Transformer Assembly SOP 1300m2 With Machines

The document outlines the layout and machine placements for a 1300 m² transformer assembly workshop, detailing the dimensions and positions of various machines and areas. It includes critical infrastructure recommendations for cranes, foundations, utilities, safety, and access, as well as workflow notes for efficient operations. The document concludes with a suggestion for adjusting machine positions based on specific requirements.

Uploaded by

ygebre024
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views3 pages

Transformer Assembly SOP 1300m2 With Machines

The document outlines the layout and machine placements for a 1300 m² transformer assembly workshop, detailing the dimensions and positions of various machines and areas. It includes critical infrastructure recommendations for cranes, foundations, utilities, safety, and access, as well as workflow notes for efficient operations. The document concludes with a suggestion for adjusting machine positions based on specific requirements.

Uploaded by

ygebre024
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Transformer Assembly Workshop — 1300 m² (65×20) with Machine Placement

Machine placement is indicative. Footprints include working clearances. Confirm final positions with supplier
drawings and structural checks.

Machine Placements & Footprints


Machine/Area Footprint (m × m) Approx Area (m²) Position (x, y) m from
SW corner (approx)
Winding Machine 1 3.5 × 1.8 6.3 22.0, 15.5
Winding Machine 2 3.5 × 1.8 6.3 26.0, 15.5
Winding Machine 3 3.5 × 1.8 6.3 30.0, 15.5
Winding Machine 4 3.5 × 1.8 6.3 34.0, 15.5
Winding Machine 5 3.5 × 1.8 6.3 38.0, 15.5
Vacuum Dryer 4.0 × 2.5 10.0 42.5, 15.0
Test Bench (Electrical) 4.0 × 2.0 8.0 50.0, 14.0
Milling Machine 3.0 × 2.5 7.5 54.5, 14.0
Small Shearing 3.0 × 1.8 5.4 58.5, 14.0
Plasma Cutter (Large) 6.0 × 3.0 18.0 16.0, 6.0
63 t Press (requires 6.0 × 4.0 24.0 8.0, 6.0
foundation)
4 m Bending Machine 5.0 × 2.5 12.5 24.0, 6.0
Tank Fabrication Area 11.0 × 8.0 88.0 1.5, 5.0
(open)
Vacuum Dry & Oil Fill 12.0 × 6.0 72.0 48.5, 4.5
(area)
Packing & Dispatch 16.0 × 4.0 64.0 1.5, 0.5
Stores (Raw Materials) 10.0 × 4.0 40.0 18.0, 0.5
Oil Storage & Filtration 6.0 × 4.0 24.0 30.0, 0.5
WIP Buffer / Spare 8.0 × 4.0 32.0 42.0, 0.5
Final QA/QC 4.0 × 6.0 24.0 58.5, 6.0
Finishing & Accessories 6.0 × 6.0 36.0 52.0, 6.0
Critical Infrastructure & Recommendations
- CRANES:
• Main EOT crane (20 t) covering winding, assembly and testing lanes (central span across top).
• Heavy lifting crane (recommended 63–80 t EOT or mobile gantry) in fabrication bay near 63 t press and tank
fabrication for handling large cores/tanks for 2000–5000 kVA units.
• Jib cranes 0.5–2 t at winding and finishing benches.

- FOUNDATIONS:
• 63 t press requires a dedicated reinforced concrete foundation sized per supplier drawings; expect point loads
in the order of several 100s of kN — engage structural engineer.
• Plasma cutter and bending machine require anchored foundations/plates and fume extraction mounts.

- UTILITIES:
• Power: Dedicated 3ϕ panels for high-power machines (press, plasma, vacuum dryer). Consider 400–630 A
switchboard capacity overall; verify per machine nameplate.
• Compressed air: 6–8 bar with receiver capacity; plasma & shearing may need high flow.
• Ventilation & extraction: Plasma cutter and welding zones require local fume extraction and blast booth
ventilation.
• Oil filtration skid and storage near vacuum/oil fill to minimize transfer piping length.

- SAFETY & ACCESS:


• Maintain minimum 1.2–1.5 m clear aisles for pedestrian movement; 3–4 m for forklift/crane travel lanes.
• Emergency exits and spill containment near oil area.
• HV testing bay must have interlocks, clear barricades and dedicated earth mat.

- WORKFLOW NOTES:
• Place winding machines together in-line for efficient material flow and shared tooling.
• Keep vacuum dryer adjacent to winding area to shorten transfer time.
• Heavy fabrication and press near tank fabrication to reduce movement of heavy plates/assemblies.
• Testing, finishing and packing positioned near end of flow with direct access to dispatch.
Recommended Next Steps
Provided these files, adjust if you want different positions or exact machine models; I can re-run placement with
updated footprints.