASAI value of 98.9971%. The system was
least available in the year 2011 with an ASAI value of 98.6558%. However, the system has the highest
duration of outage in the year 2009 with 3112 hours of aggregated outage and 3988 interruptions while the
year 2015 has the lowest duration of an outage with 2319 hours but recorded 352 interruptions. The
substation should use a proper control mechanism to monitor the state of MTBF and downtime for reliability
and availability improvement in the network. Artificial intelligence is also recommended to ascertain the
effectiveness of the network. Furthermore, the application of technological advancements such as IoE, IoT,
and service robots will reduce outage time and maximization of component revenue. There should be
considerations on methods to make the substation network smarter by data integration and collection through
autonomous robotics, IoT, analytical big data systems, cognitive systems, artificial intelligence (AI), virtual
reality, and augmented. Finally, smart grid should be encouraged in remote and rural areas to reduce the
strain on the national grid, automation of the entire network to facilitate the resolution of faults and around
substation feeders, and the implementation of the study's findings is anticipated to help electricity experts
enhance the design, planning, and operation of distribution substations.
ACKNOWLEDGMENTS
The authors acknowledge the support received from Abuja Electricity Distribution Company
(AEDC) for data collection and enabled the timely completion of this research. Also, the authors expressed
their gratitude to the editor and reviewers of this journal whose feedback has been instrumental in enhancing
this paper.
FUNDING INFORMATION
The authors declare that they have no known competing financial interests or personal
relationships that could have appeared to influence the work reported in this paper.
Int J Pow Elec & Dri Syst, Vol. 16, No. 3, September 2025: 1852-1864
Int J Pow Elec & Dri Syst ISSN: 2088-8694 1861
Name of Author C M So Va Fo I R D O E Vi Su P Fu
Jacob Kehinde Ogunjuyigbe ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
Evans Chinemezu Ashigwuike ✓ ✓ ✓ ✓ ✓
Kafayat Adeyemi ✓ ✓ ✓ ✓ ✓ ✓
Ngang Bassey Ngang ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
Timothy Oluwaseun Araoye ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
Isaac Ojochogwu Onuh ✓ ✓ ✓ ✓ ✓ ✓ ✓
Benson Stephen Adole ✓ ✓ ✓ ✓ ✓ ✓ ✓
Solomon Bala Okoh ✓ ✓ ✓ ✓ ✓ ✓ ✓
Iboi Endurance ✓ ✓ ✓ ✓ ✓ ✓
DATA AVAILABILITY
Data availability is not applicable to this paper as no new data were created or analyzed in this study.
REFERENCES
[1] Y. Shiwen, H. Hui, W. Chengzhi, G. Hao, and F. Hao, “Review on risk assessment of power system,” Procedia Computer
Science, vol. 109, pp. 1200–1205, 2017, doi: 10.1016/j.procs.2017.05.399.
[2] E. Zio, “Some challenges and opportunities in reliability engineering,” IEEE Transactions on Reliability, vol. 65, no. 4,
pp. 1769–1782, Dec. 2016, doi: 10.1109/TR.2016.2591504.
[3] T. Sucita, Y. Mulyadi, and C. Timotius, “Reliability evaluation of power distribution system with reliability index assessment
(RIA),” IOP Conference Series: Materials Science and Engineering, vol. 384, no. 1, p. 012072, Jul. 2018, doi: 10.1088/1757-
899X/384/1/012072.
[4] M. Kornatka, A. Gawlak, and G. Dudek, “Determination of reliability indices of the distribution network based on data from
AMI,” E3S Web of Conferences, vol. 84, p. 02004, Feb. 2019, doi: 10.1051/e3sconf/20198402004.
[5] H. Abunima, J. Teh, C.-M. Lai, and H. J. Jabir, “A systematic review of reliability studies on composite power systems: a
coherent taxonomy motivations, open challenges, recommendations, and new research directions,” Energies, vol. 11, no. 9,
p. 2417, Sep. 2018, doi: 10.3390/en11092417.
[6] A. Kolawole, O. O. Agboola, P. P. Ikubanni, O. G. Raji, and C. Okechukwu Osueke, “Reliability and power loss analysis: a case
study of a power plant in Nigeria,” Cogent Engineering, vol. 6, no. 1, Jan. 2019, doi: 10.1080/23311916.2019.1579426.
[7] O. Franklin and A. Gabriel, “Reliability analysis of power distribution system in Nigeria: A case study of Ekpoma Network, Edo
State,” International Journal of Electronics and Electrical Engineering, vol. 2, no. 3, 2014, doi: 10.12720/ijeee.2.3.175-182.
[8] R. Uhunmwangho and O. Eseosa, “Reliability prediction of Port Harcourt electricity distribution network using NEPLAN,” The
International Journal of Engineering And Science (IJES), vol. 3, no. 12, pp. 68–79, 2014.
[9] T. Adefarati, A. K. Babarinde, A. S. Oluwole, and K. Olusuyi, “Reliability evaluation of Ayede 330/132 KV substation,”
International Journal of Engineering and Innovative Technology (IJEIT), vol. 4, no. 4, pp. 86–91, 2014.
[10] D. Ogheneovo, “Assessment of electric power distribution feeders reliability: a case study of feeders that supply Ede town,”
International Conference on Electric Power Engineering (ICEPENG 2015). October 14 - 16, 2015, no. October 2015, pp. 167–
176, 2015.
[11] F. S. Gazijahani and J. Salehi, “Reliability constrained two-stage optimization of multiple renewable-based microgrids
incorporating critical energy peak pricing demand response program using robust optimization approach,” Energy, vol. 161,
pp. 999–1015, 2018, doi: 10.1016/j.energy.2018.07.191.
[12] V. Ghiasi, S. Ghiasi, H. Omar, B. Ebrahimi, and M. Ghiasi, “A review of metro tunnel safety parameters and role of risk
management, tehran metro,” Fourth International Symposium on Tunnel Safety and Security, Frankfurt am Main, Germany, pp.
511–515, 2010.
[13] B. Hu, X. H. He, and K. Cao, “Reliability evaluation technique for electrical distribution networks considering planned outages,”
Journal of Electrical Engineering and Technology, vol. 9, no. 5, pp. 1482–1488, 2014, doi: 10.5370/JEET.2014.9.5.1482.
[14] L. F. Rocha, C. L. T. Borges, and G. N. Taranto, “Reliability evaluation of active distribution networks including islanding
dynamics,” IEEE Transactions on Power Systems, pp. 1–1, 2016, doi: 10.1109/TPWRS.2016.2585648.
[15] M. Šnipas, V. Radziukynas, and E. Valakevičius, “Modeling reliability of power systems substations by using stochastic automata
networks,” Reliability Engineering & System Safety, vol. 157, pp. 13–22, Jan. 2017, doi: 10.1016/j.ress.2016.08.006.
[16] M. Ghiasi, M. Irani Jam, M. Teimourian, H. Zarrabi, and N. Yousefi, “A new prediction model of electricity load based on hybrid
forecast engine,” International Journal of Ambient Energy, vol. 40, no. 2, Feb. 2019, doi: 10.1080/01430750.2017.1381157.
An analytical technique for failure analysis and reliability assessment … (Jacob Kehinde Ogunjuyigbe)
1862 ISSN: 2088-8694
[17] M. Ghiasi, E. Ahmadinia, M. Lariche, H. Zarrabi, and R. Simoes, “A new spinning reserve requirement prediction with hybrid
model,” Smart Science, pp. 1–10, Apr. 2018, doi: 10.1080/23080477.2018.1460890.
[18] F. S. Gazijahani and J. Salehi, “Integrated DR and reconfiguration scheduling for optimal operation of microgrids using Hong’s
point estimate method,” International Journal of Electrical Power & Energy Systems, vol. 99, pp. 481–492, Jul. 2018, doi:
10.1016/j.ijepes.2018.01.044.
[19] N. Teera-achariyakul and D. Rerkpreedapong, “Optimal preventive maintenance planning for electric power distribution systems
using failure rates and game theory,” Energies, vol. 15, no. 14, p. 5172, Jul. 2022, doi: 10.3390/en15145172.
[20] M. Mirhosseini, A. Heydari, D. Astiaso Garcia, F. Mancini, and F. Keynia, “Reliability based maintenance programming by a
new index for electrical distribution system components ranking,” Optimization and Engineering, vol. 23, no. 4, pp. 2315–2333,
Dec. 2022, doi: 10.1007/s11081-022-09767-8.
[21] M. Abbasghorbani, Y. Damchi, and H. Rajabi Mashhadi, “Reliability-centered maintenance for overhead transmission lines in
composite power system,” International Transactions on Electrical Energy Systems, vol. 2022, pp. 1–11, Dec. 2022, doi:
10.1155/2022/1170269.
[22] M. Mahdavi, M. S. Javadi, and J. P. S. Catalão, “Integrated generation-transmission expansion planning considering power
system reliability and optimal maintenance activities,” International Journal of Electrical Power & Energy Systems, vol. 145, p.
108688, Feb. 2023, doi: 10.1016/j.ijepes.2022.108688.
[23] A. Kumar et al., “Efficient stochastic model for operational availability optimization of cooling tower using metaheuristic
algorithms,” IEEE Access, vol. 10, pp. 24659–24677, 2022, doi: 10.1109/ACCESS.2022.3143541.
[24] V. S. Maan, A. Kumar, M. Saini, and D. K. Saini, “Markov modelling and adaptive neuro fuzzy inference system computing of
hydroelectric power plant,” International Journal of Information Technology (Singapore), 2024, doi: 10.1007/s41870-024-01811-3.
[25] A. Kumar, D. Sinwar, N. Kumar, and M. Saini, “Performance optimization of generator in steam turbine power plants using
computational intelligence techniques,” Journal of Engineering Mathematics, vol. 145, no. 1, p. 12, Apr. 2024, doi:
10.1007/s10665-024-10342-6.
[26] T. Deveikis, R. Miliune, and E. V. Nevardauskas, “Reliability of divided small electric energy system,” Electronics and Electrical
Engineering, vol. 19, no. 10, Dec. 2013, doi: 10.5755/j01.eee.19.10.2727.
[27] F. S. Gazijahani and J. Salehi, “Integrated DR and reconfiguration scheduling for optimal operation of microgrids using Hong’s
point estimate method,” International Journal of Electrical Power & Energy Systems, vol. 99, pp. 481–492, Jul. 2018, doi:
10.1016/j.ijepes.2018.01.044.
[28] V. Ghiasi et al., “Design criteria of subway tunnels,” Australian Journal of Basic and Applied Sciences, vol. 4, no. 12,
pp. 5894–5907, 2010.
[29] R. S. Jayappa, M. H. Basappa, K. G. Ramaiah, and G. H. Rajappa, “Effects of integration of distributed generation on reliability
in distribution system,” International Journal of Power Electronics and Drive Systems (IJPEDS), vol. 15, no. 1, pp. 498-505,
Mar. 2024, doi: 10.11591/ijpeds.v15.i1.pp498-505.
BIOGRAPHIES OF AUTHORS
Int J Pow Elec & Dri Syst, Vol. 16, No. 3, September 2025: 1852-1864
Int J Pow Elec & Dri Syst ISSN: 2088-8694 1863
An analytical technique for failure analysis and reliability assessment … (Jacob Kehinde Ogunjuyigbe)
1864 ISSN: 2088-8694
Int J Pow Elec & Dri Syst, Vol. 16, No. 3, September 2025: 1852-1864