1. OBJECTIVE
DEPARTMENT WORKING PROCEDURE
V&S RISK PREVENTION SURE
PROJECT 'INSTALLATION OF FLOATING VINYL FLOORING IN'
NORTH GATE CONDOMINIUM 1
NEXT
IDENTIFICATION REVIEW VERSION PAGE
REVIEW
CO-PR-SA November 17, 2021 00 TO BE DEFINED Page 2 of 7
Establish the activities and controls necessary for the execution of the work and/or activities of
the work "Installation of floating and vinyl flooring in Puerta Norte 1 Condominium" in strict
compliance with the established Safety, Occupational Health and Environmental guidelines
by V&S, in order to prevent, control and eliminate sub-standard acts and conditions that
they can cause damage to personnel, equipment, infrastructure, and the environment.
2. SCOPE
This procedure is applicable to the development of the work 'Installation of floating and vinyl flooring in
"Condominium North Gate 1" that includes the protection of the physical integrity of the personnel that
works at V&S, considering also the protection of subcontracted workers and/or
suppliers that participate in the execution of the works.
3. APPLICABLE REGULATIONS
Law 16.744 'Establishes standards for occupational accidents and professional illnesses.'
D.S No. 40 "Approves the regulation on the prevention of occupational risks."
Supreme Decree No. 594 'Regulations on basic sanitary and environmental conditions in places'
of work.
Law 20.123 of Subcontracting.
Special Regulations for Contractor and Subcontractor Companies.
Regulations on Order, Hygiene, and Safety.
English speaker
Cartonero
4" angle grinder
Among others.
Cargo EPP
Safety footwear
Safety glove
Carpenter Safety lens
Hearing protector
Tool belt
DEPARTMENT WORK PROCEDURE
V&S RISK PREVENTION INSURANCE
PROJECT 'INSTALLATION OF FLOATING VINYL FLOORING IN
NORTH GATE CONDOMINIUM 1
NEXT
IDENTIFICATION REVIEW VERSION PAGE
REVIEW
CO-PR-SA November 17, 2021 00 TO BE DEFINED Page 3 of 7
Safety helmet
Safety helmet
Safety footwear
Safety glasses
Supervisor Geologist
Hearing protector
Safety footwear
Safety gloves
Assistant Safety helmets
Safety glasses
Hearing protector
6. DEFINITIONS
In construction, the element is called a slab, which is a horizontal structural component that
supports its own weight and usage overloads, walls, dynamics, etc.
Risk: Combination of the probability of an event or dangerous exposure occurring and
the severity of the damage or deterioration of health that the event or exposure can cause.
Danger: Source, situation, or act with the potential to cause harm in terms of damage
human or health deterioration, or a combination of these.
Incident: Event or events related to work in which an occurrence happens or could have happened.
occurring damage, or deterioration of health (regardless of severity), or a fatality.
7. RESPONSIBILITIES
Verify that all staff working under your supervision have received the induction of
this procedure.
Responsible for supervising the compliance with the security measures of this
procedure.
Support in security matters.
General Manager:
Workers:
In the installation of the floating floor, the joint of each plank must be overlapped, in order to
maintain an order and because this is how the tables are affirmed, it gives structure to the floor. That is why it is
It is necessary to create an installation template where the room is drawn with its measurements.
The order of the tables and their measurements shall be arranged.
Cutting of boards
With the measurements taken and the installation plan made, the boards can be cut. Use
the miter saw, as it allows for comfortable and safe series cuts.
To make the cut, place the boards with their backs facing up, as this way the splinters
They will remain on the bottom side, but the visible face will be completely clean.
Using the jigsaw, cut the horizontal tongue of the tongue and groove of all the boards.
what makes up the first row.
ISOLATION AND LEVELING
Before carrying out the installation, one must take care to put up a barrier against moisture.
and a foam that levels. For this, a polyethylene sleeve is first placed, joined at its
edges with adhesive tape, but without overlaps.
Then you have to put the leveling foam that eliminates irregularities in the floor and
isolate from the cold and the noise.
Installation of tables
Place the first row of tables without the tongue or groove of the tongue and groove. If it were
It is necessary to make the necessary reductions so that it fits on the edges of the windows.
Between the wall and the boards, place the spacers that come in the kit to allow for the gap.
necessary (approximately 5 mm) that the floor requires for future expansions of the
wood.
On the tongue or groove of the tongue-and-groove, apply a very fine bead of adhesive.
Assembly is done along the length and width of each table. This helps improve grip and connection.
between each table.
In order for each row to be well attached to the previous one, it is necessary to hit them with the piece of
impact and a hammer, it is very important to strike directly on this piece, as this way it
avoid damaging the table.
Last line
The tables in the last row probably also need to be cut to fit.
with the edge of the wall and with the required width.
When fixing the last row, in addition to using mounting adhesive, a bar must be used.
metal base, which will allow hitting it and bringing it closer to the previous row
Using the miter saw, cut the baseboards to the size of each wall, making sure to
leave the ends at a 45º angle to achieve a better fit and finish in the
joints.
FIX THE DUST COVERS
Attach the dust covers with mounting adhesive.
Press the cover down so that it sticks. You can add it to the ends.
some nails to help with a quick fastening.
9. ASSOCIATED RISKS
Use the necessary personal protective equipment according to the risk to be covered.
Use only electrical tools that have their protections, cables, plugs
and extensions in good condition.
Train the worker in the use of minor equipment,
Daily review of power tool status.
All power tools that have a cutting disc must use their guard.
of protection.
Use goggles when performing wood cuts.
DEPARTMENT WORK PROCEDURE
V&S RISK PREVENTION SURE
PROJECT 'INSTALLATION OF FLOATING VINYL FLOORING IN
NORTH GATE CONDOMINIUM 1
NEXT
IDENTIFICATION REVIEW VERSION PAGE
REVIEW
CO-PR-SA November 17, 2021 00 TO BE DEFINED Page 7 of 7
Have personal protective equipment according to the risk to which one is exposed in the
task.
Conduct daily safety talk.
The cardboard collector must have protection insurance.
In the use of cardboard, the force should always be applied in the opposite direction to the body.
When not in use, store the knife in a case, pouch, or device designed for it.
this end.
Keep the blade sharp to avoid excessive force.
10