G.R. No. 204689
G.R. No. 204689
DECISION
LEONEN, J.:
For resolution is a Petition for Review under Rule 45 of the Rules of Court assailing the
1
Decision dated November 20, 2012 of the Court of Appeals in CA-G.R. CV No. 96017. The
2
Court of Appeals ;iffirmed the Decision of the Regional Trial Court of Makati, Branch 133 in Civil
3
This case involves the proper invocation of the Construction Industry Arbitration Committee's
(CIAC) jurisdiction through an arbitration clause in a construction contract. The main issue here
is whether the dispute — liability of a surety under a performance bond — is connected to a
construction contract and, therefore, falls under the exclusive jurisdiction of the CIAC.
Spouses Rune and Lea Stroem (Spouses Stroem) entered into an Owners-Contractor
Agreement with Asis-Leif & Company, Inc. (Asis-Leif) for the construction of a two-storey house
4
on the lot owned by Spouses Stroem. The lot was located at Lot 4A, Block 24, Don Celso
Tuason Street, Valley Golf Subdivision, Barangay Mayamot, Antipolo, Rizal. 5
On November 15, 1999, pursuant to the agreement, Asis-Leif secured Performance Bond No.
LP/G(13)83056 in the amount of ₱4,500,000.00 from Stronghold Insurance Company, Inc.
(Stronghold). Stronghold and Asis-Leif, through Ms. Ma. Cynthia Asis-Leif, bound themselves
6
jointly and severally to pay the Spouses Stroem the agreed amount in the event that the
construction project is not completed.7
Asis-Leif failed to finish the projecton time despite repeated demands of the Spouses Stroem. 8
Spouses Stroem subsequently rescinded the agreement. They then hired an independent
9
Appraiser Asian Appraisal Company, Inc.’s evaluation resulted in the following percentage of
completion: 47.53% of the residential building, 65.62% of the garage, and 13.32% of the
swimming pool, fence, gate, and land development. 11
On April 5, 2001, Stronghold sent a letter to Asis-Leif requesting that the company settle its
obligations withthe Spouses Stroem. No response was received from Asis-Leif. 12
On September 12, 2002, the Spouses Stroem filed a Complaint (with Prayer for Preliminary
Attachment) for breach of contract and for sum of money with a claim for damages against Asis-
13
Leif, Ms. Cynthia Asis-Leif, and Stronghold. Only Stronghold was served summons. Ms. Cynthia
14
On July 13, 2010, the Regional Trial Court rendered a judgment in favor of the Spouses Stroem.
The trial court ordered Stronghold to pay the Spouses Stroem ₱4,500,000.00 with 6% legal
interest from the time of first demand. The dispositive portion of the trial court Decision reads:
16
WHEREFORE, finding plaintiffs’ cause of action to be sufficiently established being supported by
evidence on records, judgement is hereby rendered in favor of the plaintiff spouses Rune and
Lea Stroem and against the defendant Stronghold Insurance Company Incorporated ordering the
latter topay the plaintiff the sums of:
1) Php4,500,000.00 with six (6%) percent legal interest from the time of first demand and
interest due shall earn legal interest from the time of judicial demand until fully paid.
SO ORDERED. 17
Both Stronghold and the Spouses Stroem appealed to the Court of Appeals. 18
The Court of Appeals affirmed with modification the trial court’s Decision. It increased the amount
of attorney’s fees to ₱50,000.00. 19
SO ORDERED. 20
On March 20, 2013, this court required the Spouses Stroem to submit their Comment on the
Petition. We noted the Spouses Stroem’s Comment on July 31, 2013. We also required
21 22
Stronghold to file its Reply to the Comment, which was noted on December 9, 2013.
23 24
Stronghold argues that the trial court did not acquire jurisdiction over the case and, therefore, the
Court of Appeals committed reversible error when it upheld the Decision of the Regional Trial
Court. The lower courts should have dismissed the case in viewof the arbitration clause in the
25
agreement and considering that "[Republic Act No. 876] explicitly confines the court’s authority
only to pass upon the issue of whether there is [an] agreement . . . providing for arbitration. In the
affirmative, the statute ordains that the court shall issue an order ‘summarily directing the parties
to proceed with the arbitration in accordance with the terms thereof.’" Moreover, "the stipulations
26
in said Agreement are part and parcel of the conditions in the bond. Were it not for such
stipulations in said agreement, [Stronghold] would not have agreed to issue a bond in favor of
the Spouses Stroem. The parties tothe bond are ALB/Ms. Asis-[L]eif, Spouses Stroem and
[Stronghold] suchthat ALB/Ms. Asis-[L]eif never ceased to be a party to the surety agreement." 27
In any case, Stronghold’s liability under the performance bond is limited only to additional costs
for the completion of the project. In addition, the Court of Appeals erred inholding that
28
Stronghold changed its theory with regard to the notice requirement and in modifying the trial
29
On the other hand, the Spouses Stroem argue that Stronghold committed forum shopping
warranting dismissal of the case. According to the Spouses Stroem, Stronghold deliberately
31
committed forum shopping when it filed the present petition despite the pendency of the Spouses
Stroem’s Motion for Partial Reconsideration of the Court of Appeals Decision dated November
20, 2012. 32
More importantly, the Owners-Contractor Agreement is "separate and distinct from the Bond.
The parties to the Agreement are ALB/Ms. Asis-Leif and Spouses Stroem, while the parties to
the Bond are Spouses Stroem and Stronghold. The considerations for the two contracts are
likewise distinct. Thus, the arbitration clause in the Agreement is binding only on the parties
thereto, specifically ALB/Ms. Asis-Leif and Spouses Stroem[.]" 33
Contrary to Stronghold’s argument, Spouses Stroem argues that stronghold is liable for the full
amountof the performance bond. The terms of the bond clearly show that Stronghold is liable as
surety. Verily, notice to Stronghold is not required for its liability to attach.
34 35
(2) Whether the CIAC has exclusive jurisdiction over the controversy between the parties;
(3) Whether the Regional Trial Court should have dismissed the petition outright as
required by law and jurisprudence and referred the matter to the CIAC; and
(4) Whether petitioner Stronghold Insurance Company, Inc. is liable under Performance
Bond No. LP/G(13)83056.
(a) Whether petitioner Stronghold Insurance Company, Inc. is only liable as to the extent
of any additional cost for the completion of the project due toany increase in prices for
labor and materials.
After considering the parties’ arguments and the records of this case, this court resolves to deny
the Petition.
On forum-shopping
Respondents argue that petitioner committed forum shopping; hence, the case should have been
dismissed outright.
Records show that petitioner received a copy of the Decision of the Court of Appeals on
December 5, 2012. Petitioner did not file a Motion for Reconsideration of the assailed Decision.
36
It filed before this court a Motion for Extension of Time To File Petition for Review requesting an
additional period of 30 days from December 20, 2012 or until January 19, 2013 to file the
Petition. 37
Respondents filed their Motion for Partial Reconsideration of the Court of Appeals Decision on
December 11, 2012. They sought the modification of the Decision as to the amounts of moral
38
Respondents alleged in their Comment that as early as January 9, 2013, petitioner received a
copy of the Court of Appeals’ Resolution requiring Comment on the Motion for Partial
Reconsideration. Still, petitioner did not disclose in its Verification and Certification Against
40
For its part, petitioner claims that it did not commit forum shopping. It fully disclosed in its Petition
that what it sought to be reviewed was the Decision dated November 20, 2012 of the Court of
Appeals. "Petitioner merely exercised its available remedy with respect to the Decision of the
Court of Appeals by filing [the] Petition." What the rules mandate to be stated in the Certification
42
Against Forum Shopping is the status of "any other action." This other action involves the same
issues and parties but is an entirely different case.
as a result of an adverse opinion in one forum, a party seeks a favorable opinion (other than by
appeal or certiorari) in another. The principle applies not only with respect to suits filed in the
courts but also in connection with litigations commenced in the courts while an administrative
proceeding is pending[.] (Citation omitted)
43
This court has enumerated the elements of forum-shopping: "(a) identity of parties, or at least
such parties as represent the same interests in both actions; (b) identity of rights asserted and
reliefs prayed for, the reliefs being founded on the same facts; and (c) the identity with respect to
the two preceding particulars in the two cases issuch that any judgment rendered in the pending
cases, regardless of which party is successful, amount to res judicatain the other case." Rule
44
42, Section 2 in relation to Rule 45, Section 4 of the Rules of Court mandates petitioner to
45
submit a Certification Against Forum Shopping and promptly inform this court about the
pendency of any similar action or proceeding before other courts or tribunals. The rule’s purpose
is to deter the unethical practice of pursuing simultaneous remedies in different forums, which
"wreaks havoc upon orderly judicial procedure." Failure to comply with the rule is a sufficient
46
Records show that petitioner’s duly authorized officer certified the following on January 21, 2013:
4. I further certify that: (a) I have not commenced any other action or proceeding involving the
same issues in the Supreme Court, Court of Appeals, or any other tribunal or agency; (b) to the
best of my knowledge, no such action or proceeding is pending in the Supreme Court, the Court
of Appeals or different Divisions thereof, or any tribunal or agency; (c) if I should thereafter learn
that a similar action or proceeding has been filed or is pending before the Supreme Court, the
Court of Appeals, or different Divisions thereof, or any other tribunal or agency, I undertake to
promptly inform the aforesaid courts and such tribunal or agency of the fact within five (5) days
therefrom.48
Petitioner failed to carry out its duty of promptly informing this court of any pending action or
proceeding before this court,the Court of Appeals, or any other tribunal or agency. This court
cannot countenance petitioner’s disregard of the rules.
Petitioner changed the theory of its case since its participation in the trial court proceedings. It
raised the issue of lack of jurisdiction in view of an arbitration agreement for the first time.
Generally, parties may not raise issues for the first time on appeal. Such practice is violative of
50
the rules and due process and is frowned upon by the courts. However, it is also well-settled that
jurisdiction can never be waived or acquired by estoppel. Jurisdiction is conferred by the
51
Constitution or by law. "Lack of jurisdiction of the court over an action or the subject matter of an
52
action cannot be cured by the silence, by acquiescence, or even by express consent of the
parties."
53
Section 4 of Executive Order No. 1008 is clear in defining the exclusive jurisdiction of the CIAC:
54
SECTION 4. Jurisdiction – The CIAC shall have original and exclusive jurisdiction over disputes
arising from, or connected with, contracts entered into by parties involved in construction in the
Philippines, whether the dispute arises before or after the completion of the contract, or after the
abandonment or breach thereof. These disputes may involve government or private contracts.
For the Board to acquire jurisdiction, the parties to a dispute must agree to submit the same to
voluntary arbitration.
The jurisdiction of the CIAC may include but is not limited to violation of specifications for
materials and workmanship; violation of the terms of agreement; interpretation and/or application
of contractual timeand delays; maintenance and defects; payment, default of employer or
contractor and changes in contract cost.
Excluded from the coverage of thislaw are disputes arising from employer-employee
relationships which shall continue to be covered by the Labor Code of the Philippines. (Emphasis
supplied)
Similarly, Section 35 of RepublicAct No. 9285 or the Alternative Dispute Resolution Act of 2004
states:
SEC. 35. Coverage of the Law. - Construction disputes which fall within the original and
exclusive jurisdiction of the Construction Industry Arbitration Commission (the "Commission")
shall include those between or among parties to, or who are otherwise bound by, an arbitration
agreement, directly or by reference whether such parties are project owner, contractor,
subcontractor, quantity surveyor, bondsman or issuer of an insurance policy in a construction
project.
The Commission shall continue to exercise original and exclusive jurisdiction over construction
disputes although the arbitration is "commercial" pursuant to Section 21 of this Act. (Emphasis
supplied)
In Heunghwa Industry Co., Ltd., v. DJ Builders Corporation, this court held that "there are two
55
acts which may vest the CIAC with jurisdiction over a construction dispute. One is the presence
of an arbitration clause in a construction contract, and the other is the agreement by the parties
to submit the dispute to the CIAC." 56
This court has ruled that when a dispute arises from a construction contract, the CIAC has
exclusive and original jurisdiction. Construction has been defined as referring to "all on-site
57
works on buildings or altering structures, from land clearance through completion including
excavation, erection and assembly and installation of components and equipment." 58
In this case, there is no dispute asto whether the Owners-Contractor Agreement between Asis-
Leif and respondents is a construction contract. Petitioner and respondents recognize that CIAC
has jurisdiction over disputes arising from the agreement.
What is at issue in this case is the parties’ agreement, or lack thereof, to submit the case to
arbitration. Respondents argue that petitioner is not a party to the arbitration agreement.
Petitioner did not consent to arbitration. It is only respondent and Asis-Leif thatmay invoke the
arbitration clause in the contract.
This court has previously held that a performance bond, which is meant "to guarantee the supply
of labor,materials, tools, equipment, and necessary supervision to complete the project[,]" is59
significantly and substantially connected to the construction contract and, therefore, falls under
the jurisdiction of the CIAC.60
Prudential Guarantee and Assurance Inc. v. Anscor Land, Inc. involved circumstances similar to
61
the present case. In Prudential, property owner Anscor Land, Inc. (ALI) entered into a contract for
the construction of an eight-unit townhouse located inCapitol Hills, Quezon City with contractor
Kraft Realty and Development Corporation (KRDC). KRDC secured the completion of the
62
construction project through a surety and performance bond issued by Prudential Guarantee and
Assurance Inc. (PGAI). 63
The delay in the construction project resulted in ALI’s termination of the contract and claim
against the performance bond. "ALI [subsequently] commenced arbitration proceedings against
64
KRDC and PGAI in the CIAC." PGAI, however, argued that it was not a party to the construction
65
contract. 66
The CIAC ruled that PGAI was not liable under the performance bond. Upon review, the Court
67
of Appeals held that PGAI was jointly and severally liable with KRDC under the performance
bond.68
PGAI appealed the Court of Appeals Decision and claimed that CIAC did not have jurisdiction
over the performance bond. This court ruled:
69
A guarantee or a surety contract under Article 2047 of the Civil Code of the Philippines is an
accessory contract because it is dependent for its existence upon the principal obligation
guaranteed by it.
In fact, the primary and only reason behind the acquisition of the performance bond by KRDC
was to guarantee to ALI that the construction project would proceed in accordance with the
contract terms and conditions. In effect, the performance bond becomes liable for the completion
of the construction project in the event KRDC fails in its contractual undertaking. Because of the
performance bond, the construction contract between ALI and KRDC is guaranteed to be
performed even if KRDC fails in its obligation. In practice, a performance bond is usually a
condition or a necessary component of construction contracts. In the case at bar, the
performance bond was so connected with the construction contract that the former was agreed
by the parties to be a condition for the latter to push through and at the same time, the former is
reliant on the latter for its existence as an accessory contract.
Although not the construction contract itself, the performance bond is deemed as an associate of
the main construction contract that it cannot be separated or severed from its principal. The
Performance Bond is significantly and substantially connected to the construction contract that
there can be no doubt it is the CIAC, under Section 4 of EO No. 1008, which has jurisdiction over
any dispute arising from or connected with it. (Emphasis supplied, citations omitted)
70
At first look, the Owners-Contractor Agreement and the performance bond reference each other;
the performance bond was issued pursuant to the construction agreement.
that the . . . contractor, will faithfully comply with the requirements of the contract . . . and make
good [on the] damages sustained by the project owner in case of the contractor’s failure to so
perform." 72
It is settled that the surety’s solidary obligation for the performance of the principal debtor’s
obligation is indirect and merely secondary. Nevertheless, the surety’s liability tothe "creditor or
73
promisee of the principal is said to be direct, primary and absolute; in other words, he is directly
and equally bound with the principal." 74
ART. 1374. The various stipulations of a contract shall be interpreted together, attributing to the
doubtful ones that sense which may result from all of them taken jointly.
In the case at bar, the performance bond was silent with regard to arbitration. On the other hand,
the construction contract was clear as to arbitration in the event of disputes. Applying the said
doctrine, we rule that the silence of the accessory contract in this case could only be construed
as acquiescence to the main contract. The construction contract breathes life into the
performance bond. We are not ready to assume that the performance bond contains reservations
with regard to some of the terms and conditions in the construction contract where in fact it is
silent. On the other hand, it is more reasonable to assume that the party who issued the
performance bond carefully and meticulously studied the construction contract that it guaranteed,
and if it had reservations, it would have and should have mentioned them in the surety
contract. (Emphasis supplied)
76
This court, however, cannot apply the ruling in Prudential to the present case. Several factors
militate against petitioner’s claim.
The contractual stipulations in this case and in Prudential are different. The relevant provisions of
the Owners-Contractor Agreement in this case state:
The following documents prepared by the CONTRACTOR shall constitute an integral part of this
contract as fully as if hereto attached or herein stated, except asotherwise modified by mutual
agreement of parties, and attached to this agreement.
....
7.1 Within 30 days of the signing of this agreement, CONTRACTOR shall provide to
OWNERS a performance bond, issued by a duly licensed authority acceptable to the
OWNERS, and equal to the amount of PHP 4,500,000.00 (Four Million and Five Hundred
Thousand Philippine Pesos),with the OWNERS as beneficiary.
7.2 The performance bond will guarantee the satisfactory and faithful performance by the
CONTRACTOR of all provisions stated within this contract.
ARTICLE 8. ARBITRATION
8.1 Any dispute between the parties hereto which cannot be amicably settled shall be finally
settled by arbitration in accordance with the provision of Republic Act 876, of The Philippines, as
amended by the Executive Order 1008 dated February 4, 1985. (Emphasis in the original)
77
Article 1
CONTRACT DOCUMENTS
1.1 The following shall form part of this Contractand together with this Contract, are known as the
"Contract Documents":
a. Bid Proposal
....
d. Notice to proceed
....
j. Appendices A & B (respectively, Surety Bond for Performance and, Supply of Materials
by the Developer) (Emphasis supplied)
78
This court in Prudential held that the construction contract expressly incorporated the
performance bond into the contract. In the present case, Article 7 of the Owners-Contractor
79
Agreement merely stated that a performance bond shall be issued in favor of respondents, in
which case petitioner and Asis-Leif Builders and/or Ms. Ma. Cynthia Asis-Leif shall pay
₱4,500,000.00 in the event that Asis-Leif fails to perform its duty under the Owners-Contractor
Agreement. Consequently, the performance bond merely referenced the contract entered into
80
To be clear, it is in the Owners-Contractor Agreement that the arbitration clause is found. The
1âwphi1
construction agreement was signed only by respondents and the contractor, Asis-Leif, as
represented by Ms. Ma. Cynthia Asis-Leif. It is basic that "[c]ontracts take effect only between the
parties, their assigns and heirs[.]" Not being a party to the construction agreement, petitioner
82
cannot invoke the arbitration clause. Petitioner, thus, cannot invoke the jurisdiction of the CIAC.
Moreover, petitioner’s invocation of the arbitration clause defeats the purpose of arbitration in
relation to the construction business. The state has continuously encouraged the use of dispute
resolution mechanisms to promote party autonomy. In LICOMCEN, Incorporated v. Foundation
83
Specialists, Inc., this court upheld the CIAC's jurisdiction in line with the state's policy to promote
84
arbitration:
The CIAC was created through Executive Order No. 1008 (E. 0. 1008), in recognition of the need
to establish an arbitral machinery that would expeditiously settle construction industry disputes.
The prompt resolution of problems arising from or connected with the construction industry was
considered of necessary and vital for the fulfillment of national development goals, as the
construction industry provides employment to a large segment of the national labor force and is a
leading contributor to the gross national product. (Citation omitted)
85
SO ORDERED.
WE CONCUR:
ANTONIO T. CARPIO
Associate Justice
Chairperson
ATTESTATION
I attest that the conclusions in the above Decision had been reached in consultation before the
case was assigned to the writer of the opinion of the Court's Division.
ANTONIO T. CARPIO
Associate Justice
Chairperson, Second Division
CERTIFICATION
Pursuant to Section 13, Article VIII of the Constitution and the Division Chairperson's Attestation,
I certify that the conclusions in the above Decision had been reached in consultation before the
case was assigned to the writer of the opinion of the Court's Division.
Footnotes
* Designated acting member per S.O. No. 1910 dated January 12, 2015.
1
Rollo, pp. 38-62.
2
Id. at 194-211. The decision was penned by Associate Justice Angelita A. Gacutan and
concurred in by Associate Justices Fernanda Lampas Peralta (Chair) and Edwin D.
Sorongon of the Special Tenth Division.
3
Id. at 122-129.
4
Id. at 67–73 and 75. Asis-Leif was initially a single proprietorship under the name Asis-
Leif Builders represented by its owner, Ms. Ma. Cynthia Asis-Leif.
5
Id. at 68 and 195.
6
Id. at 75 and 195.
7
Id.
8
Id. at 196.
9
Id.
10
Id.
11
Id.
12
Id.
13
Id. at 79–88.
14
Id. at 197.
15
Id.
16
Id. at 129.
17
Id.
18
Id. at 199.
19
Id. at 210.
20
Id.
21
Id. at 213.
22
Id. at 784.
23
Id.
24
Id. at 803.
25
Id. at 45.
26
Id. at 46.
27
Id. at 793.
28
Id. at 48.
29
Id. at 53.
30
Id. at 57.
31
Id. at 226.
32
Id. at 226–227.
33
Id. at 228.
34
Id. at 229–230.
35
Id. at 231.
36
Id. at 44.
37
Id. at 40.
38
Id. at 225.
39
Id.
40
Id. at 227.
41
Id.
42
Id. at 791.
First Philippine International Bank v. Court of Appeals, 322 Phil. 280, 305 (1996) [Per J.
43
United Overseas Bank Phils. v. Rosemoor Mining & Development Corp., 547 Phil. 38,
44
45
SEC. 2. Form and contents.— . . . .
The petitioner shall also submit together with the petition a certification under
oath that he has not there to fore commenced any other action involving the
same issues in the Supreme Court, the Court of Appeals or different divisions
thereof, or any other tribunal or agency; if there is such other action or
proceeding, he must state the status of the same; and if he should thereafter
learn that a similar action or proceeding has been filed or is pending before the
Supreme Court, the Court of Appeals, or different divisions thereof, or any other
tribunal or agency, he undertakes to promptly inform the aforesaid courts and
other tribunal or agency thereof within five (5) days therefrom. (Emphasis
supplied)
Spouses Arevalo v. Planters Development Bank, et al., G.R. No. 193415, April 18,
46
2012, 670 SCRA 252, 264 [Per J. Sereno, Second Division] See Philippine Public School
Teachers Association v. Heirs of Carolina P. Iligan, 528 Phil. 1197, 1209 (2006) [Per J.
Callejo, Sr., First Division]; Far Eastern Shipping Company v. Court of Appeals, 357 Phil.
703, 716–723 (1998) [Per J. Regalado, En Banc].
RULES OF COURT, Rule 42, sec. 3. See Philippine Rabbit Bus Lines, Inc. v. Aladdin
47
Transit Corp., 526 Phil. 837, 847 (2006) [Per J. Carpio Morales, Third Division].
48
Rollo, p. 66.
First Philippine International Bank v. Court of Appeals, 322 Phil. 280, 313 (1996) [Per J.
49
Corporation, 524 Phil. 318, 335 (2006) [Per J. Callejo, Sr., First Division].
51
See Soriano v. Bravo, G.R. No. 152086, December 15, 2010, 638 SCRA 403, 422 [Per
J. Leonardo-De Castro, First Division] and BF Homes, Inc. v. Manila Electric Company,
651 Phil. 211, 235 (2010) [Per J. Leonardo-De Castro, First Division].
See Gomez-Castillo v. Commission on Elections, 635 Phil. 480, 486–487 (2010) [Per J.
52
Bersamin, En Banc].
Municipality of Pateros v. Court of Appeals, 607 Phil. 104, 116 (2009) [Per J. Nachura,
53
Third Division].
54
Otherwise known as Construction Industry Arbitration Law.
55
593 Phil. 632 (2008) [Per J. Austria-Martinez, Third Division].
56
Id. at 649.
57
See Hi-Precision Steel Center, Inc.v. Lim Kim Steel Builders, Inc., G.R. No. 110434,
December 13, 1993, 228 SCRA 397, 405 [Per J. Feliciano, Third Division Resolution] and
Metropolitan Cebu Water District v. Mactan Rock Industries, Inc., G.R. No. 172438, July
4, 2012, 675 SCRA 577, 597 [Per J. Mendoza, Third Division].
Fort Bonifacio Development Corporation v. Sorongon, 605 Phil. 689, 696 (2009) [Per J.
58
Tinga, Second Division]. See also Gammon Philippines, Inc. v. Metro Rail Transit
Development Corporation, 516 Phil. 561, 569 (2006) [Per J. Tinga, Third Division] and
Fort Bonifacio Development Corporation v. Domingo, 599 Phil. 554, 564 (2009) [Per J.
Chico-Nazario, Third Division].
Prudential Guarantee and Assurance Inc. v. Anscor Land, Inc., G.R. No. 177240,
59
September 8, 2010, 630 SCRA 368, 376 [Per J. Villarama, Jr., Third Division].
60
Id. at 377.
G.R. No. 177240, September 8, 2010, 630 SCRA 368 [Per J. Villarama, Jr., Third
61
Division].
62
Id. at 370.
63
Id. at 371.
64
Id.
65
Id. at 372.
66
Id.
67
Id.
68
Id. at 373.
69
Id.
70
Id. at 376–377.
Corporation, G.R. No. 180898, April 18, 2012, 670 SCRA 166, 179 [Per J. Mendoza,
Third Division]. See CIVIL CODE, art. 2047; See also INS. CODE, art. 175.
See Eastern Assurance & Surety Corporation v. Intermediate Appellate Court, 259 Phil.
72
Phil. 270, 280 (2006) [Per C.J. Panganiban, First Division], Philippine Bank of
Communications v. Lim, 495 Phil. 645, 651 (2005) [Per C.J. Panganiban, Third Division],
and Philippine Charter Insurance Corporation v. Petroleum Distributors & Service
Corporation, G.R. No. 180898, April 18, 2012, 670 SCRA 166, 179 [Per J. Mendoza,
Third Division].
270, 280 (2006) [Per C.J. Panganiban, First Division],citing Garcia, Jr. v. Court of
Appeals, G.R. No. 80201, November 20, 1990, 191 SCRA 493, 496 [Per J. Cruz, First
Division].
Philippine Bank of Communications v. Lim, 495 Phil. 645, 652 (2005) [Per C.J.
75
Prudential Guarantee and Assurance Inc. v. Anscor Land, Inc., G.R. No. 177240,
76
September 8, 2010, 630 SCRA 368, 379 [Per J. Villarama, Jr., Third Division].
77
Rollo, pp. 69–71.
Prudential Guarantee and Assurance Inc. v. Anscor Land, Inc., G.R. No. 177240,
78
September 8, 2010, 630 SCRA 368, 374 [Per J. Villarama, Jr., Third Division].
79
Id.
80
Rollo, p. 75.
81
Id.
82
CIVIL CODE, art. 1311. See Tan v. G.V.T. Engineering Services, 529 Phil. 751, 771
(2006) [Per J. Austria-Martinez, First Division].
83
See Rep. Act No. 9285 (2004), sec. 2.
84
G.R. No. 167022, April 4, 2011, 647 SCRA 83 [Per J. Brion, Third Division].
85
Id. at 96.