Departure 01.01.02 FILLING WITH GRANULAR MATERIAL IN LAYERS OF 0.30 m. (SELECTED OWN MATERIAL)
Performance m3/DAY MO.40.0000EQ.40.0000Direct unit cost per: m3 45.80
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL WORKER hh 2.0000 0.4000 18.20 7.28
0101040004 CIVIL WORKER hh 1.0000 0.2000 25.54 5.11
0101040005 Civil Foreman hh 0.1000 0.0200 30.65 0.61
1:00 PM
Materials
02430200040015 WATER FOR THE WORKSHOP CISTERN m3 0.0130 20.00 0.26
02450200020003 84 OCTANE GASOLINE gal 0.1075 15.35 1.65
0283020002 GRAVEL BASE m3 0.2500 45.00 11.25
13.16
Teams
0301100004 Pneumatic roller hm 0.6320 0.1264 79.00 9.99
03014000040002 MANUAL SCREEN hm 1.0000 0.2000 10.00 2.00
0301500010 4 HP PLATE TYPE VIBRATORY COMPACTOR hm 1.0000 0.2000 35.00 7.00
0306010001 HAND TOOLS %mo 5.0000 1:00 PM 0.65
19.64
Game 01.02.02 COMPACTED FILL WITH LOAN MATERIAL (GRAVEL BASE) H= 0.15
Performance m2/DAY Direct unit cost per: m2 29.48
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 2.0000 0.1524 18.20 2.77
0101040004 CIVIL WORKER hh 1.0000 0.0762 25.54 1.95
0101040005 Civil Foreman hh 0.1000 0.0076 30.65 0.23
4.95
Materials
02430200040015 WATER FOR THE WORKSHOP CISTERN m3 0.0130 20.00 0.26
02450200020003 84 OCTANE GASOLINE gal 0.1050 15.35 1.61
0283020002 BASE OF AGGREGATED MATERIAL m3 0.2500 45.00 11.25
13.12
Teams
0301100004 PNEUMATIC ROLLER hm 0.6750 0.0514 79.00 4.06
03011700010001 CATERPILLAR EXCAVATOR 115-165 HP hm 0.1170 0.0089 210.00 1.87
0301500010 4 HP PLATE TYPE VIBRATORY COMPACTOR hm 2.0000 0.1524 35.00 5.33
0306010001 HAND TOOLS %mo 3.0000 4.95 0.15
11.41
Departure 02.01.01 PREMIXED CONCRETE FALSE FLOOR e=4" f'c=140 kg/cm2 (Pump control, lobby, Accelerometric station)
Performance m2/DAY MO.65.0000EQ.65.0000Direct unit cost per: m2 48.83
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 0.4923 18.20 8.96
0101040004 CIVIL OPERATOR hh 3.0000 0.3692 25.54 9.43
18.39
Materials
02120600130011 PREMIXED CONCRETE F'C=140 kg/cm2 WITH CEMENT T-I m3 0.1100 220.00 24.20
02450200020003 84 OCTANE GASOLINE gal 0.1000 15.35 1.54
25.74
Teams
03012900010005 4 HP CONCRETE VIBRATOR 2.40" hm 0.5850 0.0720 7.20 0.52
0306010001 HAND TOOLS %mo 3.0000 18.39 0.55
1.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 0.1100 33.00 3.63
3.63
Game 03.01.01 READY-MIXED CONCRETE FOUNDATIONS f'c=350 kg/cm2, 57, CEM I, 4'' 6''
Performance m3/DAY MO.28.0000EQ.28.0000 Direct unit cost per: m3 396.56
Code Resource Description Unity Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.1429 18.20 20.80
0101040004 CIVIL OPERATOR hh 3.0000 0.8571 25.54 21.89
0101040005 Civil Foreman hh 0.1000 0.0286 30.65 0.88
43.57
Materials
02120600130086 READY-MIXED CONCRETE TYPE I F´C = 350 kg/cm2, H57, CEM I, m3 1000 282.00 310.20
SLUMP 4"-6"
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
313.58
Teams
03012900010005 4 HP 2.40" CONCRETE VIBRATOR hm 0.8750 0.2500 7.20 1.80
0306010001 HAND TOOLS %mo 3.0000 43.57 1.31
3.11
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.1000 33.00 36.30
36.30
Match 03.02.01 PREMIXED CONCRETE, TYPE I CEMENT, TANK f'c=280 kg/cm2 (W/C = 0.50)
Performance m3/DAY Unit direct cost per: m3 424.06
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.1429 18.20 20.80
0101040004 CIVIL WORKER hh 3.0000 0.8571 25.54 21.89
0101040005 CIVIL FOREMAN hh 0.1000 0.0286 30.65 0.88
43.57
Materials
02120600130093 READY-MIXED CONCRETE TYPE I F´C = 280 kg/cm2 SLUMP 4"-6",m3
57 1.1000 307.00 337.70
TYPE I A/C= 0.45
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
341.08
Teams
03012900010005 4 HP CONCRETE VIBRATOR 2.40" hm 0.8750 0.2500 7.20 1.80
0306010001 HAND TOOLS %mo 3.0000 43.57 1.31
3.11
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1,000 33.00 36.30
36.30
Departure 03.04.01 READY-MIXED CONCRETE FOUNDATION BEAM f'c=350 kg/cm2, 57, CEM I, 4'' 6''
Performance m3/DAY MO.28.0000EQ.28.0000 Direct unit cost per: m3 396.56
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.1429 18.20 20.80
0101040004 CIVIL WORKER hh 3.0000 0.8571 25.54 21.89
0101040005 Civil Foreman hh 0.1000 0.0286 30.65 0.88
43.57
Materials
02120600130086 READY-MIXED CONCRETE TYPE I F´C = 350 kg/cm2, H57, CEM I, m3 1,000 282.00 310.20
SLUMP 4"-6"
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
313.58
Teams
03012900010005 4 HP 2.40" CONCRETE VIBRATOR hm 0.8750 0.2500 7.20 1.80
0306010001 HAND TOOLS %mo 3.0000 43.57 1.31
3.11
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.1000 33.00 36.30
36.30
Departure 03.05.01 PREMIXED CONCRETE FOUNDATION SLAB f'c=350 kg/cm2, 57, CEM I, 4'' 6''
Performance m3/DAY MO.28.0000EQ.28.0000Direct unit cost per: m3 396.56
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.1429 18.20 20.80
0101040004 CIVIL OPERATOR hh 3.0000 0.8571 25.54 21.89
0101040005 Civil Foreman hh 0.1000 0.0286 30.65 0.88
43.57
Materials
02120600130086 READY-MIXED CONCRETE TYPE I F´C = 350 kg/cm2, H57, CEM I, m3 1.1000 282.00 310.20
SLUMP 4"-6"
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
313.58
Teams
03012900010005 4 HP CONCRETE VIBRATOR 2.40" hm 0.8750 0.2500 7.20 1.80
0306010001 HAND TOOLS %mo 3.0000 43.57 1.31
3.11
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.1000 33.00 36.30
36.30
Game 03.06.01 READY-MIXED CONCRETE RETAINING WALL f'c=280 kg/cm2, 67, CEM I, 4''-6''
Performance m3/DAY Direct unit cost per: m3 466.79
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.4545 18.20 26.47
0101040004 CIVIL WORKER hh 3.0000 1.0909 25.54 27.86
0101040005 Civil Supervisor hh 0.1000 0.0364 30.65 1.12
55.45
Materials
02120600130050 READY-MIXED CONCRETE TYPE I F´C = 280 kg/cm2 SLUMP 6" H=67
m3 1.4300 248.00 354.64
02450200020004 90 OCTANE GASOLINE gal 0.2690 15.35 4.13
358.77
Teams
03012900010005 4 HP 2.40" CONCRETE VIBRATOR hm 1.4218 0.5170 7.20 3.72
0306010001 HAND TOOLS %mo 3.0000 55.45 1.66
5.38
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.4300 33.00 47.19
47.19
Departure 03/06/03 REINFORCED STEEL FY= 4200 kg/cm2 GRADE 60 RETAINING WALLS
Performance kg/DAY MO.250.0000EQ.250.0000 Direct unit cost per: kg 4.41
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Materials
02110200010006 BLACK ANNEALED WIRE NO. 16 (CONSTRUCTION) OC kg 0.0210 4.66 0.10
0225040003 RIBBED STEEL FY=4,200 Kg/cm2 GRADE 60 kg 1.0650 3.08 3.28
3.38
Subcontracts
04480300050037 SC ENABLEMENT AND INSTALLATION OF REINFORCING STEEL kg 1.0000 1.03 1.03
(HEALTH AND SAFETY AT WORK)
1.03
Game 03.06.04 REINFORCING STEEL FY= 4200 kg/cm2 GRADE 60 SCREEN WALLS (JOINTS)
Performance kg/DAY MO.250.0000EQ.250.0000 Direct unit cost per: kg 4.41
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Materials
02110200010006 BLACK ANNEALED WIRE No. 16 (CONSTRUCTION) OC kg 0.0210 4.66 0.10
0225040003 RIBBED STEEL FY=4,200 Kg/cm2 GRADE 60 kg 1.0650 3.08 3.28
3.38
Subcontracts
04480300050037 SC ENABLEMENT AND INSTALLATION OF REINFORCED STEELkg 1.0000 1.03 1.03
HEALTH AND SAFETY AT WORK
1.03
Departure 03.07.01.01 READY-MIXED CONCRETE COLUMNS f'c=350 kg/cm2, 67, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 382.74
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.2800 18.20 11:30 PM
0101040004 CIVIL WORKER hh 2.0000 0.6400 25.54 16.35
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
40.63
Materials
02120600130089 READY-MIXED CONCRETE F´C = 350 kg/cm2, H67, CEM I, SLUMP 4"-6" m3 1.0500 285.00 299.25
Game 03.07.02.01 READY-MIXED CONCRETE COLUMNS f'c=350 kg/cm2, 67, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 382.74
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL WORKER hh 4.0000 1.2800 18.20 11:30 PM
0101040004 Civil Worker hh 2.0000 0.6400 25.54 16.35
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
40.63
Materials
02120600130089 READY-MIXED CONCRETE F´C = 350 kg/cm2, H67, CEM I, SLUMP 4"-6" m3 1.0500 285.00 299.25
Departure 03.07.02.02 PREMIXED CONCRETE COLUMNS f'c=280 kg/cm2, 67, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 343.89
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.2800 18.20 23:30
0101040004 CIVIL WORKER hh 2.0000 0.6400 25.54 16.35
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
40.63
Materials
02120600130050 READY-MIXED CONCRETE TYPE I F´C = 280 kg/cm2 SLUMP 6" H=67
m3 1.0500 248.00 260.40
02450200020004 90 OCTANE GASOLINE guy 0.2200 15.35 3.38
263.78
Teams
03012900010005 4 HP CONCRETE VIBRATOR 2.40" hm 1.5688 0.5020 7.20 3.61
0306010001 HAND TOOLS %mo 3.0000 40.63 1.22
4.83
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Match 03.07.02.03 READY-MIXED CONCRETE COLUMNS f'c=210 kg/cm2, 67, CEM I, 4''-6''
Performance m3/DAY MO.25.0000 EQ.25.0000 Direct unit cost per: m3 329.20
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL LABORER hh 4.0000 1.2800 18.20 11:30 PM
0101040004 CIVIL WORKER hh 3.0000 0.9600 25.54 24.52
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130094 READY-MIXED CONCRETE TYPE I F´C = 210 kg/cm2 SLUMP 4-6" H67
m3 1.0500 226.00 237.30
Columns
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
240.68
Teams
03012900010005 CONCRETE VIBRATOR 4 HP 2.40" hm 1.5688 0.5020 7.20 3.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
5.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Game 03.08.01.02 READY-MIXED CONCRETE PAVERS f'c=350 kg/cm2, 67, CEM I, 4''-6'' (WITHIN ANCHORING M)
Performance m3/DAY MO.25.0000EQ.25.0000Direct unit cost per : m3 478.14
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 Civil Laborer hh 4.0000 1.2800 18.20 23:30
0101040004 CIVIL OPERATOR hh 2.0000 0.6400 25.54 16.35
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
40.63
Materials
02120600130089 READY-MIXED CONCRETE F´C = 350 kg/cm2, H67, CEM I, SLUMP 4"-6" m3 1.3500 285.00 384.75
Match 03.08.02.01 READY-MIXED CONCRETE PLATES f'c=350 kg/cm2, 67, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 382.74
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 Civil Laborer hh 4.0000 1.2800 18.20 23.30
0101040004 CIVIL WORKER hh 2.0000 0.6400 25.54 16.35
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
40.63
Materials
02120600130089 READY-MIXED CONCRETE F´C = 350 kg/cm2, H67, CEM I, SLUMP 4"-6" m3 1.0500 285.00 299.25
Departure 03.08.02.02 READY-MIXED CONCRETE PLATES f'c=280 kg/cm2, 67, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 343.89
Code Resource Description Unity Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.2800 18.20 11:30 PM
0101040004 CIVIL WORKER hh 2.0000 0.6400 25.54 16.35
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
40.63
Materials
02120600130050 Ready-mixed concrete type I F´C = 280 kg/cm2 SLUMP 6" H=67 m3 1.0500 248.00 260.40
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
263.78
Teams
03012900010005 4 HP 2.40" CONCRETE VIBRATOR hm 1.5688 0.5020 7.20 3.61
0306010001 HAND TOOLS %mo 3.0000 40.63 1.22
4.83
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Departure 03.08.02.03 READY-MIXED CONCRETE PLATES f'c=210 kg/cm2, 67, CEM I, 4''-6''
Performance m3/DAY MO.25.0000 EQ.25.0000 Direct unit cost per: m3 329.20
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.2800 18.20 11:30 PM
0101040004 Civil Operator hh 3.0000 0.9600 25.54 24.52
0101040005 CIVIL FOREMAN hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130094 READY-MIXED CONCRETE TYPE I F´C = 210 kg/cm2 SLUMP 4-6" H67
m3 1.0500 226.00 237.30
Columns
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
240.68
Teams
03012900010005 CONCRETE VIBRATOR 4 HP 2.40" hm 1.5688 0.5020 7.20 3.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
5.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Departure 03.09.02.01 READY-MIXED CONCRETE BEAMS f'c=280 kg/cm2, 57, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 348.15
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.2800 18.20 23:30
0101040004 CIVIL OPERATOR hh 3.0000 0.9600 25.54 24.52
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130047 READY-MIXED CONCRETE TYPE I F´C = 280 kg/cm2 SLUMP 6" H=57
m3 1.0500 245.00 257.25
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
260.63
Teams
03012900010005 4 HP 2.40" CONCRETE VIBRATOR hm 1.1313 0.3620 7.20 2.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
4.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Departure 03.09.02.02 PREMIXED CONCRETE BEAMS f'c=210 kg/cm2, 57, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 326.05
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 Civil Laborer hh 4.0000 1.2800 18.20 23:30
0101040004 Civil worker hh 3.0000 0.9600 25.54 24.52
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130091 READY-MIXED CONCRETE F´C = 210 kg/cm2, 57, CEM I, 4-6" m3 1.0500 223.00 234.15
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
237.53
Teams
03012900010005 4 HP CONCRETE VIBRATOR 2.40" hm 1.5688 0.5020 7.20 3.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
5.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Game 03.10.01.01 PREMIXED CONCRETE LIGHTENED SLABS f'c=280 kg/cm2, 57, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 348.15
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.2800 18.20 11:30 PM
0101040004 Civil Worker hh 3.0000 0.9600 25.54 24.52
0101040005 CIVIL FOREMAN hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130047 READY-MIXED CONCRETE TYPE I F´C = 280 kg/cm2 SLUMP 6" H=57
m3 1.0500 245.00 257.25
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
260.63
Teams
03012900010005 CONCRETE VIBRATOR 4 HP 2.40" hm 1.1313 0.3620 7.20 2.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
4.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Departure 03.10.01.02 PREMIXED CONCRETE LIGHTWEIGHT SLABS f'c=210 kg/cm2, 57, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 326.05
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.2800 18.20 23:30
0101040004 CIVIL OPERATOR hh 3.0000 0.9600 25.54 24.52
0101040005 CIVIL FOREMAN hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130091 READY-MIXED CONCRETE F´C = 210 kg/cm2, 57, CEM I, 4-6" m3 1.0500 223.00 234.15
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
237.53
Teams
03012900010005 4 HP 2.40" CONCRETE VIBRATOR hm 1.5688 0.5020 7.20 3.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
5.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Departure 03.10.01.03 SHORING AND STRIPPING OF LIGHTENED SLAB WITH PRESTRESSED BEAMS
Performance m2/DAY MO.100.0000EQ.100.0000Direct unit cost per: m2 22.15
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 Civil Worker hh 4.0000 0.3200 18.20 5.82
0101040004 CIVIL WORKER hh 2.0000 0.1600 25.54 4.09
0101040005 Civil Foreman hh 0.1000 0.0080 30.65 0.25
10.16
Teams
0306010001 HAND TOOLS %mo 3.0000 10.16 0.30
0.30
Subcontracts
0448090039 SC BRACING OF LIGHTENED SLABS WITH PRECAST BEAMS m2 1.0030 11.66 11.69
11.69
Game 03.10.02.01 PREMIXED CONCRETE LIGHTWEIGHT SLAB f'c=280 kg/cm2 WITH PRESTRESSED BEAM
Performance m3/DAY MO.25.0000EQ.25.0000Direct unit cost per: m3 348.15
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.2800 18.20 11:30 PM
0101040004 CIVIL OPERATOR hh 3.0000 0.9600 25.54 24.52
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130047 PREMIXED CONCRETE TYPE I F'c = 280 kg/cm2 SLUMP 6" H=57 m3 1.0500 245.00 257.25
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
260.63
Teams
03012900010005 4 HP 2.40" CONCRETE VIBRATOR hm 1.1313 0.3620 7.20 2.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
4.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Departure 03.10.02.06 RIBBED STEEL FY= 4200 kg/cm2 GRADE 60 IN LIGHTWEIGHT SLAB
Performance kg/DAY MO.250.0000EQ.250.0000 Direct unit cost per: kg 4.41
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Materials
02110200010006 Annealed Black Wire No. 16 (Construction) OC kg 0.0210 4.66 0.10
0225040003 REINFORCED STEEL FY=4,200 Kg/cm2 GRADE 60 kg 1.0650 3.08 3.28
3.38
Subcontracts
04480300050037 SC ENABLING AND INSTALLATION OF REINFORCED STEEL kg 1.0000 1.03 1.03
(HEALTH AND SAFETY AT WORK)
1.03
Departure 03.11.01.01 READY-MIXED CONCRETE SOLID SLAB f'c=280 kg/cm2, H57, CEM I, 4"-6", E=0.25
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 348.15
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.2800 6:20 PM 23.30
0101040004 CIVIL WORKER hh 3.0000 0.9600 25.54 24.52
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130047 READY-MIXED CONCRETE TYPE I F´C = 280 kg/cm2 SLUMP 6" H=57
m3 1.0500 245.00 257.25
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
260.63
Teams
03012900010005 4 HP CONCRETE VIBRATOR 2.40" hm 1.1313 0.3620 7.20 2.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
4.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Game 03.11.01.02 READY-MIXED CONCRETE SOLID SLAB f'c=280 kg/cm2, H57, CEM I, 4"-6", E=0.20
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 348.15
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.2800 18.20 11:30 PM
0101040004 CIVIL WORKER hh 3.0000 0.9600 25.54 24.52
0101040005 CIVIL FOREMAN hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130047 READY-MIXED CONCRETE TYPE I F´C = 280 kg/cm2 SLUMP 6" H=57
m3 1.0500 245.00 257.25
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
260.63
Teams
03012900010005 4 HP 2.40" CONCRETE VIBRATOR hm 1.1313 0.3620 7.20 2.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
4.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Departure 03.11.01.04 RIBBED STEEL FY= 4200 kg/cm2 GRADE 60 IN SOLID SLAB
Performance kg/DAY MO.250.0000EQ.250.0000 Direct unit cost per: kg 4.41
Code Resource Description Unit Squad Quantity Price S/ Partial S/
Materials
02110200010006 BLACK ANNEALED WIRE NO. 16 (CONSTRUCTION) OC kg 0.0210 4.66 0.10
0225040003 RIBBED STEEL FY=4,200 Kg/cm2 GRADE 60 kg 1.0650 3.08 3.28
3.38
Subcontracts
04480300050037 SC ENABLEMENT AND INSTALLATION OF REINFORCING STEEL kg 1.0000 1.03 1.03
(HEALTH AND SAFETY AT WORK)
1.03
Departure 03.11.02.01 READY-MIXED CONCRETE SOLID SLAB f'c=280 kg/cm2, H57, 4"-6", LOW PERMEABILITY, E= 0.20 (W/C = 0.50)
Performance m3/DAY Unit direct cost per: m3 404.84
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.2800 18.20 11:30 PM
0101040004 CIVIL WORKER hh 2.0000 0.6400 25.54 16.35
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
40.63
Materials
02120600130040 READY-MIXED CONCRETE TYPE I F´C = 280 kg/cm2 SLUMP 4"-6",m3
57 1.0500 307.00 322.35
TYPE I REL A/C = 0.45
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
325.73
Teams
03012900010005 CONCRETE VIBRATOR 4 HP 2.40" hm 1.1313 0.3620 7.20 2.61
0306010001 HAND TOOLS %mo 3.0000 40.63 1.22
3.83
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Game 03.11.02.03 CORRUgATED STEEL FY= 4200 kg/cm2 GRADE 60 IN SOLID SLAB
Performance kg/DAY MO.250.0000EQ.250.0000 Direct unit cost per: kg 4.41
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Materials
02110200010006 BLACK ANNEALED WIRE NO. 16 (CONSTRUCTION) OC kg 0.0210 4.66 0.10
0225040003 REINFORCING STEEL FY=4,200 Kg/cm2 GRADE 60 kg 1.0650 3.08 3.28
3.38
Subcontracts
04480300050037 SC ENABLING AND INSTALLATION OF REINFORCING STEEL kg 1.0000 1.03 1.03
HEALTH, SAFETY, AND WORK
1.03
Departure December 3, 2001 READY-MIXED CONCRETE SOLID SLABS f'c=280 kg/cm2, 57, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 348.15
Code Resource Description Unit Crew Quantity Partial S/
Labor
0101040001 Civil Laborer hh 4.0000 1.2800 18.20 11:30 PM
0101040004 CIVIL OPERATOR hh 3.0000 0.9600 25.54 24.52
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130047 READY-MIXED CONCRETE TYPE I F´C = 280 kg/cm2 SLUMP 6" H=57
m3 1.0500 245.00 257.25
02450200020004 90 OCTANE GASOLINE girl 0.2200 15.35 3.38
260.63
Teams
03012900010005 4 HP CONCRETE VIBRATOR 2.40" hm 1.1313 0.3620 7.20 2.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
4.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Game 03.12.01.02 READY-MIXED CONCRETE SOLID SLABS f'c=210 kg/cm2, 57, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 326.05
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 Civil Peon hh 4.0000 1.2800 18:20 11:30 PM
0101040004 CIVIL WORKER hh 3.0000 0.9600 25.54 24.52
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130091 READY-MIXED CONCRETE F´C = 210 kg/cm2, 57, CEM I, 4-6" m3 1.0500 223.00 234.15
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
237.53
Teams
03012900010005 4 HP CONCRETE VIBRATOR 2.40" hm 1.5688 0.5020 7.20 3.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
5.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Game 03.12.01.04 RIBBED STEEL FY= 4200 kg/cm2 GRADE 60 IN SOLID SLAB
Performance kg/DAY MO.250.0000EQ.250.0000 Unit direct cost per: kg 4.41
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Materials
02110200010006 Annealed black wire No. 16 (construction) OC kg 0.0210 4.66 0.10
0225040003 REINFORCING STEEL FY=4,200 Kg/cm2 GRADE 60 kg 1.0650 3.08 3.28
3.38
Subcontracts
04480300050037 SC ENABLEMENT AND INSTALLATION OF REINFORCED STEELkg 1.0000 1.03 1.03
HEALTH AND SAFETY AT WORK
1.03
Departure 03.13.01.01 READY-MIXED CONCRETE STAIR f'c=280 kg/cm2, 57, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 348.15
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL WORKER hh 4.0000 1.2800 18.20 23.30
0101040004 CIVIL WORKER hh 3.0000 0.9600 25.54 24.52
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130047 READY-MIXED CONCRETE TYPE I F´C = 280 kg/cm2 SLUMP 6" H=57
m3 1.0500 245.00 257.25
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
260.63
Teams
03012900010005 4 HP 2.40" CONCRETE VIBRATOR hm 1.1313 0.3620 7.20 2.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
4.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Departure 03.13.02.01 READY-MIXED CONCRETE STAIR f'c=280 kg/cm2, 57, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 348.15
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.2800 18.20 23:30
0101040004 CIVIL OPERATOR hh 3.0000 0.9600 25.54 24.52
0101040005 CIVIL FOREMAN hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130047 PREMIXED CONCRETE TYPE I F´C = 280 kg/cm2 SLUMP 6" H=57 m3 1.0500 245.00 257.25
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
260.63
Teams
03012900010005 4 HP CONCRETE VIBRATOR 2.40" hm 1.1313 0.3620 7.20 2.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
4.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Game March 14, 2005 NORMAL FORMWORK AND STRIPPING OF SCREEN WALL SIDES
Performance m2/DAY MO.15.0000EQ.15.0000 Direct unit cost per: m2 46.86
Code Resource Description Unit Crew Amount Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 1.0000 0.5333 18.20 9.71
0101040004 CIVIL WORKER hh 1.0000 0.5333 25.54 13.62
0101040005 CIVIL FOREMAN hh 0.1000 0.0533 30.65 1.63
24.96
Materials
02110200010002 BLACK ANNEALED WIRE NO. 8 (CONSTRUCTION) kg 0.2000 4.66 0.93
0217030008 AVERAGE NAILS kg 0.1700 7:00 1.19
02172700010004 ADDITIVE FOR FORMWORK m2 0.2000 10.00 2.00
0271010008 GENERAL SCREW WOOD p2 1.4000 6.09 8.53
12.65
Teams
0306010001 HAND TOOLS %mo 5.0000 24.96 1.25
1.25
Subcontracts
04480300010032 SC METAL FORMWORK m2 0.2000 40.00 8.00
8:00
Game March 14, 2010 EPOXY UNION BETWEEN BASEMENT CEILING SLABS AND SCREEN WALL
Performance m/DAY MO.30.0000EQ.30.0000 Direct unit cost per: m 28.20
Code Resource Description Unit Squad Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 2.0000 0.5333 18.20 9.71
0101040004 CIVIL OPERATOR hh 1.0000 0.2667 25.54 6.81
0101040005 Civil Foreman hh 0.1000 0.0267 30.65 0.82
17.34
Materials
02172700010005 EPOXY ADDITIVE SIKADUR 32 gal 0.1499 69.00 10.34
10.34
Teams
0306010001 HAND TOOLS %mo 3.0000 17.34 0.52
0.52
Game 03.14.13 Cut for the splicing of slabs with anchored wall
Performance m/DAY MO.100.0000EQ.100.0000 Direct unit cost per: m 7.20
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 0.5000 0.0400 18.20 0.73
0101040004 CIVIL OPERATOR hh 1.0000 0.0800 25.54 2.04
0101040005 Civil Foreman hh 0.1000 0.0080 30.65 0.25
3.02
Materials
02173100030003 10KG HAMMER DEMOLITION BOSCH GSH11E and 0.0396 103.30 4.09
4.09
Teams
0306010001 HAND TOOLS %mo 3.0000 3.02 0.09
0.09
Match 03.14.15 PREMIXED CONCRETE CACHIMBAS f'c=280 kg/cm2, H57, CEM 1, 4"-6"
Performance m3/DAY MO.22.0000EQ.22.0000 Direct unit cost per: m3 355.09
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL LABORER hh 4.0000 1.4545 18.20 26.47
0101040004 CIVIL WORKER hh 3.0000 1.0909 25.54 27.86
0101040005 Civil Foreman hh 0.1000 0.0364 30.65 1.12
55.45
Materials
02120600130047 READY-MIXED CONCRETE TYPE I F´C = 280 kg/cm2 SLUMP 6" H=57
m3 1.0500 245.00 257.25
02450200020004 90 OCTANE GASOLINE gal 0.2100 15.35 3.22
260.47
Teams
03012900010005 CONCRETE VIBRATOR 4 HP 2.40" hm 1.0918 0.3970 7.20 2.86
0306010001 HAND TOOLS %mo 3.0000 55.45 1.66
4.52
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Departure 03.15.01 PREMIXED CONCRETE EQUIPMENT BASES f'c=280 kg/cm2, 57, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per : m3 348.15
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.2800 18.20 23.30
0101040004 CIVIL WORKER hh 3.0000 0.9600 25.54 24.52
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130047 PREMIXED CONCRETE TYPE I F´C = 280 kg/cm2 SLUMP 6" H=57 m3 1.0500 245.00 257.25
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
260.63
Teams
03012900010005 4 HP CONCRETE VIBRATOR 2.40" hm 1.1313 0.3620 7.20 2.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
4.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Game 03.16.01 READY-MIXED CONCRETE PAVEMENT f'c=280 kg/cm2, 57, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 348.15
Code Resource Description Unit Crew Amount Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.2800 18.20 11:30 PM
0101040004 CIVIL WORKER hh 3.0000 0.9600 25.54 24.52
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130047 PREMIXED CONCRETE TYPE I F'c = 280 kg/cm2 SLUMP 6" H=57 m3 1.0500 245.00 257.25
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
260.63
Teams
03012900010005 CONCRETE VIBRATOR 4 HP 2.40" hm 1.1313 0.3620 7.20 2.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
4.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
Departure March 16, 2003 STEEL FY=4200 KG/CM2 - JOINTS (Not in Parking Lot pavement)
Performance kg/DAY MO.250.0000EQ.250.0000 Direct unit cost per: kg 4.41
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Materials
02110200010006 BLACK ANNEALED WIRE NO. 16 (CONSTRUCTION) OC kg 0.0210 4.66 0.10
0225040003 RIBBED STEEL FY=4,200 Kg/cm2 GRADE 60 kg 1.0650 3.08 3.28
3.38
Subcontracts
04480300050037 SC ENABLING AND INSTALLATION OF REINFORCING STEEL kg 1.0000 1.03 1.03
HEALTH AND SAFETY AT WORK
1.03
Materials
02171500140185 SIKAFLEX - 11 FC PLUS and 0.4637 25.00 11:59
11:59
Materials
02171500140185 SIKAFLEX - 11 FC PLUS and 0.4637 25.00 11:59
11:59
Game 03.17.04.02 PREMIXED CONCRETE ROOF SLAB f'c=280 kg/cm2, 57, CEM I, 4''-6''
Performance m3/DAY MO.25.0000EQ.25.0000 Direct unit cost per: m3 348.15
Code Resource Description Unit Crew Quantity Price S/ Partial S/
Labor
0101040001 CIVIL PEON hh 4.0000 1.2800 18:20 23.30
0101040004 CIVIL WORKER hh 3.0000 0.9600 25.54 24.52
0101040005 Civil Foreman hh 0.1000 0.0320 30.65 0.98
48.80
Materials
02120600130047 PREMIXED CONCRETE TYPE I F´C = 280 kg/cm2 SLUMP 6" H=57 m3 1.0500 245.00 257.25
02450200020004 90 OCTANE GASOLINE gal 0.2200 15.35 3.38
260.63
Teams
03012900010005 4 HP CONCRETE VIBRATOR 2.40" hm 1.1313 0.3620 7.20 2.61
0306010001 HAND TOOLS %mo 3.0000 48.80 1.46
4.07
Subcontracts
04240100010005 CONCRETE PUMPING SERVICE m3 1.0500 33.00 34.65
34.65
20