Transformer Assembly Workshop — 1300 m² (65×20) with Machine Placement
Machine placement is indicative. Footprints include working clearances. Confirm final positions with supplier
drawings and structural checks.
Machine Placements & Footprints
Machine/Area Footprint (m × m) Approx Area (m²) Position (x, y) m from
SW corner (approx)
Winding Machine 1 3.5 × 1.8 6.3 22.0, 15.5
Winding Machine 2 3.5 × 1.8 6.3 26.0, 15.5
Winding Machine 3 3.5 × 1.8 6.3 30.0, 15.5
Winding Machine 4 3.5 × 1.8 6.3 34.0, 15.5
Winding Machine 5 3.5 × 1.8 6.3 38.0, 15.5
Vacuum Dryer 4.0 × 2.5 10.0 42.5, 15.0
Test Bench (Electrical) 4.0 × 2.0 8.0 50.0, 14.0
Milling Machine 3.0 × 2.5 7.5 54.5, 14.0
Small Shearing 3.0 × 1.8 5.4 58.5, 14.0
Plasma Cutter (Large) 6.0 × 3.0 18.0 16.0, 6.0
63 t Press (requires 6.0 × 4.0 24.0 8.0, 6.0
foundation)
4 m Bending Machine 5.0 × 2.5 12.5 24.0, 6.0
Tank Fabrication Area 11.0 × 8.0 88.0 1.5, 5.0
(open)
Vacuum Dry & Oil Fill 12.0 × 6.0 72.0 48.5, 4.5
(area)
Packing & Dispatch 16.0 × 4.0 64.0 1.5, 0.5
Stores (Raw Materials) 10.0 × 4.0 40.0 18.0, 0.5
Oil Storage & Filtration 6.0 × 4.0 24.0 30.0, 0.5
WIP Buffer / Spare 8.0 × 4.0 32.0 42.0, 0.5
Final QA/QC 4.0 × 6.0 24.0 58.5, 6.0
Finishing & Accessories 6.0 × 6.0 36.0 52.0, 6.0
Critical Infrastructure & Recommendations
- CRANES:
• Main EOT crane (20 t) covering winding, assembly and testing lanes (central span across top).
• Heavy lifting crane (recommended 63–80 t EOT or mobile gantry) in fabrication bay near 63 t press and tank
fabrication for handling large cores/tanks for 2000–5000 kVA units.
• Jib cranes 0.5–2 t at winding and finishing benches.
- FOUNDATIONS:
• 63 t press requires a dedicated reinforced concrete foundation sized per supplier drawings; expect point loads
in the order of several 100s of kN — engage structural engineer.
• Plasma cutter and bending machine require anchored foundations/plates and fume extraction mounts.
- UTILITIES:
• Power: Dedicated 3ϕ panels for high-power machines (press, plasma, vacuum dryer). Consider 400–630 A
switchboard capacity overall; verify per machine nameplate.
• Compressed air: 6–8 bar with receiver capacity; plasma & shearing may need high flow.
• Ventilation & extraction: Plasma cutter and welding zones require local fume extraction and blast booth
ventilation.
• Oil filtration skid and storage near vacuum/oil fill to minimize transfer piping length.
- SAFETY & ACCESS:
• Maintain minimum 1.2–1.5 m clear aisles for pedestrian movement; 3–4 m for forklift/crane travel lanes.
• Emergency exits and spill containment near oil area.
• HV testing bay must have interlocks, clear barricades and dedicated earth mat.
- WORKFLOW NOTES:
• Place winding machines together in-line for efficient material flow and shared tooling.
• Keep vacuum dryer adjacent to winding area to shorten transfer time.
• Heavy fabrication and press near tank fabrication to reduce movement of heavy plates/assemblies.
• Testing, finishing and packing positioned near end of flow with direct access to dispatch.
Recommended Next Steps
Provided these files, adjust if you want different positions or exact machine models; I can re-run placement with
updated footprints.