Tendernotice 1
Tendernotice 1
Volume-I
TECHNICAL PROPOSAL
WAPCOS LIMITED
CONSTRUCTION MANAGEMENT UNIT- III
1st Floor, NPCC, BUILDING, PLOT NO. 148,
SECTOR-44, GURUGRAM-122003, HARYANA
August 2025
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
DISCLAIMER
Sashastra Seema Bal (SSB), A Cental Armed Paramilitary Force (CAPF) under Ministry of Home
Affairs, Government of India, has engaged WAPCOS Limited as Project Management Consultant
for Construction & Development of Infrastructure Works at various formations of SSB in India. This
Tender Document has been prepared to give information on the Project to the interested Bidders.
The information is provided to Bidders on the terms and conditions set-out in this document and any
other terms and conditions subject to which such information is provided.
The purpose of this document is to provide Bidders with information to assist the formulation of their
bid. The information is not intended to be exhaustive. Bidders are required to make their own inquiries
and respondents will be required to confirm in writing that they have done so and they do not rely
solely on the information in the document.
The information is provided on the basis that it is non-binding on SSB / WAPCOS Limited, any of
its authorities or agencies or subsidiaries or any of their respective officers, employees, agents or
advisors.
Information provided in this document to the Applicants is on a wide range of matters, some of which
depends upon interpretation of law. The information given is not an exhaustive account of statutory
requirements and should not be regarded as a complete or authoritative statement of law. WAPCOS
accepts no responsibility for the accuracy or otherwise for any interpretation or opinion on the law
expressed herein.
SSB / WAPCOS Limited reserve the right to not proceed with the Project or to change the
configuration of the Project, to alter the timetable reflected in this document or to change the process
or procedure to be applied. It also reserves the right to decline to discuss the Project further with
any party submitting the Bid.
While WAPCOS Limited have taken due care in the preparation of the information contained herein
and believe it to be accurate, neither SSB nor WAPCOS Limited, any of its authorities or agencies
nor any of their respective officers, employees, agents or advisors gives any warranty or make any
representations, express or implied as to the completeness or accuracy of the information contained
in this document or any information which may be provided in association with it.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
TABLE OF CONTENT
VOLUME-I
SECTIONS PARTICULAR
NOTICE INVITING TENDER (NIT)
SECTION I INSTRUCTIONS TO BIDDER
SECTION II SELECTION AND QUALIFYING CRITERIA
SECTION III FORMS
LETTER OF TRANSMITTAL
FORM A : FINANCIAL INFORMATION
FORM B : SOLVENCY / BANKER’S CERTIFICATE
FORM C : CORRESPONDENCE DETAILS OF ISSUING AUTHORITY
FORM D : BID CAPACITY
FORM E : STRUCTURE & ORGANISATION
FORM F : UNDERTAKING FOR MANPOWER DEPLOYMENT
FORM G : NO-CONVICTION CERTIFICATE
FORM-H: NO DEVIATION CERTIFICATE
FORM I : UNDERTAKING REGARDING BLACKLISTING / NON DEBARMENT
FORM-J: UNDERTAKING FOR RULE 144 (XI) IN THE GENERAL FINANCIAL
RULES-2017
FORM-K1 & K2: UNDERTAKING REGARDING PERCENTAGE OF LOCAL
CONTENT
FORM-L: LETTER FOR INTEGRITY AND INTEGRITY AGREEMENT
SECTION IV GENERAL CONDITIONS OF CONTRACT
SECTION V SPECIAL CONDITIONS OF CONTRACT
SECTION VI ANNEXURES
ANNEXURE - I : FORMAT FOR CONTRACT AGREEMENT
ANNEXURE - II : FORMAT FOR LETTER OF AWARD
ANNEXURE - III: FORMAT FOR PERFORMANCE BANK GUARANTEE
ANNEXURE - IV: STANDARD FORMAT OF SBLC
ANNEXURE - V : FORMAT FOR INDENTURE FOR SECURED ADVANCES
ANNEXURE - VI : FORMAT FOR BANK GUARANTEE FOR EMD
ANNEXURE - VII: FORMAT FOR SEEKING EXTENSION OF TIME
ANNEXURE - VIII :FORMAT FOR GUARANTEE BONDS / AFFIDAVIT FOR WORK
ANNEXURE - IX :FORMAT FOR GUARANTE BONDS WATER PROOFING
AFTER COMPLETION OF WORK
ANNEXURE- X: FORMAT FOR GUARANTEE BOND FOR ANTI-TERMITE
TREATMENT
ANNEXURE - XI :SAFETY CODES
ANNEXURE - XII :MODEL RULES FOR THE PROTECTION OF HEALTH AND
SANITARY ARRANGEMENTS
ANNEXURE - XIII :CONTRACTOR’s LABOUR REGULATIONS
SECTION VII TERMS OF REFERENCE
The tender document has to be viewed/ downloaded from above specified websites. Bidders are
advised to visit above specified websites regularly for updates /Amendments/ Corrigendum, if any
and not be published elsewhere. The Updates/Corrigendum/Addendum shall be followed up to
submission of tender and it will be the part of tender.
The purpose of this NIT is to provide interested parties with information to assist the preparation of their
bid. While WAPCOS Limited has taken due care in the preparation of the information contained herein,
and believe it to be complete and accurate, neither it nor any of its authorities or agencies nor any of its
respective officers, employees, agents or advisors give any warranty or make any representations,
expressed or implied as to the completeness or accuracy of the information contained in this document
or any information which may be provided in association with it. The Bidders must read all the terms and
conditions of bidding document carefully and only submit the bid if eligible and in possession of all the
documents required.
Further, WAPCOS Limited does not claim that the information is exhaustive. Respondents to this NIT
are required to make their own inquiries/ surveys and will be required to confirm, in writing, that they have
done so and they did not rely solely on the information in NIT. WAPCOS Limited is not responsible if no
due diligence is performed by the bidders.
If the office of WAPCOS Limited, New Delhi happens to be closed on the last date and time mentioned
for any of the event, the said event will take place on the next working day at the same time and venue.
IMPORTANT POINTS
1.1 Bidder/ Contractor should be an Indian Registered Company under Companies Act 1956/
2013, Proprietorship Firm/ Partnership Firm. Joint Ventures are not accepted
1.2 Principal Employer/ Owner/Client means of Sashastra Seema Bal, Ministry of Home Affairs, Gov.t
of India herein referred as “SSB”.
1.3 Employer” shall mean “WAPCOS Limited”, A Government of India undertaking- Ministry of Jal
Shakti, as Project Management Consultant appointed by the SSB.
1.4 All Bidders are hereby cautioned that Bids containing any deviation or reservation as described
in Clauses of “Instructions to Bidders” shall be considered as non-responsive and shall be
summarily rejected.
1.5 WAPCOS Ltd. reserves the right to accept or reject any or all bids without assigning any reasons.
No Bidder shall have any cause of action or claim against the WAPCOS Ltd. For rejection of his
Bid and will not be bound to accept the lowest or any other tender.
1.6 No reimbursement of cost of any type or on any account will be paid to persons or entities
submitting their Bid.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
1.7 All information submitted in response to this NIT shall be the property of WAPCOS Limited and
it shall be free to use the concept of the same at its will.
1.8 It is hereby declared that WAPCOS is committed to follow the principle of transparency, equity
and competitiveness in public procurement. The subject Notice Inviting Tender (NIT) is an
invitation to offer made on the condition that the Bidder will sign the integrity Agreement, which
is an integral part of tender/bid documents, failing which the tenderer/bidder will stand disqualified
from the tendering process and the bid of the bidder would be summarily rejected. This
declaration shall form part and parcel of the Integrity Agreement and signing of the same shall
be deemed as acceptance and signing of the Integrity Agreement on behalf of the WAPCOS.
For and on behalf of WAPCOS LIMITED
-sd-
Chief Engineer
Construction Management Unit – III
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
SECTION– I
INSTRUCTIONS TO BIDDER
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
SECTION– I
INSTRUCTIONS TO BIDDER
1.0 SPECIAL INSTRUCTIONS TO BIDDERS FOR E-TENDERING
1.1 GENERAL
Submission of Online Bids is mandatory for this Tender. E-Tendering is a new methodology
for conducting Public Procurement in a transparent and secured manner. For conducting
electronic tendering, bidders shall use the portal www.etenders.gov.in/ eprocure. Tender is
invited in Single Stage –Two Envelope system, one Technical Bid and second as financial
bid. Accordingly, bidder is directed to make all formalities and registration on
www.etenders.gov.in/eprocure website and submit the Technical Bid and Financial bid.
The bidders are required to submit soft copies of their bids electronically on the CPP Portal,
using valid Digital Signature Certificates. The instructions given below are meant to assist
the bidders in registering on the CPP Portal, prepare their bids in accordance with the
requirements and submitting their bids online on the CPP Portal.
More information useful for submitting online bids on the CPP Portal may be obtained
at: https://etenders.gov.in/eprocure/app.
1.2 REGISTRATION
1) Bidders are required to enroll on the e-Procurement module of the Central Public
Procurement Portal (URL: https://etenders.gov.in/eprocure/app) by clicking on the
link “Online bidder Enrollment” on the CPP Portal which is free of charge.
2) As part of the enrolment process, the bidders will be required to choose a unique
username and assign a password for their accounts.
3) Bidders are advised to register their valid email address and mobile numbers as part
of the registration process. These would be used for any communication from the
CPP Portal.
4) Upon enrolment, the bidders will be required to register their valid Digital Signature
Certificate (Class III Certificates with signing key usage) issued by any Certifying
Authority recognized by CCA India (e.g. Sify / nCode / eMudhra etc.), with their profile.
5) Only one valid DSC should be registered by a bidder. Please note that the bidders
are responsible to ensure that they do not lend their DSC’s to others which may lead
to misuse.
6) Bidder then logs in to the site through the secured log-in by entering their user ID
/Password and the password of the DSC / e-Token.
search for tenders, wherein the bidders may combine a number of search parameters
such as Organization Name, Form of Contract, Location, Date, Other keywords etc.
to search for a tender published on the CPP Portal.
2) Once the bidders have selected the tenders they are interested in, they may
download the required documents / tender schedules. These tenders can be moved
to the respective ‘My Tenders’ folder. This would enable the CPP Portal to intimate
the bidders through SMS / e- mail in case there is any corrigendum issued to the
tender document.
3) The bidder should make a note of the unique Tender ID assigned to each tender, in
case they want to obtain any clarification / help from the Helpdesk.
b) Bidder should read the tender document, corrigendum, Addendum and any other
related correspondence, carefully to understand the documents required to be
submitted as part of the bid.
c) Bidder, in advance, should get ready the bid documents to be submitted as indicated
in the tender document / schedule and generally, they can be in PDF / XLS / RAR /
DWF/JPG formats. Bid documents may be scanned with 100 dpi with black and white
option which helps in reducing size of the scanned document.
2) Bidder should log into the site well in advance for bid submission so that they can
upload the bid in time i.e. on or before the bid submission time. Bidder will be
responsible for any delay due to other issues.
3) Bidder should log into the site well in advance for bid submission so that they can
upload the bid in time i.e. on or before the bid submission time. Bidder will be
responsible for any delay due to other issues.
4) The bidder has to digitally sign and upload the required bid documents one by one
as indicated in the tender document.
5) Bidder has to select the payment option as “offline” to pay the tender fee / EMD as
applicable and enter details of the instrument.
6) Bidder should prepare the EMD as per the instructions specified in the tender
document. The original should be posted/couriered/given in person to the concerned
official, latest by the last date of bid submission or as specified in the tender
documents. The details of the DD/any other accepted instrument, physically sent,
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
should tally with the details available in the scanned copy and the data entered
during bid submission time. Otherwise the uploaded bid will be rejected.
7) Bidders are requested to note that they should necessarily submit their financial bids
in the format provided and no other format is acceptable. If the price bid has been
given as a standard BoQ format with the tender document, then the same is to be
downloaded and to be filled by all the bidders. Bidders are required to download the
BoQ file, open it and complete the white coloured (unprotected) cells with their
respective financial quotes and other details (such as name of the bidder). No other
cells should be changed. Once the details have been completed, the bidder should
save it and submit it online, without changing the filename. If the BoQ file is found to
be modified by the bidder, the bid will be rejected.
8) The server time (which is displayed on the bidders’ dashboard) will be considered as
the standard time for referencing the deadlines for submission of the bids by the
bidders, opening of bids etc. The bidders should follow this time during bid
submission.
9) All the documents being submitted by the bidders would be encrypted using PKI
encryption techniques to ensure the secrecy of the data. The data entered cannot be
viewed by unauthorized persons until the time of bid opening. The confidentiality of
the bids is maintained using the secured Socket Layer 128 bit encryption technology.
Data storage encryption of sensitive fields is done. Any bid document that is uploaded
to the server is subjected to symmetric encryption using a system generated
symmetric key. Further this key is subjected to asymmetric encryption using
buyers/bid opener’s public keys. Overall, the uploaded tender documents become
readable only after the tender opening by the authorized bid openers.
10) The uploaded tender documents become readable only after the tender opening by
the authorized bid openers.
11) Upon the successful and timely submission of bids (i.e. after Clicking “Freeze Bid
Submission” in the portal), the portal will give a successful bid submission message
& a bid summary will be displayed with the bid no. and the date & time of submission
of the bid with all other relevant details.
12) The bid summary has to be printed and kept as an acknowledgement of the
submission of the bid. This acknowledgement may be used as an entry pass for any
bid opening meetings.
Project, observe the highest standard of ethics during the performance, procurement
and execution of such contracts. In pursuance of this requirement, WAPCOS Limited,
defines, for the purposes of this provision, the terms set forth below:
i. “Corrupt Practice” means the offering, giving, receiving, or soliciting, directly or
indirectly, anything of value to influence improperly the actions of another party;
ii. “Fraudulent Practice” means any act of submission of forged documentation, or
omission, including a misrepresentation, that knowingly or recklessly misleads,
or attempts to mislead, a party to obtain a financial or other benefit or to avoid
an obligation, or to succeed in a competitive bidding process;
iii. “Coercive Practice” means impairing or harming, or threatening to impair or
harm, directly or indirectly, any party or the property of the party to influence
improperly the actions of a party;
iv. “Collusive Practice” means an arrangement between two or more parties
designed to achieve an improper purpose, including influencing improperly the
actions of another party.
Will reject the award of Contract, even at a later stage, if it determines that the bidder
recommended/ selected for award/awarded has, directly or through an agent,
engaged in Corrupt, Fraudulent, Collusive, Or Coercive Practices incompeting for the
Contract;
Will sanction a party or its successors, including declaring ineligible, either indefinitely
or for a stated period of time, to participate in any further bidding/procurement
proceedings under the Project, if it at any time determines that the party has, directly
or through an agent, engaged in Corrupt, Fraudulent, Collusive, Or Coercive
Practices in competing for, or in executing, the contract; and
The party may be required to sign an Integrity Pact, if required; and WAPCOS Limited
will have the right to require the bidders, or its suppliers, contractors and consultants
to permit WAPCOS Limited to inspect their accounts and records and other
documents relating to the bid submission and contract performance and to have them
audited by auditors appointed by WAPCOS Limited at the cost of the bidders.
The Bidder must obtain for himself on his own responsibility and at his own expenses
all the information which may be necessary for the purpose of making a bid and for
entering into a contract, must examine the Drawings, must inspect the sites of the
work, acquaint himself with all local conditions, means of access to the work, nature
of the work and all matters pertaining thereto. WAPCOS Limited will in no case be
responsible or liable for those costs, regardless of the conduct or outcome of the
bidding process.
c) The Contract shall be governed by each SECTION OF TENDER DOCUMENT and
all other Conditions mentioned in the tender documents.
d) All Bidders are hereby explicitly informed that conditional offers or offers with
deviations from the Conditions of Contract, the bids not meeting the minimum
eligibility criteria, Technical Bids not accompanied with EMD and Tender Document
Fees of requisite amount in acceptable format, Bids in altered/modified formats, or in
deviation with any other requirements stipulated in the tender documents are liable
to be rejected.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
e) The company reserves the right to waive minor deviations if they do not materially
affect the capability of the Tenderer to perform the contract
f) The bidders shall not tamper or modify any part of the tender documents in any
manner. In case in part of the bid is found to be tampered or modified at any stage,
the bids are liable to be rejected, the contract is liable to be terminated and the full
earnest deposit/retention money/performance guarantee will be forfeited and the
bidder will be liable to be banned from doing any business with WAPCOS Limited.
g) Incomplete Price bid shall be liable to be rejected, at the discretion of WAPCOS
Limited. The total bid price shall cover the entire scope of works covered in the tender.
1.7 BID OPENIGN AND EVALUATION
Bids shall be opened as per the schedule. The Bidder will be at liberty to be present either
in person or through an authorized representative at the time of opening of the Bid. The
Bids will be opened in the presence of Bidders’ representative who wish to attend on the
time, date and venue as mentioned in NIT. The physical Bid shall also be opened on the
day of Tender opening
The successful bidder shall accept the Letter of Award (LOA) within 15 (Fifteen) days from
receipt of the same, failing which the EMD shall be forfeited and the award of work may
be liable to be cancelled.
If any bidder withdraws or make any changes in his offer already submitted before the
expiry of the validity period or any extension thereof without the written consent of the
company, the EMD amount will be forfeited for such act of the bidder.
WAPCOS Limited reserves the right of forfeiture of Earnest Money deposit (EMD) in case
of the successful bidder.
i. After opening of Tender, revokes his tender within the validity period or increases his
earlier quoted rates.
ii. Does not commence the work within the period as per LOA/Contract. In case the
LOA/Contract is silent in this regard then within 15 days after award of contract.
The Bidder shall bear all costs associated with the preparation and submission of his Bid,
and the Employer will in no case be responsible and liable for those costs. WAPCOS
Limited shall in no case be responsible or liable for these costs, regardless of the conduct
or outcome of the bidding process.
Any corrigendum/ addendum thus issued shall be part of the bidding documents.
Prospective Bidders shall download the same from the e-portal and submit along with the
submission of Bid as token of acceptance
In exceptional circumstances, prior to expiry of the original bid validity period, the Employer
may request the Bidder for a specified extension in the period of validity. The request and
the responses thereto shall be made in writing or by e-mail. A Bidder may refuse the
request. A Bidder agreeing to the request will not be required/nor permitted to modify his
bid.
SECTION– II
SECTION-II
Sashastra Seeme Bal (SSB), Ministyy of Home Affairs, Govt. of India has identified around
75.02 acres of land to Develop and Construct the Infrastructure facilities at the Battallion
Head Quarter at Naugarh, Siddarthnagar, Uttar Pradesh. The approximate plinth area of
the Infrastructure facilities to be developed will be 11388 Sqm.
The project shall include construction of Admin Block / Training Block and Offices, Barrack,
Residential Quarters, Electrical Sub-station, Water Tank including Civil, Electrical, MEP
works including External development, internal roads including footpaths, Water Supply
Distribution Network, Storm Water Drainage Network, Rain Water Harvesting Structures,
Underground water tanks (UGT) for fire and domestic drinking water, Boundary walls,
Horticulture & Landscaping works, Sewage Treatment Plant, Fire-fighting system, Sub-
stations etc.
In order to develop the SSB Battalion Head Quarter at Naugarh, Siddarthnagar, Uttar
Pradesh, WAPCOS intends to engage an EPC Contractor for Construction &
Development of Infrastructure Works at Battalion Headquarters SSB, Siddarthnagar,
Uttar Pradesh on EPC Mode-I.
portal which are essentially required for submission of bids. The Employer will not reply to
the queries which are not considered fit like replies of which can be implied /found in the
NIT/Tender Documents or which are not relevant or in contravention to NIT/Tender
Documents.
The intending bidders should depute their authorized person with authorization letter in
original to attend the pre-bid meeting. The pre-bid meeting shall be held at the
communication address mentioned in NIT. The Addendum/ Corrigendum/Replies to pre bid
queries as per Pre bid meeting, shall be uploaded on e-portal & WAPCOS website.
The Technical Bid shall be uploaded with coloured scanned copies of following
documents. All the documents must be Serial wise as stated below along with check
list and clearly marked page no. on each page
NOTE:
The bid capacity shall be positive. Otherwise the
bid shall be rejected.
j) EPF Registration:
The agency should have EPF registration.
p) No Deviation Certificate:
The bidder will submit ‘No Deviation Certificate’
as prescribed in Form-H.
No information relating to financial terms of services should be included in the technical bid.
Bids are to be submitted to determine that the bidder has a full comprehension of the
tendered work. Where a bidder technical submittal is found non – compliant with the
requirement or work, it may be rejected. This process is to assure that only technical
acceptable bids are considered for the tendered work.
2. Original Tender submission fee & EMD in separate sealed envelope clearly labeled
as “TENDER FEE & EMD” for the work (Write Name of Work/Project as mentioned in
NIT) along with Details of Bidders Address, Phone, E-mail on Envelope.
NOTE: All above two envelopes shall be submitted in one single envelope clearly
labeled as “Documents for Offline Submission” for the Work (Write Name of
Work/Project as mentioned in NIT) along with Details of Bidders Address, Phone, E-mail on
Envelope.
Quoted amount by the Bidder shall be firm during the performance of the Contract. Quoted
amount by the Bidder with any condition shall not be accepted and same is liable to be
rejected
Quoted amount by the Bidder shall include all Materials, Tools & Plant, labour, supervision,
profit; other levies together with all general risks, liabilities and obligations set out or implied
in the contract, applicable Labour Cess, cost of insurance to this contract, all applicable tax
liabilities like Income Tax & Surcharges, etc. Any other taxes /cess as per Government
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
directives shall be deducted from each bill paid to the Contractor, from time to time. GST
shall be payable extra as per prevailing rates.
The Contractor shall submit e-invoice / Tax Invoice (as applicable for the bidder’s Firms) to
WAPCOS showing (i) Basic amount (ii) GST amount separately in each bill. It is mandatory
to bidders to deposit GST within time limit framed by Govt. of India, if applicable. The Goods
and Services Tax (GST), shall be reimbursed to the Agency only after uploading of bills by
Contractor on GST Portal “to avail Input benefit of GST”.
The WAPCOS shall be performing all its duties of deduction of TDS and other deduction
on payment made to the contractor as per applicable legislation in force on the date of
submission of bid or to be newly/amended introduced during the execution of the Contract.
7.0 OPENING OF FINANCIAL BID
The financial bids of the technically qualified bidders shall be opened at the notified date &
time. Final selection of the bidder will be made based on the least cost method.
Failure on the part of the successful Bidder to comply with the above requirements will
constitute sufficient grounds for the annulment of the Award and forfeiture of the Bid
Security.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
SECTION – III
FORMS
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
To,
The Chief Engineer
Construction Management Unit-III
WAPCOS Limited
Having examined the details given in tender document for the above work, I/we hereby submit the
relevant information.
i. I / We acknowledge that the WAPCOS will be relying on the information provided in the Bid and
the documents accompanying the Bid & detailed provided in the enclosed “Forms” for selection
of the Contractor for the aforesaid Project, and we certify that all information provided in the Bid
are true and correct; nothing has been omitted which renders such information misleading; and
all documents accompanying the Bid are true copies of their respective originals.
ii. I/we have furnished all information and details necessary for eligibility and have no further
pertinent information to supply.
iii. I/we submit the requisite Certificate for solvency, Completion Certificates, Financial Information’s
and authorize WAPCOS Ltd. to approach the Issuing Authority to confirm the correctness thereof.
I/we also authorize WAPCOS Ltd. to approach individuals, employers, firms and corporation to
verify our competence and general reputation.
iv. I/ We acknowledge the right of the Authority to reject our Bid without assigning any reason or
otherwise and hereby waive, to the fullest extent permitted by applicable law, our right to
challenge the same on any account whatsoever.
v. I/we submit the following certificates in support of our suitability, technical knowledge and
capability for having successfully completed the following eligible similar works:
We have inspected the site of work and have made myself/ourselves fully acquainted with local
conditions in and around the site of work. We have carefully gone through each & every section of the
tender document for the work “…………… … …… …… …… …………………. (Name of work)”.
1. Our tender is offered taking due consideration of all factors mentioned in tender documents.
2. We promise to abide by all the stipulations of the Contract documents and carry out and complete
the work to the satisfaction of the Employer/ Principal Employer.
3. We also agree to procure Plants and Machineries at our cost required for the work. We also submit
that we have Organizational Structure comprising adequate Technical Personnel in the line of
requirement. We also agree to accomplish the job entrusted to us in the stipulated time laid out in
document except situations not under our control.
4. We have not made any misleading or false representation in the forms, statement and attachments
in proof of the qualification requirements;
5. We do not have records of poor performance such as abandoning the work, not properly completing
the Contract, inordinate delays in completion or financial failures etc.
6. We have submitted all the supporting documents and furnished the relevant details as per
prescribed format.
7. We are financially sound and have not applied or be under corporate debt restructuring.
8. List of Similar Works satisfying Qualification Criterion as indicated hereinafter, does not include
any work which has been carried out by us through a Subcontractor on a back-to-back basis.
9. The Cost has been quoted by me/us for bid after taking into consideration all the terms and
conditions stated in the Tender Document, our own estimates of costs and after a careful
assessment of the site and all own the conditions that may affect the project cost and
implementation of the project.
10. I / We shall keep this offer valid as period specified in the NIT.
11. I / We hereby submit our FINANCIAL BID and Offer Cost for undertaking the aforesaid Project in
accordance with the Bidding Documents and the Agreement.
12. In the event of my/ our being declared as the Selected Bidder, I/we agree to enter into a Agreement
in accordance with the format of Contract Agreement. We agree not to seek any changes in the
aforesaid format of Contract Agreement and agree to abide by the same.
Certificate:
It is certified that the information given in the enclosed bid are correct. It is also certified that I/we shall
be liable to be debarred, disqualified / cancellation of enlistment in case any information furnished by
me/us found to be incorrect.
2020-2021
2021-2022
2022-2023
2023-2024
Above Details are being furnished as per the figures in balance sheet for the last five years in respect
of M/s …………………………………….( Name & address of firm of bidder), as submitted by the firm
to the Income Tax Department.
To
WAPCOS Limited,
76-C, Institutional Area,
Sector-18, Gurugram, Haryana
This is certify that to the best of our knowledge and information that M/s ………………..…………………
having marginally noted address,……………………………… …………
………………………………………….. as a Customer of our Bank Account are/ is respectable and can
be treated as good for any engagement up to a Limit of Rs. …………………
(Rupees……………………………………………………)
This certificate is issued without any guarantee or responsibility on the bank or any of the officers.
3. Completion Certificate
Present address of the Official Email Id Landline no Other Contact no.
Issuing Authority
This is to certify that above information is correct and is gathered from the Issuing Authorities by us for
the verification of concerned documents. We understand that if the documents is not verified by the
issuing authority within 5 working days, then our bid is liable to be rejected.
Where,
A = Maximum value of engineering (Civil/ Electrical/ Mechanical as relevant to work being procured)
works executed in any one year during the last five years (updated at the current price level), taking
into account the completed as well as works in progress.
B = Value (updated at the current price level) of the existing commitments and ongoing works to be
completed in the next ‘N’ years.
NOTE:
The bidder shall furnish statements showing the value of existing commitments and on-going works as
well as stipulated period of completion remaining for each of the works separately.
The value of executed works shall be brought to the current level by enhancing the actual value of work
done at a simple rate of 7% per annum, calculated from the date of completion of last day of the month
previous to the one in which applications are invited.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Our tender is offered taking due consideration of all factors including site requirements information and
conditions stated in the detailed Instructions to Bidders to execute the work up to the standards as laid
out in Employer’s Requirements and other sections of Tender Document.
We agree to employ the number of technical staff during the execution of this work as defined in the
tender document. We shall deploy additional manpower as deemed fit and required to complete the
project within stipulated completion period, without any additional cost to the Employer.
WAPCOS shall have full power and without giving any reason to us, immediately to get removed any
representative, staff and workmen or employees on account of misconduct negligence or incompetence
or whose continued employment may in his opinion be undesirable. We shall not claim any
compensation on this account.
In case we fail to deploy the technical staff as mentioned in the tender document, we shall be liable to
pay a sum of Rs. 50,000/- (Rupees fifty Thousand only) for each month of default in the case of each
Graduate Engineer and Rs. 40,000/- (Rupees Forty Thousand only) in the case of each Diploma
Engineer and details will be submitted with each Bill. We shall not raise any objection if deduction is
made for the same from Running Bills.
This is also to certify that we are not involved in any form of Corrupt and Fraudulent Practices in past
and will never be involved in future.
This is to confirm that as per Tender conditions we have visited site before submission of our Offer and
noted the job content and site condition etc. We also confirm that we have not changed/modified the
above tender document and in case of observance of the same at any stage it shall be treated as null
and void.
We hereby also confirm that we have not taken any deviation from Tender Clause together with other
reference as enumerated in the above referred Notice Inviting Tender and we hereby convey our
unconditional acceptance to all terms & conditions as stipulated in the Tender Document.
In the event of observance of any deviation in any part of our offer at a later date whether implicit or
explicit, the deviations shall stand null and void.
This is to certify that we have taken the cognizance of Blacklisting Policy of WAPCOS Ltd. Further, we
hereby Confirm and declare that we, M/s_____________________________________ , is not
blacklisted/De-registered/debarred by any Government Department/Public Sector Undertaking /Private
Sector/ or any other agency for which we have Executed / Undertaken the works/ Services during the
last 3 Years.
FORM-J: UNDERTAKING FOR RULE 144 (XI) IN THE GENERAL FINANCIAL RULES-2017
OR
We have understood the provisions of Public Procurement (Preference to make in India) Local content
Policy against WAPCOS Tender NIT No. …………………………………… Date -………………..
We on the basis of the bidder’s representation received, hereby confirm that, offer is achieving the
minimum local content target as per of above Policy shall be 50%.
Note: The format K1 will be required from bidder if the estimated cost of work is up to Rs. 10.0
Crore (excluding GST) and form k2 will be used for estimated cost of work is in excess of Rs.
10.0 Crore (excluding GST)
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
To,
WAPCOS Limited,
76-C, Sector 18,
Institutional Area
Gurgaon, Haryana-122015
Dear Sir,
I/We acknowledge that WAPCOS is committed to follow the principles thereof as enumerated in the
Integrity Agreement enclosed with the tender/bid document at Appendix-I.
I/We agree that the Notice Inviting Tender (NIT) is an invitation to offer made on the condition that I/We
am/are signing the enclosed integrity Agreement, which is an integral part of tender documents, failing
which I/We will stand disqualified from the tendering process. I/We acknowledge that THE MAKING OF
THE BID SHALL BE REGARDED AS AN UNCONDITIONAL AND ABSOLUTE ACCEPTANCE of this
condition of the NIT.
I/We confirm acceptance and compliance with the Integrity Agreement in letter and spirit and further
agree that execution of the said Integrity Agreement shall be separate and distinct from the main
contract, which will come into existence when tender/bid is finally accepted by WAPCOS. I/We
acknowledge and accept the duration of the Integrity Agreement, which shall be in the line with Article
1 of the enclosed Integrity Agreement.
I/We acknowledge that in the event of my/our failure to sign and accept the Integrity Agreement, while
submitting the tender/bid, WAPCOS shall have unqualified, absolute and unfettered right to disqualify
the tenderer/bidder and reject the tender/bid is accordance with terms and conditions of the tender/bid.
FORM L
INTEGRITY AGREEMENT
This Integrity Agreement is made at ............... on this ........... day of ........... 20......
BETWEEN
WAPCOS Limited, New Delhi (Hereinafter referred as the ‘EMPLOYER’, which expression shall unless
repugnant to the meaning or context hereof include its successors and permitted assigns)
AND
................................................................................................................................ (Name and Address
of the Individual/firm/Company) through ................................................................................
(Hereinafter referred to as the (Details of duly authorized signatory)
“Bidder/Contractor” and which expression shall unless repugnant to the meaning or context hereof
include its successors and permitted assigns)
PREAMBLE
‘The Employer’ intends to award, under laid down organizational procedures, contract/ s for
_____________________, ‘The Employer’ values full compliance with all relevant laws of the land,
rules, regulations, economic use of resources and of fairness/ transparency in its relations with its
Bidder(s) and/ or Contractor(s).
In order to achieve these goals, the Employer shall appoint Independent External Monitors (IEMs) who
shall monitor the tender process and the execution of the contract for compliance with the principles
mentioned above.
If the Employer obtains information on the conduct of any of its employees, which is a criminal
offence under the IPC/ PC Act, or if there be a substantive suspicion in this regard, the Employer
shall inform the Chief Vigilance Officer and, in addition, can initiate disciplinary actions.
a) The ‘Bidder/ Contractor’ shall not, directly or through any other person or firm, offer, promise,
or give to any of the Employer’s employees involved in the tender process or the execution of
the contract or to any third person any material or other benefit which he is not legally entitled
to, in order to obtain in exchange any advantage of any kind whatsoever during the tender
process or during the execution of the contract.
b) The ‘Bidder/ Contractor’ shall not enter with other Bidders info any undisclosed agreement or
understanding, whether formal or informal. This applies in particular to prices, specifications,
certifications, subsidiary contracts, submission or non-submission of bids or any other actions
to restrict competitiveness or to introduce 311tilize311311on311n in the tender process.
c) The ‘Bidder/ Contractor’ shall not commit any offence under the relevant IPC/ PC Act; further,
the ‘Bidder/ Contractor’ shall not use improperly, for purposes of competition or personal gain,
or pass on to others, any information or document provided by the Employer as part of the
business relationship, regarding plans, technical proposals, and business details, including
information contained or transmitted electronically.
d) The ‘Bidder/ Contractor’ of foreign origin shall disclose the name and address of the Agents/
representatives in India if any. Similarly, the Bidder/ Contractors of Indian Nationality shall
furnish the name and address of the foreign Employers, if any. Further details as mentioned
in the “Guidelines on Indian Agents of Foreign Suppliers” shall be disclosed by the Bidder/
Contractor. Further, as mentioned in the Guidelines, all the payments made to the Indian
agent/ representative have to be in Indian Rupees only. Copy of the “Guidelines on Indian
Agents of Foreign Suppliers” is placed in Appendix to this agreement.
e) The ‘Bidder/ Contractor’ shall, when presenting their bid, disclose any and all payments made,
is committed to, or intends to make to agents, brokers, or any other intermediaries in
connection with the award of the contract.
f) Bidder/ Contractor who have signed the Integrity Pact shall not approach the Courts while
representing the matter to IEMs and shall wait for their decision in the matter.
The ‘Bidder/ Contractor’ shall not instigate third persons to commit offences outlined above or be
an accessory to such offences.
Section 3 – Disqualification from tender process and exclusion from future contracts
If the ‘Bidder/ Contractor’, before award or during execution, has committed a transgression through a
violation of Section 2, above or in any other form such as to put their reliability or credibility in question,
the Employer is entitled to disqualify the ‘Bidder/ Contractor’ from the tender process or take action as
per the procedure mentioned in the “Guidelines on Banning of business dealings”.
If Bidder makes an incorrect statement on this subject, he can be disqualified from the tender
process, or action can be taken as per the procedure mentioned in “Guidelines on Banning of
business dealings”.
If the Monitor has reported to the Head of the Organisation, a substantiated suspicion of an offence
under relevant IPC/ PC Act, and Head of the Organisation has not, within the reasonable time,
taken visible action to proceed against such offence or reported it to the Chief Vigilance Officer,
the Monitor may also transmit this information directly to the Central Vigilance Commissioner.
The word ‘Monitor’ would include both singular and plural.
For and on behalf of the WAPCOS For and on behalf of the Contractor
_1____________________________ _1_______________________
2 ____________________________ 2 _______________________
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
SECTION – IV
SECTION – III
The work involves execution as per name of work under either EPC
Mode I or Mode II or Mode III as specified in Special Conditions of
Contract
passed the full scale type testing for pseudo-static reversed cyclic test
as detailed below:
The bottom of the first storey shall be connected to the strong floor of
the test facility, and the floors of the upper storeys to the Displacement-
controlled actuators of the requisite Displacement (and force) capacity.
This proto-type shall be loaded with the due vertical gravity load
representing service level dead and live loads. The profile of
displacement loading shall be as per the force distribution profile
specified in IS 1893 (part I):2016 in the Equivalent Static Method of
design.
One test for every new type of connection system adopted shall be
conducted. If the connection type / combination of elements under
approved technology are changed, either in part or in full, the system
will be treated as new.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
The test should have been already got conducted from any
government academic institute of repute or government R&D
organization in India.
If the revised tendered amount (worked out on the basis of quoted rate
of individual items) of two or more contractors received in revised offer
is again found to be equal, then the lowest tender, among such
contractors, shall be decided by draw of lots,
In case of any such lowest contractor in his revised offer quotes rate
of any item more than their respective original rate quoted already at
the time of submission of tender, then such revised offer shall be
treated as invalid. Such case of revised offer of the lowest contractor
or case of refusal to submit revised offer by the lowest contractor shall
be treated as withdrawal of his tender before acceptance and 50% of
his earnest money shall be forfeited.
In case all the lowest contractors those have same tendered amount
(as a result of their quoted rate of individual items), refuse to submit
revised offers, then tenders are to be recalled after forfeiting 50% of
EMD of each lowest contractors.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Applicable for 4A In case of Percentage Rate EPC tenders, contractor shall fill up
Percentage percentage below/ above (in figures as well as in words) the total
Rate estimated cost given in Schedule of Quantities, he will be willing to
EPC Tender
execute the work. The tender submitted shall be treated as invalid if :-
only
i. The contractor does not quote percentage above/below on the
total amount of tender or any section/sub head of the tender.
In case all the lowest contractors those have quoted same tendered
amount, refuse to submit revised offers, then tenders are to be recalled
after forfeiting 50% of EMD of each contractor. Contractor(s), whose
earnest money is forfeited because of nonsubmission of revised offer,
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
However, if a tenderer quotes nil rates against any item in item rate
EPC tender, the tender shall be treated as invalid and will not be
considered as lowest tenderer and earnest money deposited shall be
forfeited.
Applicable for 9. In case of Percentage Rate EPC Tenders only percentage quoted shall
percentage be considered. Any tender containing item rates is liable to be rejected.
Rate Percentage quoted by the contractor in percentage rate EPC tender
EPC Tender
shall be accurately filled in figures and words, so that there is no
only
discrepancy.
Applicable for 10. In Percentage Rate EPC Tender, the tenderer shall quote percentage
Percentage below/above (in figures as well as in words) at which he will be willing
Rate to execute the work. He shall also work out the total amount of his offer
EPC Tender
and the same should be written in figures as well as in words in such
only
a way that no interpolation is possible. In case of figures, the word ‘Rs.’
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
should be written before the figure of rupees and word ‘P’ after the
decimal figures, e.g. ‘Rs. 2.15P and in case of words, the word
‘Rupees’ should precede and the word ‘Paisa’ should be written at the
end
11. i. The Contractor whose tender is accepted, will be required to
furnish performance guarantee at specified percentage of the
tendered amount as mentioned in NIT and within the period
specified in SCC. This guarantee shall be in the form of Insurance
Surety Bonds, Account Payee Demand Draft, Fixed Deposit
Receipt or Bank Guarantee of any Commercial Bank.
ii. The contractor whose tender is accepted will also be required to
furnish by way of Security Deposit for the fulfillment of his
contract, an amount equal to 5% of the tendered amount of the
work. The Security deposit will be collected by deductions from
the running bills as well as final bill of the contractor at the rates
mentioned above. The Security amount will also be accepted in
the shape of Insurance Surety Bonds, Account Payee Demand
Draft, Fixed Deposit Receipt or Bank Guarantee from any of the
Commercial Banks will be accepted for this purpose provided
confirmatory advice is enclosed.
12. On acceptance of the tender, the name of the accredited
representative(s) of the contractor who would be responsible for taking
instructions from the Engineer-in-Charge shall be communicated in
writing to the Engineer-in-Charge.
13. GST or any other tax applicable in respect of inputs procured by the
contractor for this contract shall be payable by the Contractor and
Government will not entertain any claim whatsoever in respect of the
same. However, component of GST at time of supply of service (as
provided in CGST Act 2017) provided by the contract shall be varied if
different from that applicable on the last date of receipt of tender
including extension if any. Accordingly payment or recovery shall be
done.
14. The contractor shall give a list of WAPCOS and SSB employees
related to him.
15. The tender for composite work includes, in addition to building work,
all other works such as sanitary and water supply installations drainage
installation, electrical work, horticulture work, roads and paths etc. as
mentioned in the scope of work
16. The contractor shall comply with the provisions of the Apprentices Act
1961, and the rules and orders issued thereunder from time to time. If
he fails to do so, his failure will be a breach of the contract and
WAPCOS may in his discretion, without prejudice to any other right or
remedy available in law, cancel the contract. The contractor shall also
be liable for any pecuniary liability arising on account of any violation
by him of the provisions of the said Act.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
ii. The Site shall mean the land, places on, into or where work is to
be executed under the contract or any adjacent land, path or street
or where work is to be executed under the contract or any adjacent
land, path or street which may be temporally allotted or used for
the purpose of carrying out the contract.
x. Excepted Risk are risks due to riots (other than those on account
of contractor’s employees), war (whether declared or not)
invasion, act of foreign enemies, hostilities, civil war, rebellion
revolution, insurrection, military or usurped power, any acts of
Government, damages from aircraft, acts of God, such as
earthquake, lightening and unprecedented floods, and other
causes over which the contractor has no control and accepted as
such by the Accepting Authority or causes solely due to use or
occupation by Government of the part of the works in respect of
which a certificate of completion has been issued or a cause solely
due to Government’s faulty design of works.
xvi. Tendered value means the value of the entire work as stipulated
in the letter of award.
iii. No payment for the work done will be made unless contract is signed
by the contractor.
ii. The Performance Guarantee shall be initially valid up to the stipulated date of
completion plus 2 year claim period beyond the date of completion of all contractual
obligations of the contractor, including Defect Liability Period (DLP). In case the time for
completion of work gets enlarged, the contractor shall get the validity of Performance
Security extended to cover such enlarged time. The performance Security shall be refunded
to the contractor without interest, after he duly performs and completes all obligations under
the contract not later than 365 days of completion of the Defect Liability Period.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
iii. The Engineer-in-Charge shall make a claim under the performance guarantee except for
amounts to which the WAPCOS is entitled under the contract (not withstanding and/or
without prejudice to any other provisions in the contract agreement) in the event of:
i. In the event of the contract being determined or rescinded under provision of any of the
Clause/Condition of the agreement, the performance guarantee shall stand forfeited in full and
shall be absolutely at the disposal of the WAPCOS.
ii. The performance Guarantee shall be refunded to the contractor after recording successful
Completion of Defect Liability Period.
The contractor may, at his option replace the retention amount with an unconditional BG at the following
stages:
i) After the amount reaches half the value of the limit of retention money; and
ii) After the amount reaches the maximum limit of retention money. One-half of the retention
money (or BG, which replaced retention money) shall be released on the issue of the
taking-over certificate; if the Taking Over Certificates (TOCs) are issued in parts, then in such
proportions as the engineer may determine, having regard to the value of such part or section.
The other half of the retention money (or BG, which replaced the retention money) shall be
released upon expiration of 365 days after the DLP of the works or final payment, whichever is
earlier, on certification by the engineer. In the event of different defect liability periods being
applicable to different sections or parts, the expiration of defect liability period shall be the latest
of such periods.
The Security Deposit shall be released after 6 months of successful Completion of Defect Liability
Period.
In case Liquidity Damage imposed by Principal Employer to the project at any point of time, then
full amount of Liquidity Damage (10% of the Contract Price) will be recovered from the up-coming
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
interim bills/ final bill. If the amount of up-coming interim bills/ final bill is less than the amount of
Liquidity Damage, then balance amount of Liquidity Damage will be recovered from the Performance
Security, Security Deposit and any other financial deposit of Contractor with Employer.
vii. If the contractor had secured the contract with WAPCOS as a result of wrong tendering or
other non-bonafide methods of competitive tendering or commits breach of Integrity
Agreement.
viii. If the contractor being an individual, or if a firm, any partner thereof shall at any time be
adjudged insolvent or have a receiving order or order for administration of his estate made
against him or shall take any proceedings for liquidation or composition (other than a
voluntary liquidation for the purpose of amalgamation or reconstruction) under any
Insolvency Act for the time being in force or make any conveyance or assignment of his
effects or composition or arrangement for the benefit of his creditors or purport so to do, or
if any application be made under any Insolvency Act for the time being in force for the
sequestration of his estate or if a trust deed be executed by him for benefit of his creditors.
ix. If the contractor being a company shall pass a resolution or the court shall make an order
that the company shall be wound up or if a receiver or a manager on behalf of a creditor shall
be appointed or if circumstances shall arise which entitle the court or the creditor to appoint
a receiver or a manager or which entitle the court to make a winding up order.
x. If the contractor shall suffer an execution being levied on his goods and allow it to be
continued for a period of 21 days.
xi. If the contractor assigns (excluding part(s) of work assigned to other agency(s) by the
contractor as per terms of contract), transfers, sublets (engagement of labour on a piece-
work basis or of labour with materials not to be incorporated in the work, shall not be deemed
to be subletting) or otherwise parts with or attempts to assign, transfer, sublet or otherwise
parts with the entire works or any portion thereof without the prior written approval of the
Engineer –in-Charge.
When the contractor has made himself liable for action under any of the cases aforesaid, the
Engineer-in-Charge on behalf of the WAPCOS shall have powers:
(a) To determine the contract as aforesaid so far as performance of work by the
Contractor is concerned (of which determination notice in writing to the contractor
under the hand of the Engineer-in-Charge shall be conclusive evidence). Upon such
determination, in addition to Compensation for delay, the Security Deposit already
recovered, Security deposit payable and Performance Guarantee under the contract
shall be forfeited.
(b) After giving notice to the contractor to measure up the work of the contractor and to
take such whole, or the balance or part thereof, as shall be un-executed out of his
hands and to give it to another contractor to complete the work. The contractor, whose
contract is determined as above, shall not be allowed to participate in the tendering
process for the balance work including any new items needed to complete the work.
In the event of above courses being adopted by the Engineer-in-Charge, the
contractor shall have no claim to compensation for any loss sustained by him by
reasons of his having purchased or procured any materials or entered into any
engagements or made any advances on account or with a view to the execution of the
work or the performance of the contract. And in case action is taken under any of the
provision aforesaid, the contractor shall not be entitled to recover or be paid any sum
for any work thereof or actually performed under this contract unless and until the
Engineer-in-Charge has certified in writing the performance of such work and the
value payable in respect thereof and he shall only be entitled to be paid the value so
certified.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
CLAUSE 3A
In case, the work including planning, designing and execution as per scope of contract cannot be
started due to reasons not within the control of the contractor within 1/8 th of the stipulated time for
completion of work or 180 days whichever is higher, either party may close the contract by giving
notice to the other party stating the reasons. In such eventuality, the Performance Guarantee of the
contractor shall be refunded within 30 days of closing of the contract.
Neither party shall claim any compensation for such eventuality. This clause is not applicable for
any breach of the contract by either party.
5.1 The contractor shall within 10 (ten) working days of award of work, submit a time program to
the Engineer-in Charge. Such program shall be made in due consideration of :
a) Schedule of handing over of site as specified in the Special Conditions of Contract.
Further, program shall be prepared using the mutually agreed format/software or in other
format/software as directed by Engineer-in-Charge. The said program shall be in direct
relation to the time stated in the Contract document for completion of items of the works. It
shall indicate the forecast of the dates of commencement and completion of various trades/
sections of the work and may be amended as necessary by agreement between the
Engineer-in-Charge and the Contractor, within the limitations of overall time imposed in the
Contract documents
The Engineer-in-Charge shall within 10 (ten) working days of receipt of such program chart,
make modifications, if any and communicate the approved program to the contractor. In
case of non-submission of construction program by the contractor, the program prepared
by the Engineer-in-Charge shall be deemed to be final. Such program by the Engineer-in-
Charge shall not relieve the contractor of any of the obligations under the contract.
PROGRAMME CHART
(i) The Contractor shall prepare an integrated programme chart in MS Project/Primavera
software for the execution of work, showing clearly all activities from the start of work
to completion, with details of manpower, equipment and machinery required for the
fulfillment of the programme within the stipulated period or earlier and submit the
same for approval to the Engineer-in- Charge within ten days of award of the contract.
A recovery of Rs. 2500/- (for works costing upto Rs. 20 Crores) / Rs. 5000/- (for works
costing more than Rs. 20 Crores) shall be made on per day basis in case of delay in
submission of the above programme.
(ii) The programme chart should include the following:
(a) Descriptive note explaining sequence of the various activities.
(b) Network (PERT / CPM / BAR CHART).
(c) Programme for procurement of materials by the contractor.
Programme of procurement of machinery / equipments having adequate capacity,
commensurate with the quantum of work to be done within the stipulated period,
by the contractor. In addition to above, to achieve the progress of Work as per
programme, the contractor must bring at site adequate shuttering material required
for cement concrete and R.C.C. works etc. for three floors within one month from
the date of start of work till the completion of RCC work as per requirement of
work. The contractor shall submit shuttering schedule adequate to complete
structure work within laid down physical milestone.
(iii) If at any time, it appears to the Engineer-in-Charge that the actual progress of work
does not conform to the approved programme referred above or after rescheduling
of milestones, the contractor shall produce a revised programme within 7 (seven)
days, showing the modifications to the approved programme to ensure timely
completion of the work. The modified schedule of programme shall be approved by
the Engineer in Charge. A recovery of Rs. 2500/- (for works costing upto Rs. 20
Crores) / Rs. 5000/- (for works costing more than Rs. 20 Crores) shall be made on
per day basis in case of delay in submission of the modified programme.
(iv) The submission for approval by the Engineer-in-Charge of such programme or such
particulars shall not relieve the contractor of any of the duties or responsibilities under
the contract. This is without prejudice to the right of Engineer-in-Charge to take action
against the contractor as per terms and conditions of the agreement.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
(v) The contractor shall submit the progress report using MS Project/Primavira software
with base line programme referred above along with photographs of the work done
during previous month to the Engineer-in-charge on or before 5th day of each month
failing which a recovery Rs. 2500/ - (for works costing upto Rs. 20 Crores) / Rs. 5000/-
(for works costing more than Rs. 20 Crores) shall be made on per day basis in case
of delay in submission of the monthly progress report (minimum- 3 sets) .
5.2 If the work(s) be delayed by :-
(i) force majeure, or
(ii) abnormally bad weather, or
(iii) serious loss or damage by fire, or
(iv) civil commotion, local commotion of workmen, strike or lockout, affecting any of the
trades employed on the work, or
(v) delay on the part of other contractors or tradesmen engaged by Engineer-in-
Charge in executing work not forming part of the Contract, or
(vi) any other cause which, in the absolute discretion of the Engineer-in-Charge is
beyond the Contractor’s control.
Then upon the happening of any such event causing delay, the Contractor shall immediately
give notice thereof in writing to the authority as indicated in Special Conditions of Contract.
The said authority, on receipt of such notice, considering the factual ground situation, give a
fair and reasonable ‘justified extension of time’ and reschedule the mile stones for completion
of work.
The contractor shall have no claim of damages against the delays listed in this sub clause
i.e. sub clause 5.2. The contractor shall have no claim of damages for extension of time
granted or rescheduling of milestone/s for events listed in sub clause 5.2.
The authority as indicated in Special Conditions of Contract, after examining the request,
shall give a fair and reasonable ‘justified extension of time’ for completion of work and
simultaneously reschedule the mile stones. In event of non-application by the contractor for
extension of time, the authority as indicated in Special Conditionas of Contract, after affording
opportunity to the contractor, may give, fair and reasonable justified extension and
reschedule the milestones, within a reasonable period of occurrence of the event causing
delay. Such justified extension of time shall determine the ‘justified extended date’ of
completion of work.
5.6 It is a term of contract that the authority indicated in Special Conditions of Contract while
deciding the extension of time case as per clause 5.1 to 5.5, shall also segregate the
overall period of delay in following categories :
a) delays due to reasons beyond the control of both parties (under clause 5.2)
b) delays attributable solely to the WAPCOS (under clause 5.3)
c) concurrent delays (under clause 5.3)
d) delays solely attributable to contractor (under clause 5.5)
All measurements as per the stage payments mentioned in Schedule F having financial value shall
be entered by the contractor and compiled in the shape of the Computerized Measurement Book
having pages of A-4 size as per the format of the WAPCOS so that a complete record is obtained
of all the stages of works performed under the contract.
All such measurements recorded by the contractor or his authorized representative from time to
time, during the progress of the work, shall be got checked by the contractor from the Engineer-in-
Charge or his authorized representative as per interval or program fixed in consultation with
Engineer-in-Charge or his authorized representative. After the necessary corrections made by the
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Engineer-in-Charge, the measurement sheets shall be returned to the contractor for incorporating
the corrections and for resubmission to the Engineer-in- Charge for the dated signatures by the
Engineer-in- Charge and the contractor or their representatives in token of their acceptance.
Whenever bill is due for payment, the contractor would initially submit draft computerized
measurement sheets and these measurements would be got checked/test checked from the
Engineer-in-Charge and/or his authorized representative. The contractor will, thereafter, incorporate
such changes as may be done during these checks/test checks in his draft computerized
measurements, and submit to the WAPCOS a computerized measurement book, duly bound, and
with its pages machine numbered. The Engineer-in-Charge and/or his authorized representative
would thereafter check this MB, and record the necessary certificates for their checks/test checks.
The final, fair, computerized measurement book given by the contractor, duly bound, with its pages
machine numbered, should be 100% correct. No cutting or over-writing in the measurements would
thereafter be allowed. If at all any error is noticed, the contractor shall have to submit a fresh
computerized MB with its pages duly machine numbered and bound, after getting the earlier MB
cancelled by the WAPCOS. Thereafter, the MB shall be taken in the Divisional Office records, and
allotted a number as per the Register of Computerized MBs. This should be done before the
corresponding bill is submitted to the Division Office for payment. The contractor shall submit two
spare copies of such computerized MB’s for the purpose of reference and record.
The contractor shall also submit to the Engineer-in-Charge separately his computerized Abstract of
Cost and the bill based on these measurements, duly bound, and its pages machine numbered
along with two spare copies of the bill. Thereafter, this bill will be processed by the Division Office
and allotted a number as per the computerized record in the same way as done for the measurement
book meant for measurements.
The contractor shall, without extra charge, provide all assistance with every appliance, labour and
other things necessary for checking of measurements by the Engineer-in- Charge or his
representative.
Except where any general or detailed description of the work expressly shows to the contrary,
measurements shall be taken in accordance with the procedure set forth in the contract
notwithstanding any provision in the relevant Standard Method of measurement or any general or
local custom.
The contractor shall give not less than seven days’ notice to the Engineer-in-Charge or his
authorized representative in charge of the work before covering up or otherwise placing beyond the
reach of checking and/or test checking the measurement of any work in order that the same may be
checked and/or test checked and correct dimensions thereof be taken before the same is covered
up or placed beyond the reach of checking and/or test checking measurement and shall not cover
up and place beyond reach of measurement any work without consent in writing of the Engineer-in-
Charge or his authorized representative in charge of the work who shall within the aforesaid period
of seven days inspect the work, and if any work shall be covered up or placed beyond the reach of
checking and/or test checking measurements without such notice having been given or the
Engineer-in-Charge’s consent being obtained in writing the same shall be uncovered at the
Contractor’s expense, or in default thereof no payment or allowance shall be made for such work or
the materials with which the same was executed.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
It is also a term of this contract that checking and/or test checking the measurements of any item of
work in the measurement book and/or its payment in the interim, on account of final bill shall not be
considered as conclusive evidence as to the sufficiency of any work or material to which it relates
nor shall it relieve the contractor from liabilities from any over measurement or defects noticed till
completion of the defects liability period.
An amount of ad-hoc payment not less than 75% of the net amount of the bill under check, shall be
made within 10 working days of submission of the bill. The remaining payment is also to be made
after final checking of the bill within 28 working days of submission of bill by the contractor.
All such interim payments shall be regarded as payment by way of advances against final payment
only and shall not preclude the requiring of bad, unsound and imperfect or unskilled work to be
rejected, removed, taken away and reconstructed or re-erected. Any certificate given by the
Engineer-in-Charge relating to the work done or materials delivered forming If the revised tendered
amount (worked out on the basis of quoted rate of individual items) part of such payment, may be
modified or corrected by any subsequent such certificate(s) or by the final certificate and shall not
by itself be conclusive evidence that any work or materials to which it relates is/are in accordance
with the contract and specifications. Any such interim payment, or any part thereof shall not in any
respect conclude, determine or affect in any way powers of the Engineer-in-Charge under the
contract or any of such payments be treated as final settlement and adjustment of accounts or in
any way vary or affect the contract.
Clause 7A
No Running Account Bill shall be paid for the work till the applicable labour licenses, registration with
EPFO, ESIC and BOCW Welfare Board, whatever applicable are submitted by the contractor to the
Engineer-in-Charge.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Within ten days of the completion of the work, the contractor shall give notice of such completion to
the Engineer-in-Charge and within thirty days of the receipt of such notice, the Engineer-in-Charge
shall inspect the work and if there is no defect in the work, shall furnish the contractor with a final
certificate of completion, otherwise a provisional certificate of physical completion indicating defects
(a) to be rectified by the contractor and/or (b) for which payment will be made at reduced rates, shall
be issued. But no final certificate of completion shall be issued, nor shall the work be considered to
be complete until the contractor shall have removed from the premises on which the work shall be
executed all scaffolding, surplus materials, rubbish and all huts and sanitary arrangements required
for his/their work people on the site in connection with the execution of the works as shall have been
erected or constructed by the contractor(s) and cleaned off the dirt from all wood work, doors,
windows, walls, floor or other parts of the building, in, upon, or about which the work is to be executed
or of which he may have had possession for the purpose of the execution; thereof, and not until the
work shall have been measured by the Engineer-in-Charge. If the contractor shall fail to comply with
the requirements of this Clause as to removal of scaffolding, surplus materials and rubbish and all
huts and sanitary arrangements as aforesaid and cleaning off dirt on or before the date fixed for the
completion of work, the Engineer-in-Charge may at the expense of the contractor remove such
scaffolding, surplus materials and rubbish etc., and dispose of the same as he thinks fit and clean
off such dirt as aforesaid, and the contractor shall have no claim in respect of scaffolding or surplus
materials as aforesaid except for any sum actually realized by the sale thereof.
In case, the contractor fails to submit the completion plan as aforesaid, he shall be liable to pay a
sum of 0.1 % (zero point one percent) of Tendered Value or limit prescribed in Schedule whichever
is more as may be fixed by the authority as mentioned in Schedule F and in this respect the decision
of the that authority shall be final and binding on the contractor.
If the final bill is submitted by the contractor within the period specified above and delay in payment
of final bills is made by the WAPCOS after prescribed time limit, a simple interest @ 5 % (five
percent) per annum shall be paid to the contractor from the date of expiry of prescribed time limit,
provided the final bill submitted by the contractor is found to be in order
that the contractor furnishes to the Engineer-in-Charge (1) an authorization in the form of a legally
valid document such as a power of attorney conferring authority on the bank, registered financial,
co-operative or thrift societies or recognized financial institutions to receive payments and (2) his
own acceptance of the correctness of the amount made out as being due to him by Government or
his signature on the bill or other claim preferred against Government before settlement by the
Engineer-in-Charge of the account or claim by payment to the bank, registered financial, co-
operative or thrift societies or recognized financial institutions. While the receipt given by such banks
registered financial, co-operative or thrift societies or recognized financial institutions shall constitute
a full and sufficient discharge for the payment, the contractor shall whenever possible present his
bills duly receipted and discharged through his bank, registered financial, co-operative or thrift
societies or recognized financial institutions.
Nothing herein contained shall operate to create in favour of the bank; registered financial, co-
operative or thrift societies or recognized financial institutions any rights or equities vis-à-vis the
WAPCOS.
to remove the same without being answerable or accountable for any loss or damage that may
happen or arise to such materials. The Engineer-in-Charge shall also have full powers to require
other proper materials to be substituted thereof and in case of default, the Engineer-in-Charge may
cause the same to be supplied and all costs which may attend such removal and substitution shall
be borne by the Contractor.
The contractor shall at his own expense, provide a material testing lab at the site for conducting
routine field tests. The lab shall be equipped at least with the testing equipment.
Minimum 01 year warranty for Mechanical & Electrical Equipments and other bought out items, at
the discretion of WAPCOS Limited, if supplied directly by the contractor. The standard warranty
period offered by the Manufacturer shall be retained, in case the original warranty period is more
than one year.
CLAUSE 10B :
(i) SECURED ADVANCE ON NON-PERISHABLE MATERIALS
The contractor, on signing an indenture in the form to be specified by the Engineer-in-
Charge, shall be entitled to be paid during the progress of the execution of the work up to
75% of the assessed value of any materials which are in the opinion of the Engineer-in-
Charge non-perishable, non-fragile and non-combustible and are in accordance with the
contract and which have been brought on the site in connection therewith and are adequately
stored and/or protected against damage by weather or other causes but which have not at
the time of advance been incorporated in the works. When materials on account of which an
advance has been made under this sub-clause are incorporated in the work, the amount of
such advance shall be recovered/ deducted from the next payment made under any of the
clause or clauses of this contract.
Such secured advance shall also be payable on other items of perishable nature, fragile and
combustible with the approval of the Engineer-in-Charge provided the contractor provides a
comprehensive insurance cover for the full cost of such materials. The decision of the
Engineer-in-Charge shall be final and binding on the contractor in this matter. No secured
advance, shall however, be paid on high-risk materials such as ordinary glass, sand, petrol,
diesel etc.
This advance shall further be subject to the condition that such plant and equipment (a) are
considered by the Engineer-in-Charge to be necessary for the works; (b) and are in working
order and are maintained in working order; (c) hypothecated to the WAPCOS as specified
by the Engineer-in-Charge before the payment of advance is released. The contractor shall
not be permitted to remove from the site such hypothecated plant and equipment without the
prior written permission of the Engineer-in-Charge. The contractor shall be responsible for
maintaining such plant and equipment in good working order during the entire period of
hypothecation failing which such advance shall be entirely recovered in lump sum. For this
purpose, steel scaffolding and form work shall be treated as plant and equipment. The
contractor shall insure the Plant and Machinery for which mobilization advance is sought and
given, for a sum sufficient to provide for their replacement at site. Any amounts not recovered
from the insurer will be borne by the contractor.
(iv) INTEREST & RECOVERY
The mobilization advance and plant and machinery advance in (ii) & (iii) above bear simple
interest at the rate of 10 percent per annum and shall be calculated from the date of payment
to the date of recovery, both days inclusive, on the outstanding amount of advance. Recovery
of such sums advanced shall be made by the deduction from the contractors bills
commencing after first ten percent of the gross value of the work is executed and paid, on
pro-rata percentage basis to the gross value of the work billed beyond 10% in such a way
that the entire advance is recovered by the time eighty percent of the gross value of the
contract is executed and paid, together with interest due on the entire outstanding amount
up to the date of recovery of the installment.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
At least to 10% of prescribed Tests as per Central Public Works Department Manual/IS Codes of
construction materials shall be carried out from the outside approved/NABL recognized Laboratory
as may be approved by WAPCOS without any extra expenditure to WAPCOS.
The Contractor shall establish a field test laboratory on the site with latest equipment’s for carrying
out field tests of construction materials and will maintain proper records of all the test results.
On receipt of such proposal, either individually or covering group of items, the Engineer-in-
charge shall examine the proposal regarding its admissibility and finalize the proposal/rates
within 45 days after receipt of proposal with all requisite details and documents from the
contractors, after giving due consideration to the proposal, analysis and rates of materials
and labours, etc.
12.3.1 The increase/decrease in the rates due to deviations/variations shall be decided based on
the following criteria:-
a) Pricing of deviations
a) If the item of work as stipulated in the schedule of quantity/scope of work deviates
on plus side, then the rate for the deviated quantity shall be paid at the agreement
rate upto the deviation limit as specified in Special Conditions of Contract with
the same terms & conditions of the contract. Beyond deviation limit as specified
in the Special Conditions of Contract, rate shall be payable on market rates to be
determined based on the relevant documents and prevailing market rates, as per
Para (ii) below
b) If the item of work as stipulated in the schedule of quantity/scope of work deviates
on minus side, then the amount for such deviated quantity shall be deducted
proportionately at the agreement rate.
b) Pricing of variations
If there are changes in the quantity/ specifications/ alterations/ substitutions/
additions, etc. in the items, other than mentioned in para- (i) above, the rates shall
be determined based on detailed analysis of rates with original stipulated scope of
items & newly proposed/provided items. The difference of rates so determined shall
be payable to/ recoverable from the contractor. The rates for both the components
i.e. materials &labour shall be based on prevailing market rates. The rate finalized
by the Engineer-in-Charge shall be final and binding.
12.3.2 In case of either non-submission of timely proposal or incomplete proposal by the contractor
for deviations/variations, the Engineer-in-Charge shall give final opportunity to the Contractor
to submit the complete proposal for change of cost within next 15 days. In case of non-
submission or further incomplete submission by the contractor within the stated period, the
Engineer-in-Charge shall initiate the proposal and decide the change of cost. In such case
the proposal finalized by the Engineer-in-Charge shall be final and binding on the contractor.
ii) Notwithstanding anything to the contrary in this clause 12, any change arising from
default of the contractor in the performance of his obligations under this agreement shall
not be deemed to be deviations/variations, and shall not result in any adjustment of the
contract price or the project completion schedule.
The contractor shall, if required by the Engineer- in-Charge, furnish to him, books of account, wage
books, time sheets and other relevant documents and evidence as may be necessary to enable him
to certify the reasonable amount payable under this condition.
The reasonable amount of items on (i), (iii) and (iv) above shall not be in excess of 2% of the cost
of the work remaining incomplete on the date of closure, i.e. total stipulated cost of the work as per
accepted tender less the cost of work actually executed under the contract and less the cost of
contractor’s materials at site taken over by the WAPCOS as per item (ii) above. Provided always
that against any payments due to the contractor on this account or otherwise, the Engineer-in-
Charge shall be entitled to recover or be credited with any outstanding balances due from the
contractor for advance paid in respect of any tool, plants and materials and any other sums which
at the date of termination were recoverable by the WAPCOS from the contractor under the terms of
the contract.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
In the event of action being taken under Clause 13 to reduce the scope of work, the contractor may
furnish fresh Performance Guarantee on the same conditions, in the same manner and at the same
rate for the balance tendered amount and initially valid up to the extended date of completion or
stipulated date of completion if no extension has been granted plus minimum 180 days beyond that.
Wherever such a fresh Performance Guarantee is furnished by the contractor the Engineer-in-
Charge may return the previous Performance Guarantee
(ii) If the suspension is ordered for reasons (b) and (c) in sub-para (i) above:
(a) the contractor shall be entitled to an extension of time equal to the period of every such
suspension plus 25%, for completion of the item or group of items of work for which a
separate period of completion is specified in the contract and of which the suspended
work forms a part, and;
(b) If the total period of all such suspensions in respect of an item or group of items or work
for which a separate period of completion is specified in the contract exceeds thirty days,
the contractor shall, in addition, be entitled to such compensation as the Engineer-in-
Charge may consider reasonable in respect of salaries and/or wages paid by the
contractor to his employees and labour at site, remaining idle during the period of
suspension, adding thereto 2% to cover indirect expenses of the contractor provided the
contractor submits his claim supported by details to the Engineer-in-Charge within fifteen
days of the expiry of the period of 30 days.
(iii) If the works or part thereof is suspended on the orders of the Engineer-in-Charge for more
than three months at a time, except when suspension is ordered for reason (a) in subpara
(i) above, the contractor may after receipt of such order serve a written notice on the
Engineer-in-Charge requiring permission within fifteen days from receipt by the Engineer-in-
Charge of the said notice, to proceed with the work or part thereof in regard to which progress
has been suspended and if such permission is not granted within that time, the contractor, if
he intends to treat the suspension, where it affects only a part of the works as an omission
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
of such part by WAPCOS or where it affects whole of the works, as an abandonment of the
works by WAPCOS, shall within ten days of expiry of such period of 15 days give notice in
writing of his intention to the Engineer-in-Charge. In the event of the contractor treating the
suspension as an abandonment of the contract by WAPCOS, he shall have no claim to
payment of any compensation on account of any profit or advantage which he might have
derived from the execution of the work in full but which he could not derive in consequence
of the abandonment. He shall, however, be entitled to such compensation, as the Engineer-
in-Charge may consider reasonable, in respect of salaries and/or wages paid by him to his
employees and labour at site, remaining idle in consequence adding to the total thereof 2%
to cover indirect expenses of the contractor provided the contractor submits his claim
supported by details to the Engineer-in-Charge within 30 days of the expiry of the period of
3 months.
Contractor shall repair/replace and restore the damaged structures/services in a time bound
manner as required and as directed by the Engineer-in-Charge. Contractor shall not be given
any benefit of hindrance caused in the execution of the work owing to such damaged
structure/service and time taken in its restoration by the contractor.
Such defects and deficiencies shall be made good by the contractor at his own cost after
getting instructions/notice from the Engineer-in-Charge within the time period specified in
such instructions/notice.
However, contractor need not wait for instructions/notice from Engineer-in-Charge for
rectification of defects in work which come to his notice and he should initiate action for
needful rectification of defect on priority, under intimation to Engineer-in-Charge, to avoid
any untoward incident.
17.5 Contractor’s failure to rectify defects as defined in the sub-clauses 17.1, 17.2, 17.3 & 17.4
In the event that the contractor fails to repair or rectify the defect or deficiency within the period
specified by the Engineer-in-Charge, the Engineer-in-Charge shall be entitled to get the same
repaired, rectified or remedied at the contractor’s cost and recover such amount from any dues
like performance guarantee, security deposits etc. available with Engineer-in-Charge.
Engineer-in-Charge may take action for debarment of contractor from tendering in WAPCOS
by following due process. For inacti on or failure to rectify the defects covered under sub clause
17.3 within specified time limit, the Engineer-in-Charge may also initiate legal and/or other
actions under other applicable laws in addition to other remedies available in the contract.
Provided further, that the security deposit shall be released within a month of its due date as
stated above only if satisfactory performance is observed during the said period and after
deduction of Government dues from the contractor, if any.
so doing, the same may be provided by the Engineer-in-Charge at the expense of the contractor
and the expenses may be deducted, from any money due to the contractor, under this contract or
otherwise and/or from his security deposit or the proceeds of sale thereof, or of a sufficient portions
thereof.
Any failure to fulfill these requirements shall attract the penal provisions of this contract arising out
of the resultant non-execution of the work
CLAUSE 19A
No labour below the age of fourteen years shall be employed on the work.
amount from the minimum wage payable to the workmen as and by way of commission or
otherwise.
(viii) The contractor shall ensure that no amount by way of commission or otherwise is deducted
or recovered by the Jamadar from the wage of workmen.
CLAUSE 19C
In respect of all labour directly or indirectly employed in the work for the performance of the
contractor’s part of this contract, the contractor shall at his own expense arrange for the safety
provisions as per C.P.W.D. Safety Code framed from time to time and shall at his own expense
provide for all facilities in connection therewith. In case the contractor fails to make arrangement and
provide necessary facilities as aforesaid, he shall be liable to pay a penalty of Rs.200/- for each
default and in addition, the Engineer-in- Charge shall be at liberty to make arrangement and provide
facilities as aforesaid and recover the costs incurred in that behalf from the contractor.
CLAUSE 19 D
The contractor shall submit by the 4th and 19th of every month, to the Engineer-in-Charge, a true
statement showing in respect of the second half of the preceding month and the first half of the
current month respectively:-
(1) The number of labourers employed by him on the work,
(2) Their working yours,
(3) The wages paid to them,
(4) The accidents that occurred during the said fortnight showing the circumstances under which
they happened and the extent of damage and injury caused by them, and
(5) The number of female workers who have been allowed maternity benefit according to Clause
19F and the amount paid to them.
Failing which the contractor shall be liable to pay to WAPCOS, a sum not exceeding Rs.200/- for
each default or materially incorrect statement. The decision of the Engineer-In-Charge shall be final
in deducting from any bill due to the contractor; the amount levied as fine and be binding on the
contractor.
CLAUSE 19 E
In respect of all labour directly or indirectly employed in the works for the performance of the
contractor’s part of this contract, the contractor shall comply with or cause to be complied with all
the rules framed by Government from time to time for the protection of health and sanitary
arrangements for workers employed by the WAPCOS and its contractors.
CLAUSE 19 F
Leave and pay during leave shall be regulated as follows:-
1. Leave :
(i) in the case of delivery – maternity leave not exceeding 8 weeks, 4 weeks up to and
including the day of delivery and 4 weeks following that day,
(ii) in the case of miscarriage – upto 3 weeks from the date of miscarriage.
2. Pay :
(i) in the case of delivery – leave pay during maternity leave will be at the rate of the
women’s average daily earnings, calculated on total wages earned on the days when full
time work was done during a period of three months immediately preceding the date on
which she gives notice that she expects to be confined or at the rate of Rupee one only
a day whichever is greater.
(ii) in the case of miscarriage – leave pay at the rate of average daily earning calculated on
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
the total wages earned on the days when full time work was done during a period of three
months immediately preceding the date of such miscarriage.
3. Conditions for the grant of Maternity Leave:
No maternity leave benefit shall be admissible to a woman unless she has been employed
for a total period of not less than six months immediately preceding the date on which she
proceeds on leave.
4. The contractor shall maintain a register of Maternity (Benefit) in the Prescribed Form as
shown in appendix –I and II, and the same shall be kept at the place of work.
CLAUSE 19 G
In the event of the contractor(s) committing a default or breach of any of the provisions of the
WAPCOS, Contractor’s Labour Regulations and Model Rules for the protection of health and
sanitary arrangements for the workers as amended from time to time or furnishing any information
or submitting or filing any statement under the provisions of the above Regulations and’ Rules which
is materially incorrect, he/they shall, without prejudice to any other liability, pay to the Government
a sum not exceeding Rs.200/- for every default, breach or furnishing, making, submitting, filing such
materially incorrect statements and in the event of the contractor(s) defaulting continuously in this
respect, the penalty may be enhanced to Rs.200/- per day for each day of default subject to a
maximum of 5 per cent of the estimated cost of the work put to tender. The decision of the Engineer-
in-Charge shall be final and binding on the parties.
Should it appear to the Engineer-in-Charge that the contractor(s) is/are not properly observing and
complying with the provisions of the C.P.W.D. Contractor’s Labour Regulations and Model Rules
and the provisions of the Contract Labour (Regulation and Abolition) Act 1970, and the Contract
Labour (R& A) Central Rules 1971, for the protection of health and sanitary arrangements for work-
people employed by the contractor(s) (hereinafter referred as “the said Rules”) the Engineer-in-
Charge shall have power to give notice in writing to the contractor(s) requiring that the said Rules
be complied with and the amenities prescribed therein be provided to the work-people within a
reasonable time to be specified in the notice. If the contractor(s) shall fail within the period specified
in the notice to comply with and/observe the said Rules and to provide the amenities to the work-
people as aforesaid, the Engineer-in-Charge shall have the power to provide the amenities
hereinbefore mentioned at the cost of the contractor(s). The contractor(s) shall erect, make and
maintain at his/their own expense and to approved standards all necessary huts and sanitary
arrangements required for his/their work-people on the site in connection with the execution of the
works, and if the same shall not have been erected or constructed, according to approved standards,
the Engineer-in-Charge shall have power to give notice in writing to the contractor(s) requiring that
the said huts and sanitary arrangements be 350tilize350350 and/or reconstructed according to
approved standards, and if the contractor(s) shall fail to remodel or reconstruct such huts and
sanitary arrangements according to approved standards within the period specified in the notice, the
Engineer-in-Charge shall have the power to remodel or reconstruct such huts and sanitary
arrangements according to approved standards at the cost of the contractor(s).
CLAUSE 19 H
The contractor(s) shall at his/their own cost provide his/their labour with a sufficient number of huts
(hereinafter referred to as the camp) of the following specifications on a suitable plot of land to be
approved by the Engineer-in-Charge.
(i) (a) The minimum height of each hut at the eaves level shall be 2.10m (7 ft.) and the floor
area to be provided will be at the rate of 2.7 sq.m. (30 sq.ft.) for each member of the worker’s
family staying with the labourer.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
(b) The contractor(s) shall in addition construct suitable cooking places having a minimum
area of 1.80m x 1.50m (6’x5’) adjacent to the hut for each family.
I The contractor(s) shall also construct temporary latrines and urinals for the use of the
labourers each on the scale of not less than four per each one hundred of the total
strength, separate latrines and urinals being provided for women.
(d) The contractor(s) shall construct sufficient number of bathing and washing places, one
unit for every 25 persons residing in the camp. These bathing and washing places shall
be suitably screened.
(ii) (a) All the huts shall have walls of sun-dried or burnt-bricks laid in mud mortar or other
suitable local materials as may be approved by the Engineer-in-Charge. In case of sun-dried
bricks, the walls should be plastered with mud gobri on both sides. The floor may be kutcha
but plastered with mud gobri and shall be at least 15 cm (6”) above the surrounding ground.
The roofs shall be laid with thatch or any other materials as may be approved by the
Engineer-in-Charge and the contractor shall ensure that throughout the period of their
occupation, the roofs remain water-tight.
(b) The contractor(s) shall provide each hut with proper ventilation.
I All doors, windows, and ventilators shall be provided with suitable leaves for security
purposes.
(d) There shall be kept an open space of at least 7.2m (8 yards) between the rows of huts
which may be reduced to 6m (20 ft.) according to the availability of site with the approval
of the Engineer-in-Charge. Back to back construction will be allowed
(iii) Water Supply – The contractor(s) shall provide adequate supply of water for the use of
labourers. The provisions shall not be less than two gallons of pure and wholesome water
per head per day for drinking purposes and three gallons of clean water per head per day
for bathing and washing purposes. Where piped water supply is available, supply shall be at
stand posts and where the supply is from wells or river, tanks which may be of metal or
masonry, shall be provided. The contractor(s) shall also at his/ their own cost make
arrangements for laying pipe lines for water supply to his/ their labour camp from the existing
mains wherever available, and shall pay all fees and charges therefore.
(iv) The site selected for the camp shall be high ground, removed from jungle.
(v) Disposal of Excreta – The contractor(s) shall make necessary arrangements for the
disposal of excreta from the latrines by trenching or incineration which shall be according to
the requirements laid down by the Local Health Authorities. If trenching or incineration is not
allowed, the contractor(s) shall make arrangements for the removal of the excreta through
the Municipal Committee/authority and inform it about the number of labourers employed so
that arrangements may be made by such Committee/authority for the removal of the excreta.
All charges on this account shall be borne by the contractor and paid direct by him to the
Municipality/authority. The contractor shall provide one sweeper for every eight seats in case
of dry system.
(vi) Drainage – The contractor(s) shall provide efficient arrangements for draining away sullage
water so as to keep the camp neat and tidy.
(vii) The contractor(s) shall make necessary arrangements for keeping the camp area sufficiently
lighted to avoid accidents to the workers.
(viii) Sanitation – The contractor(s) shall make arrangements for conservancy and sanitation in
the labour camps according to the rules of the Local Public Health and Medical Authorities.
CLAUSE 19 I
The Engineer-in-Charge may require the contractor to dismiss or remove from the site of the work
any person or persons in the contractors’ employ upon the work who may be incompetent or
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
misconduct himself and the contractor shall forthwith comply with such requirements. In respect of
maintenance/repair or renovation works etc. where the labour have an easy access to the individual
houses, the contractor shall issue identity cards to the labourers, whether temporary or permanent
and he shall be responsible for any untoward action on the part of such labour.
CLAUSE 19J
It shall be the responsibility of the contractor to see that the building under construction is not
occupied by unauthorized person(s) during construction, and is handed over to the Engineer-in-
Charge with vacant possession of complete building. If such building though completed is occupied
illegally, then the Engineer-in-Charge shall have the option to refuse to accept the said building /
buildings in that position. Any delay in acceptance on this account will be treated as the delay in
completion and for such delay, a compensation shall be levied upto 5% of tendered value of work
may be imposed by the WAPCOS whose decision shall be final both with regard to the justification
and quantum and be binding on the contractor.
However, WAPCOS, through a notice, may require the contractor to remove the illegal occupation
any time on or before construction and delivery.
The Contractor shall devise a quality assurance mechanism to ensure compliance with the
provisions of this Agreement (the “Quality Assurance Plan” or “QAP”).
(i) The Contractor shall, submit to the Engineer-in-Charge, its Quality Assurance Plan 15
(fifteen) days in advance of start of the execution stage specified in the NIT. The
Engineer-in-Charge shall convey its comments to the Contractor within a period of 7
(seven) days of receipt of the QAP stating the modifications, if any, required and the
Contractor shall incorporate those in the QAP conforming with the provisions of this
clause. The QAP shall include the following:
a) Contractor’s Organization & structure, duties and responsibilities of individual key
personnel, quality policy of contractor, procedure for control of non-conformities and
corrective action, inspections and documentation.
b) Internal quality audit system.
c) Machinery, Shuttering, other Tool & Plants, etc. required to be deployed at site.
d) Method statement of important activities. These can be submitted as per the
sequencing of the activities of the work.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
All the tests in field lab setup at construction site shall be carried out by the QA Staff
deployed by the contractor and shall be witnessed by the Engineer-in-Charge or his
authorized subordinates as specified in NIT. The contractor shall provide all necessary
facility to them for witnessing the tests in the field laboratory. In general, contractor
shall carry out 90% of field tests in site laboratory and 10% tests shall be got carried
out from outside laboratory as indicated below. Contractor shall endeavour to obtain
test reports for tests conducted from outside laboratory in a reasonable time.
(vi) The Contractor shall procure all relevant codes, publications, apparatus and
instruments, fuel, consumables, water, electricity, labour, materials, samples and
qualified personnel as are necessary for examining and testing the Works, Materials
and workmanship in accordance with the Quality Assurance Plan.
(vii) All the cost of testing including cost of samples, packaging, transportation, testing
charges of Construction, Materials and workmanship under this clause shall be borne
by the contractor.
(viii) The contractor shall submit monthly quality progress report on implementation of the
provisions of Quality Assurance Plan on the format approved by the Engineer-in-
Charge.
22.3 Samples
The Contractor shall, at its own expense and without delay, provide the samples of Materials
and relevant information like Manufacturer’s test reports, standard samples of manufactured
Materials and Samples of such other Materials as the Engineer-in- Charge may require for
review and approvals in accordance with Clause 10A of GCC
before actual use.
22.4 Test
(i) For determining that the Works conform to the Specifications and Standards, the
Engineer-in-Charge shall require the Contractor to carry out or cause to be carried out
tests, at such time and frequency and in such manner as specified in this Agreementand
in accordance with sound engineering practice for quality assurance. Frequency and the
manner in which tests shall be conducted shall be in the following order of preference:
a) Contract provisions.
b) CPWD specifications.
c) BIS codes.
d) IRC codes.
e) MoRTH Specifications.
f) International Codes.
g) Manufacturer’s specifications.
Outside tests shall be conducted at Government labs /IITs/NITs and other approved
laboratories by the Engineer-in-Charge for testing of materials
(ii) The Contractor shall, with due diligence, carry out all the tests in accordance with the
Agreement and furnish the results thereof to the Engineer-in-Charge. The Engineer-in-
Charge or his authorized representative shall witness or participate during the testing as
specified in NIT. The contractor shall provide all necessary assistance for
witnessing/participating in the field tests.
(iii) In the event that results of any tests conducted under this clause establish any defects
or deficiencies in the Works, the Contractor shall carry out remedial measures at its own
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
cost and furnish a report to the Engineer-in-Charge in this regard. The Engineer-in-
Charge shall require the Contractor to carry out or cause to be carried out tests to
determine that such remedial measures have brought the works into compliance with
the Specifications and standards and the procedure shall be repeated until such Works
conform to the Specifications and Standards.
Suitable actions shall be taken as per the provisions contained in the relevant clauses of the
agreement, if the work is not found to be as per specifications or quality as specified in the
agreement.
22.9 Examination of work before covering up/ Test Check of item of Work
In respect of the work which the Engineer-in-Charge or his authorized representatives are
required to examine, inspect, measure or test before it is covered up or put out of view or any
part of the work is placed thereon, the Contractor shall give notice to the Engineer-in-Charge
whenever any such work is ready and before it is covered up. The Engineer-in-Charge shall
then either carry out the examination, inspection or testing without unreasonable delay within
7 days, or promptly give notice to the Contractor that the Engineer-in-Charge does not require
him to do so. Provided, however, that if any work is of a continuous nature where it is not
possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule
of carrying out such work to give sufficient opportunity, not being less than 3(three) business
days’ notice, to the Engineer-in-Charge to conduct its inspection, measurement or test while
the work is continuing. Provided further that in the event the Contractor receives no response
from the Engineer-in-Charge within a period of 3 (three) business days from the date on which
the Contractor’s notice hereunder is delivered to the Engineer-inCharge, the Contractor shall
be entitled to assume that the Engineer-in-Charge would not undertake the said inspections.
22.10 Rejection
(i) If, as a result of an examination, inspection, measurement or testing, any Plant, Materials,
design or workmanship is found to be defective or otherwise not in accordance with the
provisions of this Agreement, the Engineer-in-Charge may reject such piece of work, Plant,
Materials, design or workmanship by giving notice to the Contractor, with reasons. The
Contractor shall then promptly make good the defect and ensure that the rejected item
complies with the requirements of this Agreement.
(ii) If the Engineer-in-Charge requires a Piece of work, Plant, Material, design or workmanship
to be retested, the tests shall be repeated on the same terms and conditions, as applicable
in each case. If the rejection and retesting cause the WAPCOS to incur any additional costs,
such costs shall be recoverable by the Engineer-in-Charge from the Contractor and may
be deducted by the Engineerin-Charge from any amount due to be paid to the Contractor.
(iii) The Contractor shall not be entitled to any extension of time on account of rectifying any
defect or retesting as specified in this clause.
(ii) If the Contractor fails to comply with the instructions issued by the Engineer-inCharge
under aforesaid para, within the time specified in the notice or as mutually agreed, the
Engineer-in-Charge may get the work executed by another agency. The cost so incurred
by the Engineer-in-Charge for undertaking such work shall, without prejudice to the rights
of the Engineer-in-Charge to recover damages in accordance with the provisions of this
Agreement, be recoverable from the Contractor and may be deducted by the Engineer-
in-Charge from any amount due to be paid to the Contractor
CLAUSE 24
All works to be executed under the contract shall be executed under the direction and subject to the
approval in all respects of the Engineer-in-Charge who shall be entitled to direct at what point or
points and in what manner they are to be commenced, and from time to time carried on.
Except where otherwise provided in the contract, all questions and disputes relating to the meaning of
the specifications, design, drawings and instructions here-in before mentioned and as to the quality of
workmanship or materials used on the work or as to any other question, claim, right, matter or thing
whatsoever in any way arising out of or relating to the contract, designs, drawings, specifications,
estimates, instructions, orders or these conditions or otherwise concerning the works or the execution
or failure to execute the same whether arising during the progress of the work or after the cancellation,
termination, completion or abandonment thereof shall be dealt with as mentioned hereinafter:
I. If the Contractor considers any work demanded of him to be outside the requirements of the
Contract, or disputes any drawings, record or decision given in writing by the Engineer-in-
Charge on any matter in connection with or arising out of the Contract or carrying out of the
work, to be unacceptable, he shall promptly within 15 days request Engineer-in-Charge in writing
for written instruction or decision. Thereupon, the Engineer-in-Charge shall give his written
instructions or decision within a period of one month from the receipt of the Contractor’s letter.
II. In case the Contractor is not satisfied with the decision of Engineer-in-Charge, he may proceed
for arbitration as detailed in Clause 25.2 hereinafter.
III. It is a term of Contract that each party invoking arbitration must exhaust the aforesaid
mechanism of settlement of claims/disputes prior to invoking arbitration.
IV. Performance of this Agreement/ Contract shall continue during arbitration proceedings or any
other dispute resolution mechanism pursuant to Clause 25.2. No payment due or payable by
the Employer shall be withheld on account of pending reference to the arbitration or other
dispute resolution mechanism excepts to the extent that such payment of dispute.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
25.2 Arbitration
Any dispute, controversy of claims arising out of or relating to this Agreement or the breach, termination
or invalidity thereof, shall be settled through following mechanism:
a. Firstly, the aggrieved party shall write a letter to the other party detailing its grievances and
calling upon the other party to amicably resolve the dispute by convening a joint meeting.
Accordingly, the parties as per their convenience shall jointly convene the said meeting(s),
wherein minutes of the said meeting(s) shall be prepared and countersigned by all the parties.
It is mandatory to prepare minutes of meeting(s) and to be countersigned by all the parties,
irrespective of the outcome of the said meeting(s).
b. In the event the parties are unable to reach on any settlement in the said meeting(s), then the
aggrieved party shall mandatorily resort to pre-litigation mediation mechanism with Delhi High
Court Mediation Cell, New Delhi.
c. It is only upon failure of the pre-litigation mediation mechanism with Delhi High Court Mediation
Cell, then the aggrieved party shall resort to resolution of disputes through arbitration of a Sole
Arbitrator. The appointing authority of Sole Arbitrator is CMD, WAPCOS Limited, to which
neither of the parties have any objection nor they shall ever object.
d. Subject to the parties agreeing otherwise, the Arbitration proceedings shall be conducted in
accordance with the provisions of the Indian Arbitration and Conciliation Act, 1996 (amended
as on date).
e. It is also acknowledged and accepted that the Employer is only working as intermediary between
the Contractor/Supplier and the Principal Employer/Owner, thus in the event, any dispute arises
under the present agreement and referred to Arbitration for adjudication, then subject to
corresponding clause in the Contract between Principal Employer/Owner & the Employer,
Principal Employer/Owner shall also be made party to the said Arbitration proceedings. Also,
the award including costs if any passed against the Employer and costs incurred in the
proceedings shall be the sole responsibility of Principal Employer/Owner. The said clause if
found inapplicable, even then the other terms of the Arbitration Clause shall survive and shall
be acted upon.
f. The place/seat of arbitration shall be Delhi and any award whether interim or final, shall be
made, and shall be deemed for all purposes between the parties to be made, in Delhi. The
arbitral procedure shall be conducted in English language and any award or awards shall be
rendered in English. The procedural law of the arbitration shall be Indian Law. The award of the
arbitrator shall be final and conclusive and binding upon the Parties.
g. The Contract and any dispute or claim arising out of or in connection with it or its subject matter
or formation (including non-contractual disputes or claims) shall be governed by and construed
in accordance with the laws of India and the Parties submit to sole & exclusive jurisdiction of
courts at Delhi.”
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
The request for arbitration, the answer to the request, the terms of reference, any written submissions,
any orders and awards shall be in English and, if oral hearings take place, English shall be the language
to be used in the hearings.
Pending the submission of and/or decision on a Dispute and until the arbitral award is published, the
Parties shall continue to perform their respective obligations under the Contract without prejudice to a
final adjustment in accordance with such award.
The decision of Engineer-in-Charge regarding the quantum or reduction as well as justification thereof
in respect of payment for sub-standard work which may be decided to be accepted will be final and
would not be open to arbitration.
It is an agreed term of the contract that the sum of money or moneys so withheld or retained
under the lien referred to above by the Engineer-in-Charge or Government will be kept
withheld or retained as such by the Engineer-in-Charge or Government till the claim arising
out of or under the contract is determined by the arbitrator (if the contract is governed by the
arbitration clause) by the competent court, as the case may be and that the contractor will
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
have no claim for interest or damages whatsoever on any account in respect of such
withholding or retention under the lien referred to above and duly notified as such to the
contractor. For the purpose of this clause, where the contractor is a partnership firm or a limited
company, the Engineer-in-charge or the Government shall be entitled to withhold and also
have a lien to retain towards such claimed amount or amounts in whole or in part from any
sum found payable to any partner/limited company as the case may be, whether in his
individual capacity or otherwise.
(ii) Government / WAPCOS shall have the right to cause an audit and technical examination of
the works and the final bills of the contractor including all supporting vouchers, abstract, etc.,
to be made after payment of the final bill and if as a result of such audit and technical
examination any sum is found to have been overpaid in respect of any work done by the
contractor under the contract or any work claimed to have been done by him under the contract
and found not to have been executed, the contractor shall be liable to refund the amount of
over-payment and it shall be lawful for Government to recover the same from him in the
manner prescribed in sub-clause (i) of this clause or in any other manner legally permissible;
and if it is found that the contractor was paid less than what was due to him under the contract
in respect of any work executed by him under it, the amount of such under payment shall be
duly paid by Government to the contractor, without any interest thereon whatsoever.
Provided that the Government shall not be entitled to recover any sum overpaid, nor the
contractor shall be entitled to payment of any sum paid short where such payment has been
agreed upon between the Superintending Engineer or Executive Engineer on the one hand
and the contractor on the other under any term of the contract permitting payment for work
after assessment by the Superintending Engineer or the Engineer-in-Charge.
Where ceiling price for imported labour has been fixed by State or Regional Labour Committees not
more than that ceiling price shall be paid to the labour by the contractor.
The contractor shall immediately remove any labourer who may be pointed out by the Engineer-in-
Charge as being a coal mining or controlled area labourer. Failure to do so shall render the
contractor liable to pay to WAPCOS a sum calculated at the rate of Rs.10/- per day per labourer.
The certificate of the Engineer-in-Charge about the number of coal mining or controlled area
labourer and the number of days for which they worked shall be final and binding upon all parties to
this contract.
It is declared and agreed between the parties that the aforesaid stipulation in this clause is one in
which the public are interested within the meaning of the exception in Section 74 of Indian Contract
Act, 1872.
As per tendered amount (worked out on the basis of quoted rate of individual items)and before
commencement of the work, intimate in writing to the Engineer-in-Charge, the name(s),
qualifications, experience, age, address(s) and other particulars along with certificates, of the
principal technical representative to be in charge of the work and other technical
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
representative(s) who will be supervising the work. Minimum requirement of such technical
representative(s) and their qualifications and experience shall not be lower than specified in
Special Conditions of Contract. Even of the contractor (or partner(s) in case of firm/
company)is himself / herself an Engineers, it is necessary on the part of the contractor to
Employ principal technical representative / technical representative (s) as per stipulation in
Special Conditions of Contract.
All the provisions applicable to the principal technical representative under the Clause will also
be applicable to other technical representative(s) The principal technical representative and
other technical representative(s) shall be present at the site of work for supervision at all times
when any construction activity is in progress and also present himself/themselves, as required,
to the Engineer-in-Charge and/or his designated representative to take instructions.
Instructions given to the principal technical representative or other technical representative(s)
shall be deemed to have the same force as if these have been given to the contractor. The
principal technical representative and other technical representative(s) shall be actually
available at site fully during all stages of execution of work, during recording /checking/test
checking of measurements of works and whenever so required by the Engineer-in-Charge and
shall also note down instructions conveyed by the Engineer-in-Charge or his designated
representative(s) in the site order book and shall affix his/their signature in token of noting
down the instructions and in token of acceptance of measurements/checked measurements/
test checked measurements. The representative(s) shall not look after any other work.
Substitutes, duly approved by Engineer-in-Charge of the work in similar manner as aforesaid
shall be provided in event of absence of any of the representative(s) by more than two days.
If the Engineer-in-Charge, whose decision in this respect is final and binding on the contractor,
is convinced that no such technical representative(s) is/are effectively appointed or is/are
effectively attending or fulfilling the provision of this clause, a recovery (non-refundable) shall
be effected from the contractor as specified in Special Conditions of Contract and the decision
of the Engineer-In-Charge as recorded in the site order book and measurement recorded
checked/test checked in Measurement Books shall be final and binding on the contractor.
Further if the contractor fails to appoint suitable technical Principal technical representative
and/or other technical representative(s) and if such appointed persons are not effectively
present or are absent by more than two days without duly approved substitute or do not
discharge their responsibilities satisfactorily, the Engineer-in-Charge shall have full powers to
suspend the execution of the work until such date as suitable other technical representative(s)
is/areappointed and the contractor shall be held responsible for the delay so caused to the
work. The contractor shall submit a certificate of employment of the technical representative(s)
(in the form of copy of Form-16 or CPF deduction issued to the Engineers employed by him)
along with every on account bill/ final bill and shall produce evidence if at any time so required
by the Engineer-in-Charge.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
(ii) The contractor shall provide and employ on the site only such technical assistants as are
skilled and experienced in their respective fields and such foremen and supervisory staff as
are competent to give proper supervision to the work.
The contractor shall provide and employ skilled, semiskilled and unskilled labour as is
necessary for proper and timely execution of the work.
The Engineer-in-Charge shall be at liberty to object to and require the contractor to remove
from the works any person who in his opinion misconducts himself, or is incompetent or
negligent in the performance of his duties or whose employment is otherwise considered by
the Engineer-in-Charge to be undesirable. Such person shall not be employed again at works
site without the written permission of the Engineer-inCharge and the persons so removed shall
be replaced as soon as possible by competent substitutes.
ii. The contractor shall deposit royalty and obtain necessary permit for supply of the red bajri,
stone, kankar, etc. from local authorities.
iii. If pursuant to or under any law, notification or order any royalty, cess or the like becomes
payable by the Government of India and does not any time become payable by the contractor
to the State Government, Local authorities in respect of any material used by the contractor in
the works, then in such a case, it shall be lawful to the Government of India and it will have
the right and be entitled to recover the amount paid in the circumstances as aforesaid from
dues of the contractor
However, effect of variation in rates of GST or Building and Other Construction Workers
Welfare Cess or imposition or repeal of any other tax, levy or cess applicable on output of the
works contract shall be adjusted on either side, increase or decrease.
Provided further that for Building and Other Construction Workers Welfare Cess or any tax
(other than GST), levy or cess varied or imposed after the last date of receipt of tender
including extension if any, any increase shall be reimbursed to the contractor only if the
contractor necessarily and properly pays such increased amount of taxes/levies/cess.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Provided further that such increase including GST shall not be made in the extended period
of contract for which the contractor alone is responsible for delay as determined by WAPCOS
for extension of time.
(ii) The contractor shall keep necessary books of accounts and other documents for the purpose
of this condition as may be necessary and shall allow inspection of the same by a duly
authorized representative of the Government and/or the Engineer-in-Charge and shall also
furnish such other information/document as the Engineer-in-Charge may require from time to
time.
(iii) The contractor shall, within a period of 30 days of the imposition of any such further tax or levy
or cess, or variation or repeal of such tax or levy or cess give a written notice thereof to the
Engineer-in-charge that the same is given pursuant to this condition, together with all
necessary information relating thereto.
NOTE: By the term “near relatives” is meant wife, husband, parents and grandparents, children and
grandchildren, brothers and sisters, uncles, aunts and cousins and their corresponding in-laws.
in Special Conditions of Contract. In case any item is executed for which standard
constants for the consumption of cement or bitumen are not available in the above
mentioned schedule/statement or cannot be derived from the same shall be calculated
on the basis of standard formula to be laid down by the Engineer-in-Charge.
(b) Theoretical quantity of steel reinforcement or structural steel sections shall be taken as
the quantity required as per design or as authorized by Engineer-in-Charge, including
authorized lappages, chairs etc. plus 3% wastage due to cutting into pieces, such
theoretical quantity being determined and compared with the actual issues each diameter
wise, section wise and category wise separately.
(c) Theoretical quantity of G.I. & C.I. or other pipes, conduits, wires and cables, pig lead and
G.I./M.S. sheets shall be taken as quantity actually required and measured plus 5% for
wastage due to cutting into pieces (except in the case of G.I./M.S. sheets it shall be 10%),
such determination & comparison being made diameter wise & category wise.
of materials and the purpose for which they were collected shall be final and binding on all parties
to this contract.
Provided always that no compensation shall be payable for any loss in consequence of hostilities or
warlike operations (a) unless the contractor had taken all such precautions against air raid as are
deemed necessary by the A.R.P. Officers or the Engineer-in-Charge (b) for any material etc. not on
the site of the work or for any tools, plant, machinery, scaffolding, temporary building and other
things not intended for the work. In the event of the contractor having to carry out reconstruction as
aforesaid, he shall be allowed such extension of time for its completion as is considered reasonable
by the Engineer-In-Charge.
CLAUSE42: INSURANCE
1. Requirements
Before commencing execution of works, unless stated otherwise in the special conditions of
contract, it shall be obligatory for the contractor to obtain at his own cost stipulated insurance
cover under the following requirements:
a) Contractor’s all risk and Third Party Cover.
b) Liability under the workmen’s compensation Act, 1923, Minimum Wages Act, 1948 and
Contract Labour (Regulation and Abolition) Act, 1970.
c) Accidents to staff, Engineers, Supervisors and others who are not governed by workmen’s
compensation Act.
d) Damage to material, machinery and works due to fire theft etc.
e) Any other risk to be covered by insurance as may be specified by the employer in the special
conditions of contract.
3. Currency of Policy
The policies shall remain in force throughout the period of execution of the works and till the
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
expiry of the defect liability period. The contractor shall, whenever called upon, produce to the
engineer or his representative the various insurance policies obtained by him as also the rates
of premia and the premia paid by him to ensure that the polices indeed continue to be in force.
If the contractor fails to effect or keep in force or provide adequate cover in the insurance policies
mentioned in the sub clause 46(1) or any other insurance he might be required to effect under
the contract, then in such cases, the employer may effect and keep in force any such insurance
or further insurance and the cost and expenses incurred by him in this regard shall be deductible
from payments due to the contractor or from the contractor’s performance security.
1.7 The contractor shall not change the natural gradient of the ground unless specifically
instructed by the architects / landscape consultant. This shall cover all natural features like
water bodies, drainage gullies, slopes, mounds, depressions, rocky outcrops, etc. Existing
drainage patterns through or into any preservation area shall not be modified unless
specifically directed by the Engineer-in-charge.
1.8 The contractor shall not carry out any work which results in the blockage of natural drainage.
1.9 The contractor shall ensure that existing grades of soil shall be maintained around existing
vegetation and lowering or raising the levels around the vegetation is not allowed unless
specifically directed by the Engineer-in-charge
1.10 Contractor shall reduce pollution and land development impacts from automobiles use during
construction.
1.11 Overloading of trucks is unlawful and creates and erosion and sedimentation problems,
especially when loose materials like stone dust, excavated earth, sand etc. are moved.
Proper covering must take place. No overloading shall be permitted.
2.3 Contractor shall be required to develop and implement a waste management plan,
quantifying material diversion goals. He shall establish goals for diversion from disposal in
landfills and incinerators and adopt a construction waste management plan to achieve these
goals. A project-vide policy of “Nothing leaves the Site” should be followed. In such a case
when strictly followed, care would automatically be taken in ordering and timing of materials
such that excess doesn’t become “waste”. The Contractor’s ingenuity is especially called
towards meeting this prerequisite/ credit (GRIHA). Consider recycling cardboard, metal,
brick, acoustical tile, concrete, plastic, clean wood, glass, gypsum wallboard, carpet and
insulation. Designate a specific area(s) on the construction site for segregated or
commingled collection of recyclable material, and track recycling efforts throughout the
construction process. Identify construction haulers and recyclers to handle the designated
materials. Note that diversion may include donation of materials to charitable organizations
and salvage of materials on-site.
2.4 Contractor shall collect all construction waste generated on site. Segregate these wastes
based on their utility and examine means of sending such waste to manufacturing units which
use them as raw material or other site which require it for specific purpose. Typical
construction debris could be broken bricks, steel bars, broken tiles, spilled concrete and
mortar etc.
2.5 The contractor shall provide clean drinking water for all workers
2.6 The contractor shall provide the minimum level of sanitation and safety facilities for the
workers at site. The contractor shall ensure cleanliness of workplace with regard to the
disposal of waste and effluent; provide clean drinking water and latrines and urinals as per
applicable standard. Adequate toilet facilities shall be provided for the workman within easy
access of their place of work. The total no. to be provided shall not be less than 1 per 30
employs in any one shift. Toilet facilities shall be provided from the start of building
operations, connection to a sewer shall be made as soon as practicable. Every toilet shall
be so constructed that the occupant is sheltered from view and protected from the weather
and falling objects. Toilet facilities shall be maintained in a sanitary condition. A sufficient
quantity of disinfectant shall be provided. Natural or artificial illumination shall be provided.
2.7 The contractor shall ensure that air pollution due to dust/generators is kept to a minimum,
preventing any adverse effects on the workers and other people in and around the site. The
contractor shall ensure proper screening, covering stockpiles, covering brick and loads of
dusty materials, wheel-washing facility, gravel pit, and water spraying. Contractor shall
ensure the following activities to prevent air pollution during construction:
Clear vegetation only from areas where work will start right away
Vegetate / mulch areas where vehicles do not ply.
Apply gravel / landscaping rock to the areas where mulching / paving is impractical
Identify roads on-site that would be used for vehicular traffic. Upgrade vehicular roads
(if these are unpaved) by increasing the surface strength by improving particle size,
shape and mineral types that make up the surface & base. Add surface gravel to
reduce source of dust emission. Limit amount of fine particles (smaller than
0.075mm) to 10 – 20%
Water spray, through a simple hose for small projects, to keep dust under control.
Fine mists should be used to control fine particulate. However, this should be done
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
with care so as not to waste water. Heavy watering can also create mud, which when
tracked onto paved public roadways, must be promptly removed. Also, there must be
an adequate supply of clean water nearby to ensure that spray nozzles don’t get
plugged. Water spraying can be done on:
a) Any dusty materials before transferring, loading and unloading
b) Area where demolition work is being carried out
c) Any un-paved main haul road
d) Areas where excavation or earth moving activities are to be carried out
The contractor shall ensure that the speed of vehicles within the site is limited to 10
km/hr.
All material storages should be adequately covered and contained so that they are
not exposed to situations where winds on site could lead to dust / particulate
emissions.
Spills of dirt or dusty materials will be cleaned up promptly so the spilled material
does not become a source of fugitive dust and also to prevent of seepage of pollutant
laden water into the ground aquifers. When cleaning up the spill, ensure that the
clean-up process does not generate additional dust. Similarly, spilled concrete
slurries or liquid wastes should be contained / cleaned up immediately before they
can infiltrate into the soil / ground or runoff in nearby areas
Provide hoardings of not less than 3m high along the site boundary, next to a road or
other public area
Provide dust screens, sheeting or netting to scaffold along the perimeter of the
building Cover stockpiles of dusty material with impervious sheeting
Cover dusty load on vehicles by impervious sheeting before they leave the site
2.8 Contractor shall be required to provide an easily accessible area that serves the entire
building and is dedicated to the separation, collection and storage of materials for recycling
including (at a minimum) paper, corrugated cardboard, glass, plastics, and metals. He shall
coordinate the size and functionality of the recycling areas with the anticipated collections
services for glass, plastic, office paper, newspaper, cardboard, and organic wastes to
maximize the effectiveness of the dedicated areas. Consider employing cardboard balers,
aluminium can crushers, recycling chutes, and collection bins at individual workstations to
further enhance the recycling program.
2.9 The contractor shall ensure that no construction leach ate (Ex: cement slurry), is allowed to
percolate into the ground. Adequate precautions are to be taken to safeguard against this
including, reduction of wasteful curing processes, collection, basic filtering and reuse. The
contractor shall follow requisite measures for collecting drainage water run-off from
construction areas and material storage sites and diverting water flow away from such
polluted areas. Temporary drainage channels, perimeter dike/swale, etc. shall be
constructed to carry the pollutant-laden water directly to the treatment device or facility
(municipal sewer line).
2.10 Staging (dividing a construction area into two or more areas to minimize the area of soil that
will be exposed at any given time) should be done to separate undisturbed land from land
disturbed by construction activity and material storage.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
2.11 The contractor shall Comply with the safety procedures, norms and guidelines (as
applicable) as outlined in the document Part 7 _Constructional practices and safety, 2005,
National Building code of India, Bureau of Indian Standards. A copy of all pertinent
regulations and notices concerning accidents, injury and first-aid shall be prominently
exhibited at the work site. Depending upon the scope & nature of work, a person qualified in
first-aid shall be available at work site to render and direct first-aid to causalities. A telephone
may be provided to first-aid assistant with telephone numbers of the hospitals displayed.
Complete reports of all accidents and action taken thereon shall be forwarded to the
competent authorities.
2.12 The contractor shall ensure the following activities for construction workers safety, among
other measures:
- Guarding all parts of dangerous machinery.
- Precautionary signs for working on machinery
- Maintaining hoists and lifts, lifting machines, chains, ropes, and other lifting tackles in
good condition.
- Durable and reusable formwork systems to replace timber formwork and ensure that
formwork where used is properly maintained.
- Ensuring that walking surfaces or boards at height are of sound construction and are
provided with safety rails or belts.
- Provide protective equipment; helmets etc.
- Provide measures to prevent fires. Fire extinguishers and buckets of sand to be provided
in the fire-prone area and elsewhere.
- Provide sufficient and suitable light for working during night time.
2.13 Adopt additional best practices, prescribed norms in construction industry.
2.14 The storage of material shall be as per standard good practices as specified in Part 7, Section
2 – Storage, Stacking and Handling practices, NBC 2005 and shall be to the satisfaction of
the Engineer-in-charge to ensure minimum wastage and to prevent any misuse, damage,
inconvenience or accident. Watch and ward of the Contractor’s materials shall be his own
responsibility. There should be a proper planning of the layout for stacking and storage of
different materials, components and equipments with proper access and proper
manoeuvrability of the vehicles carrying the materials. While planning the layout, the
requirements of various materials, components and equipments at different stages of
construction shall be considered. The Owner shall not take any responsibility on any account.
2.15 The contractor shall provide for adequate number of garbage bins around the construction
site and the workers facilities and will be responsible for the proper 373tilize373373on of
these bins for any solid waste generated during the construction. The contractor shall ensure
that the site and the workers facilities are kept litter free. Separate bins should be provided
for plastic, glass, metal, biological and paper waste and labelled in both Hindi and English.
2.16 The contractor shall prepare and submit ‘Spill prevention and control plans’ before the start
of construction, clearly stating measures to stop the source of the spill, to contain the spill,
to dispose the contaminated material and hazardous wastes, and stating designation of
personnel trained to prevent and control spills. Hazardous wastes include pesticides, paints,
cleaners, and petroleum products.
2.17 Contractor shall collect the relevant material certificates for materials with high recycled (both
post-industrial and post-consumer) content, including materials for structural use like TMT
steel rolled with high percentage of recycled steel, and RMC mix with fly-ash etc. (see
appendix)
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
2.18 Contractor shall collect the relevant material certificates for rapidly renewable materials such
as bamboo, wool, cotton insulation, agrifiber, linoleum, wheat board, strawboard and cork.
2.19 Contractor shall adopt an IAQ (Indoor Air Quality) management plan to protect the system
during construction, control pollutant sources, and interrupt pathways for contamination. He
shall sequence installation of materials to avoid contamination of absorptive materials such
as insulation, carpeting, ceiling tile, and gypsum wallboard. He shall also protect stored on-
site or installed absorptive materials from moisture damage.
2.20 The contractor shall ensure that a flush out of all internal spaces is conducted prior to
andover. This shall comprise an opening of all doors and windows for 14 days to vent out
any toxic fumes due to paints, varnishes, polishes, etc.
2.21 Contractor shall make efforts to reduce the quantity of indoor air contaminants that are
dorous or potentially irritating harmful to the comfort and well-being of installer and building
occupants. Contractor shall ensure that the VOC (Volatile Organic Compounds) content of
paints, coatings and primers used must not exceed the VOC content limits mentioned below:
Paints
Non-flat – 150 g/L
Flat (Mat) – 50 g/L
Anti corrosive/ anti rust – 250 g/L
Coatings
Clear wood finishes
Varnish – 350 g/L
Lacquer – 550 g/L
Floor coatings – 100 g/L
Stains – 250 g/L
Sealers
Waterproofing sealer – 250 g/L
Sanding sealer – 275 g/L
Other sealers – 200 g/L
The VOC (Volatile Organic Compounds) content of adhesives and sealants used must be
less than VOC content limits mentioned:
2.22 Wherever required, Contractor shall meet and carry out documentation of all activities on
site, supplementation of information, and submittals in accordance with GRIHA program
standards and guidelines. Towards meeting the aforementioned building environmental
rating standard(s) expert assistance shall be provided to him up on request.
2.23 Water Use during Construction
Contractor should spray curing water on concrete structure and shall not allow free flow of
water. After liberal curing on the first day, all the verticals surfaces of concrete structures
should be painted with curing chemical to save water nothing extra shall be paid. Concrete
structures should be kept covered with thick cloth/gunny bags and water should be sprayed
on them. Contractor shall do water ponding on all sunken slabs using cement and sand
mortar.
2.24 The Contractor shall remove from site all rubbish and debris generated by the Works and
keep Works clean and tidy throughout the Contract Period. All the serviceable and
nonservice able (malba) material shall be segregated and stored separately. The malba
obtained during construction shall be collected in well-formed heaps at properly selected
places, keeping in a view safe condition for workmen in the area. Materials which are likely
to cause dust nuisance or undue environmental pollution in any other way, shall be removed
from the site at the earliest and till then they shall be suitable covered. Glass & steel should
be dumped or buried separately to prevent injury. The work of removal of debris should be
carried out during day. In case of poor visibility artificial light may be provided.
2.25 MATERIALS & FIXTURES FOR THE PROJECT
2.26 The contractor shall 375tilize375 to source most of the materials for construction at this
project within a distance of 800 km radius from the project site. Contractor shall collect the
relevant material certificates to prove the same
h) Any material that is to be sourced from outside the prescribed radius shall be done after
securing the necessary approval from the Engineer-in-charge.
i) All cement used at site for reinforced concrete, precast members, mortar, plaster, building
blocks, etc shall be PPC (Ordinary Portland Cement). The PPC must meet the requirements
of IS 1489: 1991. (Minimum 25% replacement of cement with fly ash in PPC (Portland
Pozzolona Cement) by weight of the cement used in the overall RC for meeting the
equivalent strength requirements).
j) As a measure to reduce wastage and water consumption during construction, the contractor
shall source or set up the infrastructure for a small scale ready mix concrete, all concreting
works at site shall 375tilize only batch mix concrete.
k) The contractor has to comply as per MoEF issued notification 8.0.763I dated 14th Sept.1999
containing directive for greater fly ash utilization, where it stipulates that ii. Every construction
agency engaged in the construction of buildings within a radius of 50 km radius of a Thermal
Power Plant, have to use of 100% fly ash based bricks/blocks in their construction. Any
brick/block containing more than 25% fly ash is designated as fly ash brick/block. As per
GRIHA credits, bricks / blocks should contain more than 40% fly ash.
l) The contractor shall ensure that sand from approved source is used in place of sand in an
all concreting works unless specifically instructed otherwise by the Engineer-in-charge.
m) Timber and aluminum use should be minimized in the project. If used, timber shall constitute
of reclaimed timber and aluminum shall constitute recycled content. The source of such
reclaimed timber shall be approved by the Engineer-in-charge.
n) The contractor shall ensure that nontoxic anti-termite and other pest control is strictly used.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
o) The contractor shall ensure that all paints, polishes, adhesives and sealants used both
internally and externally, on any surface, shall be Low VOC products. The contractor shall
get prior approval from the Engineer-in-charge before the application of any such material.
p) All plumbing and sanitary fixtures installed shall be as per the requirement of the of the
GRIHA and shall adhere to the minimum LPM and LPF mentioned.
q) The contractor shall employ 100% zero ODP (ozone depletion potential) insulation; HCFC
hydro-chlorofluorocarbon)/ and CFC (chlorofluorocarbon) free HVAC and refrigeration
equipment’s and/halon-free fire suppression and fire extinguishing systems.
r) The contractor shall ensure that all composite wood products/agro-fibre products used for
cabinet work, etc do not contain any added urea formaldehyde resin.
2.29 Documentation
a) The contractor shall, during the entire tenure of the construction phase, submit the following
records to the Engineer-in-charge on a monthly basis:
(i) Water consumption in litres
(ii) Electricity consumption in ‘kwh’ units
(iii) Diesel consumption in litres
(iv) Quantum of waste generated at site and the segregated waste types divided into
inert, chemical and hazardous wastes.
(v) Digital photo documentation to demonstrate compliance of safety guidelines as
specified here.
b) The contractor shall, during the entire tenure of the construction phase, submit the following
records to the Engineer-in-charge on a weekly basis:
i) Quantities of material brought into the site, including the material issued to the
contractor.
ii) Quantities of construction debris (if at all) taken out of the site
iii) Digital photographs of the works at site, the workers facilities, the waste and other
material storage yards, pre-fabrication and block making works, etc as guided by the
Engineer-in-charge.
c) The contractor shall submit one document after construction of the buildings, a brief
description along with photographic records to show that other areas have not been
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
disrupted during construction. The document should also include brief explanation and
photographic records to show erosion and sedimentation control measures adopted.
(Document CAD drawing showing site plan details of existing vegetation, existing buildings,
existing slopes and site drainage pattern, staging and spill prevention measures, erosion and
sedimentation control measures and measures adopted for top soil preservation during
construction
d) The contractor shall submit to the Engineer-in-charge after construction of the buildings, a
detailed as built quantification of the following:
i) Total materials used,
ii) Total top soil stacked and total reused
iii) Total earth excavated,
iv) Total waste generated,
v) Total waste reused,
vi) Total water used,
vii) Total electricity, and
viii) Total diesel consumed.
e) The contractor shall submit to the Engineer-in-charge, before the start of construction, a site
plan along with a narrative to demarcate areas on site from which top soil has to be gathered,
designate area where it will be stored, measures adopted for top soil preservation and
indicate areas where it will be reapplied after construction is complete.
f) The contractor shall submit to the Engineer-in-charge, a detailed narrative (not more than
250 words) on provision for safe drinking water and sanitation facility for construction workers
and site personnel.
g) Provide supporting document from the manufacturer of the cement specifying the fly-ash
content in PPC used in reinforced concrete.
h) Provide supporting document from the manufacturer of the pre-cast building blocks
specifying the fly ash content of the blocks used in an infill wall system.
i) The contractor shall, at the end of construction of the buildings, submit to the Engineer-in-
charge, submit following information, for all material brought to site for construction purposes,
including manufacturer’s certifications, verifying information, and test data, where
Specifications sections require data relating to environmental issues including but not limited
to: Source of products: Supplier details and location of the supplier and brand name.
j) Project Recyclability: Submit information to assist Owner and WAPCOS in recycling
materials involved in shipping, handling, and delivery, and for temporary materials necessary
for installation of products.
k) Recycled Content: Submit information regarding product post industrial recycled and post
consumer recycled content. Use the “Recycled Content Certification Form”, to be provided
by the Commissioning Authority appointed for the Project.
l) Product Recyclability: Submit information regarding product and product’s component’s
recyclability including potential sources accepting recyclable materials.
m) Clean tech: Provide pollution clearance certificates from all manufacturers of material
o) Indoor Air quality and Environmental Issues: Submit following certificates:
a) Certifications from manufacturers of Low VOC paints, adhesives, sealant and
polishes used at this particular project site.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
p) Provide total support to the Engineer-in-charge appointed by the WAPCOS in completing all
Green Building Rating related formalities, including signing of forms, providing signed letters
in the contractor’s letterhead.
2.30 EQUIPMENT
a) To ensure energy efficiency during and post construction all pumps, motors and engines
used during construction or installed, shall be subject to approval and as per the
specifications of the architects.
b) All lighting installed by the contractor around the site and at the labour quarters during
construction shall be CFL/LED bulbs of the appropriate illumination levels. This condition is
a must, unless specifically prescribed.
The contractor is expected to go through all other conditions of the GRIHA rating stipulations,
which can be provided to him by the architects.
Failure to adhere to any of the above mentioned items, without necessary clearances from
the architects and the Engineer-in-charge, shall be deemed as a violation of contract and the
contractor shall be held liable for penalty as determined by the architects.
Within each Request for Payment the Contractor shall show separately:
(i) the amounts which the Contractor claims to be payable as the cost of the Works
completed during that month; and
(ii) the cumulative amount of all prior payments made by WAPCOS Limited; and
(iii) any amounts to which the Contractor considers are due and payable to it in
accordance with the provisions of the Contract.
• The provisions of revised ‘Public Procurement (Preference to Make in India) Order 2017
Revision’ issued by Department of Industrial Policy and Promotion under Ministry of Commerce
and Industry vide letter no.-P45021/2/2017-PP (BE-II) as amended on 16.09.2020 shall be
applicable to the bidding process and award of the contract shall be done accordingly. In this
connection, the minimum local content shall be 50% and the margin of purchase preference
shall be 20%.
• Verification of Local Content
The bidder at the time of tender, bidding or solicitation shall be required to indicate percentage
of local content and provide self-certification that the item offered meets the local content
requirement of the tender. They shall also give details of the location(s) at with the local value
addition is made.
In cases of procurement for a value in excess of Rs 10 Crores, the bidder shall be required
to provide a certificate from the statutory auditor or cost auditor of the company (in the case of
companies) or from a practicing cost accountant or practicing chartered accountant (in respect
of suppliers other than companies) giving the percentage of local content.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
CLAUSE 46: RULE 144 (xi) IN GENERAL FINANCIAL RULES (GFRs) 2017
i) Any bidder from a country which shares a land border with India will be eligible to bid in this
tender only if the bidder is registered with the Competent Authority.
ii) “Bidder “(including the term ‘tenderer’, ‘consultant’ or ‘service provider’ in certain contexts)
means any person or firm or company, including any member of a consortium or joint venture
(that is an association of several persons, or firms or companies), every artificial juridical
person not falling in any of the descriptions of bidders stated hereinbefore, including any
agency branch or office controlled by such person, participating in a procurement process.
iii) “Bidder from a country which shares a land border with India” for the purpose of this Order
means:-
(a) An entity incorporated, established or registered in such a country; or
(b) A subsidiary of an entity incorporated, established or registered in such a country; or
(c) An entity substantially controlled through entities incorporated, established or registered in
such a country; or
(d) An entity whose beneficial owner is situated in such a country; or
(e) An Indian (or other) agent of such an entity; or
(f) A natural person who is a citizen of such a country; or
(g) A consortium or joint venture where any member of the consortium or joint venture falls under
any of the above
iv) The beneficial owner for the purpose of 1.4.2.(iii) above will be as under:
1. In case of a company or Limited Liability Partnership, the beneficial owner is the natural
person(s), who, whether acting alone or together, or through one or more juridical person,
has a controlling ownership interest or who exercise control through other means.
Explanation-
2. In case of a partnership firm, the beneficial owner is the natural person(s) who, whether
acting alone or together, or through one or more juridical person, has ownership of
entitlement to more than fifteen percent of capital or profits of the partnership;
4. Where no natural person is identified under (1) or (2) or (3) above, the beneficial owner is
the relevant natural person who holds the position of senior managing official;
5. In case of a trust, the identification of beneficial owner(s) shall include identification of the
author of the trust, the trustee, the beneficiaries with fifteen percent or more interest in the
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
trust and any other natural person exercising ultimate effective control over the trust through
a chain of control or ownership.
v) An Agent is a person employed to do any act for another, or to represent another in dealings with
third person.
vi) The successful bidder shall not be allowed to sub-contract works to any contractor from a country
which shares a land border with India unless such contractor is registered with the Competent
Authority.
The Blacklisting Policy of the company is available on official website of WAPCOS Limited. The
Bidder/tenderer/consultant/contractors have to mandatorily furnish an undertaking addressing the
same to Engineer-in-Charge in the form of certificate to abide the contents of Blacklisting Policy as
per FORM-C. Any action in violation of the blacklisting policy or to the certificate furnished shall
result in cancellation of tender at the stage before or after the award of work.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
SECTION– IV
SECTION–IV
New Minimum Amount of Running The Contractor shall periodically submit Running
Clause-1 Account Bill Account (RA) bills for the gross work done not be less
than Rs 2.00 Cr. for Construction. All running bills
shall be accompanied with the Geo-tagged (GPS)
clear photographs in sufficient number and angles
illustrating the progress of work and for which claims
raised in RA bill. The photographs shall be duly
signed by the Contractor. The contractor shall submit
the bill in the standard format agreed by the SSB/
WAPCOS
Clause 1: General:
The following Additional Conditions of Contract shall be read in conjunction with General Conditions of
Contract. The same shall be considered as an extension and not limitation of the obligations of the
Contractors. In case of any discrepancy between Additional Conditions of Contract and the General
Conditions of Contract, these Additional Conditions of Contract shall take precedence over the
General Conditions of Contract.
The Contractor has to construct and maintain proper bench marks at all salient locations/positions
in order that the lines and levels may be accurately checked at all times.
Theodolite/ Total Station, Levels, Prismatic Compass, Chain, Steel and FRP Tapes and all other
surveying instruments found necessary on the works shall be provided by the Contractor for use
at site in connection with this work.
a. The Works and the Temporary works to the full value of such works.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
b. The materials, constructional plant, centering, shuttering and scaffolding materials and other
things brought to the site for their full value.
Whenever required by Employer, the Contractor shall produce the policy or the policies of insurance
and the receipts for payment of the current premium.
Contractor is required to take insurance cover under the Workman Compensation Act, 1923
amended from time to time from Nationalized insurance company and pay premium charges thereof.
Wherever required by Employer the Contractor shall produce the policy or the policies of Insurance
and the receipt of payment of the current premiums.
Contractor is required to take third party insurance cover for an amount of 5% (five percent) of
contract value from Nationalized insurance company for insurance against any damage, injury or
loss which may occur to any person or property including that of Employer / Owner, arising out of
the execution of the Works or Temporary works. Wherever required by Employer the Contractor
shall produce the policy or the policies of Insurance and the receipt of payment of the current
premiums.
4.4 If the Contractor shall fail to effect and keep in force the insurances referred to above, or
any other insurance which he may be required to effect under the terms of the Contract, then and
in any such case the Employer on advice of the EIC may effect and keep in force any such
insurance and pay such premium or premiums as may be necessary for that purpose and from
time to time deduct the amount so paid by the Employer as aforesaid from any moneys
due or which may become due to the Contractor, or recover the same as debt due from the
Contractor.
4.5 The Contractor shall at all times indemnify Employer and Owner against all claims, damages
or compensation under the provision of Payment of wages act-1936, Minimum Wages Act-1948,
Employer’s liability Act-1938, the workmen’s compensation Act-1947, Industrial Disputes Act-1947
and Maternity Benefit Act-1961 or any modifications thereof or any other law in force or as
consequence of any accident or injury to any workman or other persons in or about the works,
whether in the employment of the Contractor or not, against all costs, charges and expenses of any
suit, action or proceedings arising out of such incident or injury and against all sum or sums which
may with the consent of the Contractor be paid to compromise or compound any such claim. Without
limiting his obligations and liabilities as above provided, the Contractor shall insure against all claims,
damages or compensation payable under the Workmen’s Compensation Act 1923 or any
modification thereof or any other law relating thereto.
4.6 The Contractor, in case of re-building or reinstatement after fire, shall be entitled to such
extension of time for completion as the EIC may deem fit, but shall, however not be entitled to
reimbursement by the Employer or any shortfall or deficiency in the amount finally paid by the Insurer
in settlement of any claim arising as set out herein.
5.3 The Engineer-in-Charge’s approval shall not alter the Contractor’s responsibility for
design of the Temporary Works.
Further, if and to the extent that the delay of possession of site caused by any error or delay by the
Contractor, including an error in, or delay in the submission of, any of the Contractor’s Documents,
the Contractor shall not be entitled to such extension of time and any payment.
In case of any dispute between the agencies engaged on the same work, decision of Engineer-
in-Charge shall be final and binding.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Labour Camp is permitted at site. However, no labour shall be permitted to stay in the partly
completed building at any time. Unauthorized occupation of any area/partly completed building by
the Contractor’s labourer will be treated as trespass and action will be taken to evict them including
termination of Contract if deemed fit. Sanitary as well as water supply and drainage facilities as
required by the labour laws in force, are to be provided by the Contractors at his own cost. The
labour camp should be dismantled by the Contractor before handing over the buildings.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
The Contractor shall not deposit materials anywhere at work site which will seriously inconvenience
the public. The Engineer-in-Charge may require the Contractor to remove any materials which are
considered to be a danger or inconvenience to the public or cause them to be removed at the
Contractor’s cost.
The Contractor shall exercise full care to ensure that no damage is caused by him or his workmen,
during the operation to the existing water supply and power lines. The cost of any such damage and
risks arising out of this shall be entirely borne by the Contractor.
Clause 15: Drainage around the Buildings and Foundation for other Works
The Contractor shall be entirely responsible for the provision and maintenance of efficient drainage
arrangements in the work site to lead all water whatsoever pumped out from the excavations on
account of rains, floods, springs or any other source whatsoever. The foundation trenches shall be
kept free from water while all the works below ground level are in progress.
Flooding or ponding of water in the work site shall not be permitted under any circumstances
whatsoever and the Contractor shall take all necessary precautions to prevent the same by
providing suitable pumps and other dewatering arrangement.
The cost of repairing damages if any, to the work under execution or to any government property in
and around the site shall be entirely borne by the Contractor where such damages are due to his
non-compliance with the above conditions.
Samples of various materials required for testing shall be provided free of charge by the
Contractors. Testing charges if any, including all other expenses required to be incurred for taking
the samples, conveyance, packing etc., shall be borne by the Contractors.
In addition to submission of samples of materials, the Contractor shall make a sample mock up
ready in all respects, including the finishing items of works of civil works including installation of
fittings as well as those of water supply, plumbing and sanitation work and electrical, internal fittings,
fixtures and wiring etc. to determine the acceptable standard of materials and workmanship. The
sample mock up with all final finishes and installations etc. shall be got approved from the Engineer-
in-Charge in advance before taking up the finishing items of the work in the building(s). Each of these
samples of items of work / trade / materials approved by the Engineer-in-Charge will be endorsed as
“Guide line samples”, as per which further works shall be executed in strict conformity with standard
of materials & workmanship.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
The provision of co-ordination and co-operation with other agencies shall be mutatis- mutandis
applicable to the above mentioned “Sample mock-up / Sample finishing works” also.
Testing charges shall be borne by the Contractor. If any additional test needs to be at site,
Contractor shall bear the cost.
The Engineer-in-Charge shall make alternative arrangements for supply of water at the risk
and cost of Contractor(s) if the arrangements made by the Contractor(s) for procurement of
water are in the opinion of the Engineer-in-Charge, unsatisfactory.
The Contractor shall arrange to provide a minimum storage of 5000 Liters. (Or two days requirement
whichever is higher) of water at building location with all necessary pumps for storage of water shall
be built by the Contractor at his own cost at location to be approved by the Engineer-in-Charge.
The water storage tanks should be leak proof and wastage and misuse of water is strictly prohibited,
Contamination and pollution of water to be strictly avoided. Construction water should not be used
for drinking or for domestic purpose. Contractor will make his own arrangement for water required
for drinking purposes at site of work at his own cost.
in good and safe condition as required under relevant rules and BIS codes of practice etc. However,
the following precautions and directives shall be followed in addition to observing other essential
rules:
a. The minimum clearance (measured at the lowest sag point) to be maintained for all
overhead lines shall be 4 Mtrs. Cross country or along roads and 6.1 metres across roads.
b. Metallic poles as a general rule should be avoided and if used should be earthed
individually.
c. All loose hanging of wires and cables should be avoided. The line wires should be
properly supported and an approved method of fixing shall be adopted.
d. Installation shall not cause any hindrance to the normal movement of men and
materials at site.
e. All cables and wires should be adequately protected against mechanical damage
during construction activity of all Contractors, working at site.
g. Laying of cable and wires direct on floor shall not be allowed but if absolutely
necessary for some very short lengths, the same shall be taken through suitable
mechanical covering like G.I. / M.S. Pipes etc.
h. All the cut door switch boards, equipment etc., should be adequately protected against
rain or preferably they should not be exposed to weather.
i. If overhead lines using bare conductors are installed, a guard wire system of adequate size
shall run along the cables / wires and earthed effectively.
j. The connection for portable machines shall be taken only through suitably rated 3 pin
socket points. Iron clad industrial type outlets are preferred. While taking supply
through socket outlet a plug top must be used, avoiding inserting of loose wires in the
sockets. The third pin of the plug shall invariably be earthed and 3 core wire of appropriate
specifications and capacity shall be used.
l. Duly authorized persons having valid wireman’s license / competence certificate must be
employed under the supervision of a qualified and experienced Electrical Supervisor for
carrying out electrical work and repair of electrical equipment, installation and
maintenance etc. at site.
m. Special precaution shall be taken by the Contractor not to disturb the sapling/trees
recently planted by the side of the compound wall. The sapling/trees fall within the
building/road etc. shall be transplanted to suitable place with written approval of the
Engineer-in-Charge and maintained by the Contractor till completion of works at his own
cost.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
The Engineer-in-Charge shall be entitled to have tests made without any extra cost to the Employer
at the laboratory selected by the Employer for any stores and or materials supplied by the
Contractors, who shall provide at his own expense all the facilities which the Engineer-in-Charge
may require for this purpose.
Any stores and materials brought to site for use on the work and which has been rejected by
Engineer-in-Charge shall be immediately removed off the site by Contractor at his own expenses
and intimate in writing accordingly to the Engineer-in-Charge. The rejected materials shall not be
used in any manner in the construction of the project.
Copies of the drawings approved by the Engineer-in-Charge and the construction drawings issued
shall be kept by the Contractor at the site and the same shall at all reasonable times be made
available for inspection and use by the Engineer-in-Charge and any other person authorized by the
Engineer-in-Charge.
All materials and articles brought by the Contractor to the work site shall have to be declared at the
security gate. Similarly, no materials shall be taken out from the premises without proper gate pass.
The Contractors, Suppliers, vendors, workers engaged in work/business will be issued with
renewable entry permit to avoid unauthorized entry in the work site on scrutiny of applications in
prescribed form.
For working on Sundays, Holidays and late hours, even though permission will be accorded by the
Engineer-in-Charge, the Contractor will have to make application to the Engineer-in-Charge also
and keep them informed well in advance.
The area where the proposed work is to be carried is residential / non-residential area under the
control of Security authorities, entry to the site of work shall be through the main gate only. The
Contractor shall follow strictly the security regulations at site of work regarding entry of personnel,
materials etc. and other regulations that might be enforced from time to time at the work site
and also in the campus for smooth and efficient operation. The Contractors, his agents,
representatives, workmen etc. and his materials, carts, trucks or other means of transport etc.
will be allowed to enter through and leave from such point of entry/exit at such times, the
authorities in charge of the area, at their sole discretion, may permit.
The Contractors, his agents and representatives are required to be in possession of the individual
identity / muster cards or passes. The muster cards or passes are examined by the security staff at
the time entry / exit inside the premises and also at any time or number of times within such area.
The Contractor will have to apply for entry/muster permits of likely number of labour to be engaged
during the week for the workers and authorize their representatives to collect the entry permits for
labour from the Employer’s Security Authorities.
It will be the responsibility of the Contractor to maintain the list of laborers permitted to work inside the
premises in a register and the representative of Contractor’s labour will have to issue entry pass to
each labour after making necessary entry in the registers.
The Contractor, his agents, representatives, workmen shall strictly observe the orders pertaining to
prevailing fire precautions.
In addition to the above, other security regulations as may be imposed by the Security authorities
/ Engineer-in-Charge shall be complied with / observed by the Contractor and his workmen, in
addition to the above.
Any breach of above security regulations and rules in force from time to time will be viewed
seriously. No claim whatsoever will be entertained by the Employer on account of the observation
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
It will be the entire responsibility of the Contractor to protect the work(s) carried out by them
including the fittings, fixtures and other accessories provided by them till the entire work is
satisfactorily handed over to the Employer.
The Contractor shall also be responsible for consequential effects arising out during the inspection
done by the third party from time to time and will take appropriate action for rectification of defective
work. Rectification of defective works or replacement of sub-standard materials or articles, as
pointed out by the third party authorized by Employer, will be carried out or replaced by the
Contractor at his own risk and cost. The Employer will not pay any extra amount for such
rectification or replacement.
4. All mass Reinforced Cement Concrete work shall be design mix concrete of specified grade
and initial design mix shall be carried out from the Govt. approved Laboratory/NABL
accredited lab/ NIT/IIT immediately after award of work. The Design Mix report shall be
submitted to WAPCOS before commencement of the RCC works at site.
5. The Contractor shall submit the Standard Operating Procedure (SOP) / Quality Control &
Quality Assurance Plan as finalized and submit to the WAPCOS & Third Party Quality
Assurance Agency (TPQAA) for checking & verification during visit of TPQAA. The reports
of TPQAA will be the part of the Running Account Bills which will be raised after completion
of important milestones / critical activities as defined.
6. If required, the contractor has to do site clearance, enabling work, barricading, diversion of
Roads, shifting/ realignment of existing utility services, drains, nallahs etc. at his own cost
as per direction of Engineer-in-charge and the contractor shall not be entitled for any extra
payment whatsoever in this regard.
7. Necessary arrangements including its maintenance are to be made by the contractor for
temporary diversion of flow of existing drain and road, as the case may be. The existing
drain, road would be demolished, wherever required, with the progress of work under the
scope of proposed project. The existing Road and Drain, which are not in the alignment of
the said project but are affected and/ or need to be demolished during execution for smooth
progress of the project, shall be rehabilitated to its original status and condition (including
black topping) by the contractor at his own cost. The cost to be incurred by contractor in
these regards shall be deemed to be included in the quoted rates of the Bill of Quantities
items and contractor shall not be entitled for any extra payment whatsoever, in these
regards.
8. The Contractor shall be responsible to co-ordinate with service provider/concerned
authorities for cutting of trees, shifting of utilities and removal of encroachments etc. and
making the site un-encumbered from the project construction area required for completion
of work. This shall include initial and frequent follow up meetings/ actions/ discussions with
each involved service provider/ concerned authorities. The contractor shall not be entitled
for any additional compensation for delay in cutting of trees, shifting of utilities and removal
of encroachments by the service provider/ concerned authorities.
9. The information about the public utilities (whether over ground or underground) like
electrical/ telephone/ water supply lines, OFC Cables, open drain etc. is the
responsibility of contractor to ascertain the utilities that are to be affected by the works
through the site investigation and collection of information from the concerned utility. The
Contractor shall render all help and assistance in documenting the total sequence of this
project by way of photography, slides, etc. nothing extra shall be payable to the agency on
this account.
10. Contractor shall provide R.O. Plant sufficient for workers employed at site, his technical staff
and site staff.
11. The Contractor shall make his own arrangements for obtaining electric connection and
water Connection/arrangement (if required). The water charges and electricity charges as
charged by the Owner and Local Authorities shall be borne by the Contractor. No dispute in
this regard shall be entertained.
12. The Contractor shall dispose of all the dismantled materials, debris, garbage, waste outside
of the campus of the works at his own cost and provide clear and clean site at the time of
handing over the works
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
13. The Contractor shall be entirely and exclusively responsible for the horizontal, vertical and
other alignment, the level and correctness of every part of the work and shall rectify
effectively any errors or imperfections therein. Such rectifications shall be carried out by the
Contractor at his own cost to the instructions and satisfaction of the Engineer-in-Charge.
14. The cost/rates quoted by the Contractor are deemed to be inclusive of site clearance, setting
out work, profile, establishment of reference bench mark, spot levels, construction of all
safety and protection devices, barriers, earth embankments, preparatory works, all testing
of materials working during monsoon, working at all depths, height and locations etc. unless
specified in the schedule of quantities.
15. The contractor shall deposit royalty and obtain necessary permit for supply of bajri, stone,
kankar, sand etc. from the local authorities and quoted rates shall be inclusive of royalty on
any account whatsoever.
16. Any cement slurry added over base surface (or) for continuation of concreting for better
bond is deemed to have been in-built in the items and nothing extra shall be payable (or)
extra cement considered in consumption on this account.
17. Samples of various materials required for testing shall be provided free of charges by the
Contractor. Testing charges, if any, unless otherwise provided shall be borne by the
Contractor. All other expenditure required to be incurred for taking the samples,
conveyance, packing etc. shall be borne by the Contractor himself.
18. The Contractor shall have to make approaches road to the site, if so required and keep
them in good condition for transportation of labour and materials as well as inspection of
works by the Engineer-in-Charge. Nothing extra shall be paid on this account.
19. No payment shall be made for any damage caused by rain, snowfall, flood or any other
natural calamity, whatsoever during the execution of the work. The Contractor shall be fully
responsible for any damage to the govt. property and work for which the payment has been
advanced to him under the contract and he shall make good the same at his risk and cost.
The Contractor shall be fully responsible for safety and security of his material, T&P,
Machinery brought to the site by him.
20. Wherever work is specified to be done or material procured through specialized agencies,
their names shall be got approved well in advance from Engineer-in-Charge. Failure to do
so shall not justify delay in execution of work. It is suggested that immediately after award
of work, Contractor should negotiate with concerned specialist agencies and send their
names for approval to Engineer-in-Charge. Any material procured without prior approval of
Engineer-in-Charge in writing is liable to be rejected. Engineer-in-Charge reserves right to
get the materials tested in laboratories of his choice before final acceptance. Nonstandard
materials shall not be accepted.
21. The construction joints shall be provided in predetermined locations only as decided by
Engineer-in-Charge. The cost of shuttering for these construction joints shall be included in
item of Concrete work / RCC work and nothing extra shall be payable on this account to the
Contractor.
22. No chase cutting/dismantling of plaster/RCC/CC shall be allowed, so Contractor has to
execute the electrical work accordingly.
23. The Contractor shall invariably prepare the samples of finishing items i.e. flooring of different
types, external & internal finishing i/c colour scheme of paint, tiles in dado, flooring in
platforms & staircase, water supply & sanitary fittings and any other item as per direction of
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Engineer-in-Charge. The Contractor shall proceed with further finishing items only after
getting the samples of these items approved in writing from Engineer-in-Charge. No extra
claim whatsoever beyond the payments due at agreement rates will be entertained from the
Contractor on this account.
24. Special Conditions for Steel: The Contractor shall procure TMT bars of Fe500D grade
from primary steel producers as per the list of approved makes.
25. Special Conditions for Waterproofing: The contractor shall associate himself with the
specialized firm, to be approved by the Engineer-in-Charge in writing, for water proofing
treatment for lower ground floor, underground tank, pump room and on roofs. Guarantee in
the prescribed proforma attached with tender document shall be given by the specialized
firm, for a period of ten years from the date after the maintenance period prescribed in the
contract, which shall be counter signed by the contractor as token of overall responsibility.
If however any defect is noticed during the guarantee period, it shall be rectified by the
contractor within seven days of intimation. In case it is not attended to, the same will be got
done by another agency at the risk and cost of the contractor. This guarantee deposit can
however be released in full if a bank guarantee of equivalent amount for 10 years is
produced and deposited with the Employer.
26. Use of Fly Ash Bricks: The contractor is required to use fly ash clay bricks conforming to
IS 3812, in view of the Fly Ash Notification issued by the Government of India from time to
time.
27. Contractor shall not divert any advance payments or part thereof for any work other than that
needed for completion of the contracted work. All advance payments received as per terms
of the contract (i.e., mobilization advance, secured advance against materials brought at site,
secured advance against plant & machinery and/or for work done during interim stages, etc.)
are required to be re-invested in the contracted work to ensure advance availability of
resources in terms of materials, labour, plant & machinery needed for required pace of
progress for timely completion of work.
28. The Contractor shall be responsible for consequential effects arising out during the
inspection done by the Chief Technical Examiner Cell, Central Vigilance Commission or
Committee constituted by the WAPCOS or construction site visiting team of WAPCOS or by
the Building Works Committee or third party authorized by WAPCOS or any Statuary
Committee or by any duly authorized representative of WAPCOS, during the progress or any
time after the construction and development of project up to the defect liability period, and
will take appropriate action for rectification of defective work and modifications as suggested
by the above teams/ group/ individual. Rectification of defective works or replacement of sub-
standard materials or articles or modifications, as pointed out by the Chief Technical Cell,
Central Vigilance Commission, committee constituted by WAPCOS, construction site
visiting team, Building Works Committee or authorized representative of WAPCOS or third
party authorized by WAPCOS or any Statuary Committee, will be carried out or replaced/
modified by the Contractor at his own risk and cost.
29. Any Circular/Guidelines/SOP issued by the WAPCOS during the progress/ execution of the
construction work shall be followed by the contractor without any dispute.
30. If any official of contractor is not following the directions of WAPCOS in the best interest of
work in that case, WAPCOS has full authority to get replaced that official from site of work
with prior notice.
31. Handing Over of the Project: Contractor will hand over the project to Owner /Client after
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
successful completion of each component of the project along with submission of all the
required documents i.e. As- built drawings, Inventory list, guarantee / warranty bonds,
certificates & invoices of equipment, lock and key of each room and NoCs form various
Departments with complete satisfaction and acceptance. Contractor shall provide necessary
Completion Certificate/NOC from all local Government/ Statuary Authorities including Fire,
Forest, Electrical, Environment, Lift, DG Set, Complete inventory list, duly signed as-build
drawings, required before handing over the project to the client. The partial handing over of
works components shall not be considered. Defect Liability period of Two years will start
from the date of successful completion of each component of the project and handing over
with all satisfaction & acceptance along with submission of all the required documents i.e.
As-built drawings, Inventory list, guarantee / warranty bonds, certificates & invoices of
equipment, lock and key of each room and NoCs form various Departments .
32. All the modifications and any additional works (basic requirement after use of premises by
user) suggested by client at the time of handing over of the project and after occupancy of
premises by client during Defect Liability Period must be taken up by contractor without any
disputes.
33. If any dispute/ hindrance may arise during construction due to any reason whatsoever, the
contractor is not liable for any financial claim or damages due to such circumstances.
34. Royalty at the prevailing rates wherever payable shall have to be paid by the contractor on
the boulders, metal, shingle, sand and bajri etc. Or any other material collected by him for
the work direct to revenue authorities and nothing extra shall be paid by the WAPCOS for
the same.
35. The contractor shall provide at his own cost suitable weighing, surveying and leveling and
measuring arrangements as may be necessary at site for checking. All such equipment shall
be got calibrated in advance from laboratory, approved by the Engineer-in-Charge. Nothing
extra shall be payable on this account.
36. The contractor shall comply with proper and legal orders and directions of the local or public
authority or municipality and abide by their rule and regulations and pay all fees and charges
which he may be liable.
37. Removal of rejected/sub-standard materials.
The following procedure shall be followed for the removal of rejected/sub-standard materials
from the site of work:
(i) Whenever any material brought by the contractor to the site of work is rejected, entry
thereof should invariably be made in the Site Order Book under the signature of the
Engineer-In-Charge, giving the approximate quantity of such materials.
(ii) As soon as the material is removed, a certificate to that effect shall be recorded by the
Engineer-In-Charge against the original entry, giving, the date of removal and mode of
removal, i.e., whether by truck, carts, or by manual labour. If the removal is by truck,
the registration number of the truck should be recorded.
(iii) When it is not possible for the Engineer-In-Charge to be present at the site of work at
the time of actual removal of the rejected/sub-standard materials from the site, the
required certificate should be recorded by the Authorized Representative of WAPCOS,
and the Engineer-In-Charge should countersign the certificate recorded by the
Authorized Representative.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
38. If the work is carried out in more than one shift or during night, no claim on this account shall
be entertained. The contractor has to take permission from the police & local authorities etc.
if required for work during night hours. No claim / hindrance on this account shall be
considered if work is not allowed during night time. The requisite supervision shall be made
available by the WAPCOS along with necessary issue of material under joint custody.
39. In case of any inconsistency between clauses, the clause favorable/ beneficiary to the project
will prevail which will be decided by the owner and WAPCOS.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
SECTION – VI
ANNEXURES
ANNEXURE-I
(Format for “Contract” to be signed on Non-Judicial Stamp Paper of Rs. 100 by successful
bidder)
CONTRACT AGREEMENT
This Contract made on the____ day of ___ 20____between WAPCOS Limited, a Company in corporate
under Indian Company’s Act and having its registered office at
5th floor, Kailash Building, 26, K. G. Marg, New Delhi (hereinafter called “WAPCOS” of the one part)
and (Name of Contractor Firm & Address)_______________________________ (hereinafter called
“Contractor” of the other part).
In this Contract words and expressions shall have the same meanings as are respectively assigned to
them in the Conditions of Contract hereinafter referred to.
The following documents shall be deemed to form and be read and construed as part of this Contract,
viz;
a) Tender Document no._____________________________dtd._____________
b) Letter of Award to Contractor by WAPCOS
c) Documents furnished by the Contractor during Bidding process
d) Corrigendum/Amendments, if any
e) Clarifications / Correspondences, if any
f) Any other documents as forming part of the contract
1. The aforesaid documents shall be taken as complementary and mutually explanatory of one
another.
3. WAPCOS hereby covenants to pay the Contractor in consideration of the execution and completion
of the Works and the remedying of defects therein the Contract Price or such other sum as may
become payable under the provisions of the contract at the time and in the manner prescribed by
the Contract.
IN WITNESS whereof the parties hereto have caused this Agreement to be executed in accordance
with Laws of India on the day, month & year indicated above.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
For and on behalf of the WAPCOS For and on behalf of the Contractor
1_________________________________ 1____________________________
2 _________________________________ 2 ____________________________
NOTE: Contractor shall submit the Original Power of Attorney on Non-Judicial Stamp Paper for
this particular Work / Project, in the name of Person who will sign the Contract with WAPCOS
after award of Work.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
ANNEXURE - II
FORMAT FOR LETTER OF AWARD
Dear Sir,
1. The “Date of Commencement of Work” shall be immediately / ……….days after award of work and
accordingly, planning should be started for deploying manpower, resources as per Terms &
Conditions of Tender document.
2. The tender document wholly accepted by you along with all related correspondences at the time of
bidding shall form a part of this letter of award.
3. You are requested to submit the following as per Terms & Conditions of
Performance Security @5% of Tendered Value as per the form enclosed in the tender document
before signing of the Agreement within 21 (Twenty One) days of the date of acceptance of the
letter of award and sign the Contract Agreement.
Schedule Plan/ Bar chart to complete the work in stipulated time period.
Details of manpower to be deployed at site along with CVs
List of Lab Equipment required for the work for approval of Engineer-in charge.
4. The terms & conditions of the Work will be governed as mentioned in the tender document.
This letter of award is being issued to you in duplicate. You are requested to return the duplicate copy
of the letter of award immediately duly signed and stamped as a token of your unequivocal acceptance
and confirmation of the same.
Thanking You,
Yours faithfully,
(Name & Designation
of the Tendering Authority)
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Annexure – III
We, ____________________ (name & address of bank) (hereinafter referred to as "the Bank" which
expression shall, unless repugnant to the context or meaning thereof, include its successors,
administrators, executors and assigns) do hereby guarantee and undertake to pay the Employer, on
demand any or, all monies payable by the Contractor to the extent of Rs. _____________ (Rupees
__________________only) as aforesaid at any time upto ___________ without any demur,
reservation, contest , recourse or protest and/or without any reference to the Contractor or court.
Any such demand made by the Employer on the bank shall be conclusive and binding notwithstanding
any difference between the Employer and the Contractor or any dispute pending before any Court,
Tribunal, Arbitrator or any other authority. The Bank undertakes not to revoke this guarantee during its
currency without previous consent of the Employer and further agrees that the guarantee herein
contained shall continue to be enforceable till the Employer discharges this guarantee.
We the said Bank further agree that the guarantee herein contained shall remain in full force and effect
during the period that would be taken for the performance of the said Contract and that it shall continue
to be enforceable till all the dues of the Employer under or by virtue of the said contract have been fully
paid and its claims satisfied or discharged or till the Employer certifies that the terms and conditions of
the said Contract have been fully and properly carried out by the said Contractor and accordingly
discharges the guarantee.
The Employer shall have the fullest liberty without affecting in any way the liability of the Bank under
this guarantee, from, time to time to extend the time for performance of the Contract by the Contractor.
The Employer shall have the fullest liberty without affecting this guarantee, to postpone from time to
time the exercise of any powers vested in them or of any right which they might have against the
Contractor and to exercise the same at any time in any manner and either to enforce or to forbear to
enforce any covenants, contained or implied, in the Contract between the Employer and the Contractor
or any other course or remedy or security available to the Employer. The bank shall not be released of
its obligations under these presents by any exercise by the Employer of its liberty with reference to the
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
matters aforesaid or any of them or by reason of any other act or forbearance or other acts of omission
or commission on the part of the Employer or any other indulgence shown by the Employer or by any
other matter or thing whatsoever which under law would but for this provision, have the effect of relieving
the Bank. The guarantee shall not be affected by a change in the constitution of the bank or of the
employer.
The bank also agrees that the Employer at its option shall be entitled to enforce this Guarantee against
the Bank as a principal debtor, in the first instance, without proceeding against the Contractor and
notwithstanding any security or other guarantee that the Employer may have in relation to the
Contractor's liabilities.
We The Said Bank do hereby declare that we have absolute and unconditional power to issue this
guarantee in your favour under the Memorandum and Articles of Association or such other
constitutional documents of the Bank and the undersigned have full power to execute this guarantee
under the Power of Attorney / Post Approval Authorization dated _____________________ of the bank
granted to him / us by the Bank. We the said bank do hereby declare and undertake that your claim
under the guarantee shall not be affected by any deficiency or other defect in the powers of the bank
or its officials and the guarantee shall be deemed to have been issued as if the bank and its officials
have all the powers and authorization to give this guarantee on behalf of the bank.
We the said bank do hereby certify the genuineness and appropriateness of the Stamp paper and
stamp value used for issuing the guarantee. We the said bank do hereby declare and undertake that
your claim under the guarantee shall not be affected by any deficiency or other defect in the stamp
paper or its stamp value.
We the said bank do hereby declare that our payments hereunder shall be made to you , free and clear
of and without and deduction, reduction on account of any reasons including any and all present and
future taxes, levies, charges of withholding whatsoever imposed or collected with respect thereto.
Notwithstanding anything contained hereinabove our liability under this guarantee is restricted to Rs.
_____________(Rupees ____________________ only) and it shall remain in force upto and including
_____________ and shall be extended from time to time for such period as may be desired by M/s
WAPCOS Limited to whom this bank guarantee has been given.
Signature Signature
Name………………………………………….. Name…………………………………………..
Signature Code/ S.S no. …………………… Signature Code/ S.S no. ……………………………
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
ANNEXURE-IV
(To be submitted on non-judicial stamp paper of Rs. 100)
To,
The WAPCOS Limited,
76-C, Sector 18, Institutional Area
Gurugram, Haryana-122015
In consideration of WAPCOS LTD. (hereinafter referred to as “the Employer”) which expression shall,
unless repugnant to the context or meaning thereof include its successors, administrators and assigns)
having awarded to _______________________ (Contractor’s name) with its Registered /Head Office
at __________________(hereinafter referred to as “the Contractor” which expression shall unless
repugnant to the context or meaning thereof, include its successors, administrators, executors and
assigns) a contract, by issue of Employer’s Notification of Award No. ____________________ dt.
__________ and the same having been unequivocally accepted by the Contractor, resulting into a
contract valued at Rs.____________________
(Rupees_____________________________________________________only) for
_______________ (hereinafter called “the contract”) and the Employer having agreed to make an
advance payment to the Contractor for performance of the above Contract amounting to Rs.
_________________ (Rupees ______________only) as an advance against bank guarantee to be
furnished by the Contractor.
We, __________________ (name & address of bank) having its Head Office at _____________
(hereinafter referred to as “the Bank” which expression shall, unless repugnant to the context or
meaning thereof, include its successors, administrators, executors and assigns) do hereby guarantee
and undertake to pay the Employer immediately on demand any or, all monies payable by the
Contractor to the extent of Rs. ______________ (Rupees ________________only) as aforesaid at any
time upto ___________ without any demur, reservation, contest, recourse or protest and/or without
any reference to the Contractor. Any such demand made by the Employer on the bank shall be
conclusive and binding notwithstanding any difference between the Employer and the Contractor or
any dispute pending before any Court, Tribunal, Arbitrator or any other authority. We agree that the
Guarantee herein contained shall be irrevocable and shall continue to be enforceable till the Employer
discharges this guarantee. We further agree that no change in the constitution of the Bank or of the
Employer shall affect this guarantee.
The Employer shall have the fullest liberty without affecting in any way the liability of the Bank under
this guarantee, from time to time, to vary the advance or to extend the time for performance of the
Contract by the Contractor. The Employer shall have the fullest liberty without affecting this guarantee,
to postpone from time to time the exercise of any powers vested in them or of any right which they
might have against the Contractor and to exercise the same at any time in any manner, and either to
enforce or to forbear to enforce any covenants, contained or implied, in the Contract between the
Employer and the Contractor or any other course or remedy or security available to the Employer. The
bank shall not be released of its obligations under these presents by any exercise by the Employer of
its liberty with reference to the matters aforesaid or any of them or by reason of any other act or
forbearance or other acts of omission or commission on the part of the Employer or any other
indulgence shown by the Employer or by any other matter or thing whatsoever which under law would
but for this provision, have the effect of relieving the Bank.
The bank also agrees that the Employer at its option shall be entitled to enforce this Guarantee against
the Bank as a principal debtor, in the first instance without proceeding against the Contractor and
notwithstanding any security or other guarantee that the Employer may have in relation to the
Contractor's liabilities.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
We the Said Bank do hereby declare that we have absolute and unconditional power to issue this
guarantee in your favour under the Memorandum and Articles of Association or such other
constitutional documents of the Bank and the undersigned have full power to execute this guarantee
under the Power of Attorney/ Post Approval Authorization dated ____________ of the bank granted to
him / us by the Bank. We the said bank do hereby declare and undertake that your claim under the
guarantee shall not be affected by any deficiency or other defect in the powers of the bank or its officials
and the guarantee shall be deemed to have been issued as if the bank and its officials have all the
powers and authorization to give this guarantee on behalf of the bank.
We the said bank does hereby certify the genuineness and appropriateness of the Stamp paper and
stamp value used for issuing the guarantee. We the said bank does hereby declare and undertake that
your claim under the guarantee shall not be affected by any deficiency or other defect in the stamp
paper or its stamp value.
We the said bank do hereby declare that our payments hereunder shall be made to you , free and clear
of and without and deduction, reduction on account of any reasons including any and all present and
future taxes, levies, charges of withholding whatsoever imposed or collected with respect thereto.
Notwithstanding anything contained hereinabove our liability under this guarantee is limited to
Rs.______________ (Rupees ________________ only) and it shall remain in force upto and including
_______________ and shall be extended from time to time for such period (not exceeding one year),
as may be desired by M/s _____________ on whose behalf this bank guarantee has been given.
Signature Signature
Name………………………………………….. Name…………………………………………..
Signature Code/ S.S no. …………………… Signature Code/ S.S no. ……………………………
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
ANNEXURE-V
(On non-judicial stamp paper of Rs. 100 duly attested by Notary / Magistrate)
any part thereof being stolen, destroyed or damaged or becoming deteriorated in a greater
degree than is due to reasonable use and wear thereof the Contractor will forthwith replace the
same with other materials of like quality or repair and make good the same as required by the
Divisional Officer.
(5) That the said materials shall not on any account be removed from the site of the said works
except with the written permission of the Divisional Officer or an officer authorised by him on that
behalf.
(6) That the advances shall be repayable in full when or before the Contractor receives payment from
the WAPCOS of the price payable to him for the said works under the terms and provisions of the
said agreement. Provided that if any intermediate payments are made to the Contractor on
account of work done than on the occasion of each such payment the WAPCOS will be at liberty
to make a recovery from the Contractor’s bill for such payment by deducting there from the value
of the said materials then actually used in the construction and in respect of which recovery has
not been made previously, the value for this purpose being determined in respect of each
description of materials at the rates at which the amounts of the advances made under these
presents were calculated.
(7) That if the Contractor shall at any time make any default in the performance or observance in any
respect of any of the terms and provisions of the said agreement or of these presents the total
amount of the advance or advances that may still be owing to the WAPCOS shall immediately
on the happening of such default be repayable by the Contractor to the WAPCOS together with
interest thereon at twelve per cent per annum from the date or respective dates of such advance
or advances to the date of repayment and with all costs charges, damages and expenses
incurred by the WAPCOS in or for the recovery thereof or the enforcement of this security or
otherwise by reason of the default of the Contractor and the Contractor hereby covenants and
agrees with the WAPCOS to repay and pay the same respectively to him accordingly.
(8) That the Contractor hereby charges all the said materials with the repayment to the WAPCOS of
the said sum of Rupees …………………………………………and any further sum or sums
advanced as aforesaid and all costs charges, damages and expenses payable under these
presents PROVIDED ALWAYS and it is hereby agreed and declared that notwithstanding
anything in the said agreement and without prejudice to the powers contained therein if and
whenever the covenant for payment and repayment herein before contained shall become
enforceable and the money owing shall not be paid in accordance therewith the WAPCOS may
at any time thereafter adopt all or any of the following courses as he may deem best :-
(a) Size and utilize the said materials or any part thereof in the completion of the said works on
behalf of the Contractor in accordance with the provisions in that behalf contained in the
said agreement debiting the Contractor with the actual cost of effecting such completion
and the amount due in respect of advances under these presents and crediting the
Contractor with the value of work done as if he had carried it out in accordance with the said
agreement and at the rates thereby provided. If the balance is against the Contractor he
is to pay same to the WAPCOS on demand.
b) Remove and sell by public auction the seized materials or any part thereof and out of the
moneys arising from the sale retain all the sums aforesaid repayable or payable to the
WAPCOS under these presents and pay over the surplus (if any) to the Contractor.
(c) Deduct all or any part of the moneys owing out of the security deposit or any sum due to the
Contractor under the said agreement.
(9) That except in the event of such default on the part of the Contractor as aforesaid interest on the
said advance shall not be payable.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
(10) That in the event of any conflict between the provisions of these presents and the said agreement
the provisions of these presents shall prevail and in the event of any dispute or difference arising
over the construction or effect of these presents the settlement of which has not been herein
before expressly provided for the same shall be finally resolved as per provisions of clause 25 of
the contract.
In witness whereof the said Contractor and WAPCOS by the order and under the direction of the
WAPCOS have hereunto set their respective hands the day and year first above written.
For and on behalf of the Contractor For and on behalf of the WAPCOS
2 ____________________________ 2 _______________________
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
ANNEXURE-VI
SEALED with the Common Seal of the said Bank this ………………… day of ……………month………
year.
Signature Signature
Name………………………………………….. Name……………………………………..
Signature Code/ S.S no. …………………… Signature Code/ S.S no. ………………
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
ANNEXURE-VII
1. Name of Contractor:
2. Name of work:
3. Agreement No. and Date:
4. Date of commencement of work as per Agreement:
5. Period and Stipulated date of completion as per Agreement:
6. Period for which extension of time already given:
It is understood that we will not claim any additional cost due to above extension of time and also
understand that WAPCOS have rights to act in accordance with provisions in relevant clauses of
Contract Agreement.
Dated………………………..
Contractor’s Signature and Stamp
HINDRANCE STATEMENT
S.No. Hindrance Date of Date of Activity Overlaping Net Weightage Net
Start of Removal Effected Hindrance Effective
Remarks
Hindrance of in Days Days
Hindrance
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Annexure – VIII
(On Rs. 100 non- Judicial Stamp Paper duly attested by Notary / Magistrate)
The Supplementary Agreement made this ____ day of ______ 20___ between (Name of Contractor firm &
address) _____________ (hereinafter called the CONTRACTOR / GUARANTOR of the one part) and the
WAPCOS LIMITED, 5th floor, Kailash Building, 26, K. G. Marg, New Delhi (hereinafter called WAPCOS of the
other part) for the Work ………………………………(Name of Work) …………………………………in respect of
Contract Agreement (hereinafter called the “Original Agreement” signed between ………(Name of Contractor
firm) and WAPCOS on……………….. dated ………………….., whereby the contractor interalia, under look to
render the work in the said contract recited structurally stable workmanship and use of sound materials.
AND WHEREAS THE GUARANTOR agreed to give a guarantee to the effect that the said work will remain
structurally stable and guarantee against faulty workmanship, manufacturing defects of materials etc.
NOW THE GUARANTOR hereby guarantee that work executed by him will remain structurally stable, for the
minimum life of ten years, to be reckoned from the date of start of Defect Liability Period or Maintenance Period
which ever is later, prescribed in the Contract.
The decision of the WAPCOS with regard to nature and cause of defects shall be final. During the period of
guarantee the Guarantor shall make good all defects to the satisfaction of the WAPCOS calling upon him to
rectify the defects, failing which the work shall be got done by the WAPCOS by some other agencies at the
Guarantor’s cost and risk. The decision of the WAPCOS as to the cost payable by the Guarantor shall be final
and binding.
That if the Guarantor fails to make good all the defects, commits breach thereunder then the guarantor will
indemnify the Principal and his successor against all loss, damage cost expense or otherwise which may be
incurred by him by reason of any default on the part of the GUARANTOR in performance and observance of this
Supplementary Agreement. As to the amount of loss and / or damage and / or cost incurred by the WAPCOS the
decision of the WAPCOS will be final and binding.
IN WITHNES WHEREOF those presents have been executed by the GUARANTOR ………………………..(Name
and Designation who sign the Original Contract Agreement) on behalf of .........................................( Name of
Contractor Firm) and WAPCOS on the day, month and year first above written.
For and on behalf of the Contractor For and on behalf of the WAPCOS
2 ____________________________ 2 _______________________
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Annexure – IX
(On Rs. 100 non- Judicial Stamp Paper duly attested by Notary / Magistrate)
This Agreement made on this ____ day of ______ 20___ between___________________ (Name of
Contractor firm & address) _____________ (hereinafter called the CONTRACTOR / GUARANTOR of
the one part) and the _______________________________(hereinafter called Principal Employer of
the other part) for Water proofing Works of __________________________________________
(Name of Work)
WHEREAS This Agreement is Supplementary, to a Contract (hereinafter called the Contract) Contract
no._______________________________ dated ________and made between the
_____________________________ (Name of Contractor) and WAPCOS LIMITED, 5th floor, Kailash
Building, 26, K. G. Marg, New Delhi, whereby the contractor, inter alia, undertook to render the buildings
and structures in the contract recited completely water and leak-proof for Toilets, Shower , Under
Ground Tank, Roof, Over Head Tank, Basement and any other allied areas of building.
AND WHEREAS THE GUARANTOR agreed to give a guarantee to the effect that the said structures
will remain water and leak-proof for ten years from the date after the Defect Liability Period or
Maintenance Period which ever is later, prescribed in the contract. NOW THE GUARANTOR hereby
guarantees that water proofing treatment given by him will render the structures completely leak proof
and the minimum life of such water proofing treatment shall be ten years to be reckoned from the date
after the Defect Liability Period / Maintenance Period which ever is later, prescribed in the contract.
Provided that the Guarantor will not be responsible for the leakage caused by earthquake or structural
defects or misuse of roof or alteration and for such purpose:
a. Misuse of roof shall mean any operation which will damage proofing treatment, like chopping of
firewood and things of the same nature which might cause damage to the roof.
b. Alteration shall mean construction of an additional storey or a part of the roof or construction
adjoining to existing roof whereby proofing treatment is removed in parts.
c. The decision of the Principal Employer with regard to cause of leakage/seepage shall be final.
During this period of guarantee the Guarantor shall make good all defects and in case of any defect
being found, render the building water proof to the satisfaction of the Principal Employer at his cost and
shall commence the work for the rectification within seven days from the date of issue of the notice from
the Principal Employer calling upon him to rectify the defects failing which the work shall be done by
the Principal Employer by some other agency at the GUARANTOR’s risk and cost. The decision of the
Principal Employer as to the cost payable by the Guarantor shall be final and binding. That if Guarantor
fails to make good all defects or commits breach there under then the Guarantor will indemnify the
principal and his successors against all loss, damage, cost expense otherwise which may be incurred
by him by reason of any default on the part of the GUARANTOR in performance and observance of
this Supplementary Agreement. As to the amount of loss and/or damage and/or cost incurred by the
Principal Employer the decision of the owner will be final and binding on the parties.
........ .( Name of Contractor Firm) and Principal Employer on the day, month and year first above
written.
For and on behalf of the Contractor For and on behalf of the Principal
Employer
_1_________________________ _1____________________
2 _________________________ 2 _______________________
2 _________________________ 2 _______________________
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
ANNEXURE IX (a)
(Not required for the works of Tendered Value below Rs. 5.0 Crore excluding GST)
2. We............................... (indicate the name of the bank) do hereby undertake to pay the amounts
due and payable under this Guarantee without any demure, merely on a demand from Principal
Employer stating that the amount claimed is required to meet the recoveries due or likely to be
due from the said contractor(s). Any such demand made on the Bank shall be conclusive as
regards the amount due and payable by the bank under the Guarantee. However, our liability
under this guarantee shall be restricted to an amount not exceeding Rs.
……………………………(Rupees ………………………only).
3. We............................ (indicate the name of the bank) further undertake to pay to Principal
Employer any money so demanded notwithstanding any dispute or disputes raised by the
contractor(s) in any suit or proceeding pending before any court or Tribunal relating thereto, our
liability under this present being absolute and unequivocal.
The payment so made by as under this bond shall be a valid discharge of our liability for payment
there under and the contractor(s) shall have no claim against us for making such payment.
4. We............................... (indicate the name of the Bank) further agree that the guarantee
hereinafter contained shall remain in full force and effect during the period that would be taken
for the performance of the said agreement and that it shall continue to be enforceable till all the
dues of Principal Employer under or by virtue of the said agreement have been fully paid and its
claims satisfied or discharged or till Principal Employer certified that the terms and condition of
the said agreement have been fully and properly carried out by the said contractor(s) and
accordingly discharges this guarantee.
5. We………………………….. (indicate name of the bank) further agree with Principal Employer
that Principal Employer shall have the fullest liberty without our consent and without effecting in
any manner our obligations hereunder to vary any of the terms and conditions of the said
agreement or to extend time of performance by the said contractor(s) from time to time or to
postpone for any time or from time to time any of the powers exercisable by Principal Employer
against the said contractor(s) and to for bear or enforce any of the terms and conditions relating
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
to the said agreement and we shall not be relieved from our liability by reason of any such
variation, or extension being granted to the said contractors(s) or for any bearance, act of
commission of the part of Principal Employer or any indulgence by Principal Employer to the said
contractor(s) or by any such matter of thing whatsoever which under the law relating to sureties
would, but for this provision, have effect of so relieving us.
6. This guarantee will not be discharged due to the change in the constitution of Bank or the
contractor(s).
7. We……………………… (indicate the name of the Bank) lastly undertake not to revoke this
guarantee except with the previous consent of Principal Employer in writing
8. This guarantee shall be valid upto ........................... unless extended on demand by Principal
Employer. Notwithstanding anything mentioned above, our liability against this guarantee is
restricted to Rs. ……………………………(Rupees ………………………only) and unless a claim
in writing is lodged with us within six months of the date of expiry or the extended date of expiry
of this guarantee all our liabilities under this guarantee shall stand discharged
Signature Signature
Name…………………………………….. Name………………………………………..
Signature Code/ S.S no. ………………… Signature Code/ S.S no. …………………
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Annexure – X
(On Rs. 100 non- Judicial Stamp Paper duly attested by Notary / Magistrate)
This Agreement made on this ____ day of ______ 20___ between___________________ (Name of
Contractor firm & address) _____________ (hereinafter called the CONTRACTOR / GUARANTOR of
the one part) and the _______________________________(hereinafter called Principal Employer of
the other part) for Anti Termite Treatment Works
for__________________________________________ (Name of Project)
WHEREAS This Agreement is Supplementary, to a Contract (hereinafter called the Contract) Contract
no._______________________________ dated ________and made between the
_____________________________ (Name of Contractor) and WAPCOS LIMITED, 5th floor, Kailash
Building, 26, K. G. Marg, New Delhi, whereby the contractor, inter alia, undertook to render the wooden
work in the said contract recited completely Termite proof.
THE GUARANTOR hereby guarantee that the anti-termite treatment given by him will render the
wooden works completely Termite proof and the minimum life of such Anti-Termite treatment shall be
five years to be reckoned from the from the date after the Defect Liability Period or Maintenance Period
which ever is later, prescribed in the contract.
During the period of guarantee the Guarantor shall make good all defects and in case of any defects
being found render the wooden works termite proof to the satisfaction of the Principal Employer at his
cost and shall commence the work for such rectification within seven days from the date of issue of
notice from the Principal Employer calling upon him to rectify the defects, failing which the work shall
be got done by the Principal Employer through some other Agency at the Guarantor’s cost and risk.
The decision of the Principal Employer as to the cost payable by the Guarantor shall be final and
binding.
That if the guarantor fails to execute the Anti-termite works, or commits breach thereunder then the
guarantor will indemnify the Principal and his successor against all loss, damage, cost of expenses or
otherwise which may be incurred by him by reason of any of any default on the part of the GUARANTOR
in performance and observance of this Supplementary Agreement. As to the amount of loss and / or
cost incurred by the Principal Employer on the decision of the Principal Employer will be final and
binding.
IN WITHNES WHEREOF those presents have been executed by the GUARANTOR ……………………
(Name and Designation who sign the Contract) on behalf of ........................................( Name of
Contractor Firm) and Principal Employer on the day, month and year first above written.
2 _________________________ 2 _______________________
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
ANNEXURE – XI
SAFETY CODES
1. Suitable scaffolds should be provided for workmen for all works that cannot safely be done from
the ground, or from solid construction except such short period work as can be done safely from
ladders. When a ladder is used, an extra mazdoor shall be engaged for holding the ladder and if
the ladder is used for carrying materials as well suitable footholds and hand-hold shall be provided
on the ladder and the ladder shall be given an inclination not steeper than ¼ to 1(¼ horizontal
and 1 vertical).
2. Scaffolding of staging more than 3.6 m (12ft.) above the ground or floor, swung or suspended
from an overhead support or erected with stationary support shall have a guard rail properly
attached or bolted, braced and otherwise secured at least 90 cm. (3ft.) high above the floor or
platform of such scaffolding or staging and extending along the entire length of the outside and
ends thereof with only such opening as may be necessary for the delivery of materials. Such
scaffolding or staging shall be so fastened as to prevent it from swaying from the building or
structure.
3. Working platforms, gangways and stairways should be so constructed that they should not sag
unduly or unequally, and if the height of the platform or the gangway or the stairway is more than
3.6 m (12ft.) above ground level or floor level, they should be closely boarded, should have
adequate width and should be suitably fastened as described in (2) above.
4. Every opening in the floor of a building or in a working platform shall be provided with suitable
means to prevent the fall of person or materials by providing suitable fencing or railing whose
minimum height shall be 90 cm. (3ft.).
5. Safe means of access shall be provided to all working platforms and other working places. Every
ladder shall be securely fixed. No portable single ladder shall be over 9m. (30ft.) in length while
the width between side rails in rung ladder shall in no case be less than 29 cm. (11½") for ladder
upto and including 3 m. (10 ft.) in length. For longer ladders, this width should be increased at
least ¼” for each additional 30 cm. (1 foot) of length. Uniform step spacing of not more than 30
cm shall be kept. Adequate precautions shall be taken to prevent danger from electrical
equipment. No materials on any of the sites or work shall be so stacked or placed as to cause
danger or inconvenience to any person or the public. The contractor shall provide all necessary
fencing and lights to protect the public from accident and shall be bound to bear the expenses of
defence of every suit, action or other proceedings at law that may be brought by any person for
injury sustained owing to neglect of the above precautions and to pay any damages and cost
which may be awarded in any such suit; action or proceedings to any such person or which may,
with the consent of the contractor, be paid to compensate any claim by any such person
6. (a) Excavation and Trenching - All trenches 1.2 m. (4ft.) or more in depth, shall at all times be
supplied with at least one ladder for each 30 m. (100ft.) in length or fraction thereof, Ladder
shall extend from bottom of the trench to at least 90 cm. (3ft.) above the surface of the
ground. The side of the trenches which are 1.5 m. (5ft.) or more in depth shall be stepped
back to give suitable slope or securely held by timber bracing, so as to avoid the danger of
sides collapsing. The excavated materials shall not be placed within 1.5 m. (5ft.) of the edges
of the trench or half of the depth of the trench whichever is more. Cutting shall be done from
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
7. Demolition - Before any demolition work is commenced and also during the progress of the work,
(i) All roads and open areas adjacent to the work site shall either be closed or suitably
protected.
(ii) No electric cable or apparatus which is liable to be a source of danger or a cable or
apparatus used by the operator shall remain electrically charged.
(iii) All practical steps shall be taken to prevent danger to persons employed from risk of fire
or explosion or flooding. No floor, roof or other part of the building shall be so overloaded
with debris or materials as to render it unsafe.
2 to 3 hours before any man is allowed to enter into the manhole for working inside.
(c) Before entry, presence of Toxic gases should be tested by inserting wet lead
acetate paper which changes colour in the presence of such gases and gives
indication of their presence.
(d) Presence of Oxygen should be verified by lowering a detector lamp into the
manhole. In case, no Oxygen is found inside the sewer line, workers should be sent
only with Oxygen kit.
(e) Safety belt with rope should be provided to the workers. While working inside the
manholes, such rope should be handled by two men standing outside to enable him
to be pulled out during emergency.
(f) The area should be barricaded or cordoned of by suitable means to avoid mishaps
of any kind. Proper warning signs should be displayed for the safety of the public
whenever cleaning works are undertaken during night or day.
(g) No smoking or open flames shall be allowed near the blocked manhole being
cleaned.
(h) The malba obtained on account of cleaning of blocked manholes and sewer lines
should be immediately removed to avoid accidents on account of slippery nature of
the malba.
(i) Workers should not be allowed to work inside the manhole continuously. He should
be given rest intermittently. The Engineer-in-Charge may decide the time up to
which a worker may be allowed to work continuously inside the manhole.
(j) Gas masks with Oxygen Cylinder should be kept at site for use in emergency.
(k) Air-blowers should be used for flow of fresh air through the manholes. Whenever
called for, portable air blowers are recommended for ventilating the manholes. The
Motors for these shall be vapour proof and of totally enclosed type. Non sparking
gas engines also could be used but they should be placed at least 2 metres away
from the opening and on the leeward side protected from wind so that they will not
be a source of friction on any inflammable gas that might be present.
(l) The workers engaged for cleaning the manholes/sewers should be properly trained
before allowing to work in the manhole.
(m) The workers shall be provided with Gumboots or non sparking shoes bump helmets
and gloves non sparking tools safety lights and gas masks and portable air blowers
(when necessary). They must be supplied with barrier cream for anointing the limbs
before working inside the sewer lines.
(n) Workmen descending a manhole shall try each ladder stop or rung carefully before
putting his full weight on it to guard against insecure fastening due to corrosion of
the rung fixed to manhole well.
(o) If a man has received a physical injury, he should be brought out of the sewer
immediately and adequate medical aid should be provided to him.
(p) The extent to which these precautions are to be taken depend on individual situation
but the decision of the Engineer-in-Charge regarding the steps to be taken in this
regard in an individual case will be final.
The Contractor shall not employ men and women below the age of 18 years on the work of
painting with products containing lead in any form. Wherever men above the age of 18 are
employed on the work of lead painting, the following precaution should be taken:-
(a) No paint containing lead or lead products shall be used except in the form of paste or
readymade paint.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
(b) Suitable face masks should be supplied for use by the workers when paint is applied in
the form of spray or a surface having lead paint is dry rubbed and scrapped.
(c) Overalls shall be supplied by the contractors to the workmen and adequate facilities shall
be provided to enable the working painters to wash during and on the cessation of work.
9. The Contractor shall not employ women and men below the age of 18 on the work of painting
with product containing lead in any form, wherever men above the age of 18 are employed on the
work of lead painting, the following principles must be observed for such use :
(i) White lead, sulphate of lead or product containing these pigment, shall not be used in
painting operation except in the form of pastes or paint ready for use.
(ii) Measures shall be taken, wherever required in order to prevent danger arising from the
application of a paint in the form of spray.
(iii) Measures shall be taken, wherever practicable, to prevent danger arising out of from
dust caused by dry rubbing down and scraping.
(iv) Adequate facilities shall be provided to enable working painters to wash during and on
cessation of work.
(v) Overall shall be worn by working painters during the whole of working period.
(vi) Suitable arrangement shall be made to prevent clothing put off during working hours
being spoiled by painting materials.
(vii) Cases of lead poisoning and suspected lead poisoning shall be notified and shall be
subsequently verified by medical man.
(viii) WAPCOS may require, when necessary medical examination of workers.
(ix) Instructions with regard to special hygienic precautions to be taken in the painting trade
shall be distributed to working painters.
10. When the work is done near any place where there is risk of drowning, all necessary equipments
should be provided and kept ready for use and all necessary steps taken for prompt rescue of
any person in danger and adequate provision, should be made for prompt first aid treatment of
all injuries likely to be obtained during the course of the work.
11. Use of hoisting machines and tackle including their attachments, anchorage and supports shall
conform to the following standards or conditions :-
(i) (a) These shall be of good mechanical construction, sound materials and adequate
strength and free from patent defects and shall be kept repaired and in good working
order.
(b) Every rope used in hoisting or lowering materials or as a means of suspension shall
be of durable quality and adequate strength, and free from patent defects.
(ii) Every crane driver or hoisting appliance operator, shall be properly qualified and no
person under the age of 21 years should be in charge of any hoisting machine including
any scaffolding winch or give signals to operator.
(iii) In case of every hoisting machine and of every chain ring hook, shackle swivel and pulley
block used in hoisting or as means of suspension, the safe working load shall be
ascertained by adequate means. Every hoisting machine and all gear referred to above
shall be plainly marked with the safe working load. In case of a hoisting machine having
a variable safe working load each safe working load and the condition under which it is
applicable shall be clearly indicated. No part of any machine or any gear referred to
above in this paragraph shall be loaded beyond the safe working load except for the
purpose of testing.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
(iv) In case of departmental machines, the safe working load shall be notified by the
Electrical Engineer-in-Charge. As regards contractor’s machines the contractors shall
notify the safe working load of the machine to the Engineer-in-Charge whenever he
brings any machinery to site of work and get it verified by the Electrical Engineer
concerned.
12. Motors, gearing, transmission, electric wiring and other dangerous parts of hoisting appliances
should be provided with efficient safeguards. Hoisting appliances should be provided with such
means as will reduce to the minimum the risk of accidental descent of the load. Adequate
precautions should be taken to reduce to the minimum the risk of any part of a suspended load
becoming accidentally displaced. When workers are employed on electrical installations which
are already energized, insulating mats, wearing apparel, such as gloves, sleeves and boots as
may be necessary should be provided. The worker should not wear any rings, watches and carry
keys or other materials which are good conductors of electricity.
13. All scaffolds, ladders and other safety devices mentioned or described herein shall be maintained
in safe condition and no scaffold, ladder or equipment shall be altered or removed while it is in
use. Adequate washing facilities should be provided at or near places of work.
14. These safety provisions should be brought to the notice of all concerned by display on a notice
board at a prominent place at work spot. The person responsible for compliance of the safety
code shall be named therein by the contractor.
15. To ensure effective enforcement of the rules and regulations relating to safety precautions the
arrangements made by the contractor shall be open to inspection by the Labour Officer or
Engineer-in-Charge of the department or their representatives.
16. Notwithstanding the above clauses from (1) to (15), there is nothing in these to exempt the
contractor from the operations of any other Act or Rule in force in the Republic of India.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
ANNEXURE – XII
1. APPLICATION
These rules shall apply to all buildings and construction works in which twenty or more workers
are ordinarily employed or are proposed to be employed in any day during the period during
which the contract work is in progress.
2. DEFINITION
Work place means a place where twenty or more workers are ordinarily employed in connection
with construction work on any day during the period during which the contract work is in
progress.
3. FIRST-AID FACILITIES
(i) At every work place, there shall be provided and maintained, so as to be easily
accessible during working hours, first-aid boxes at the rate of not less than one box for
150 contract labour or part thereof ordinarily employed.
(ii) The first-aid box shall be distinctly marked with a red cross on white back ground and
shall contain the following equipment:-
(a) For work places in which the number of contract labour employed does not exceed
50- Each first-aid box shall contain the following equipments :-
1) 6 small sterilised dressings.
2) 3 medium size sterilised dressings.
3) 3 large size sterilised dressings.
4) 3 large sterilised burn dressings.
5) 1 (30 ml.) bottle containing a two per cent alcoholic solution of iodine.
6) 1 (30 ml.) bottle containing salvolatile having the dose and mode of
administration indicated on the label.
7) 1 snakebite lancet.
8) 1 (30 gms.) bottle of potassium permanganate crystals.
9) 1 pair scissors.
10) 1 copy of the first-aid leaflet issued by the Director General, Factory Advice
Service and Labour Institutes, Government of India.
11) 1 bottle containing 100 tablets (each of 5 gms.) of aspirin.
12) Ointment for burns.
13) A bottle of suitable surgical antiseptic solution
(b) For work places in which the number of contract labour exceed 50. Each first-aid box
shall contain the following equipments.
1) 12 small sterilised dressings.
2) 6 medium size sterilised dressings.
3) 6 large size sterilised dressings.
4) 6 large size sterilised burn dressings.
5) 6 (15 gms.) packets sterilised cotton wool.
6) 6.1 (60 ml.) bottle containing a two per cent alcoholic solution iodine.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
7) 1 (60 ml.) bottle containing salvolatile having the dose and mode of
administration indicated on the label
8) 1 roll of adhesive plaster.
9) 1 snake bite lancet.
10) 1 (30 gms.) bottle of potassium permanganate crystals.
11) 1 pair scissors.
12) 1 copy of the first-aid leaflet issued by the Director General Factory Advice
Service and Labour Institutes / Government of India.
13) A bottle containing 100 tablets (each of 5 gms.) of aspirin.
14) Ointment for burns.
15) A bottle of suitable surgical antiseptic solution.
(iii) Adequate arrangements shall be made for immediate recoupment of the equipment
when necessary
(iv) Nothing except the prescribed contents shall be kept in the First-aid box.
(v) The first-aid box shall be kept in charge of a responsible person who shall always be
readily available during the working hours of the work place.
(vi) A person in charge of the First-aid box shall be a person trained in First-aid treatment in
the work places where the number of contract labour employed is 150 or more.
(vii) In work places where the number of contract labour employed is 500 or more and
hospital facilities are not available within easy distance from the works. First-aid posts
shall be established and run by a trained compounder. The compounder shall be on duty
and shall be available at all hours when the workers are at work.
(viii) Where work places are situated in places which are not towns or cities, a suitable motor
transport shall be kept readily available to carry injured person or person suddenly taken
ill to the nearest hospital.
4. DRINKING WATER
(i) In every work place, there shall be provided and maintained at suitable places, easily
accessible to labour, a sufficient supply of cold water fit for drinking.
(ii) Where drinking water is obtained from an Intermittent public water supply, each work
place shall be provided with storage where such drinking water shall be stored.
(iii) Every water supply or storage shall be at a distance of not less than 50 feet from any
latrine drain or other source of pollution. Where water has to be drawn from an existing
well which is within such proximity of latrine, drain or any other source of pollution, the
well shall be properly chlorinated before water is drawn from it for drinking. All such wells
shall be entirely closed in and be provided with a trap door which shall be dust and
waterproof.
(iv) A reliable pump shall be fitted to each covered well, the trap door shall be kept locked
and opened only for cleaning or inspection which shall be done at least once a month.
5. WASHING FACILITIES
(i) In every work place adequate and suitable facilities for washing shall be provided and
maintained for the use of contract labour employed therein.
(ii) Separate and adequate cleaning facilities shall be provided for the use of male and
female workers.
(iii) Such facilities shall be conveniently accessible and shall be kept in clean and hygienic
condition.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
8. CRECHES
(i) At every work place, at which 20 or more women worker are ordinarily employed, there shall
be provided two rooms of reasonable dimensions for the use of their children under the age
of six years. One room shall be used as a play room for the children and the other as their
bedroom. The rooms shall be constructed with specifications as per clause 19H (ii) a,b & c.
(ii) The rooms shall be provided with suitable and sufficient openings for light and ventilation.
There shall be adequate provision of sweepers to keep the places clean.
(iii) The contractor shall supply adequate number of toys and games in the play room and
sufficient number of cots and beddings in the bed room.
(iv) The contractor shall provide one ayaa to look after the children in the creche when the
number of women workers does not exceed 50 and two when the number of women workers
exceed 50.
(v) The use of the rooms earmarked as creches shall be restricted to children, their
attendants and mothers of the children.
9. CANTEENS
a. In every work place where the work regarding the employment of contract labour is likely
to continue for six months and where in contract labour numbering one hundred or more
are ordinarily employed, an adequate canteen shall be provided by the contractor for the
use of such contract labour.
b. The canteen shall be maintained by the contractor in an efficient manner.
c. The canteen shall consist of at least a dining hall, kitchen, storeroom, pantry and
washing places separately for workers and utensils.
d. The canteen shall be sufficiently lighted at all times when any person has access to it.
e. The floor shall be made of smooth and impervious materials and inside walls shall be
limewashed or colour washed at least once in each year.
Provided that the inside walls of the kitchen shall be lime-washed every four months.
f. The premises of the canteen shall be maintained in a clean and sanitary condition.
g. Waste water shall be carried away in suitable covered drains and shall not be allowed
to accumulate so as to cause a nuisance.
h. Suitable arrangements shall be made for the collection and disposal of garbage.
i. The dining hall shall accommodate at a time 30 per cent of the contract labour working
at a time.
j. The floor area of the dining hall, excluding the area occupied by the service counter and
any furniture except tables and chairs shall not be less than one square metre (10 sft)
per diner to be accommodated as prescribed in sub-Rule 9.
k. (a) A portion of the dining hall and service counter shall be partitioned off and reserved
for women workers in proportion to their number.
(b) Washing places for women shall be separate and screened to secure privacy.
l. Sufficient tables stools, chair or benches shall be available for the number of diners to
be accommodated as prescribed in sub-Rule 9.
m. (a) 1. There shall be provided and maintained sufficient utensils crockery, furniture and
any other equipments necessary for the efficient running of the canteen.
2. The furniture utensils and other equipment shall be maintained in a clean and
hygienic condition.
(b) 1. Suitable clean clothes for the employees serving in the canteen shall be provided
and maintained.
2. A service counter, if provided, shall have top of smooth and impervious material.
3. Suitable facilities including an adequate supply of hot water shall be provided for
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
11. The above rules shall be incorporated in the contracts and in notices inviting tenders
and shall form an integral part of the contracts.
12. AMENDMENTS
Government may, from time to time, add to or amend these rules and issue directions - it may
consider necessary for the purpose of removing any difficulty which may arise in the
administration thereof.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
ANNEXURE-XIII
2. DEFINITIONS
(i) Workman means any person employed by contractor directly or indirectly through a
subcontractor with or without the knowledge of the WAPCOS to do any skilled, semiskilled or
unskilled manual, supervisory, technical or clerical work for hire or reward, whether the terms
of employment are expressed or implied but does not include any person :-
(a) Who is employed mainly in a managerial or administrative capacity : or
(b) Who, being employed in a supervisory capacity draws wages exceeding five hundred
rupees per mensem or exercises either by the nature of the duties attached to the office
or by reason of powers vested in him, functions mainly of managerial nature: or
(c) Who is an out worker, that is to say, person to whom any article or materials are given
out by or on behalf of the Employer/ Principal Employers to be made up cleaned,
washed, altered, ornamental finished, repaired adopted or otherwise processed for
sale for the purpose of the trade or business of the Employer/ Principal Employers
and the process is to be carried out either in the home of the out worker or in some
other premises, not being premises under the control and management of the principal
employer.
(i) No person below the age of 14 years shall be employed to act as a workman.
(ii) Fair Wages means wages whether for time or piece work fixed and notified under
the provisions of the Minimum Wages Act from time to time.
(iii) Contractors shall include every person who undertakes to produce a given result other
than a mere supply of goods or articles of manufacture through contract labour or who
supplies contract labour for any work and includes a subcontractor.
(iv) Wages shall have the same meaning as defined in the Payment of Wages Act.
3. 3
(i) Normally working hours of an adult employee should not exceed 9 hours a day.
. The working day shall be so arranged that inclusive of interval for rest, if any, it
shall not spread over more than 12 hours on any day.
(ii) When an adult worker is made to work for more than 9 hours on any day or for
more than 48 hours in any week, he shall be paid over time for the extra hours
put in by him at double the ordinary rate of wages.
(iii) Every worker shall be given a weekly holiday normally on a Sunday, in
accordance with the provisions of the Minimum Wages (Central) Rules 1960 as
amended from time to time irrespective of whether such worker is governed by
the Minimum Wages Act or not.
(iv) Where the minimum wages prescribed by the Government under the Minimum
Wages Act are not inclusive of the wages for the weekly day of rest, the worker
shall be entitled to rest day wages at the rate applicable to the next preceding
day,
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
(iv) provided he has worked under the same contractor for a continuous period of
not less than 6 days.
(v) Where a contractor is permitted by the Engineer-in-Charge to allow a worker to
work on a normal weekly holiday, he shall grant a substituted holiday to him for
the whole day on one of the five days immediately before or after the normal
weekly holiday and pay wages to such worker for the work performed on the
normal weekly holiday at overtime rate.
5. PAYMENT OF WAGES
(i) The contractor shall fix wage periods in respect of which wages shall be payable.
(ii) No wage period shall exceed one month.
(iii) The wages of every person employed as contract labour in an establishment or by a
contractor where less than one thousand such persons are employed shall be paid before
the expiry of seventh day and in other cases before the expiry of tenth day after the last
day of the wage period in respect of which the wages are payable.
(iv) Where the employment of any worker is terminated by or on behalf of the contractor the
wages earned by him shall be paid before the expiry of the second working day from the
date on which his employment is terminated.
(v) All payment of wages shall be made on a working day at the work premises and during
the working time and on a date notified in advance and in case the work is completed
before the expiry of the wage period, final payment shall be made within 48 hours of the
last working day.
(vi) Wages due to every worker shall be paid to him direct by contractor through Bank or ECS
or online transfer to his bank account.
(vii) All wages shall be paid through Bank or ECS or online transfer.
(viii) Wages shall be paid without any deductions of any kind except those specified by the
Central Government by general or special order in this behalf or permissible under the
Payment of Wages Act 1956.
(ix) A notice showing the wages period and the place and time of disbursement of wages shall
be displayed at the place of work and a copy sent by the contractor to the Engineer-in-
Charge under acknowledgment.
(x) It shall be the duty of the contractor to ensure the disbursement of wages through bank
account of labour.
(xi) The contractor shall obtain from the Junior Engineer or any other authorised representative
of the Engineer- in-Charge as the case may be, a certificate under his signature at the end
of the entries in the “Register of Wages” or the “Wage-cum-Muster Roll” as the case may
be in the following form:-
a. Fines
b. Deductions for absence from duty i.e. from the place or the places where by the
terms of his employment he is required to work. The amount of deduction shall be in
proportion to the period for which he was absent.
c. Deduction for damage to or loss of goods expressly entrusted to the employed person
for custody or for loss of money or any other deduction which he is required to account,
where such damage or loss is directly attributable to his neglect or default.
d. Deduction for recovery of advances or for adjustment of overpayment of wages,
advances granted shall be entered in a register.
e. Any other deduction which the Central Government may from time to time allow.
ii) No fines should be imposed on any worker save in respect of such acts and omissions on
his part as have been approved of by the Chief Labour Commissioner.
Note :- An approved list of Acts and Omissions for which fines can be imposed is enclosed
at Appendix-X
iii) No fine shall be imposed on a worker and no deduction for damage or loss shall be made
from his wages until the worker has been given an opportunity of showing cause against
such fines or deductions.
iv) The total amount of fine which may be imposed in any one wage period on a worker shall
not exceed an amount equal to three paise in a rupee of the total wages, payable to him in
respect of that wage period.
v) No fine imposed on any worker shall be recovered from him by instalment, or after the expiry
of sixty days from the date on which it was imposed.
vi) Every fine shall be deemed to have been imposed on the day of the act or omission in
respect of which it was imposed.
7. LABOUR RECORDS
i) The contractor shall maintain a Register of persons employed on work on contract in Form
XIII of the CL (R&A) Central Rules 1971 (Appendix IV)
ii) The contractor shall maintain a Muster Roll register in respect of all workmen employed by
him on the work under Contract in Form XVI of the CL (R&A) Rules 1971 (Appendix V).
iii) The contractor shall maintain a Wage Register in respect of all workmen employed by
him on the work under contract in Form XVII of the CL (R&A) Rules 1971 (Appendix VI).
iv) Register of accident - The contractor shall maintain a register of accidents in such form
as may be convenient at the work place but the same shall include the following
particulars:
a. Full particulars of the labourers who met with accident.
b. Rate of Wages.
c. Sex
d. Age
e. Nature of accident and cause of accident.
f. Time and date of accident.
g. Date and time when admitted in Hospital,
h. Date of discharge from the Hospital.
i. Period of treatment and result of treatment.
j. Percentage of loss of earning capacity and disability as assessed by Medical
Officer.
k. Claim required to be paid under Workmen’s Compensation Act.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
v) The contractor shall maintain a Register of Fines in the Form XII of the CL (R&A) Rules 1971
(Appendix-XI) The contractor shall display in a good condition and in a conspicuous place
of work the approved list of acts and omissions for which fines can be imposed (Appendix-
X)
vi) The contractor shall maintain a Register of deductions for damage or loss in Form XX of
the CL (R&A) Rules 1971 (Appendix-XII)
vii) The contractor shall maintain a Register of Advances in Form XXIII of the CL (R&A)
Rules 1971 (Appendix-XIII)
viii) The contractor shall maintain a Register of Overtime in Form XXIII of the CL (R&A)
Rules 1971 (Appendix-XIV)
i) The contractor shall issue an Attendance card-cum-wage slip to each workman employed
by him in the specimen form at (Appendix-VII)
ii) The card shall be valid for each wage period.
iii) The contractor shall mark the attendance of each workman on the card twice each day,
once at the commencement of the day and again after the rest interval, before he actually
starts work.
iv) The card shall remain in possession of the worker during the wage period under reference.
v) The contractor shall complete the wage slip portion on the reverse of the card at least a
day prior to the disbursement of wages in respect of the wage period under reference.
vi) The contractor shall obtain the signature or thumb impression of the worker on the wage slip
at the time of disbursement of wages and retain the card with himself.
9. EMPLOYMENT CARD
The contractor shall issue an Employment Card in Form XIV of the CL (R&A) Central Rules 1971 to
each worker within three days of the employment of the worker (Appendix-VIII).
complaint regarding the default made by the contractor or subcontractor in regard to such
provision.
18. AMENDMENTS
The Central Government may from time to time add to or amend the regulations and on any
question as to the application/Interpretation or effect of those regulations the decision of the
Engineer-in-charge concerned shall be final.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
SECTION – VII
TERMS OF REFERENCE
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
SECTION-VII
TERMS OF REFERENCE
1.0 INTRODUCTION
WAPCOS Limited, as Project Management Consultant (PMC) on behalf of Sashastra
Seema Bal (SSB) invites bids from qualified and experienced Contractor for the
Development & Construction of Battalion Head Quarters of SSB at Naugarh,
Siddarthnagar, Uttar Pradesh, hereinafter referred to as the Project /Work.
The project shall include construction of Admin Block / Training Block and Offices,
Barrack, Residential Quarters, Electrical Sub-station, Water Tank including Civil,
Electrical, MEP works including External development, internal roads including
footpaths, Water Supply Distribution Network, Storm Water Drainage Network, Rain
Water Harvesting Structures, Underground water tanks (UGT) for fire and domestic
drinking water, Boundary walls, Horticulture & Landscaping works, Sewage Treatment
Plant, Fire-fighting system, Sub-stations etc.
In order to develop the SSB Battalion Head Quarter at Naugarh, Siddarthnagar, Uttar
Pradesh, WAPCOS intends to engage an EPC Contractor for Construction &
Development of Infrastructure Works at Battalion Headquarters SSB,
Siddarthnagar, Uttar Pradesh on EPC Mode-I.
The execution shall be done on the basis of drawings and schedule to be prepared by
the EPC Contractor with due approval of WAPCOS.
The scope of work includes the Development and Construction of plinth area of
11,388.27 Sqm including all development works as mentioned below and duly
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
The Contractor shall take the risk and responsibility of maintaining security, law and
order till handover of entire project.
WAPCOS shall release payment to Contractor, upon availability of funds, on behalf
of SSB after assuming
a) Achievement of payment milestones by Contractor
b) Quality of works executed strictly as per Drawings, Design and Specifications
finalised by WAPCOS
c) Quantity / Quality of works executed as per Drawings, Designs and
Specifications.
special floor finishing, staircase, door and window frames, plaster, angles,
lighting & sanitary fittings, glass, paint works and finishing till the same is handed
over.
j. The Contractor shall maintain Safety Codes
k. The Contractor shall be provided (i) Land for implementation of project for
temporary site installation and labour hutments (free from all encumbrances)
l. The Contractor shall provide before release of each payment detailed site visit
report along with a certification that works completed / milestones achieved is
strictly as per approved design, drawings and specification.
m. The Contractor must satisfactorily complete any/all other additional activities as
assigned by WAPCOS in the interest of the Project.
n. The Contractor must do all needful required for timely completion of Project.
o. The Contractor must comply to any / all observations, requirements and obtain
all necessary approvals of Third Party Monitors / State & Central Government
Department / Authorities.
p. The Contractor must comply to any/all observations, requirements and obtain
all necessary approvals, etc of Pollution Control Board/ MoEFCC/ CGWA/
Local, State & Central Government Departments/ authorities as and when
required in the interest of the Project.
The Contractor shall complete all Project approvals / clearances from all the statutory
bodies, completion of all Project Preparatory works, Site Developments & Site
Mobilization works which also includes:
(a) Starting construction activities of the Project after all approvals (after
finalisation of architectural plan, structural design & drawing, vetting by
competent authority). The Contractor must ensure timely Submission of all
required documents fees expenses compliances etc required for Approvals,
PCB's Consent to establish & Operate, SEIAA's/ MOEFCC's Environmental
Clearances (if applicable), Aviation Clearances (if applicable), NoC from Fire
Fighting Services Department, Approval from State Electricity Inspectorate,
other applicable Clearances/ approvals/ sanctions required for
commencement and completion of all Project Works.
(b) Site Office of PMC and Contractor, Temporary Labour Hutments & Material
Storage Godowns, Temporary Construction Power Supply arrangements,
Water Boring/Water arrangement for Drinking purposes for Labourers and
construction water, filling and levelling of site etc.
(c) The buildings are to be planned and registered to meet THREE STAR
GRIHA rating. The contractor is required to execute the work in a befitting
manner to suit these standards. The contractor shall take all precautions and
abide by all rules, regulations and directions of the regulatory authorities,
municipalities, traffic, labour, green tribunal in respect of all kind of pollution,
C&D waste management, labour safety measure etc.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
b) Sign board and Exit signages shall be provided for the various services, at various
floors of the building as per requirement.
c) Fire Figthing System with wet riser & sprinklers for the buildings and equipments
as per the requirement of NBC 2016 with upto date amendments, updated BIS
codes, Fire Bye-laws of Govt. of Tripura and CPWD specifications and as per
specifications and makes. This will also includes peripheral header/ring mains and
isolation of ring main at minimum 3 points in the header around the building, the
provision of testing valve in the fire pump house with the facility to transfer the water
again in the fire sump to avoid the wastage of water, isolation valve in the feeder
pipe line to each and every wet riser in the building, electric & diesel fire pump,
internal fire hydrants, Portable fire extinguishers etc.
e) Provision of Lifts (if any) in buildings : The design parameters of lifts are as per
NBC-2016 and CPWD Specifications.
f) Power cabling work shall be with XLPE insulated PVC sheathed armoured cable
as per IS 7098 only.
g) The scope of the work of contractor includes Quality Assurance Policy & Check
List of E&M Services as per CPWD Hand book as amended upto date and
obtaining mandatory approvals from local bodies/ State & Central authorities/
Municipal Corporation, clearance NOC from Fire Department etc. The scope of
work also includes two year defect liability period of all E&M services as mentioned
above.
Note
i. All works has to be executed as per specifications provided in the bid document,
CPWD Specifications (for Civil Works, Electrical Works and Horticulture &
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Landscaping works) and National Building Codes (latest), (in case of difference if
any, stringent / higher specification of the two shall be followed). In absence of
CPWD Specification, IS Codes, MoRTH Specifications, National Building Code
(latest) & sound engineering practices and other standard specifications suitable
for buildings and latest technology shall be adopted as per order of precedence
defined in the contract.
ii. The scope of works & specification are given in general but they are not exhaustive
i.e. does not mention all the incidental works required to be carried out for complete
execution of the work. The work shall be carried out, all in accordance with true
intent and meaning of the specifications and the drawings taken together,
regardless of whether the same may or may not be particularly shown on the
drawings and/ or described in the specifications, provided that the same can be
reasonably inferred there from. There may be several incidental works, which are
not mentioned in the contract document/specifications but will be necessary to
complete the items in all respect. All these incidental works/ costs which are not
mentioned, but are necessary to complete the work shall be deemed to have been
included in the overall amount quoted by the contractor for various components of
work. No adjustment of rates shall be made for any variation in quantum of
incidental works due to variation/change in actual working drawings. Also, no
adjustment of rates shall be made due to any change in incidental works or any
other deviation in such element of work (which is incidental to the items of work
and are necessary to complete such items in all respects) on account of the
directions of Engineer-in-charge. Nothing extra shall be payable on this account.
iii. In case, some of descriptions are missing in the scope of work or specifications in
the bidding documents, items / work shall be executed as given in the CPWD
Specifications, NBC-2016, IS Codes and according to sound engineering practices
so as to make the building including related services fully functional. No claim what
so ever shall be entertained at later stage. All cost of providing and making project
/ buildings with services, landscape and horticulture works fully complete and
making buildings functional in all aspect unless specifically mentioned in the
contract document.
iv. Deviation in the Plinth Area given in the NIT: In case of deviation in Plinth Area
upto 5%, given in the NIT, on positive side, will not be counted for payment and
the payment shall be made only for the Plinth Area mentioned in the NIT. For
deviation in Plinth Area, given in the NIT, beyond permissible 5% on positive side,
shall be paid on the quoted rates of the contractor. Deviation in Plinth Area, given
in the NIT, on minus side shall be admissible as per the quoted rates only.
v. In case of change in specification of any item of the contract and same being
available in DSR 2023 with another item also being available in the DSR-2023,
variation in cost (Plus/Minus) shall be made as per difference of cost of the
respective items in DSR 2023, increased/ decreased by the quoted % (Plus/
Minus)(as quoted by the bidder for the building/item/work in question) and such
increase/decrease shall be applicable only for the actual executed quantities to be
measured separately.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Architectural planning & Structural designing of buildings & services in the campus
and obtaining all statutory/ local body approvals (Pre & Post Construction) through
the Statutory bodies. The Contractor shall also take permission from Municipality/
Fire Department/ Environment/ Pollution control Board, other necessary approvals
from local bodies etc required to start construction work as per plinth area given.
Signature / authority of department or the client department whenever required shall
be provided to the contractor. All liasoning and charges to the concerned authority
shall be paid by the contractor for obtaining the clearance. The charges so paid by
the contractor are in the scope of the work. This also includes Environmental Impact
Assessment & clearance and compliance, Traffic Impact assessment and design of
merging/ demerging of traffic etc.
The structural design of earthquake resistant RCC framed structure buildings &
design of services in the campus and getting approval from PMC and vetting of
drawings by any IIT approved by WAPCOS and cost for the same shall be borne
by Contractor.
Design and construction of buildings, services, fittings etc. as per 3 STAR GRIHA
rating including dual plumbing system (One from the normal water supply line and
the other from the treated water supply of STP for flushing, horticulture purpose),
energy saving LED lights etc.
Building shall be designed for differently-abled persons as per the latest norms of
Central Govt.
In case of any stream/nalla/channel/canal in the site, the contractor shall design the
structres in such a way that the natural flow shall not be obstructed.
The contractor shall visit the site and make himself aware of the actual site
conditions. In case of any depressions in the site, the contractor shall ensure the
safe and sound structrues designed and constructed. No extra claim shall be
entertained by on account of site conditions.
The guidelines & regulation issued by National Disaster Management Authority for
management of building should also be incorporated in the design of building.
b) Execution of Works
After approval from WAPCOS and getting approval from local bodies including
necessary modifications as per the requirements, execution of work as per the
scope of buildings & services defined in the contract document, CPWD
Specifications, NBC (latest), IS Codes, MoRTH Specifications and Sound
Engineering Practices and handing over the assets.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Submission of completion plan of the buildings & services including getting approval/
clearance from local bodies. Submission of buildings & services plan & drawings
and other related documents both in hard copy 6 nos. and the soft copy (in Auto
CAD and other software used for the purpose) after completion (i.e. 'as-built').
Clearance of site before Handing over of the buildings and facilities after fulfilling all
the obligations under the contract.
Defect Liability Period for works executed by the Contractors is 2 years after completion
of project in all respect.
marked materials may be permitted by the WAPCOS only when BIS marked materials
are not manufactured. If any make / brand of the “Material / Article” is not mentioned in
following make list, then standard top 5 Manufacturers/ Agencies /Brand Make for that
“Material / Agency” will be considered for approval by WAPCOS.
are not manufactured. If any make / brand of the “Material / Article” is not mentioned in
following make list, then standard top 5 Manufacturers/ Agencies /Brand Make for that
“Material / Agency” will be considered for approval by SMFPL/PMA.
After award of the Contract, the Employer expects all of the proposed personnel to be
available during implementation of the Contract.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
If the Engineer-in-Charge asks the Contractor to remove a person who is a member of the
Contractor’s staff or his work force stating the reasons the Contractor shall ensure that the
person leaves the Site within seven days and has no further connection with the work in
the Contract.
check and certify the laboratory and field tests carried out by the Contractor and
also carry out independent tests, if required. The report of such test shall be
submitted to the Engineer-in-Charge within a period of 7 days of such tests.
inspect the works during the construction period and the Defects Liability Period,
and to issue Defects Liability Certificates after rectification by the Contractor of
defects notified to him by the Engineer-in-Charge;
check the setting out the works;
instruct the removal from the site of materials which are not as per specifications
or reconstruction of parts of the works which do not comply with the specification;
direct to submit monthly progress reports, Quarterly progress report, Final
completion Report and Bar Chart / Programme chart to complete the work in
stipulated time period.
direct to prepare Running Account Bills for works carried out by the Contractor,
and certify completion of parts or the totality of the works and record of
measurements in the measurement book.
direct to send certified bill to the WAPCOS office for approval of competent
authority and payment.
direct to prepare deviation / variation (if any) with duly certified supporting
documents as per the provisions in contract and will send the same to WAPCOS
office for the approval of Competent Authority.
9.4 DUTIES & RESPONSIBILITIES OF THE PROJECT HEAD/PROJECT MANAGER OF
CONTRACTOR
The duties of the Project Head/Project Manager of the Contractor are, to supervise
construction of the works and, to test and examine any material to be used or
workmanship employed in connection with the works. The principal responsibilities of the
Project Head/Project Manager of the Contractor are likely to be but not limited to as
follows:
To follow the instructions given by the Engineer-in charge, Principal Employer and
WAPCOS
To prepare detailed bar chart depicting each & every activity of the work along with
quantity and time bar, to complete the work in stipulated time period, which will be
displayed in the Site office.
To provide the all residential facility at site camp to the Engineer-in-Charge as per
provisions
to ensure that the construction work is accomplished in accordance with the
technical specifications and Contract Conditions;
to identify construction problems and delays and to recommend to the Engineer-
in- Charge, actions to expedite progress
to ensure proper keeping of records
to monitor and check the day-to-day quality control and quantity measurements of
the work carried out under the Contract
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Note: The work of plantation and internal services, etc. shall be completed
simultaneously during the progress of work as per direction of Engineer-in-
Charge.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
The contractor shall provide fully equipped office for Engineer-in-charge/ site engineer/
Principal Employer along with facility of 24 hours electric and drinking water supply,
sanitary facilities, an inspection vehicle (with Driver, fuel, lubricants and their maintenance
etc.), furniture and desktop computers of latest version along with printers and internet
connection at construction site and any other miscellaneous requirement as directed by
Engineer-in-charge for finalizing immediate technical solutions/decisions on the site, so
that the work progress may not be hampered till the completion of Defect Liability Period.
An amount equal to 1% of the gross amount of running account bills and final bill will be
deducted, if above facilities are not provided at site.
In addition to above, an amount equal to X% (As detailed below in table) of the gross
amount from all the running account bills and final bill will be recovered as given below:-
PMC Site Engineers / Inspection Teams, comprising of fully furnished rooms with
attached kitchen & toilet along with full facilities of 24 hours electricity & drinking
water supply.
The contractor shall also make sufficient arrangement for Photography/
Videography preferably by maintaining a camera/ video camera at site so that video
photographs.
The Contractor shall regularly share the geotagged photographs of ongoing
construction to designated what’s App group. The photographs need to be shared
in every stage of construction for important items and milestones like foundation
reinforcement, RCC casting of foundations, columns, beams & slab, masonry work,
etc. These photographs shall also be submitted as part of each Running Account
Bill.
The Contractor shall provide at his own cost, sufficient numbers of sign boards at
site of approved design. The names of the Project, Employer, Consultants,
Engineer and Contractor etc. shall be exhibited as directed.
The Contractor shall make all arrangements for ground breaking ceremony/
inaugural function etc for the project as required and the cost towards it deemed to
be included in his rates/offer.
The same shall be furnished as per requirement of Monthly Progress report /
Quarterly Progress Report/ Final completion report.
The Contractor shall provide arrangements for firefighting at his own cost. For this
purpose, he shall provide requisite number of fire extinguishers and adequate
number of buckets, some of which are to be always kept filled with sand and some
with water. This equipment shall be provided at suitable prominent and easily
accessible places and shall be properly maintained. The Contractor may be subject
to periodic fire prevention inspections and any deficiency or unsafe condition shall
be corrected by the Contractor at his own cost and to approval of the Engineer-in-
Charge and the relevant authorities.
These fire prevention inspections shall include but not limited to the following:
Proper handling, storage and disposal of combustible materials, liquids and
wastes.
Work operations which can create fire hazards.
Access for firefighting equipment.
Type, size, number and location of fire extinguishers or other firefighting
equipment.
Inspection and maintenance records for extinguishers
Type, number and location of containers for the removal of surplus materials
and rubbish.
General housekeeping
For the purpose of quick communication between the Engineer-in-Charge and the
Contractor or his Representative, Site Order Books shall be maintained at site in
the manner as described below:
Any communication, relating to the works may be conveyed through records in the
site order book. Such a communication from one party to the other shall be deemed
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
to have been adequately served in terms of the Contract. Each site order book shall
have machine- numbered pages in triplicate and shall be carefully maintained and
preserved by the Contractor and shall be made available to the Engineer-in-Charge
as and when demanded. Any instruction which the Engineer-in-Charge may like to
issue to the Contractor may be recorded by him in the site order book and two
copies thereof taken by the Engineer-in-Charge for his record. The Contractor or
his Contractor or Representative may similarly record in the site order book any
communication he may like to send to the Engineer-in-Charge. Two copies thereof
when sent to the Engineer-in-Charge and receipt obtained thereof, will constitute
adequate services of the communication to the Engineer-in-Charge.
The Contractor shall display all permissions, licenses, registration certificates and
other statements required to be displayed under various labour laws and other
legislations applicable to the works at the site office and also maintain the requisite
register / records factually and up to date and keep them ready for inspection by
the concerned authorities and also make available the same to the Engineer-in-
Charge / Owner for inspection.
The relevant I.S. codes of practice and other relevant codes shall be of latest
version with their amendments/ revisions. The Contractor shall keep and maintain
copies of the latest editions of codes at the work site and make it available to
Employer whenever required.
In case of Guarantees specified for certain periods for due performance of materials
and specialist items of work, the Contractor shall be a co-guarantor with the
Specialist Contractor or Supplier offering such Guarantee and shall offer such co-
Guarantee in a format approved by the Employer.
The Contractor has to make own security arrangement. Contractor shall maintain
upto date record of in & out of the material & labour / staff at the security gate of
campus at its own expenses.
If desired by the Employer, the Contractor shall stack and spread to the require
profile the excess earth available suitable for filling in layers not exceeding 200mm,
watering, consolidation within the campus and dispose of all surplus material to the
nearest dumping ground/ land fill area without any additional cost, etc.
The Employer may if require, request the assistance of Contractor labour for
purpose other than from part of Contract. The Contractor will not unreasonably deny
such assistance and the Engineer-in-Charge decision in this regard shall be binding
on the Contractor. The Contractor will be then paid on the basis of minimum wages
rates and provision made in the General Conditions of Contract.
The Contractor shall provide safety equipment to the Employers/officers (whenever
required).
Contractor shall deploy security/ watchmen for 24 hours on site at entire execution
period and up to successful handing over of the project to the PMA/SMFPL.
Contractor shall provide safety gadgets to the Employer officers.
Contractor shall properly cover up & protect all the work throughout the duration of
work at his cost until successful handing over to the PMA/SMFPL, particularly
flooring, risers, mouldings, steps, terrace or special floor finishes (by a layer of 25
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
On the basis of approved Drawings, the Contractor shall submit and issue the “GOOD FOR
CONSTRUCTION” drawings at site. The discrepancy, if any, shall be brought to the notice
before execution of the work. The Contractor alone shall be responsible for any loss or
damage occurring by the commencement of work based on any erroneous and or
incomplete information and no claim whatsoever shall be entertained by the department on
this account.
The levels, measurements and other information concerning the existing site as shown on
the conceptual / layout drawings are believed to be correct, but the Bidders should verify
the same for themself and also examine the nature of the ground as no claim or allowance
whatsoever shall be entertained on account of any errors or omissions and commissions in
the levels or strata turning out different from what is shown on the drawings.
Two copy of contract documents including Drawings furnished to the Contractor shall be
kept at the Sites and the same shall at all reasonable times be available for inspection.
Within the time frame agreed with the Engineer-in-Charge, the Contractor shall prepare
shop drawings using latest version of AutoCAD. Shop drawings shall show all layouts,
details in plans & sections showing all connections, junctions, bends, supports,
clearances. fixing arrangements with dimensions room, etc shall be prepared by the
Contractor on AutoCAD based on the architectural drawings and site measurements. All
measurable items quantities shall be mentioned on each shop drawing being submitted
for approval by the Contractor. 3 sets of shop drawings (soft copy also) shall be submitted
for approval and Seven sets of final shop drawings after approval by Engineer-in-Charge
shall be submitted by the Contractor along with the soft copy. The shop drawings, shall
be prepared as per schedule given in PERT Chart.
ii. The Contractor shall make available three (04) sets of all services drawings including
Electrical work internal services i.e. Water Supply, Sanitary line and Drainage lines.
This shall be the prerequisite for payment of final bill. These drawings shall have the
following information:
a. Run off for all piping and their diameters including soil, waste pipes and vertical
stacks.
b. Ground and invert level of all drainage pipes together with locations of all
manholes and connections, up to outfall.
c. Run off for all water supply lines with diameters location of control valves,
access panels etc.
Enclosure-I
Desired Site Organization Structure
Notes:
1. The bider shall submit the Detailed CV of the above Key Personnels with the Technical Bid
2. In case an bidder is proposing key professional from educational/ research institutions, a ‘No
Objection Certificate/ Consent Letter’ from the concerned institution Consultant/Agency shall
be enclosed with his CV clearly mentioning his/ her availability for the assignment. In the
absence of such certificate, his/ her CV will not be evaluated.
3. Upper Age limit of any Key Expert shall be 62 years (Rejection criteria)
4. No changes shall be made in the Kep Personnel propsoed by the bidders. If, for any reason
beyond the reasonable control of the Contractor, such as retirement, death, medical
incapacity, among others, it becomes necessary to replace any of the Personnel, the
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
b) has reasonable cause to be dissatisfied with the performance of any of the Personnel,
then the agency shall, at the Employer’s written request specifying the grounds
therefore, forthwith provide as a replacement a person with qualifications and experience
acceptable to the Employer.
c) Any of the Personnel provided as a replacement under Clauses (a) and (b) above, does
not qualify any sort of claim for additional expenditure.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Enclosure-II
Deployment of Minimum no. of Plant and Machinery by the Contractor
Whereas it is entirely the responsibility of the contractor to deploy sufficient plant and
modern mechanical equipment to ensure compliance with the Contract, the following list
is an indicative list of the minimum plant and machinery.
Note: The Bidder shall deploy additional plant & machinery as deemed fit and required
to complete the project within stipulated completion period, without any additional
cost to the Employer.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Enclosure-III
All necessary equipment for conducting necessary tests shall be provided at the site laboratory
by the Bidder at his own cost.
SN Equipment Quantity
1 Cube testing machine 1 No.
2 Slump Cone 2 Nos.
3 Tensile Briquette testing machine 1 No.
4 Vicats apparatus with Desk Pot 1 No.
5 Megger & earth resistance tester 4 Nos.
Pumps and pressure gauges for hydraulic testing of
6 1 No.
pipes
7 Weighing scale platform type 100 kg capacity 1 No.
8 Graduated glass cylinder As per requirement
9 Sets of sieves for coarse aggregate (40,20,10,4.75mm) 2 Nos.
Sets of sieves for fine aggregate [4.75; 2.36,
2 Nos.
10 18; 600; 300 & 150 micron
11 Core cutter for soil compaction with accessories 1 No.
12 Cube moulds size 150mm x 150mm x 150mm 30 Nos.
13 Moisture content rapid moisture meter standard 1 No.
14 Hot Air Oven Temp. Range 50oC to 300oC 1 No.
15 Electronic balance 600g x 0.01g. 10kg and 50kg 1 No.
16 Physical balance weight up to 5kg 1 No.
17 Digital thermometer up to 1500oC 1 No.
18 Poker Thermometer (Concrete Road) 0oC to 100oC 1 No.
Measuring Jars 100ml, 200ml, 500ml 1 set of each size
19
20 Gauging trowels 100mm & 200mm with wooden 2 Nos.
Spatula 100mm & 200mm with long blade wooden 2 Nos. set of each
21
handle size.
22 Vernier calipers 12” and 6” sizes 1 No. each
23 Digital pH meter least count 0.1pH 1 No.
24 Digital Micrometer least count 0.01mm 1 No.
25 Digital paint thickness meter for steel 500-micron range 1 No.
GI tray 600x450x50mm, 450x300x40mm,
26 1 Nos. Each
300x250x40mm
27 Electric Mortar mixer 0.25 Cum capacity 1 No.
28 Rebound hammer test Digital rebound hammer 1 No.
29 Screw gauge 0.1mm – 10mm, least count 0.05 mm 1 No.
30 Water testing Kit 1 No.
Aggregate impact value testing machine with blow
31 As per requirement
counter
32 Crushing value apparatus As per requirement
33 Thickness gauge for measuring flakiness index As per requirement
34 Elongation gauge As per requirement
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
NOTE: Any other equipment for laboratory tests at site will be the way it is outlined in
relevant IS Codes and / or as directed by the Employer’s Representative. Quality Control
Engineer shall monitor collection of Sample and conducting regular testing at site
maintaining propriety and the very best standard followed in industry of construction.
SECTION – VIII
Technical Specifications
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
SECTION -VIII
TECHNICAL SPECIFICATIONS OF WORKS
1. GENERAL
Unless otherwise specified, the Work will be executed strictly in accordance with the CPWD
specification corrected up to date at the time of tenders, unless specified to contrary. The
specifications to be generally followed will be the following specifications and codes:
a) CPWD specification
b) BIS specification
c) National building code
d) Schedule of Quantities (SoQ) and Drawings, if any
e) Particular specification as applicable for respective works specified herein.
Error or omission, if any in the nomenclature, rate or unit of the items or work shall
be corrected as per DSR 2023.
Measurement of work shall be done as per CPWD specifications and BIS codes,
as applicable.
Actual quantities of completed and accepted work shall only be paid.
Nothing extra will be paid to the contractor for any lead or lift unless otherwise
specified for any material required directly or indirectly under the contract.
Nothing extra will be paid to the contractor for diverting water in the channels or
streams if it becomes necessary for the execution and completion of the work.
The contractor shall be responsible and liable for proper and complete execution
of the entire work and ensure coordination and completion of Civil, Electrical,
Plumbing, Mechanical/ Fire Fighting works, etc.
Any rock extracted during excavation from site shall be recovered and the same
shall be used in the random rubble masonry or for stone pitching as much as
possible. However, any Royalty to be paid to the Government shall be paid by the
contractor.
d. Before start of the work the Contractor is required to submit the shop drawings. The
shop drawings shall be approved by the Engineer-in-Charge.
e. Before placing orders on the manufacturer for supply of cables, pole, fittings, pipes, etc.
the contractor is required to get assessed the exact requirement of each size of the
cable at site of work and get the same approved from the Engineer-in-charge. The
Employer shall not take back any spare quantity of cable whether in pieces or in sealed
drums/ containers, if procured more than that required at site / approved by the
Engineer-in-charge.
f. However, it may be noted that the contractor shall have to arrange extra quantity of the
cables, poles, fittings, pipes, etc. over and above that assessed by the contractor,
before start of the work and approved by the Engineer-in-charge, if such additional
quantity of the cables, poles, fittings, pipes, etc., is required at site, in order to make the
installation as covered in Scope of this work and in order to make the installation
operational. Such quantity shall be paid as per contractual provisions of the Agreement.
3. COMPLETENESS OF WORK
All hardware items such as screws, thimbles, G.I. wires, etc. which are essentially required
for completing an item as per specifications will be deemed to be included in the item even
when the same have not been specifically mentioned. All hardware materials such as nuts/
bolts/screws/ washersetc. to be used in the scheduled items shall be zinc/cadmium plated
iron. Nothing extra on account of same shall be paid.
For items/equipment requiring initial inspection at manufacturer’s works’ the contractor will
intimate the date of testing of equipment at the manufacturer’s works before dispatch. The
Employer also reserves the right to inspect the fabrication job at factory and the Contractor
has to make the arrangement for the same. The Contractor shall give sufficient advance
notice regarding the dates proposed for such tests/inspection to the Employer’s
representative(s) to facilitate his presence during testing/fabrication. The Engineer-in-
charge at his discretion may waive off such testing/fabrication. The cost of the Engineer-in-
charge’s visit to the factory will be borne by the Contractor. Also, equipment may be
inspected at the Manufacture’s premises before dispatch to the site by the contractor.
b) Safe mechanical and electrical stress on all parts under all specified conditions of
operation.
In case it is felt by the Employer that undue delay is being caused by the contractor in doing
this, the same will be got done by the Employer at the risk and cost of the contractor. The
decision of the Engineer-in-Charge in this regard shall be final.
The entire installation shall be at the risk and responsibility of the contractor until these are
tested and handed over to the Employer. However, if there is any delay in construction from
the Employer side, the installation may be taken over in parts, but the decision on the same
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
shall rest with Engineer-in Charge which shall be a binding on the contractor.
9. POWER SUPPLY
Electrical power/Alternate source including backup power supply (as and when required)
shall be arranged by the contractor for Construction, installation purpose at his own cost
and payment for electricity charges shall be made by contractor. Electrical power supply
required for testing of entire installation after completion shall be arranged by the Contractor.
Contractor shall submit completion plan/ Electrical drawings in triplicate before finalisation
of bill.
13. PAINTING:
All equipment works shall be painted at the workshops/factory/manufacturing unit before
dispatch to the site. Care shall be taken by the contractor while handling and installing the
various equipment and components of the work to avoid damage to the finishes of
equipment. He shall be responsible for repairing all damages and restoring the same to
their original finish at his cost. He shall also remove at his cost all unwanted and waste
materials arising out for the installation from the site of work.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
The contractor shall ensure that all the skilled persons managed / deployed for executing
the electrical work possess wireman license issued by approved authorities, otherwise he
will not be permitted to execute the work. Also, consequences arising due to the default of
the contractor to comply with this condition would be contractor’s responsibility only.
3.2.3 Frame and shutters in wet PVC/FRP/WPC door frames & shutters in wet areas.
area
3.3 Window shutters Factory made colour anodized/ powder coated/
polyester powder coated Z-section aluminum shutters/
standard uPVC/WPC section for windows glazed with
glazing of float/ toughened glass and with/ without
reflective coating/ high performance coatings or double
glazed unit as per design & requirement.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
2 Superstructure
a) For multi-storey RCC framed RCC frame & filler walls of autoclaved aerated
structure cement concrete (ACC) blocks / fly ash bricks.
b) Internal partition Half brick thick masonry in autoclaved aerated
cement concrete (ACC) blocks / fly ash bricks.
c) Toilet floor slab No Sunken floor slab except floor depression for
maintaining slopes. However, camouflaging of water
supply and sanitary line of upper floor to be done be
false ceiling as per the architectural drawings.
3 Doors and Windows
a Frames (except of toilet/bath
& WC)
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
3 External Electrification:
a) Substation building (i) Plinth area- As per requirement
(ii) Floor height - As per requirement
(iii) Building shall RCC framed structure.
(iv) Flooring -CC
(v) Internal Painting- White Wash
(vi) Door- Laminated Machine Pressed Flush Door
(vii) Window - Steel Glazed Door
(viii) Rolling Shutters as per requirement
b) LT / HT Panel Fabricated from CPRI approved workshop
c) External wiring/cable The capacity of sub-station shall be 630 kVA.
connection using U.G.
cables from sub-station
to feeder pillar, building
& pump house and
necessary connection
from DG set to
infrastructures.
d) Sub-Station Equipments Supplying, installation, testing and commissioning of
33 kV/ 0.433 kV or 11 kVA kV/ 0.433 kV substation
equipment comprising HT panel, dry type/ Oil type
transformers, HT cable, bus trunking from transformer
to LT panel, LT panels, automatic power factor
correction panel, active harmonic filters, TVSS
(transient voltage suppression system), SPD (surge
protection system), essential panel, earthing, required
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Street Lighting
12
Street Lighting Supplying, installation, testing and commissioning of
A
with LED LED street/ compound/ high mast/ pathway/ landscape
lighting for the entire campus. The Street lighting shall
be provided with Solar lights in addition to normal LED
street lighting.
Work under this contract shall consist of furnishing all labour, materials, equipment and
appliances necessary and required. The Contractor is required to completely furnish all the
Plumbing and other specialized services as described hereinafter and as specified in the
Schedule of Quantities and/or shown on the Plumbing Drawings.
Without restricting to the generally of the foregoing, the sanitary installations shall include
the following Plumbing Works
a. Sanitary ware Installation
16.2 Specifications
Work under this contract shall be carried out strictly in accordance with Specifications
attached with the tender and as per requirement, CPWD specifications with upto date
amendments, relevant IS standards and in case of its absence as per British Standard Code
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
of Practice.
b) The Contractor shall cooperate with all trades and agencies working on the site. He
shall make provision for hangers, sleeves, structural openings and other requirements
well in advance to prevent hold up of progress of the construction schedule.
16.4 Drawings
i. Plumbing drawings that shall be issued to Successful Bidder shall be diagrammatic
but shall be followed as closely as actual construction permits. Any deviations
made shall be in conformity with the Architectural and other services drawings.
ii. Architectural drawings shall take precedence over Plumbing or other services
drawings as to all dimensions
iii. Contractor shall verify all dimensions at site and bring to the notice of the Engineer-
in-Charge all discrepancies or deviations noticed. Decision of the Engineer-in-
Charge shall be final.
iv. Large size details and manufacturers dimensions for materials to be incorporated
shall take precedenceover small scale drawings.
For examination and testing of materials and works at the site Contractor shall provide all
Testing andGauging Equipment necessary but not limited to the followings: -
i. Theodolite, Steel tapes
ii. Dumpy level
iii. Weighing machine
iv. Plumb bobs, Spirit levels, Hammers
v. Micrometers, Tachometers
vi. Thermometers, Stoves
vii. Hydraulic test machine
viii. Smoke test machine
All such equipment shall be tested for calibration at any NABL accredited laboratory, if
required by the Engineer-in-Charge
All Testing Equipment shall be preferably located in a special room meant for the purpose.
Samples of all materials shall be got approved before placing order and the approved
samples shall bedeposited with the Engineer-in-Charge or kept at site in a sample room as
prepared by the Engineer-in-Charge. Any materials declared defective Engineer-in-Charge
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
All corrections, deviations and changes made on the site shall be shown on these reference
drawings for final incorporation in the completion drawings. All changes to be made shall be
initialed by the Engineer-in-Charge.
No completion certificate shall be issued unless the above drawings are submitted.
Contractor shall provide two sets of catalogues, service manuals manufacturer’s drawings,
performance data and list of spare parts together with the name and address of the
manufacturer for all electrical and mechanical equipment provided by him.
16.9 Testing
Piping and drainage works shall be tested as specified under the relevant clause(s) of the
specifications.Tests shall be performed in the presence of the Engineer-in-Charge.
All materials and equipment found defective shall be replaced and whole work tested
to meet the requirements of the specifications.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Contractor shall perform all such tests as may be necessary and required by the local
authorities to meetMunicipal or other bye-laws in force.
Contractor shall provide all labour, equipment and materials for the performance of the tests.
No walls, terraces shall be cut for making and opening after water proofing has been done
without written approval of Engineer-in-Charge.
16.13 Mirror
Providing and fixing beveled edge mirror of superior glass (of approved quality) desired
thickness, fixed with stainless steel studs, complete with cutting, making holes, studs, all
fittings, screws, washers and making good the walls.
The Pumps shall conform to Indian standard IS: 8034. Pumps and motors shall be mounts on
a commonMS structural base plate. The pump shall be water cooled coupled to induction
motor of suitable H.P and R.P.M specified in schedule of quantities. Pumping set shall be
provides with a Gun Metal “Bourden” type pressure gauge with gunmetal isolation cock and
connecting piping. The pump set shallbe provided with gun metal gate valve of appropriate
sizes on delivery & non-return valve of appropriate size and a pressure gauge with cock shall
be provided on the delivery line.
steel shaft, ceramic bearings, tungsten carbide shaft protection bushes and mechanical
seal driven by suitable kW, RPM, 400/440 Volts, Cycles, AC 3 –phase TEFC vertical flange
motor. Each pump shall be capableof operating with in a performance pressure characteristic
range sufficient below and above the requiredworking pressure. Pumps shall be suitable for
manual operation. Pumps and motors shall be mounts on a common MS structural base
plate. Each pump shall be provides with a totally enclosed fan cooled induction motor of
H.P and R.P.M specified in schedule of quantities Each pumping set shall be provides with
a Gun Metal “Bourden” type pressure gauge with gunmetal isolation cock and connecting
piping. Appropriate vibration eliminating pads shall be provides with each pump. The pump
set shall be provided with gun metal gate valve of appropriate sizes on delivery. a non-
return valve of appropriate size and a pressure gauge with cock shall be provided on the
delivery line. Suction and delivery lines of the pumps shall be provided with double flanged
reinforced Neoprene flexible pipe connectors. Connectors shall be suitable for a working
pressure of each pump as specified in Scheduleof Quantities
Pump casings shall be aluminum and impellers of SS. All pumps shall have combination ball
and rollerbearings and shaft seals should be mechanical. Motor shall be submersible and
shall be rated for minimum HP specified or the BHP absorbed in the operating range of the
pump.
Pump shall be C.I. casing and C.I. two vane open type with a dynamically balanced impeller
connectedto a common shaft of the motor. The vane for sewage pump will be open type,
while for drainage pump,etc. it will be of semi open type. The MOC of the sump shall be in
accordance to schedule of quantity.
Stuffing box shall be provided with mechanical seals.
Each pump shall be provided with a suitably rated induction motor suitable for 415 volts, 3
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
phase, 50 Hz A.C. power supply. Each pump shall be provided with in built liquid level
controller for operating the pump between predetermined levels
The pumping set shall be for stationary application and shall be provided with pump
connector unit. The delivery pipe shall be joined to the pump through a rubber diaphragm,
and bend and guide pipe for easy installation
Pump shall be provided with all accessories and devices necessary and required for the
pump to makeit a complete working system.
Sump pump shall be complete with level controllers, power and control switch gear,
Auto/off/Manual switches, pumps priority selections and control and power cabling upto
motor and controller/probes etc. (Including earthing). Level control shall be such that one
pump starts on required level, 2nd pump cuts in at high level and alarms is given at extra
high level. All level controllers shall be provided withremote level indications.
The stator shall be heat shrunk fitted into the enclosure and shall not use bolts, pins or other
fasteners that penetrate through the stator enclosure. The starter shall be equipped with a
thermal switch embedded in series in the coils of the stator windings to protect the stator
from wheel.
The motors shall be designed for continuous running duty type at 415 volts, 3 phase, 50 Hz
power supply and capable of sustaining a minimum of 20 starts/stops per hour.
Between stator housing and pump, a tandem seal arrangement will be provided with an oil
barrier. Bothseals run in oil, allowing dry running without seal damage. Both seals shall be
of the rubber bellows ormetallic bellow type with positive drive between shaft and rotating
seal face.
Starters for motors shall be fully automatic type with push buttons. Direct on line (DOL) for
motor up-to 10 HP. Starters for motors above 10 H.P. shall be automatic star-delta starters.
Motor control centrefor the entire plant shall be dust and vermin proof construction fabricated
from corrosion resistant M.S.sheets and comprising of:
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
3 duty conditions.
f) Drive rating shall be based on the largest of the following:
i) Rated pump discharge at rated head
ii) 150% of rated discharge @ 65% of rated head
iii) Maximum power absorbed by the pump in its operating range i.e. no-
delivery to free discharge.
17.2 Accessories
The Fire Pumps shall be complete with the following accessories:
a) Suction and discharge eccentric reducers
b) Pump coupling guard
c) Common base frame, fabricated mild steel or cast iron.
Each pump shall have independent set of pressure switches. The pressure switch shall be
snap action SPDT switch rated 10A @ 220 V operated through a stainless-steel diaphragm. The
switch shall have a pointerfor manual adjustment of set point, and all electrical connections shall
be terminated in a screwed terminalconnector. The entire unit shall be encased in a cold drawn
steel (heavy gauge) enclosure. The diaphragm shall be designed for a maximum operating
pressure of the system. Each pressure switch shall be provided with a pressure gauge in
parallel as shown on the drawings and all gauges and pressure switches shall be mounted in
an instrument panel with necessary control piping and drainage facility.
at 1.0mabove the floor level. Instantaneous outlets for the hydrants shall be of
standard pattern approved and suitable for 63mm dia fire brigade hoses. Wherever
necessary, pressure reducing orifices plate and shallbe provided so as to limit the
pressure to 3.5 kg/sqcm or any other rating as required by the Local Fire Authority.
b. Each landing valve shall have a hose reel cabinet as shown on drawings.
i. Landing valve with single 63 mm dia outlet and 80 mm dia inlet.
ii. First-aid hose reel with 30 m long 25 mm dia high pressure double braided rubber
hose (IS:444 marked)with 25 m dia Ball Valve.
iii. 2 Nos. 15.0-Meter-long 63 mm dia Reinforced Rubber Lined (RRL) hoses with
gun metal I.S. markedinstantaneous couplings.
iv. One-gun metal branch pipe.
c. The First Aid Hose shall conform to IS 884 and be wound on a heavy-duty circular
hose reel with a bracket. The hose shall be permanently connected on one end to
the Wet Riser through a 25m Ball Valve with necessary hose adapter and a gun
metal nozzle at the other end.
d. Hoses shall be in two lengths of 15.0 m each, of RRL type with instantaneous
couplings, neatly rolled into bundles and held in position with steel brackets. Hoses
shall be tested and certified by the manufacturer, to withstand an internal water
pressure of not less than 35 kg / sqcm without bursting. The hose shall also
withstand a working pressure of 7 kg / sqcm without leakage.
e. The hose cabinet shall be fabricated from 2mm mild steel sheet duly rust inhibited
through a process of degreasing and phosphating. The cabinet shall have double
flap hinged doors with 4mm clear glass and shall have necessary openings for riser
main and brackets for all internals. The cabinet shall receive two coats of red oxide
primer both inside and outside before two after coats of final paint of approved
colour shade.
f. The fire brigade connection shall consist of two / three/four headed 63mm dia gun
metal outlets with built-in check valve and drain plugs connected to a 150mm dia
outlet connection to the water reservoir or to the hydrant main. The fire brigade
collecting head shall conform to IS 904.
Fire pump with mounting frame, excluding concrete foundation shall be measured per unit.
Instrument panel with pressure gauges, pressure switches, control piping etc. shall be
measured as one unit. Controlcabling from pressure gauge panel to the respective starters
shall be measured in running meter and paid at unit rates.
17.7.2 Black mild steel pipes, when laid underground, shall be protected against corrosion by two
coats of hotbitumen and 2mm thick wrapping of pypkote. Fittings shall be weld able wrought
iron, suitable for buttwelding and 10% of the welded joints shall be radio graphically tested
and found in order. The weldedjoints shall be random selected for testing in consultation with
the Engineer-in-charge. All flanges shallbe slip-on welded type to IS 6392 with a 3mm fibre-
reinforced Teflon gasket and rated for 2.0 N/sq. mm.
17.7.3 Underground mains shall be laid not less than 750 mm below the ground level and shall be
at least 2maway from the building face and supported on concrete pedestals at every 3.5m
and held on with galvanised iron clamps. Concrete thrust anchors shall be provided at all
bends and tees as shown on drawing and as directed. All excavation for pipe laying shall
be carried out with sufficient width for making proper joints. Backfilling shall be done only
after the piping is hydro-statically pressure tested.Piping shall be constantly kept clean till
tested.
17.7.4 All valves shall be housed in brick masonry chambers over 150mm cement concrete (1:3:6)
foundation.The brick walls of the chamber shall be plastered inside and outside with 20mm
cement sand plaster 1:4with a floating coat of neat cement. Chambers shall be 650 x 650 mm
clear for depths upto 1200 mm and 1000 x 1000 mm for depths beyond or as required. Each
chamber shall have a cast iron surface box approved by theEngineer in-charge.
17.7.5 Piping laid above ground shall be supported on cement concrete (1:2:4) pedestals raising
the bottom ofthe pipe at least 150mm over the ground level and held to the pedestals with
galvanised clamps. Pedestals shall be made at 3.0m centre to centre and as shown on
drawings. Cement concrete 1:2:4 thrust anchors shall be provided at all tee-off points and
change of direction as shown on drawings and as required. Pipeslaid on walls and ceiling shall
have galvanised steel brackets.
17.8 Internal
17.8.1 All internal pipes shall be, unless otherwise specified, heavy quality mild steel tubes to IS
1239 using wrought steel heavy duty screwed fittings. Flanges shall be provided to mate
with valves and other equipment and shall conform to IS 6392. Flanges shall be screwed
type. Flanges shall be rated for 2.0 N/sqmm.
17.8.2 Valves shall be suitable for external piping.
17.8.3 All pipes shall be of approved make and best quality without rust marks. Pipes and fittings
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
shall be fixed in a manner as to provide easy accessibility for repair, maintenance and shall
not cause obstruction in shafts, passages etc. Pipes and fittings shall be fixed truly vertical,
horizontal or in slopes as required in a neat workmanship manner. Pipes shall be securely
fixed to walls and ceilings by suitable supports at intervals specified. Only approved type of
anchor fasteners shall be used for RCC ceiling and walls.
17.8.4 All pipes shall be adequately supported from ceiling or walls through structural supports
fabricated from mild steel structural e.g., rods, channels, angels and flats generally as
shown on drawings. Fasteners shall be shear type anchor fasteners in concrete walls and
ceilings and wrought steel spikes of at least 75mm long in brick walls. All pipes support shall
be painted with 1 coats of red oxide primer and two coats of black enamel paint.
17.8.5 All low point loops in the piping shall be provided with 25mm Ball Valves with rising spindle
for draining the system. All valves shall have screwed brass caps. Likewise, 25mm gun
metal air vents shall be provided at all high point loops to prevent air-locking.
17.8.6 All piping shall have flanged joints at about 25m intervals to facilitate easy maintenance.
17.9.1 All pipes shall be provided with threaded joints up to 50mm diameter and welded joints for
pipe above 50mm diameters. Hold tite shall be used for sealing.
17.9.2 All welded joints shall be tested by radiography test.
17.9.3 Joints between CI and GI pipes shall be made by providing a suitable flanged tail or socket
piece and MS flange on the GI pipe. Flanges shall have appropriate number of holes and
shall be fastened with nuts, bolts and 1.5mm thick compressed asbestos gasket.
a) Valves and other accessories
b) Gate Valves
i. Sluice / Gate valves shall be used for isolation of flow in pipe lines For sizes
upto 65 mm, gate valves shall be outside screw rising spindle type and shall
be as per IS: 778 Class-I and Class-II, as applicable.For sizes 80 mm to 300
mm, gate valve shall be as per IS: 780, PN=1.0 and shall be of inside screw
andnon-rising type and cast iron double flanged.
ii. Gate valves shall be provided with a hand wheel, draining arrangement of
seat valve and locking facility (as required). Gate valves shall have back
setting bush to facilitate gland renewal during full open condition.
iii. The Body, bonnet, Stuffing Box, cap and hand wheel shall be of cast iron to
IS:210, grade FG 200 / 260.The non-rising spindle shall be of solid forged
high tensile brass or carbon steel to AISI 304 construction.The Body seating
and wedge ring shall be of solid leaded gun metal. The Bonnet gasket shall
be of highquality rubber.
iv. The Valve shall be PN 1.0 rated but shall withstand tests of upto 20 kg / cm2.
The ends shall be flanged.The batch number of the valve shall be punched
on the top of the flange. The spindle shall be removable type, and shall be
easily rotated.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
c) Pressure Switch
i. The Pressure switches shall be employed for starting and shutting down
operation of pumps automatically,dictated by line pressure. The Pressure
Switch shall be diaphragm type. It shall be suitable for line pressures upto
15 kg / cm2. The scale range for cut in and cut out shall be from 0 to 10 kg /
cm2.
ii. The Switch shall be suitable for consistent and repeated operations without
change in values. It shall be provided with IP: 66 water and environment
protection.
iii. The enclosure shall be of aluminium and pressure element and wetted
parts shall be of stainless steel.The switch shall be snap acting type with 1
number N O / N C contact.
d) Pressure Vessel
i. The Pressure Vessel shall be provided to compensate for slight loss of
pressure in the system and to provide an air cushion for counter acting
pressure surges whenever the pumping set comes into operation.It shall be
normally partly full of water; the remaining being filled with air which will be
under compression when the system is in normal operation.
ii. Pressure vessel shall be fabricated from 8-10 mm thick MS plate with dished
ends and suitable supporting legs. It shall be provided with a 50 mm dia
flanged connections from pump, one 25 mm drain with ballvalve, one water
level gauge and 25 mm sockets for pressure switches. The pressure vessel
shall be hydraulically tested as required.
iii. The Pressure Vessel shall be for Hydrant Systems. The Pressure Switches
shall be mounted on the drainend of each Vessel. The Vessel shall also be
provided with an air release valve mounted at the top.
e) Pressure Gauge
The Pressure Gauge shall be constructed of die cast aluminum and stove
enameled. It shall be weatherproof with an IP 55 enclosure. It shall be a stainless
steel Bourden tube type Pressure Gauge with a scalerange from 0 to 16 Kg / cm2
and shall be constructed as per IS: 3624. Each Pressure Gauge shall have a
siphon tube connection. The Shut off arrangement shall be by Ball Valve.
f) Ball Valve
The Ball Valve shall be made from die cast brass and tested to 14 Kg/cm2
pressure.
i. The valve shall be internally threaded to receive pipe connections.
ii. The Ball shall be made from brass and machined to perfect round shape and
subsequently chrome plated.The seat of the valve body- bonnet gasket and
gland packing shall be of Teflon.
iii. The handle shall be of chrome plated steel with PVC jacket. The handle shall
also indicate the directionof `open' and `closed' situations. The gap between
the ball and the teflon packing shall be sealed to preventwater seeping upto 14
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Kg/cm2 pressure.
iv. The handle shall also be provided with a lug to keep the movement of the ball
valve within 90 degree. The lever shall be operated smoothly and without
application of any unnecessary force.
h) Butterfly Valve
i. The Butterfly Valve shall be suitable for waterworks and tested to minimum
of 16 kg / sq cm pressure. The Valves shall fulfil the requirements of
AWWA (American Water Works Association) C 504, API 609 and MSS-
SP-67.
ii. The body shall be of cast iron to IS: 210 in circular shape and of high
strength to take the minimum water pressure of 10 kg/cm2. The disc shall
be heavy duty cast iron with anti-corrosive epoxy or nickel coating.
iii. The valve seat shall be of high-grade elastomer or nitrile rubber. The Valve
in closed position shall have complete contact between the seat and the
disc throughout the perimeter. The elastomer rubber shall have a long life
and shall not give away on continuous applied water pressure. The shaft
shall be of EN 8 grade carbon steel.
iv. The Valve shall be fitted between two flanges on either side of pipe
flanges. The Valve edge rubber shall be projected outside such that they
are wedged within the pipe flanges to prevent leakage.
v. The Valves shall be supplied with manual gear operated opening / closing
system by lever.
i) Pipe supports
All pipes whether horizontal or vertical shall be suitably supported using
galvanized mild steel clamps/clevis hanger manufactured of good quality as
approved by engineer in-charge.
j) Vertical Pipes
The pipes running vertical shaft shall be supported by galvanised mild steel rigid
clamps fixed to wallwith anchor bolts and studs.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
When the horizontal distance between the centre line of two adjacent pipes is less
than 300 mm a powdercoated rail shall be fixed to wall the pipes independently
clamped to the rail with `U' bolt clamps.
k) Horizontal Pipes
Pipes running horizontal shall be supported from structural beam/slab by using
appropriate galvanised m.s. pipe clevis hangers. Other specification as per
CPWD.
Supports for horizontal piping longer than 15m in a stretch shall be provided
with swivel clamps. Otherwise, the clamps shall be universal clamps or rigid
clamps as required by the project engineer.
All surfaces to be painted shall be thoroughly cleaned with wire brush to remove completely
rust and other extraneous substances. Over the cleaned surfaces one coat of red oxide
primer shall be applied completely covering the exposed surfaces. Finishing coat of enamel
paint shall be applied one day afterthe prime coat, after ensuring that the paint is dry. The
second coat shall be done before the installationis handed over and after approval to do so
from the Engineer-in-charge.
18.1 Standards
The following standards and rules and regulations shall be applicable:
IS:2176 : Portable fire extinguisher Dry power type
IS:2878 : Portable fire extinguisher carbon-dioxide type
18.2 Extinguishers
Carbon dioxide type
a. The extinguishers shall be rated for 4.5 and 9 kg by weight or carbon dioxide, unless
stated otherwise.The contents shall be with a filling ratio not exceeding 0.667.
b. The body shall be steel cylinder made according to IS:2872 and approved by the
chief controller of explosives.
c. The discharge head shall be simple and safe to operate conforming to IS:3224 with
a safety release to IS:5903 set to 18.0 to 20.0 N/sqmm. A syphon tube of copper
or PVC shall be fitted. A non-conducting discharge horn and a high pressure hose
(27.5 N/sqmm pressure) shall be fitted with each extinguisher.
d. The discharge system shall be designed to expel 95% of the contents in continuous
discharge as follows:
2.00 8 - 16 2
6.00 15 - 24 4
d. The internal and external components and surface shall be treated for anti-
corrosion as for dry powder type extinguishers.
General requirement
19.1.1 Switchgear
A. Molded Case Circuit Breakers (MCCB)
Type Molded case circuit breaker
Operating voltage 415/690-volt 3 phase 50 Hz
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
No of Poles - 3 or 4 as required
Arc chutes shall be provided for each pole, and shall be suitable for being lifted
out for the inspectionof the main and the arcing contacts.
Common Operating handle required for three phase MCCBs for simultaneous
operation and tripping of all the three phases.
Sheet steel hinged lockable doors for each separate compartment shall be
provided and duly interlockedwith the breaker in "ON" and "OFF" position.
Protection Microprocessor based releases and/or thermal magnetic releases
shall be provided for the Circuit Breakers as stipulated in the Schedule of
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Quantities
Type test certificates Submit Certificates from a recognized test house for the
Circuit Breakers offered.
19.1.2 Switchboard
Supply System Three phase 4 wire, 415-volt, 50 Hz, Indian TN-S system.
Panel Compartmentation
Compartment Tier 3A as per IEC 6043 (Part-I) unless otherwise stated in
Schedule of Quantities.
Circuit Breaker Metering Separate segregated compartment shall be provided for
accommodating instruments, indicating lamps, control contactors and control
MCB etc. These shall be accessible for testing and maintenance without any
danger of accidental contact with live parts of the circuit breaker, bus bars and
connections.
Control wiring compartment a horizontal wire way with screwed cover shall be
provided at the top to take interconnecting control wiring between vertical
sections.
Panel Configuration
Panel configuration - MCCB's arranged multi-tier formation.
Air Circuit Breakers - Single or double tier formation.
Spare Space provision - The Switchboards shall have a provision of 25% spare
space to accommodate possible future additional switch gear.
Extensible shall be extensible on both sides.
Panel Construction
Metal clad totally enclosed,
Dead front
Floor mounted
Free standing type
Modular extensible design
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Switchboard cubicles, doors and covers - Fabrication with CRCA Sheet Steel
Cubicles - Thickness shall be 3.0 mm for load bearing compartments and 2.0 mm for non-
load bearing compartments, folded and braced to ensure rigid support for all components.
Doors/ covers - Thickness not less than 1.6 mm & should be properly earthed.Joints - Seam
welded
Welding slag - Ground off
Welding pits - Wiped smooth with plumber metal.
All joints should be neatly formed and finished flush with adjacent surfaces, No joints shall
be located incorners. Bare edges shall be round/covered
Structural members and bracings where ever required shall be welded or bolted to the
frame. The frameshall be of modular design and extensible.
Bus Bar Insulation Heat shrunk PVC sleeking of 1.1 kV grade and bus bar joints
provided with clip-on shrouds.
Bus Bar supports Non-breakable, non-hygroscopic epoxy resin or glass fiber reinforced
polymer insulated supports able to withstand operating temperature of - 25°C to 130°C
(degree of protection IP 65 IEC 60529) at regular intervals, to withstand the forces
arising from a fault level as stipulated in schedule of quantities.
Colour coding all bus bars shall be colour coded.
Auxiliary Bus Electrolytic Copper Auxiliary buses for control power supply, space heater
power supply or any other specified service shall be provided. These shall be insulated,
adequately supported and sized to suit specific requirement.
Switchboard Interconnections
Interconnection material Unit ratings up to 100 amps,
FRLS PVC insulated copper conductor wires with crimped terminations.
Rating of 100 amps and above solid copper/aluminum connections PVC sleeved
Interconnection jointing all connections, tapings etc.
Shall be made to ensure minimum contact resistance.
Shall be firmly bolted and clamped with even tension before assembly.
Joint surfaces shall be filed or finished to remove burrs, dents and oxides and Silvered
to maintain good continuity at all joints.
All screws, bolts, washers shall be cadmium plated.
Approved spring washers shall be used with cadmium plated high tensile steel bolts
with BSF threads.
Instrument and control wiring all wiring for relays and meters shall be with ZHFR PVC
insulated copper conductor wires. The wiring shall be coded and labelled with approved
ferrules for identification. All power circuit wiring shall be minimum 2.5 sqmm and
control circuit wiring shall be of minimum 1.5 sqmm and for CT & PT minimum 4sqmm
copper cable shall be considered.
Earthing
Continuous earth bus sized for prospective fault current shall be provided with arrangement
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
for connecting to station earth at two points. Hinged doors / frames shall be connected to
earth through adequately sized flexible braids.
Space Heaters
Anti- condensation heaters shall be fitted in each cubicle together with an ON/OFF isolating
switch suitable for electrical operation at 230 volts A.C 50 Hz single phase of sufficient
capacity to raise the internal ambient temperature by 5°C operation interlocked with
switchgear.
Sheet Steel Treatment and Painting Sheet steel used in the fabrication of
switchboards shall undergo arigorous cleaning and surface treatment seven
tank process comprising of alkaline degreasing, descaling in dilute Sulphur acid
and a recognized phosphating process after which a coat of primer paint comp
actively with the final paint shall be applied over the treated surface. Final paint
coat of oven baked powder coating, of minimum 50-micron thickness, of sheet
approved by Engineer-in- Charge shall then be provided.
Relay adjustment
Trip test
Insulation test with 500 volts megger. The insulation resistance should be more than
100 mega ohms
Local Authority Requirements. All requirements by the local Authority including those
listed below shall be complied with
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Rubber floor mat of minimum 6 mm thickness and 1 m width provided for the full
length of the switchboard.
A dry chemical type fire extinguisher of required capacity with approved label.
In case of C.T. operated thermal overload and magnetic instantaneous short circuit release.
The overload releases shall be such that each phase can be individually set depending on
the phase unbalanced currents. The releases shall have inverse time current characteristics
and the magnetic release shall be time delayed with a minimum setting of 25 ms varying up
to 300 ms for discrimination without effecting the breaking current capacity of the ACB.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
CTs shall be mounded such that they are easily accessible for inspection,
maintenance and replacement.Wiring for CT shall be with copper conductor FRLS
PVC insulated wires with proper termination works and wiring shall be bunched
with cable straps and fixed to the panel structure in a neat manner.
Voltmeters
Voltmeters shall be moving iron type range of 3 phase 415-volt voltmeters shall be 0-500.
Volt meters shall be provided with protection fuse.
Watt meter
Wattmeter shall be of 3 phase electro dynamic type and shall be provided with a maximum
demand indicator if required.
Power factor meter
3 phase power factor meters shall be of electro dynamic type with current and potential coils
suitable for operation with current and potential transformers provided in the panel. Scale
shall be calibrated for 50% lag - 100% - 50% readings. Phase angle accuracy shall be +40.
Energy and reactive power meters
Trajectory meters shall be two elements, integrating type, kWh, kVA, kVArh meters. Meters
shall confirm to IEC 170 in all respects. Energy meters, kVA, and kVArh meters shall be
provided with integrating registers. The registers shall be able to record energy conception
of 500 hours corresponding to maximum current at rated voltage and unity power factor.
Meters shall be suitable for operation with current and potential transformers available in
the panel.
General requirements for tests for lead acid storage batteries IS 8320
Battery
The battery shall be sealed maintenance free / valve regulated led acid
(SMF/VRLA) battery. The batteries shall be manufactured using “absorbent glass
matt” technology in which the electrolyte is in absorb condition, held within the
pores of the glass matt separator. The separator is packed tightly between the
positive and negative plates. “Led Calcium Tin Alloy” shall be used in the plate grid
structure to eliminate harmful effect of early gassing. The container and the lid of
the battery shall be of high-grade polypropylene. The vent plugs shall be provided
with self-resealing relief valves. The battery shall be rated for minimum 100 AH at
24-volt DC unearthed system. The battery sizing calculation to be carried out by
vendor during detailed engineering stage and to be submitted to Electrical
consultant for verification and approval.
when the batteries are fully charged the charging shall automatically change from
boostcharge to trickle charge.
Construction feature
The float cum boost charger and DC distribution board shall be housed in sheet
steel cubicle of angle iron frame work with panels of 2.0 mm thickness, louvers for
ventilation, glands plate will be provided for cable entry from front bottom. The
cubicle shall be painted in siemens grey shade. Four wheels/2 nose channels shall
be provided at the base.
Performance
The DC output voltage of float /boost charger shall be stabilized within ± 2% for
AC. Input variation of 230 V ± 10%, frequency variation of 50 Hz ±5% and DC load
variation of 0-100%. The voltage regulation shall be achieved by a constant voltage
regulator having fast response IGBT. The ripple content in output will be within 3%
of DC output nominal voltage.
There shall be provision to select auto float/manual float /manual boost modes.
During auto float modethe battery charging shall automatically changeover from
boost mode to flat mode and vice versa. During manual float/boost modes it shall
be possible to set the output volts by separate potentiometers.The battery charger
shall have automatic output current limiting feature.
Components
The battery charger shall essentially comprise of the following
1 no. double pole ON/OFF MCB at AC input
1 no. pilot lamp to indicate charger ON.
1 no. main transformer: Double wound, naturally air cooled, having
copper windings.
1 no. rotary switch to select auto float / manual float / manual boost.
During auto float mode automatic changeover shall take place from float
mode to boost mode and vice versa.
1 set solid state constant potential controller to stabilize the DC output
voltage of the float cum boost charger at ±2% of the set value for AC
input voltage variation of 230 V ± 10%, frequency variation of
±5% from 50 Hz and simultaneous load variation of 0-100% and also
complete with current limiting circuit to drop the float charger output
voltage upon overloads to enable the battery to take over.
1 no. electronic controller to automatically changeover battery charging
from boost
to float and vice versa 1 no. DC ammeter and toggle switch to read
charger output current and battery charge/discharge current.
1 no. moving coil DC voltmeter to read the DC output voltage.
2 set potentiometers to adjust the output voltage during manual/auto float
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Visual and audible alarm with manual accept/ reset facility shall be provided for
the following:
i. AC mains fail
ii. Charger fails
iii. Load / output over volt
iv. Potential free contact for BMS connectivity for maintaining battery status.
a) Number of poles 3
The post insulators used in the A.B. Switches shall have the following ratings:-
19.4.2 Standards
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
rod shall be medium gage of 32mm diameter nominal bore G.I. pipe single length 6
meters. The phase coupling rod for gang operationshall be of medium gauge 25 mm
dia. nominal bore G.I pipe. The Rating post insulators shall be provide with suitable
bearing mounted on a base channel with 8mm dia thrust collar and 6mm split pin
made out of stainless steel. The operating down rod shall be coupled to the spindle
(minimum) dia – 32mm for gang operation through another suitable bearing by two
numbers 10mm dia stainless steel bolts with double nuts. All the bearingsshall be
provided with grease nipple. All metal (ferrous) parts shall be galvanized a polished.
The pipe shall be galvanized in accordance with IS-4736/1968.The post insulators
should be fixed with the base channel using Galvanized Nuts and Bolts.
Mounting: - The A.B. Switches shall be suitable for horizontal mounting in double
pole sub-station structures. MS Galvanized base Channel & base support channel
shouldbe of min. size 75x40x6 mm.
Switching Blades: - It shall be made out of electrolytic copper with silver plated. The
approximate size shall be 220mm X 50X 6 mm. The Switch shall have such a spring
mechanism so as to ensure that the speed of the opening of contact is independent of
speedof manual operation.
Fixed Contracts: - The fixed Jaw type female contracts shall be made of electrolytic
copper (minimum 95% copper composition) duly silver coated controlled by
stainless steel high pressure spring housed in robust G.I. Cover. It is essential that
provision shall be made in fixed female contracts to take the shock arising from the
closing of move contract blade without the same being transmitted to the post
insulator. The arrangement made in this regard shall be specifically shown in the
drawing.
Arcing Horn: - As the switches are generally meant for isolating transmission line and
distribution transformers, suitable arcing horns shall be provided for breaking the
charging current horn shall be made of 10mm dia. G.I. Rod with spring assisted
operation.
Spacing: - The minimum clearance between phases to the switch shall be 760mm.
Theoperation down rod shall be at a transverse distance of 300mm from the outer
limb of theswitch. The centre spacing between two post insulators of the same phase
shall be 380mm.In the open position of the A.B. switches the moving blade shall rotate
through 90o. Thisshall be exhibited in the drawing.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Sample, Drawing & Literatures: - Sample of each items 11KV 200 amps. A.B. Switch
shall be furnished and three copies of drawings item similar to the sample shall be
furnished along with the tender.
The details of construction and materials of different parts of the A.B. Switch shall
clearly be indicate in the tender and illustrative pamphlet / literature for the same shall
besubmitted along with the tender.
f. Operational test.
The transformer offered be complete with all parts and accessories which are necessary or
usual for their efficient and satisfactory operation. Such parts and accessories be deemed
to be within the scope of this specification whether specifically mentioned or not. Main tank
body may be delivered in unpacked condition, but delicate parts like indicating meter,radiator,
and conservator. Pressure Relief Valve, equalizer pipe, be packed to avoid damage due to
transport, shipment.The equipment and work conform to General Specifications for electrical
works of CPWD (Part– I, II, IV) as amended up to date, BSI /IEC and relevant Indian
Electricity rules, Indian Electricity Act 2003 and other relevant regulations with statutory
regulation and safety codes that is related to the work.
19.5.1 Location
The equipment supplied be suitable for satisfactory performance for the rated capacity at all
weather conditions in summer, monsoon, and winter at Sambalpur, Odisha as under: -
(a) Altitude: less than 1,000 mtr.
(b) Max. ambient air temp: 50°C
(c) Max. daily average ambient air temp: 40°C
(d) Max. yearly weighted average ambient temp: 32°C
(e) Min. yearly weighted average ambient temp: -5°C
(f) Temp. rise at the above conditions:
(g) By resistance method: 55°C (Max. temp. being 95°C)
(h) By Thermometer: 50°
(i) By Maximum Humidity: 79%
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
With the above Ambient Temperature Condition Allowable Maximum Temperature Rise be
As Mentioned Below
Type of Cooling Oil in °C Winding in °C
ONAN 40 45
19.5.8 Taps
Transformer be provided with off load taps ranging from +5% to -10% in steps of 2.5% each
on H.V winding for H.V. variation. The tap changing switch be in a convenient position so
that it can he Operated from Ground level. The Control Box be provided with Tap Position
Indication & Locking Arrangement.
Technical Specification of Off Load Tap Changer to be supplied with 200 kVA 11kV/433 V
Transformer
The Off-load tap changer be designed suitable for local manual as well as local
electrical operation
An oil immersed tap selector and arching switch or are suppressing tap selector,
provided with reactor or resistor for reduction of make and break arcing voltages and
short circuits
19.5.10 Terminal
Cable Box on HV & LV Sides for Cable Termination
19.5.13 Cores
The Cores be constructed from high grade cold rolled non-aging grain-oriented silicon
steel laminations having magnate coating as insulation. The core thickness shall be
27 microns
Successful bidder will offer the Core for inspection and/or approval by the purchaser
during the manufacturing stage. Manufacturer’s Call notice for the purpose should be
accompanied with the following as applicable as a proof towards use of Prime Core
materials:
i. Invoice of supplier
Core materials be procured either from the core manufacturer or through their
accredited marketing organization of repute.
Tendered should preferably have in-house Core cutting facility for proper monitoring
and Control on quality.
The materials used for insulation have high interred lamination resistance and rust
inhibiting property. It not deteriorates by aging from hottest operating temperature and
clamping pressure of the core or disintegrate due to core vibration. It not has any
tendency to absorb moisture or to react with insulating oil.
The assembled core be securely clamped on the limbs and yoke with uniform
pressure to minimize noise emission from it.
The top main core clamping structure be connected to the tank body by a copper strip.
The bottom clamping structure be earthed by one or more of the following methods
(i) by connecting through vertical tie rods to the top structure (ii) by direct metal to
metal contact with the tank base by the weight of the core and winding (iii) by a
connection to the top structure on the same side of core as the main earth connection
to the tank.
All parts of the cores be robust design capable of withstanding any shock, to which
they may be subjected during lifting, transport, installation, and service.
Adequate lifting lugs be provided to enable the core and winding to be lifted.
Adequate provision be made to prevent movement of the core and winding relative to
the tank during transport and installation or while in service.
The supporting framework of the cores be so designed as to avoid the presence of
pockets which would prevent complete emptying of the tank through the drain valve
or cause trapping of air during filling.
The insulation structure for the core to bolts and core to clamp plates be such as to
withstand a voltage of 2000 V AC at 50HZ for one minute.
Flux Density at rated voltage and frequency shall not exceed 1.69
tesla or as per latest IndianStandards.
The No load current shall not exceed 1.5 % of the full load current.
The no load current shallnot exceed 3 % of the full load current in L.
V. Winding when the applied voltage is 112.5%
19.5.15 Winding
All windings shall be electrolytic copper (99.9% purity) be fully insulated.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
The Total number of earth electrodes shall be 4 (2 for neutral and 2 for connection to
a common earth bus for body earthing) in two different places
19.5.19 Tanks
Tank Pressure be as per Manufacturer Standard and comply the latest IS Standard
Construction:
The Transformer tank and cover be fabricated from good commercial grade low
carbon steel suitable for welding and of adequate thickness. The tanks of all
transformers be complete with all accessories and be designed so as to allow the
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
complete transformer in the tank and filled with oil, to be lifted by crane or jacks,
transported by- rail, road without overstraining any joint and without causing
subsequent leakage of oil.
The main tank body be capable of withstanding vacuum gauge pressure 68 kN/sq. m
(500 mm. of Hg). The under carriage of the tank be made of channel of suitable size
and design.
The base of each tank be so designed that it be possible to move the complete
transformer unit by skidding in any direction without injury when using plate or rails.
Where the base is at a channel construction. It be designed to prevent retention of
water.
Tank stiffeners be deigned to prevent retention of water. Wherever possible the
transformer tank and its accessories be designed without pockets wherein gas may
accumulate. Where pockets cannot be avoided, pipes be provided to vent the gas into
the main expansion pipe
All joints other than those which may have to be broken be welded when required
they be double welded. All bolted joints to the tank be fitted with suitable oil tight
gaskets which give satisfactory service under the operating conditions and
guaranteed temperature rise conditions. Special attention be given to the methods of
making hot oil tight joints between the tank and the cover as also between the cover
and busing and all other outlets to ensure that the joints can be remade at site
satisfactorily.
Tank cover
Each tank cover be of adequate strength and not distort when lifted. Inspection
openings be provided as necessary to give easy access to bushings or changing ratio
or testing the earth connection. Each inspection opening be of ample size for the
purpose for which it is provided.
The tank cover and inspection cover be provided with suitable lifting arrangement.
The tank cover be fitted with pockets for thermometer and for the bulbs of oil and
winding temperature indicators. The thermometer pocket be fitted with a captive
screwed top to prevent the ingress of water. Protection be provided, where necessary
for each capillary tube. The pocket be in the position of maximum oil temperature and
it be possible to remove the instrument bulbs without lowering the oil in the tank.
Turrets should provide on tank cover to house the bushing. The tuners of both HV &
LV bushings should be connected through pipes with main tank pipe to drive out
trapped air or should have air release plug to drive out trapped air.
Conservator vessels
The conservator should be normal type to prevent direct contact of Transformer oil
with atmospheric air for retarding oxidation and contamination of oil. The air cell be
made from suitable material with inner coating resistant to transformer oil & outer
coating resistant to ozone & weathering.
The conservator be provided with necessary valves to drive out the air in the space
between conservator wall & air cell during filling of oil drain valves for complete
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Oil Gauges
Normally one Magnetic type oil gauge be provided. The oil level at 30°C be marked
on the gauge
Connection
The oil connection from the transformer tank to the conservator vessel be arranged
at a raising angel of 3° to 9°C to the horizontal and consist of pipe with inside diameter
50 mm/80 mm as per capacity of the transformer and as per IS : 3639. Two valves be
provided between the conservator and transformer main tank to cut off the oil supply
to the transformer after providing a straight run of pipe for at least a length of five
times the internal diameter of the pipe on the tank side of the gas and oil actuated
relay and at least three times the internal diameter of the pipe on the conservator side
of the gas and oil actuated relay. The valves should be fitted on both sides of the Gas
and Oil actuated Relay.
Breather
Conservator vessel be fitted with a glass container type breather in which silica gel is
dehydrating agent and so designed that:
i. The passage of air through the silica gel
ii. The external atmosphere is not continuously in contact with the silica gel
iii. he moisture absorption indicated by a change in colour of the tinted
crystals can be easily observed from the distance
iv. breather be mounted at approximately 1400 mm above ground level and
be connected to the air cell of the conservator through pipe for the
purpose of breathing during contraction or expansion of the air cell
Bushings
Pollution free type insulator should be used for the bushings. The bushing should be
locatedon suitable turrets (with air release plugs). Adjustable arcing horns should be
provided on theBushings; Bushings of identical voltage rating be interchangeable. All
bushings be equippedwith suitable terminals of approved type size and be suitable for
bimetallic connections
The bushings have high factor of safety against leakage to ground and so located as
to provide adequate electrical clearance between bushing and grounded parts.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Both HV & LV Bushing should be suitable for use in heavily polluted atmosphere as
per IS 2099 & IS 3347. 3 Nos. H.V Bushings & 4 Nos. L.V. Bushing should be supplied
with the transformer.
Filter, drain valves, sampling devices and air release plugs Each transformer be fitted
with the following
A drain valves as specified below be fitted to each conservator for diameter
up to 650 mm:Size of the valve 15 mm: for diameter above 650 mm: Size of
the valve 25 mm.
Suitable oil sampling device be provided at the top and bottom of the main
tank. The sampling device is not fitted on the filter valves specified under (ii)
above
One 15 mm air release plug on the main tank of the transformer
All other valves opening to atmosphere be fitted with blank flanges.
Radiator
Radiators be so designed as to avoid pockets in which moisture may collect and
withstandthe pressure tests. The radiator tubes / fins be seamless, made of mild steel
having minimum wall thickness of approx. 1.0 mm and a clean bright internal surface
free from dust and scaleThey be suitably braced to protect them from mechanical
shocks, normally met in transportation and to damp the modes of vibration transmitted
by the active part of the transformer in service. Each cooler unit have a lifting eye.
The butterfly or similar metal valves be provided for isolating detachable radiator
assembly. One cock each at the bottom of radiator stack be provided for draining oil
from radiator stacks.
Air release plug each at the top of radiator stack be provided for release of locked air
from radiator stack. Removable blanking plates be provided to permit the blanking off
main oil connection of each cooler. Radiator fixing bands in top & bottom of radiators
to be provided to minimize the vibration of the same.
Lifting and haulage facilities Each tank be provided with
i. Lifting lugs suitable for lifting of transformer complete with oil.
a. A minimum of four jacking lugs, in accessible positions to enable the
transformer to complete with oil to be raised or lowered using hydraulic or
screw jacks. The minimum height of the lugs above the base
b. Transformer up to and including 10 tonnes weight -300 mm.
c. Transformer above 10 tonnes weight – 500 mm
ii. Suitable haulage holes be provided
Insulating oil
The transformer and all associated oil filled equipment be supplied complete with
insulating new oil required for first filling including 10% extra oil for future use during
commissioning. The transformer tank be dispatched filled oil and the balance oil be
supplied in non-returnablesealed drums along with the Transformers.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
The wheels be suitable for being turned through an angle of 90°C and locked in that
position when the tank is jacked up. All wheels be detachable and be made of Cast
iron or Steel. Suitable locking arrangement be provided to prevent the accidental
movement of the transformer.
Painting
Before painting or filling with oil all metallic parts be completely cleaned and free from
rust, scale and grease and all external surface cavities on castings be filed by metal
deposition
The interior of al transformer tank and other oil filled chambers and internal structure
steel work be thoroughly cleaned of all scale and rust by sand blasting or other
approved method. These surfaces be painted with hot Oil resisting varnish or paint.
Unexposed weld need not be painted.
Except for nuts, bolts, and washers, which may have to be removed for maintenance
purposes all external surface receives a minimum of three coats of paint.
The primary coat be applied immediately after cleaning. The second coat be of oil
paint of weather resisting nature and preferably of a shade or colour easily
distinguishable from the primary and final coats be applied after the primary coats
have been touched up where necessary. The final coat be of a glossy oil and weather
resisting non-fading paint of Dark Admiralty Grey shade no. 632 of IS:5. Primer paint
be ready-made zinc chrome as per IS: 104: intermediate and final costs of paint be
as per IS: 2932.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
All interior surfaces of mechanism chambers and kiosks except those which have
received anti-corrosion treatment receive three coats of paint applied to the
thoroughly cleaned metal surface as per procedure mentioned above. The final coat
be of a light-coloured anti- condensation mixture.
Any damage to paint work incurred during delivery be made good by the manufacturer
by thoroughly cleaning the damage portion and applying the full number of coats of
paint that had been applied before the damage caused.
Earthing terminal
Two earthing terminals capable of carrying the full amount of lower voltage short
circuit current of transformer continuously for a period of 5 second provisions be made
at positions close to each of the bottom two corners of the tank for bolting the earthing
terminals to the tank structure to suit local conditions.
The winding temperature indicator with two electrical contacts for alarm and trip
purposes be provided with anti-vibration mounting. The winding temperature indicator
be housed in the marring box.
The oil and winding temperature indicator should be of renowned make preferably of
“Perfect Control”. The scale on the dial of the thermometer should be 0°C to 150°C.
The angular displacement of thermometer should be 270.
All contacts be adjustable on a scale and be accessible on removal of the cover. The
Temperature indicators be so designed that it shall be possible to check the operation
of contacts and associated equipment.
For measuring winding temperature, a hearer coil fed from a C.T. (Current
transformer) must be provided on the pocket for winding temperature indicator bulb.
The connection from C.T. to heater should be through a link arrangement on tank
cover suitably housed in a weatherproof box so that C.T. current and heated coil
resistance can be checked.
Rating diagram
The following plates shall be fixed to the transformer tank at a suitable height so that
the particulars could be read by standing at ground level.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
A rating plate bearing the date specified in the relevant clause of IS: 2026
including figures of temperature rise of oil and winding and high voltage test
values.
A diagram plate showing the internal numbering of taps, tapping switch
connection of windings and the voltages vector relationship in accordance with
IS:2026 and in addition a plan view of the transformer giving the correct physical
relationship of the terminals. No loadvoltage be indicated for each tap. the losses
should be mentioned with impedances
Foundation
The Contractor shall furnish foundation plan of the transformer showing the fixing
arrangement of the transformer so that the purchase may be able to finalize the
foundation drawing.
certificates of the material / equipment offered for inspection and testing indicating
probable date of inspection and testing.
The supplier shall arrange all possible facilities for such inspection and testing at any
lane during manufacture free of cost.
Test certificates
Seven copies of the approved Test certificates as mentioned above are to be
furnished to the Owner before dispatch of the equipment.
Drawing and manuals
The following drawings and details shall be furnished in triplicate along with the tender:
i. General Arrangement outline drawing with plan, elevation and end views showing
various dimensions of transformer and its vital component including height of the
bottom most portion of bushing from the bottom of base channel and also
indicating thereon physical center line and position of center of gravity.
ii. Three copies of sketches for height of crane hook above ground for lifting and
undertaking core, shipping dimensions, complete lists of fittings and devices, net
weights of core, winding, tank, radiator, oil, conservator and total weight, fixing
arrangement of transformer in foundation.
iii. Installation, operation, and maintenance manual.
iv. The following drawings and manuals in six sets shall be submitted for approval
within 15 (fifteen) days from dale of placement of LOI / ORDER.
Cross sectional details with plan, elevation and views showing all internal
clearances.
Drawing of Name & rating plate
Drawing of diagram
The manual clearly indicates the installation method, check-ups and tests to be
carried outbefore and after commissioning of the transformer.
Performance certificates
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Credentials
Tenderer shall furnish documents in support, delivery, of similar equipment indicating
thereon names of the organization quantity ordered, quality supplied along with
tender.
Deviations
All deviations from the specifications shall be recorded in the “Deviation Sheet” with
reference to respective clauses of the Specification by drawing Specification for the
same. Unless deviations are recorded in the Deviation Sheet and submitted with the
offer, it will be taken for granted that the offer is made in conformity with Specification.
Spare parts
The Contractor shall submit a recommended list of spare parts for five years of
operation along with item wise price for each item of spares.s
Validity period
Validity period of the offer be reckoned from the date of opening of tender provided it
is technically and commercially complete one. Otherwise, it will be counted from the
date of receipt of complete information.
20. GNERAL
All civil, electrical, Horticulture & Landscaping works, even if not specified above, shall be
executed strictly in accordance with the CPWD specifications corrected up to date at the time
of tenders, unless specified to contrary, as given below:
A. Civil Works Specifications
CPWD Specification Volume-I – 2019
CPWD Specifications Volume-II – 2019
SECTION – IX
Tender Drawings
TOPOGRAPHICAL SURVEY 98.98
R
E701270
E701290
E701310
E701330
E701350
E701370
E701390
E701410
E701430
E701450
E701470
E701490
E701510
E701530
E701550
E701570
E701590
E701610
E701630
E701650
E701670
E701690
E701710
E701730
E701750
E701770
E701790
E701810
E701830
E701850
E701870
E701890
E701910
E701930
E701950
E701970
E701990
E701110
E701130
E701150
E701170
E701190
E701210
E701230
E701250
N3018220
99.10
R
99.16
R
N3018200
A RH 99.14
98.80
R 98.83
E
UG IN
R R
98.76
R 98.66
98.67 98.78
99.20
BC
B 98.44 R
A CL
R 98.71
CK BC
000
R
ON
98.57
98.4298.57 98.81
A 98.56 R
98.76
RR
98.7 98.58 I
B R
B 98.67
BA
98.85
N3018180 T 99.20
99.19
R
R Ab
98.70
N
hc
98.27
. 98.32
hc
98.40
.
98.59
R
98.56
BB 98.43 R 98.70
98.50
T B
.
TR
AW
EC
98.45
T 98.46 98.45
98.42 98.86 98.85
J 98.34 T
98.42
98.42 98.33 .
98.39
T 98.47
T 98.38
.
R R
98.73
E
N EL
BBC . 98.37 T 98.51 . 98.91
LI
98.320
98.39
98.56 . T R
.00
98.32
BC . 98.40 98.37 98.88 98.92
. 98.34 98.42 B R
8.498.55 T .
98.38 98.68 T . R
B
9.98.44 C 98.90
RI
R
T 98.62
T 98.41 98.38
98.29
98.53 98.42 98.51 98.41
. . .
CT
99.40 . 98.51 B B
GRD 98.59
98.61 98.98
R B R
N3018160 98.46 .
99.37 98.30
.
E 98.45
98.40
98.79
EL
98.45 .
R 98.64 . . B
98.41 .
B 98.60 98.34 .
VILLAGE : KATYA . . 98.40
.
98.45 B .
98.91
98.42 R
98.32
98.81
98.42 . . 98.73
98.56 98.43 . 98.47 R
B . .
98.45
99.30 98.40 98.36
R 98.400 .
98.58 98.51 . B
98.91
R
N3018140 0 . .
98.48 98.72
98.43
.
98.5000
. B
99.26 98.46
R 98.49 .
. 98.84
99.20 98.6298.44 .
MANGO
R 98.59 98.52
98.46 98.52 98.47 B . 98.92
. .
MANGO . EP . R
98.58 98.43 98.50
B 98.50 . .
MANGO
99.20 .
99.23 R 98.62 98.44 98.44
R 98.66 . 98.46 98.53 98.89
98.49 B 98.35 . . B .
. . 98.42
B
N3018120 98.44
. 98.97
R
98.35 98.42 98.45
B 98.77 98.64 .
99.25 98.50 . .
B . 98.37
R B .
98.41
. 99.00
98.500
98.31 98.50 .
B 98.58 98.62
0
98.500
98.33 98.59 . 98.47
99.17 B
B 98.49 .
. B
R 98.60 . 98.61
98.34 98.34 . 98.46
B . 98.94
B 98.36 . 98.49
98.58 . 98.45 . 98.43 R
0
B . . 98.47
98.77 B 98.77
N3018100 99.15 98.94 n
EP
98.31 98.48
.
.
n . 98.39 98.55
98.55 B 98.53 98.57
98.4
. . 98.57
98.56 98.45 . .
99.02 98.30 . 98.43
B . 98.34
98.5000
. 98.41
EP . 98.45 98.59 98.49 .
98.34 .
B 98.39TBM9 .
000
98.32 . 98.47 98.46
B . 98.39 . 98.39 .
98.92 . .
98.48 98.46 98.51
. . . 98.45
98.44 98.63
98.49 .
98.42 . .
98.92 98 98.37
B
. 98.60
EP
98.40 .50 . 98.46 98.46 B
N3018080 . 00 98.36
. .
98.43
98.83 98.40 98.54 98.55 .
. . B 98.44
98
B . .
98.33
.30
.
98.43 98.45
99.12 97.95 . 98.40 98.28
00
. 98.37
98.19 . . 98.44 98.50 . . .
98.4000
98.53 98.59 98.27 98.31
R 98.38 98.47 . .
. EP
98.30
.
.
98.28
.
B
EP
98.39
. . 98.34
.
98.37
. 98.45
.
98.59
.
98.50
.
98.39
B PLANTATION OF MANGO TREE
98.46 98.44
N3018060 0
000
97.7298.29 98.45 98.40
97.900
97.95 . .
R 99.03 .
.
B
98.33
98.29
.
.
98.46
.
.
VILLAGE : SONWAL
00
98.5
98.39 98.36
.
0.97.92 . .
98.0
98.56 98.44
. . 98.14
.
98.300
98.29 98.17
97.99 .
R
VILLAGE : KATYA 98.93
98.30
B
97.72
98.28
.
98.30
.
.
98.21
. 98.35
.
98.47
. 98.49
.
98.45
B
N3018040 97.95
97.67
98.59n
.
. . 98.36
.
98.39
98.48
.
98.40
.
AREA PART (A) : 38597.25 SQM.
0
R .
98.37
98.36 98.30
97.6000
97.10 98.22 TBM8 .HT 98.51
CP . 98.22 HT
98.88
97.00 98.35
00
. 97.38 98.33 .
97.99 98.37
97.84 96.97 n 98.91 B 98.24 98.41
40 98.38
96.96 EP 97.80 . 98.47
R B . . 98.31 B
OB . 98.19
. 98.38
.
. .
98
98.06 B 98.26
E .
N3018020
97.86
R
97.27
EP
97.19
97.05
OB
OB
SS
B
OF
IC
.
RR
97.76
OB
97.97
97.97
97.99
98.03
B
98.61
.
MANGO
98.38
T 98.18
97.54
n
98.51
99.00
.
98.35 97.49
. n
98.88
.
97.91
97.75
. EP 97.86
TBM8
98.94
B
97.85
. 97.89
98.24
B
TBM8 97.89 98.26
98.25
.
98.27
98.28
.
TOTAL AREA (A+B) : 305000.84 SQM.
97.50 B
96.88 97.97 98.00 B B .
n TBM8 98.91
.
. 9797.89 98.27 .
. .9
97.70 R 98.02 97.88
B 98.03 98.87 97.84 B
. 0
R B 98.36 98.30 n 98.92
97.73
97.75
R
.
. 97.92 97.98
R . . .
TBM8
98.98 00 98.28 98.27
98.30
98.04
R R 97.90
97.87 98.14 98.00
98.12 97.68 98.600
. 97.92 97.77
B .
98.47 B
.
97.8000 R
B
98.02
97.88
B B
. 98.14
98.14
.B
n
97.59
0 99.01
.
EP .
97.82
98.31
B
.
98.13 PLANTATION OF MANGO TREE
OB 97.98 98.17
96.76
B
97.64
.
97.68
.
. 98.07 B 98.0000 97.95 B 98.17
98.20
n . 98.35
B
. 98.21
.
= : 75.36 ACRES
97.94 97.93 B B 98.06
98.01 B 99.03 97.84
97.78 96.82 97.97 98.46 98.28
N3018000 R OB
R
97.91OB 97.92
97.88 . 98.02 97.93
B. 98.05 . 98.05
B 98.13 98.82
.
98.96
. B . 98.16
97.56 97.91 97.88 R 97.87 97.83 BB B97.86 B
.
. . 97.62 98.16
98.23 .
96.58 B 98.11
98.03 99.19 n . EP
. R R OB B
97.84 98.09
EP 97.55 B
B 97.90
97.87
97.93 97.56 98.09 .
EP . 97.86
97.79 96.90 BM . 97.83 . 97.89 n 98.91 . 97.91
R 97.37 BM6
OB 97.68 97.92 . B 98.03 98.09 98.15
EP . R 98.14 99.04 97.59 . .
98.47 98.60 B .
tbm-1 tbm-1
0
97.52
p1 97.10
97.100097.24
97.54
.
.
97.81
0
.
B .
98.24 n
98.77
.
B
97 98.12
00
OB 97.86 EP B 99.33 97.45
97.14 . 98.19 97.54 97.88
97.88
.4 97.78 97.90 98.04 97.98 .
00
GRID INTERVAL : 20.00 x 20.00 M.
. . 98.00 . n
98
G 98.05 97.64 98.91 . .
.4
97.73 98.03
97.94 B 98.06 B
R
96.94
96.93
97.19 97.71
R
B
. BB
00 . 0 . 99.26 n .
98
B G
EP 97.25 97.91 97.92 97.86
97 98.1
97.78 . 98.05
00
. R 97.67 R . . 98.19 97.45 98.83
. E
97.87 97.76
.6097.60 97.93 B 98.99 n .
90
. OB 99.33
R . 97.89 .
N3017980 97.32 .
00 . 97 97.84
97.83
98.70 .
98.38
98.53 98.06 98.03
98.02
98.20 .
99.31
99.3 99.38
98.70
97
CONTOUR INTERVAL : 0.10 M.
EP . B
97.85
.90 EP
000
. 97.69 97.98
98.03 BC . . . 97.42 .
T 98.16 .
000 0
.
97.71 G 98.77
. 00
97.83 97.82
97.77 R 97.68
97.78 97.99 00 BB
98.66
IN 98.10 T 98.07 n
.
98.3
97.11 97.70 . . .
.
DG 97.96 . B
R T
LD
. 97.73
00
. HT . 98.63 97.61
97.9
97.94 98.03 98.05 99.21
97.55 HT 97.75 T 98.00
BU
97.69 97.50 97.79 . . . n
R 97.75 R . B
.40
0
R . DG 97.82 98.56
98.53 98.08 99.47
HT 97.89 97.61
W
0
97.53 97.69 97.66 R . BC 98.48 B .
97.23 98.03 E 98.58 n
.20
R . 97.99
97.73
R
NBC 98.03
98
. 98.06 98.52 98.02
98.06
97.697.59 EP 97.85 BC
NOTES :
EP
EP 98.49
97.11 96.88 97.77 DG BC 98.26 . B B
00
97.22 97.60 . 98.56
EP
97.22
JCOQ!
97 . R 97.34 000 97.87 . 97.83 97.80 BC
BC .
00
97.85 . . 98.52
98.51 98.02
. . .
.0 0
NG
B 97.54 BC 98.52
98.51 B 98.05
R 97.75 97.77 98.14
98.0
0
97.22 97.68
97
98
R 97.31 97.80 BC 97.94
DI
. 98.66 B 98.10
97.800
.
.4
96.64 . . R .
N3017960 R 97.83 BC .
000
98
97.57 98.01 B
JCOQ! 97.49 96.86
97.56 L 98.60
.4
.3
.
97
ER
98.11
BU
97.27 R fbm3
tbm-3 97.69 98.59 BC .
00
. 97.54 . B
00
98.03
QT 97.24 97.82 97.87
98.03 BC
R
. R 97.79 BM6
Bm4 W 97.99 . 97.95
0
O
NE
97.63 97.27 97.44 . 98.07
JC
1. ALL DIMENSIONS ARE IN METERS
0
R 97.96 .
97.28 R . . 97.70 97.71 B
.
. 97.78
98.2 98.02
0
. 97.56 . 97.91 . 97.98
97.96
97.54
R 97.97.19
2000 .
. 98.56
98.56
000 97
97.94 .
98.0
96.79 R 97.92 BC
BC 97.86 97.96 . 98.27
JCOQ!
97.49
97.98 97.92 98
000 .90
. . FB 97.99 . . B
97.70
97.27
. 97.57
97.67 97.70 . . .
98.41 97.98 .00
. . 97.75
00
97.7 00
WS 97.62 97.70 97.91 97.90
.
000
R 97.22 97.69 FB .
98.49
R
97.72 97.13
R
. 97.16 . 97.67 .
97.78
. .
98.07
2. ALL LEVELS ARE IN METERS.
W
MANGO
.
JC
96.90 MANGO
R . 97.52 . . . 97.95
N3017940 97.78
OR
97.35
97.34 R 98.55
98.56
O
R HM97.58 97.72 .
K
.
97.59 97.19 . . . G . 97.91
ES
BM7
96.41
T IN
SH
C 97.57 . EP R . 97.66 . .
OP
. .
97.88
HM 97.22
97
97.42
97.60
.
bb
LC
.
.90 BU
98.56
97.87
98.26
98.28
98.25
97.9
97.78
97.86
.
. 98.00
. 97.80
97.97
3. ALL LEVELS ARE RECORDED WITH RESPECT TO
E
97.16 97.8498.57 .
R 97.36 97.23
.
.
.20
97.07
97.50. . R
BA 97.68 0
BM6 0
97.87 . BC W
BC
BM6
B3
BM3
TBM3 . 97.87 .
97.81
T 97.54 R 97.04
LI NE
.
0 97.93
97.20 0
00
.
96.16 97.69 97.69
R 96.88 97.43
97.66
C
97.200 00 97.21 .
BA
bb T 97.85
97.84 .
DATUM POINT. DATUM POINT IS ON THE OFFSET OF
OR
. 97.59 97.67
98.45 B R POND POND 97.51 . 97.16 97.71 97.81 97.88 .
.8
97
97.63 MANGO
C 97.50 97.48 97.59 . . 97.89
97.23 .
LC
R WS
97.59 97.58 97.61 97.19 GARDAN
97.50 . . . . 97.67 97.79
R 97.00 . 98.56 .
97.88 R TSC GARDAN POND GARDAN . 96.97 . .
N3017920
R
97.41
97.51
GARDAN
97.44
97.39GARDAN
GARDAN
97.17
.
96.84 .
97.54
97.55
98.91
tbm-1 97.56
.TBm2
TBM2
fbm2
tbm2
R
.
97.33
97.14
.
TB
A 97.62
.
BC
97.86
97.73
.
97.83
.
97.70
. CULVERT PARAPET AND ITS RL IS 100.000
OO
98.56 97.46 MANGO
97.90 . 97.83 97.82 97.98
GARDAN 97.15 97.15 97.19 R
R 97.19
. 97.5000 97.39 TS
R
MANGO
97.48
.
. . .
97.57
R 97.34 97.26 97.57 97.54
F 97.56
.
97.76
97.65
. 97.85.
.
97.85
.
97.81
. 97.95
. .
97.55 97.58 97.16 R 97.07 . .
97.6000 . 97.7 97.84 .
G
96.69 .
00
EP 96.75 97.44
97.42 GARDAN 97.57
EP
B H T 97.07 .
97.29 GARDAN 97.59
00
K
97.39 97.52
GARDAN 97.48 R . 97.62
97.61 97.65
97.57 T 97.14 97.60 . 97.89
.60
RC
00
97.60 . . 97.16 97.17 B
TBM4 . .
97.60
.70
97.06 JA R 97.36 97.21 . 97.60
98.52 97.44 . .
PA
LEGEND
97.51 .
97
R B 97.55 GARDAN
.20
GARDAN
GARDAN . 97.58
97.57
0
AN 0
97.9000
97.63 . 97.83 97.66
97
R 97.43 97.20 .
97.5R 97.41
00
97.36 97.48 97.87
97.68 . . .
96.58
B 97.61 BA 97.87 97.11
R . 98.06
97
JC BM6
.BM1 97.53 97.27 97.67
97.68
.5
RR 97.48 .
N3017900 96.95 B JB
97.28 TSC
97.12
.
.
97.65 97.53 R .
97.5000 97.54 97.45
97.64
. . 97.77 97.75 97.80
97
. AC . 97.14 R 97.84 97.57 97.47 . . .
. 97.24 QG 97.21 97.68
97.67 . . 97.66
. .
K 97.71
00
97.58 97.23 . 97.18 97.49 . 97.49
tbm4
TBM5 . . . 97.70
97.33 97.50 97.67 .
. 97.36
R 97.47 .
.10
T TS GRDN 97.07 . . .
98.81 97.57 97.28 . . 97.91
97.33 FP . . 97.42 97.79 98.00
97
S. NO.
R 97.33 97.03 . . .
97.57 . 97.71
B 97.4897.57 JC 97.37 . . 97.17 97.26
97.5000 . 97.66 97.63
NAME SYMBOLS
97.5000
FP JC 97.40 97.05 97.47 97.74
. 97.21
97.5000
R R TBM3
TBM6 .
000
96.56 97.47 97.53 97.55
97.35 .
97.4
97.47 .
97.7
. 97.18 97.39 97.37 . 97.08 97.21 .
97.06 . 97.38 97.49 97.53 97.73
. . . 97.18 GRDN 97.06 QG 97.33 97.20
. 97.46 97.47 97.61
96.53EPP QG .
96.23 NS
97.38 GRDN GRDN 97.03 . . . . 97.81 .
0 97.61
00
. B . 97.56 97.77
97.31 96.99 97.56 97.49 97.52
.97.68 .
N3017880 97.30 NS 97.41
97
00
97.53 97.35 97.40 . .
.6
. . . . 97.44 . .
. .
.
97.02
.20 97.15
. . 97.25
. 97.44 .
97 1 FENCING
.30
GRDN 97.35
97
97.36 97.28 . 97.63 97.76
96.63 TBM7 97.58 96.98 . .
. 97.42 . 97.17 97.45 97.37 .
. .
0
K
97.67
00
. B JB JC 97.06
97.06 .
RR
97.59 EP
2
97
. .
96.93
BOUNDARY WALL
97
R
96.24 JB AN 97.40 97.57 97.19
MANGO
97.59 .
97.21 97.50 97.3297.31
97.49
GRDN 96.99
97.2000 .
000
AN
T 97.69
. BA JB JB . 97.69 97.40 . . . .
.
97.58 .
MANGO MANGO
10
.
I 96.80 RR JB T 97.65 T 97.46 97.27 97.23
97.3
W
97.24 97.20
MANGO
FB .
96.52 96.88
NS
. 97.38 . . T .
N3017860
00
AC
JA
97.56
S
ES
R
96 . 97.21
BA
EP 97.47
MANGO
97.63
. .
96.98 . .
97.5 3 BUILDINGS
AN
T 96.98 97.21
.1 96.05 96.68 97.34 GRDN
MANGO
97.17 97.39 . .
.
0. 0 97.54
W
.50 .6
. . . .
96
00
GRDN 97.11 . 97.41 .
. 97.42
97.4000
96.69
GRDN 96.96 MANGO
97.56 .
97 00 97.72
.10
97.22 .
.5
. GRDN T
96.59 96.10 96.73 .
. 96.90 97.14 0
00
97
B . . 96.81 . 96.91 97.30
97.09
GRDN . . 97.16 . 97.34
97.35 97.38 97.43
.
0
. .
96.79 97.26
96.80 96.86 97.53
00
. . 97.28 .
4 HAND PUMP
97
MANGO
GRDN 96.90 97.31
N3017840 . 97.14 MANGO
.90 96.85
GRDN 96.96 . 96.89 96.92 T 96.90
. . . 97.74
.2
96.45 95.83 GRDN . . 97.53
96
96.53 96.77 97.08 97.09 . 96.95 .
. .
97.58
0
BB GRDN 96.94 96.91
. . 96.99 .
96.9
00
96.81 96.78 96.94 . 97.14 .
97.18 . . .
GRDN GRDN . . 97.67
97
96.40 GRDN 96.89 PEEPAL
95 96.97 PEEPAL
96.71 97.26 97.22 96.66 . 96.43 B
97.62
96.80 . GRDN 96.89 PEEPAL
97.01
. 96.11
.90 97.23 . GRDN .
.0
. 96.95 97.35 96.89 . 97.13
000
00
T
96.8000
B . . 96.79 .
97.09 97.13 96.93 T . 97.28
97.24 GRDN
96.93 97.15
. GRDN GRDN 96.85 . 97.31
5 ELECTRIC POLE
0
. 96.74
97
. . . 97.19
96.18 GRDN GRDN 96.82 96.83
96.94 . 97.33
. 96.69 .
96
.3
96.72 . 97.04 96.86 97.14 .
GRDN .
N3017820 95.58 97.08 GRDN 96.81 . . 96.86 97.12
0
97.14 . 97.30
.7
. . 97.12
97.13 GRDN 97.08 . 96.84 . . 97.24
00
96.82 PEEPAL
96.78 . 97.74
GRDN 96.81 . .
00
. 96.67 GRDN
96.49 . . 96.92 97.40 .
. 96.68 97.11 96.65
B . 97.01 .
0
. T 96.69
00
. GRDN 96.80 GRDN 96.71 .
96.80 96.99
96.06
96.69 GRDN .
.
96.66 97.2 97.24
6.7.
. . 97.19
96.64 96.59
.
PEEPAL
96.67
96.69
.
96.74
. . 00. 0 97.19 97.01 .
. B
97.03
97.01
.
96.97
. 9 96.91
GRDN
96.92
.
96.66
.
96.67
.
96.87
. 96.84 96.95
97.01 97.07
96.97
96.99
.
.
N3017800 96.99
.
97.61
96.94
. . 96.7096.69
96.72
. B
97.09
B 97.45 .
.97.73 96.69 96.67 . . 97.36 .
. 96.56 97.00
96.57
B
T
97.03
. 96.67
.
.
. 96
96.48 .500
96.94
.
96.95 B .
96.54
.
.
96.98
96.79
96.72
GRDN
96.65
96.73
. . 0 96.91
B 96.99
. 97.10
.
97.36
96.44 . .
. . 96.91 . 96.78
96.61
97.19
96.08
96.62
.
96.51
.
.
96.57
96.56
.
.
96.44
96.71
96.72
.
96.7
.
96.92 97.08
97.00 8 EARTHEN ROAD
B
.
.
.
96.73 96.48
. . 96.9000 . B
.
.
96.77
.
96.41
.
96 96.59 96.52
0 00 96.87
. 96.92
96.90
97.18
. 97.56
96.61 97.08 96.87
96.56
0 . .5 . . B 97.17 97.07
97.24
.
N3017780 . . 96.89
96.89 . 96.57 96.46
00 97.03 . B
00
00
. .
. . .
96.54 96.40 .
0 .
9 PLANTATION
96
96.73 96.29
97.64
97.2
96.49
7 97.01 97.25
50
96.63 .
6.
. 96.52 . .
96
B . . .
.7
.
96.95
9 97.000
98.10
96
96.55 . 96.92
96.92 97.27
.3
. . .
0
. 96.56
. BB B
000
96.30
00
96.68
00
.
96.80 . . 96.97
0
0 00 .
96.47 96.54
. 96.85
B
97.06
.
96.94
.
.
10 CONTOUR
96.3
96.77 96.97
. . .
96.85
96.82 e. 97.88
0 . .
97.900
BB 96.36 96.81 96.87
.
N3017760 96.34 96.25
96.40
.
. . B
96.94
. 96.90
96.58 . 96.33 . B
96.70 96.77 . 96.81
. 96.75 96.39 97.04
. . B
. 96.69
. 98.07
96.4000 96.58
.
. 97.85
.
96.60
.
96.51
.
96.43
.
.
. 96.96
.
11 CONTOUR LEVEL 99.467
97.92 96.41 96.68 96.89
96.33
96
. 96.29 . B .
. . 96.25 96.27
. .
.40
96.49 97.36 97.34
96.34 96.74
96.46 96.43 96.75 96.22 96.31 . 96.58 .B .
96.18 . 96.48 B
. 96.29 . .
N3017740 B . .
96
00
.
12
PEEPAL
96.70 . .
96.48
B . 96 96.34
.8
96.96
.
TREE MANGO
. . 96.33
96.29 96.23 96.51 B
. . . . .4 00 96.75
96.74
96.53 96.79 96.46 96.41
0 96.54 .
000
. 96.54
7
. . . 96.24 96.18 .
96.36 .
. 97.19
13
.46
96.66 96.29 . .
96.45
B .
96.24
96.65
.
. 96.53
B
97.11 HT
HT
97.12
SPOT LEVEL
99
96.33 .
N3017720 .
. 96.48 96.27
. 96.25 96.50
B
97.04 HT
96.63
b
96.20
.
96.37
.
.
96.72
.
96.36
.
96.27
.
.
96.30
. 96.19
.
96.32
.
96.35
96.44
.
96.57
96.58
B
HT
PYLON
96.55
.
96.53
.
96.07
.
96.42 96.24
. 96.45
96.43
. 96.54
.
14 BANC H MARCK
96.12 . . 96.39
0
96.27 B
.
96.3000
96.34 . 96.44
96.500
INE
. . 96.26 .
. 95.01 96.42
N3017700 96.23 96.60 . 96.26
B
96.77 . .
96
. .
15 CULVERT
NL
b .
96.69
. 96.60
96.26
EP .30
000
SSIO
.
96.40
.
96.05
. 96.30
96.18
. 00 96.38
96.2
. 96.29 B
96.4000
SMI
96.21
. .
96.55
96.5000
96.50
. 96.29 96.16 96.34
96.46
.
b
96.20 96.66 . . B
N
TRA
.
96.63
.
96.41
.
.
96.75
.
96.77 96.39
96.21
.
96.31
.
16 PYLON
N3017680 . .
96.19
.
96.25
. 96.20
B
96.16
96.40 96.51 .
96.33 96.56 . .
96.51
. EP
96.300
b 96.25
0
96.66 .
17
00
. 96.14
.
96.41 96.20
96.23
. 96.16
ELECTRIC LINE
.2
. . .
96
96.08 . . .
96.42 . 96.18 .
96.17 96.15 .
b 96.38 96.72 . 96.16
.
N3017660 96.62
. . B
b 96.73
EP
96.78
.
96.68
.
96.43
.
96.29
.
96.16
. 18 SURVEY DATE 25/3/2023
96.25
96.56 .
96.49 96.45
. . 96.23 96.13
. 96.14 96.21
96.18 . . .
. B
96.13
.
N3017640
96.74
b
96.46
.
96.51
. 96.60
96.75
96.42
.
96.16
.
96.37
.
96.18
.
96.14
.
IMPLEMENTATION AGENCY
.
.
96.11
96.4
96.77 96.45 .
96.12
b . 96.25
.
96.68
96.21 . 96.3 B
000 0
000
96.55 96.27 .
. 96.63
96.64
96.20
. 96.25
00 96.16
96.47 96.56
96.43
96.53 EP
ep . 96.09 .
96.28 .2 .
96
ep/ 96.05 HT 96.33
. .
N3017620 EP
HT . ; 9
-I
96.07
0
WAPCOS Ltd.
96.41 96.14 96.10 .
.
. 96.40
.
00 96.11
HT
0
.30 1
:2
HT
96.35
.
96.39
96.34 96 PYLON 96.06 96.11
96.07
B 96.05
96.06
96.00
00
96.21 96.15
96.14 . .
96.37 .
B .
. .
. 96.34
B
8
96.16
8
96.45 96.22
00
96.23
. B . .
96.18
N3017600
MIN
96.22 B 96.18
.
:2
. 96.07
96.16
01
B
.
TN
RI
96.11
.
0
( A GOVERNMENT OF INDIA UNDERTAKING )
A
A-
96.26
96.10
.
96.37
96.19
.
96.08
96.2000
96.06
I ; ISO9
WAPCOS
. 96.11 . 96.21
ep .
. 96.23 .
96.14 96.19
B . .
96.1000
N3017580 96.05
.
96.09
B
96.18
. 96.17
96.020.
96.17 96.41
96.25 96.06 96.08 .
96.04
CLIENT:
. 96.14
96.20 . B
96.15 ep 96.25 . 96.14
96.20EP
ep .
. ep 96.22 96.11 96.09
B
96.17
96.16
B
ep
96.29
96.60
.
95.880 96.11
.
96.02
.
B
EP
ep 96.00
00
N3017560 96.36
ep
.
.20
96.05 96.33
96
. .
96.24 96.07
.
96.14
.
96.09
. 96.03
.
96.07
B
96.17
96.24 96.13
96
ep
EP . B
96.16
96.28
.30
/EP
B 96.13
.
N3017540 96.28 96.13
00
. . 96.28 96.02
96.04 .
.
B
96.21 96.01
B . 96.08
96.25 95.94 .
. .
96.14
96.10
ep
EP
95.98
96.05
96.10
.
. 96.0
000
NE
96.03
N3017520 B 95.97
B
N LI
96.02 96.07 .
PROJECT:
. . 95.90 95.97
PYLON O 96.1000
. .
IS S I
96.12 95.94
B 95.96 B 96.02
96.03 95.98
95.93 ep
EP 96.07
B B B
96.19 .
NSM
. 96.04
B 95.74
96.07
T RA
95.88 . 95.90
96.04 B 95.85
96.00 B B
B 96.01 B
N3017500 B
96.11
B
96.19
.
95.96
B 95.85
.
95.83
B
95.84
. B
95.95 CONSTRUCTION & DEVELOPMENT OF INFRASTRUCTURE
B 95.95 95.98
95.85 95.96 95.91 95.86 . .
. 96.02 B
95.78
N3017480 .
LEGEND
YLO
N
6M
S. NO. NAME SYMBOLS
P WI
DE
D R 1
OA
OA
D FENCING
R
E
TRAN ID
SMISS W 2
ION L
INE 6M BOUNDARY WALL
3 BUILDINGS
PY
LO 4 HAND PUMP
N
12 5 ELECTRIC POLE
24 174
4 73.1325'
128.2570'
27 6 CANAL
11
9M
12 D 7 PAINTED ROAD
W
OA 11
ID
R
DE 8
E
I
RO
W 11 ON 8 EARTHEN ROAD
9M
AD
L
PY
11
9 PLANTATION
13
10 CONTOUR
22
OAD
11 CONTOUR LEVEL 99.467
I DE R
29
17 5
6MW
12
PEEPAL
TREE MANGO
CANAL 9M
9 196.5665'
W 13
67
ID SPOT LEVEL
.4
E
99
9M
RO
AD
W
14 AD
ID
RO 14 BANC H MARCK
E
15 DE
RO
I
A
W
D
1 2M 15 CULVERT
51.6943'
NEW EXISTING
PARKING 16 PYLON
AD
BULDING
RO
E
ID NEW EXISTING 12
W BULDING
7 20 17 ELECTRIC LINE
9M 9M 2 3
9 M WIDE ROAD
47.1039'
19 W NEW EXISTING
ID
BULDING
1 NO. BLOCK AUTHORIZED PROPOSED TOTAL NO. OF
E NAME PLINTH AREA PLINTH AREA FLOORS
RO 9M
18 AD W
ID D 21 21 ADMIN 1398SQ.M. 1398SQ.M. G+1
E A
9M
D
1
RO RO OA
12
AD 46.6442'
E OFFICES 1082SQ.M. 1082SQ.M. G+1
W
R
ID
M
ID
E
W
ID
W
E
18 M 67.1180'
49.2796' 49.9865'
15.3812' 2 STORES 712SQ.M. 0.0SQ.M. G+1
ID
R
W
12
12.5512'
OA
6
E
9M
83.0403'
D
RO
43.3699'
3 QUARTER 527SQ.M. 0.0SQ.M. GROUND
AD
192.0240'
9 M WIDE ROAD GUARD FLOOR
58.6749'
155.0317'
12 M WIDE ROAD
4 TRADESMAN 131SQ.M. 0.0SQ.M. GROUND
SHOP FLOOR
23.9091'
16
AD IC LINE 5 MT GARAGE 606SQ.M. 0.0SQ.M. GROUND
RO ELECTR
18 M WIDE ROAD
IC LINE W 23
ELECTR
9 M WIDE ROAD
9M 23
7 SERVICE COY 327SQ.M. 0.0SQ.M. GROUND
W
10
ID
O
NG
MA
103.3462' O
NG
90.0387'
MA
E
27.9316'
O
NG
MAGAZINE FLOOR
MA
86.8204'
AD
6 M WIDE ROAD
31 11 TRAINING SHED 371SQ.M. 0.0SQ.M. GROUND
31
12 180 MEN / WOMEN 6267SQ.M. 2228SQ.M. G+4(128
NE BARRACK MEN
ELE CTRIC LI PHASE-1)
13 DOG KENNEL & 284SQ.M. 0.0SQ.M. GROUND
PHARMACY (5 FLOOR
DOGS)
RAMP
UP
GAS BANK
COURTYARD
12210 X 4500
LVL.±450
ROOM ROOM
3000X4000 3000X5660
KITCHEN
9660 X 5770
4485X2885
COUNTER
SERVING
DINNING HALL
14770 X 7000
DRINKING WATER &
PLATE WASH
5770X3000
CORRIDOR
OPEN
SHAFT SHAFT
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
NO. OF RISER=22
TREAD =300
WIDE =1500
BATH BATH BATH BATH BATH BATH BATH BATH
RISER=150
TABLE
1200X1500 1200X1500 1200X1500 1200X1500 1200X1500 1200X1500 1200X1500 1200X1500
TABLE
TABLE
ROOM ROOM
TABLE
TABLE
TABLE
TABLE
TABLE
3600X3335 3600X3335
RAILING
RAILING
UP
UP
UP
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
1500 MM WIDE 1500 MM WIDE BARRACK SPACE FOR 22 PERSONS 1500 MM WIDE 1500 MM WIDE BARRACK SPACE FOR 22 PERSONS 1500 MM WIDE 1500 MM WIDE
CORRIDOR CORRIDOR 22175 X 8100 CORRIDOR CORRIDOR 22175 X 8100 CORRIDOR CORRIDOR
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
WATER WATER
COOLER COOLER
DRYING AREA ENTRANCE AREA DRYING AREA
2870X2076 6200X4950 2870X2076
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
W.C. W.C. W.C. W.C. W.M W.M W.C. W.C. W.C. W.C.
1200X1500 1200X1500 1200X1500 1200X1500 1200X1500 1200X1500 1200X1500 1200X1500
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
RAILING RAILING
SHAFT SHAFT
UP
TABLE
TABLE
CABINET
CABINET
1500 MM WIDE
CORRIDOR TERRACE
CABINET
CABINET
CABINET
TABLE
TABLE
TABLE
CABINET
CABINET
CABINET
RECREATION ROOM
15000 X 7000
CORRIDOR
2000 WIDE
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
DN
DN
DN
NO. OF RISER=22
NO. OF RISER=22
TREAD =300
TREAD =300
WIDE =1500
WIDE =1500
RISER=150
TABLE
1200X1500 1200X1500 1200X1500 1200X1500 ROOM ROOM 1200X1500 1200X1500 1200X1500 1200X1500
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
3600X3335 3600X3335
RAILING RAILING
UP
UP
UP
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
1500 MM WIDE 1500 MM WIDE BARRACK SPACE FOR 21 PERSONS 1500 MM WIDE 1500 MM WIDE BARRACK SPACE FOR 21 PERSONS 1500 MM WIDE 1500 MM WIDE
CORRIDOR 22175 X 8100 1800 MM WIDE 22175 X 8100 CORRIDOR
CORRIDOR CORRIDOR CORRIDOR CORRIDOR
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
DRYING AREA
ROOM ROOM 2870X2076
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
W.C. W.C. W.C. W.C. DRYING AREA W.M W.C. W.C. W.C. W.C.
W.M 3600X3335 3600X3335
1200X1500 1200X1500 1200X1500 1200X1500 1200X1500 1200X1500 1200X1500 1200X1500
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
RAILING RAILING
SHAFT SHAFT
TERRACE
BELOW
LEGEND :-
Water Tap
Wash Basin
TERRACE
Door
Stairs
Urinal
OPEN
WC European Type
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
DN
DN
DN
WC Indian Type
NO. OF RISER=22
NO. OF RISER=22
TREAD =300
TREAD =300
WIDE =1500
WIDE =1500
RISER=150
TABLE
1200X1500 1200X1500 1200X1500 1200X1500 ROOM ROOM 1200X1500 1200X1500 1200X1500 1200X1500
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
3600X3335 3600X3335
RAILING
UP
UP
UP
CABINET
CABINET
CABINET
RAILING
CABINET
CABINET
CABINET
CABINET
CABINET
1500 MM WIDE 1500 MM WIDE BARRACK SPACE FOR 21 PERSONS 1500 MM WIDE 1500 MM WIDE BARRACK SPACE FOR 21 PERSONS 1500 MM WIDE 1500 MM WIDE 1. ALL DIMENSIONS ARE IN MM.
CORRIDOR 1800 MM WIDE
CORRIDOR 22175 X 8100 CORRIDOR CORRIDOR 22175 X 8100 CORRIDOR CORRIDOR
2. ONLY FIGURED DIMENSIONS
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
WATER
COOLER
2870 WATER
COOLER SHOULD BE FOLLOWED
2076
DRYING AREA
ROOM 2870X2076 IMPLEMENTING AGENCY:-
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
TABLE
W.C. W.C. W.C. W.C. W.M DRYING AREA W.M W.C. W.C. W.C. W.C.
1200X1500 1200X1500 1200X1500 1200X1500 3600X3335 1200X1500 1200X1500 1200X1500 1200X1500
; 90
WAPCOS Ltd.
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
CABINET
-I 01
RAILING
:2
008
RAILING
SHAFT SHAFT
( A GOVERNMENT OF INDIA UNDERTAKING )
2008
M IN
IR
TN
A
01
A
- 90
I ; ISO
WAPCOS
CLIENT:-
SECOND FLOOR PLAN
SASHASTRA SEEMA BAL
631.46 Sqm
PROJECT:-
DRAWING TITLE:-
128 MEN BARRACK
FOR TENDER PURPOSE ONLY FLOOR PLANS
OFFICE CUM ADMIN BLOCK
GROUND AREA - 913.5 SQ.M.
WC
1500X1600
RTS
FIRST FLOOR AREA - 967.2 SQ.M.
BATH
1500X1345
GUARD ROOM
6600 X 5000
3750 X 5000
ARMOUR SECOND FLOOR AREA - 606.2 SQ.M.
5660X5000
CELL
3375 X 5000 TOILET
PORCH AREA - 59.29 SQ.M.
1500X1800
TOTAL AREA - 2546.19 SQ.M.
UP
1500
+600
QUARTER GUARD
OPEN TO SKY
SERVICE
STORE 5535X5645
KOTE
6885X4145
8685 X 4145
D.W
TOILET(M)
3860X3200
UP
A.C A.C
5085X4885 5085X4885
2000 WIDE CORRIDOR
RAMP RATION UP
UP 1:10
LIFT
6 PERSON
ENTRANCE
LOBBY TOILET
W.T ELECTRICAL (F)
STORE ROOM 3860
STORE ROOM STORE ROOM
X3200
4770X5085 4885X5085 4273X6205 4297X6205
2100 WIDE
VERANDAH
D.W
UP
2000 WIDE CORRIDOR
WAPCOS Ltd.
:2
008
( A GOVERNMENT OF INDIA UNDERTAKING )
8
MI
200
NI
RA
:
TN
01
A
- 90
I ; ISO
WAPCOS
DATE SCALE TITLE:
COMMANDANT
8810X5385
ANTI
ROOM
3025X2635
WAITING
3735X3875
TOILET
3025X2635
DN D.W
TOILET(M)
3860X3200
UP
A.C(ENG.) STORE
5085X4885 6885X4235
2000 WIDE CORRIDOR
LECTURE HALL
10770x12535
COY SECOND IN
OFFICE-04 COMMANDANT
5085X4885 6885X5420
UP
COY
OFFICE-03 LIFT
5420X3000 LOBBY 6 PERSON
TOILET
(F)
3860X
DY. DY.
DN 3200
COMMANDANT COMMANDANT
4770X6885 4885X6885
COY
OFFICE-02 D.W
6000X3000
COY
OFFICE-01
5420X3000 QM AND PIONEER PL. UP DN
WRITER OFFICE
4700X5085 4885X5085
REV. DESCRIPTION DATE DRN CHK APP
PROJECT
PROJECT MANAGEMENT CONSULTANCY (PMC)
SERVICES FOR CONSTRUCTION & DEVELOPEMENT OF
INFRASTRUCTURE WORKS AT BN HQRS. SSB
SIDDARTHNAGAR (UP)
ESSTT. AND ACCOUNT
OWNER
10770X8685 DIRCTORATE GENERAL, SSB (Govt. of India, MHA)
East Block - V, R.K.Puram, New Delhi- 110066
PMC CONSULTANT
; 90
-I 01
WAPCOS Ltd.
:2
008
( A GOVERNMENT OF INDIA UNDERTAKING )
8
MI
200
NI
RA
:
TN
01
A
- 90
I ; ISO
WAPCOS
DATE SCALE TITLE:
FIRST FLOOR PLAN
DEPT: SSB OFFICE & ADMIN BLOCK
DRN BY:
CHK BY:
FIRST FLOOR PLAN
DOCUMENT ID
APP BY:
FOR TENDER PURPOSE ONLY JOB NO. REV.
OFFICE CUM ADMIN BLOCK
SECOND FLOOR AREA - 606.2 SQ.M.
TERRACE
LIBRARY
12300X5270
D.W
DN
TOILET(M)
3860X3200
UP
FEMALE RESTROOM
2000 WIDE CORRIDOR
5085X4885
EDUCATION
OFFICE
5058X9770
SCHOOL OFFICE
RECORD
5058X4770
TERRACE
WIRELESS
STATION
4300X3000 LIFT
6 PERSON
LOBBY CLASSROOM
9770X5085
TOILET
(F)
3860X
3200
DOWN
D.W
MONITORING
STATION
3210X3000
2000 WIDE CORRIDOR
TELEPHONE
REV. DESCRIPTION DATE DRN CHK APP
STATION UP DN
CLASSROOM
9770X5085
4300X3000 PROJECT
STORE ROOM PROJECT MANAGEMENT CONSULTANCY (PMC)
5270X8685 SERVICES FOR CONSTRUCTION & DEVELOPEMENT OF
INFRASTRUCTURE WORKS AT BN HQRS. SSB
SIDDARTHNAGAR (UP)
OWNER
DIRCTORATE GENERAL, SSB (Govt. of India, MHA)
East Block - V, R.K.Puram, New Delhi- 110066
PMC CONSULTANT
; 90
-I 01
WAPCOS Ltd.
:2
008
( A GOVERNMENT OF INDIA UNDERTAKING )
8
MI
200
NI
RA
:
TN
01
A
- 90
I ; ISO
WAPCOS
DATE SCALE TITLE:
C.B. C.B.
DW1 DW1
V V
TOILET TOILET
2150x1600 2150x1600
D3 D2 D3 D3 D2 D3
BALCONY UTILITY UTILITY BALCONY
D2
1200x1820 DW2 1885x1200 STAIRCASE 1885x1200 1200x1820
D2 D2
LEGEND
DW1 DW1
ENTRY UP DOWN
ENTRY
D1 D1
UNIT AREA CALCULATION FOR TYPE - III
AREA PROVIDED
S.NO. DESCRIPTION (IN SQ M)
ENTRY
ENTRY
D1 D1
D3
TOILET
D2 D3 D3 D2
TOILET
D3
NOTE:-
2150x1600 2150x1600
1. ALL DIMENSIONS ARE IN MM.
TOILET
1600x2000
TOILET
1600x2000
2. ONLY FIGURED DIMENSIONS
BED ROOM BED ROOM
V
3150x3500 3150x3500
V SHOULD BE FOLLOWED
V V
IMPLEMENTING AGENCY:-
WAPCOS Ltd.
C.B. DW1 DW1 C.B. -I
; 90
01
:2
008
BALCONY BALCONY
2445x1200 2445x1200
8
MI
( A GOVERNMENT OF INDIA UNDERTAKING )
200
NI
RA
:
TN
01
A
- 90
I ; ISO
WAPCOS
CLIENT:-
TYPE-II PROJECT:-
D3
STORE STORE
D3
1535x1365 1535x1365
V V
BED ROOM TOILET TOILET BED ROOM
1650x2400 1650x2400
3300x4000 3300x4000
TOILET TOILET
2400x1650 2400x1650
D3 D2 D3 D3 D2 D3
UTILITY UTILITY
BALCONY DW2 1985x1200 1985x1200 DW2 BALCONY
1200x4045 D2 1200x4045
D2 STAIRCASE
DW1 DW1
DRAWING DRAWING
BED ROOM &DINING &DINING BED ROOM
4000x3300 3580x5840 KITCHEN KITCHEN 3580x5840 4000x3300 LEGEND
2100x3000 2100x3000
C.B. C.B.
230MM THICK BRICK WALL
ENTRY
ENTRY
UP DOWN
D3
D3
ENTRY
ENTRY
D3
D3
UNIT AREA CALCULATION FOR TYPE - III
AREA PROVIDED
S.NO. DESCRIPTION (IN SQ M)
BED ROOM DRAWING 2100x3000 2100x3000 DRAWING BED ROOM TOTAL UNIT AREA
3 92.00
4000x3300 &DINING &DINING 4000x3300 (WITH CIRCULATION )
DW1
3580x5840 3580x5840 DW1 4 TOTAL AREA 4 UNIT 368.00
TOILET TOILET
2400x1650 2400x1650 NOTE:-
BED ROOM
3300x4000
TOILET
1650x2400
TOILET
1650x2400
BED ROOM
3300x4000
1. ALL DIMENSIONS ARE IN MM.
V V
2. ONLY FIGURED DIMENSIONS
STORE
SHOULD BE FOLLOWED
STORE 1535x1365
1535x1365
D3
D3
C.B. DW1 DW1 C.B.
BALCONY BALCONY IMPLEMENTING AGENCY:-
2445x1200 2445x1200
WAPCOS Ltd.
; 90
-I 01
:2
008
8
MI
( A GOVERNMENT OF INDIA UNDERTAKING )
200
NI
RA
:
TN
01
A
- 90
I ; ISO
WAPCOS
CLIENT:-
TYPE III
TYPICAL FLOOR PLAN (G + 3)
FOR TENDER PURPOSE ONLY
TOILET TOILET
1500 x 2000 1500 x 2000
TOILET UTILITY BALCONY UTILITY BALCONY TOILET
2250 X 1500 1800 X 2865 1800 X 2865 2250 X 1500
2650X1200
BALCONY
2650X1200
BALCONY
UP DN
BEDROOM BEDROOM
3485 x 3225 3485 x 3225
BOX BOX
1300X2060 1300X2060
BEDROOM 2 BEDROOM 2
DRAWING ROOM DRAWING ROOM
3300 X 3000 3300 X 3000
3600 X 4165 3600 X 4165
CB VERANDAH VERANDAH CB
4880X1200 4880X1200
NOTE:-
1. ALL DIMENSIONS ARE IN MM.
2. ONLY FIGURED DIMENSIONS
SHOULD BE FOLLOWED
IMPLEMENTING AGENCY:-
:2
008
AREA PROVIDED
TYPE-IV
8
MI
( A GOVERNMENT OF INDIA UNDERTAKING )
200
NI
S.NO. DESCRIPTION
RA
:
TN
01
(IN SQ M) A
- I ; ISO
90
WAPCOS
1 TOTAL UNIT AREA 134.60
(INCLUDING SERVANT ROOM AND BALCONY )
CLIENT:-
2 STAIRCASE,CIRCULATION AREA
9.33
2 UNIT (18.66)
3 TOTAL UNIT AREA
(WITH CIRCULATION ) 143.93 SASHATRA SEEMA BAL
4 TOTAL AREA 2 UNIT 287.86
PROJECT:-
NOTE: CIRCULATION AREA IS EXCLUDING SHAFTS FOR SERVICES LIKE
ELECTRICAL /FIREFIGHTING/SANITARY & VENTILATION SHAFT AS PER CLAUSE
LEGEND
1.4.8. OF REVISED PLINTH AREA NORMS, MOUD, DATED 07 AUGUST 2013
CONSTRUCTION & DEVELOPMENT OF INFRASTRUCTURE
230MM THICK BRICK WALL WORKS AT BN. HQRS. SSB
SIDDARTHNAGAR, UTTAR PRADESH
TITLE:-
115MM THICK BRICK WALL
TYPE IV
TYPICAL FLOOR PLAN (STILT + 3)
BEDROOM
3600x3900
NOTE :-
1. ALL DIMENSIONS ARE IN MM.
VERANDAH DINING HALL 2. ONLY FIGURED DIMENSIONS
1500X3585 4800X5290 SHOULD BE FOLLOWED
UP DRAWING ROOM
3840X5290 IMPLEMENTING AGENCY:-
WAPCOS Ltd.
; 90
-I 01
:2
008
GARAGE
8
MI
( A GOVERNMENT OF INDIA UNDERTAKING )
200
NI
RA
:
TN
01
3000X5400 A
- I ; ISO
90
WAPCOS
STUDY
3300X3900 CLIENT:-
VERANDAH
3400X2100 SASHATRA SEEMA BAL
BEDROOM
3270x3261 TOILET PROJECT:-
1650X CONSTRUCTION & DEVELOPMENT OF INFRASTRUCTURE
2250
WORKS AT BN. HQRS. SSB
SIDDARTHNAGAR, UTTAR PRADESH
TITLE:-
TYPE V
TYPICAL FLOOR PLAN
10 GO'S MESS
48 11 TRAINING SHED 12 M WIDE ROAD
9 M WIDE ROAD
30 13 DOG KENNEL &
20
PHARMACY (5
14
176
6M DOGS)
PYLON WI 32
3.5 M WIDE ROAD
D ER 14 CPC
AD OA
D
7 13
RO 15 FWC
E
TRAN ID PHASE 2 ROAD
SMISS W 34
16 SINGLE OFFICER
34
36
ION L
INE 6M
17 SINGLE SOS
13
BOUNDARY WALL
18 TYPE-II
48 NOS.
26
63
33
OAD
30 MEMORIAL
Ministry of Home Affairs
3.5
31 GUARD HOUSE
IDE R
M
132 35
29 CLIENT : Government of India
W
ID
9
E
17
RO
6MW
AD
11
9 EXECUTING AGENCY:
CANAL 9M
W
ID
E WAPCOS Ltd.
RO
28
AD (A GOVERNMENT OF INDIA UNDERTAKING)
14 AD
RO
76-C, Institutional Area, Sector-18
21 15 E Gurugram (Haryana), 122015
ID
W
M
22
12
17
397
PROJECT TITLE :
108 NEW EXISTING
119 BUILDING
PARKING 26
AD
18
RO 19
ID
E NEW EXISTING
BUILDING 12
5M
W
2 7 3 20 CONSTRUCTION & DEVELOPMENT
3. 94
17
NEW EXISTING
BUILDING OF INFRASTRUCTURE WORKS AT
3.5
M AD 1 BN. HQRS. SSB SIDDHARTHNAGAR,
RO
18
W
ID UTTAR PRADESH
14
AD
3.5
M
21 21
78
13
DRAWING TITLE :
9M
AD
RO
W
ID
22 24
E
34
RO
W
6
9M
AD
11
11
5
31
SHEET SIZE : DEALT BY : DRAWING NO. :
10
49
12
12 M WIDE ROAD AR.CHARU AR-MLP-01
18 48
20
39
D
16 48
DATE : CHECKED BY : NORTH :
A
RO 23-07-25 AR.ROHIT
19
E
18 M WIDE ROAD
40
ID
9M
IC LINE W
IDE RO
ELECTR
23 SCALE :
9 M WIDE ROAD
9M
43
23
W
23 20
10
ID
54
13
16
E
30 N.T.S
12 M W
RO
17 95
34
AD
15
83
54
CANAL
26 38
49
39
6 M WIDE ROAD
ARCHITECT:
37
4 31 31 6
89
MRIDUANJALI
66
15
26
12
38
88
48
57
EXIT
30
ELECTRIC LINE
ENTRY
GUARD ROOM & BOUNDARY WALL 1. DO NOT SCALE THE DRAWING, FOLLOW WRITTEN
DIMENSION ONLY.
2. ALL DIMENSIONS IN MM.
3. 750 WIDE PLINTH PROTECTION TO BE PROVIDED ALL
AROUND THE BUILDING.
4. SKIRTING SHALL BE 100MM. HIGH FROM FINISHED
FLOOR LEVEL.
5. TOILET,PANTRY, KITCHEN VERANDAH & BALCONY
FLOOR LEVEL SHALL BE 12 MM. DOWN FROM GENERAL
ROOM BELOW
800
600
SSB NAME
1700
FILLING AS PER SPEC.
600
BEAM AS PER STR.
600
600
SLAB AS PER STR.
600 600
PLAN AT 5000MM LEVEL
LVL. ±00
1 2 3 Ver. 3 2 1
UP UP
750 mm Wide
LVL. +450
LVL. ±00
In - Out D1
Guard Room
2400 X 2400
W1
W1
COLUMN BEHIND
BOUNDARY WALL AS
600
PER DETAIL
600
1700
ARCHITECTURE DRAWING
GL1 CLIENT : SASHATRA SEEMA BAL
600
GRANITE AT
WINDOW SILL LEVEL
2 WAPCOS Ltd.
200
8
M IN
2008
( A GOVERNMENT OF INDIA UNDERTAKING )
IR
:
TN
A
A - 01
90
I ; ISO
WAPCOS
50X50X6 mm. M.S. ANGLE CONCERTINA COIL 9 HORIZONTAL R.B.T. 300x150 mm.
GROUTED IN RCC COLUMN 25 ROUNDS IN 3M. SPAN REINFORCED BARBED RCC COPING
WIRE AS/SEPC. PROJECT TITLE :
CONSTRUCTION & DEVELOPMENT
OF INFRASTRUCTURE WORKS AT
BN. HQRS. SSB SIDDARTHNAGAR,
UTTAR PRADESH
DRAWING TITLE :
MAIN GATE, GUARD ROOM &
BOUNDARY WALL
SHEET SIZE : DEALT BY : DRAWING NO. :
RCC COLUMN
AR.ANUSHK AR-02
SCALE :
N.T.S
2
250 mm. THK.
BRICK WALL
RCC CLOUMN
(250X300 MM)
300X150MM.
RCC COPING MRIDUANJALI
ARCHITECTS & ENGINEERS PVT. LTD.
9900
9100
9000
450
1700
900
BRICK WALL
230
SSB NAME
SLOPING ROOF
ARCHITECTURE DRAWING
CLIENT : SASHATRA SEEMA BAL
LIGHT AT THE BOTTOM OF THE SLAB
500
600 600
1550
SSB LOGO
1450
PER SPEC. I; 90
- 01
:
WAPCOS Ltd.
200
8
M IN
2008
( A GOVERNMENT OF INDIA UNDERTAKING )
IR
:
TN
A
01
WAPCOS
SIDDHARTH NAGAR, U.P.
SSB NAME IN
LOCAL LANGUAGE
900
BOUNDARY WALL
PROJECT TITLE :
500
AS PER DETAIL.
CONSTRUCTION & DEVELOPMENT
5000
OF INFRASTRUCTURE WORKS AT
BN. HQRS. SSB SIDDARTHNAGAR,
UTTAR PRADESH
750
1200
DRAWING TITLE :
BOUNDARY WALL
3750
MAIN GATE, GUARD ROOM &
AS PER DETAIL. BOUNDARY WALL
465 465 SHEET SIZE : DEALT BY : DRAWING NO. :
2550
AR.ANUSHK AR-01
21/11/24 AR.ROHIT
SCALE :
450
N.T.S
ARCHITECT:
GRANITE AS
PER SPEC.
FRONT ELEVATION MRIDUANJALI
ARCHITECTS & ENGINEERS PVT. LTD.
FOR
CHIEF ENGINEER,
CONSTRUCTION MANAGEMENT UNIT-III,
WAPCOS LTD.
NPCC BUILDING, PLOT NO.-148, SECTOR-44,
GURUGRAM, HARYANA-122003.
MAY- 2024
ALLIED ENGINEER’S
FLAT NO.54-A, ED-BLOCK, PITAMPURA,
DELHI-110034
PH-(O) +918588963664, (M) 09350104466,
EMAIL:[email protected]
-0-
AEs
TABLE OF CONTENT
CHAPTER 1 INTRODUCTION 1
1.1 GENERAL
ANNEXURES:-
‘A’ SOIL PROFILE AND BORE LO G DATA 16-21
FIGURE:-
BORE-HOLE LAY OUT PLAN 34
GOOGLE BH LOCATION PLAN 35
SITE DRILLIMH PHO TOGRAPH 36-41
16
AEs
CHAPTER:- 1
INTRODUCTION
1.1 GENERAL
Chief Engin eer, Con st ru ction Management Unit-III, WAPCOS Ltd ., has
pro po sed to co nst ruct infrast ruct ure at S.S.B. Batt alio n Head Quart ers (Bn. H.Q.)
at Siddart h Nagar, Utt ar Pradesh. To design an effic ient and eco no mic fo u nd at io n
o f t he st ruct ure, t he knowledg e of gener al Geo t echn ical char act er ist ics, su bso i l
st rat a, it s charact er ist ics st rengt h, co mpressib ilit y and info r mat io n about
gro und wat er t able is an essent ial requirement .
Keeping above in view, Chief Engin eer, Const ru ction Management Unit-III,
WAPCOS Ltd ., has proposed to conduct a det ailed geo t echn ical invest ig at ion o f
t he pro ject sit e and ent rust ed t he work o f so il invest ig at io n to M/S ALLIED
ENGINEERS, Flat No. 54-A, ED- Block, Pitampu ra- Delhi 1100 34.
The report present s t he analys is o f t est result s and reco mmendat io n regard ing
t ype o f fou ndat io n and safe bear ing capacit y. T he o bser ved dat a o f fie ld
invest igat ion and laborat o ry t est s are present ed and u ses t o access t he nat ure o f
sub so il st rat a and t o evaluat e t he so il paramet er requ ired fo r t he desig n o f
fou ndat ion fo r d iffer ent st ruct ure.
1.2 SITE & STRUCTURE :-
The sit e o f t he pro posed st ruct ure is locat ed in S idd art h Nagar d ist r ict o f Ut t ar
Pradesh. T he pro po sed SSB head quart ers co mp lex co nt ains var ious st ruct ures
such as Admin blo ck, o ffices, st o re rooms, quart er guard, Tradesman sho p, MT
garage, hospit al bu ild ing, ser vice co y, exp lo sive magazine, SO’S. Mess, GO’S
Mess, t raining shed, 180 men and wo men barrack, dog kennel & p har macy, CPC,
FWC, single officer s room, sing le SOS, resident ial quart er ’s t yp e-II to t ype-V,
parade ground, ESS, STP, gat e ho use, bo undar y wall, baffle range, Mart yer ’s
Memor ial, UG t ank wit h pu mp ho use, Memo r ial & g uard house et c at t he pro ject
sit e. The propo sed bu ild ings consist o f st ilt /gro und flo or wit h o ne t o fo ur and six
addit io nal st orey st ruct ures wit ho ut basement . The general gro und o f t he
pro posed locat io ns is almost p lane & dressed up.
AEs
1
CHAPTER 2
SCOPE OF WORK:-
The det ailed scope o f work of geot echnical invest igat io n for t he pro ject was limit ed
to t he fo llowing.
Mo bilizat ion o f equ ipment and perso nnel t o t he pro ject sit e, set t ing u p t he
equ ipment and carr ying o ut t he field invest ig at ion and demo bilizat io n o f t he same
aft er co mp let io n of field act ivit ies.
Dr illing 6.0 Nos. of 100– 150 mm d iamet er bore ho les using shell and aug er up t o
t he dept h o f 15.0 m or up to refusal whichever occurs ear lier.
Co ndu ct ing st andard penet rat io n t est at regular int ervals o r at t he chang e o f
st rat a which ever is ear lier and also collect io n of each SPT samp le for
labo rat o ry t est .
Co llect io n of t he dist urbed and und ist ur bed so il sample at su it able int er val or at
t he chang e of t he st rat a whichever is ear lier.
Reco rd ing t he gro und wat er t able in t he bore ho le ( if o bser ved).
Co llect io n o f wat er & so il samp les fro m the bo re ho les fo r t he aggressive chemical
co nt ent s. Per fuming 2.0 no s. t est s o f chemical examinat io n o n wat er sample fo r pH,
Su lphat e, chlo r ide & t er mit es.
Per fo r ming 3.0 no s. chemical t est on so il samp les for su lp hat e, car bo nat es,
chlo r ide, nit rat e, magnesiu m, calciu m, so d iu m & po t assium
Per fo r ming chemical t est on wat er sa mp le fo r dr ink ing purpose as per relevant IS
spec ificat io ns.
.
AEs
2
Co ndu ct ing all necessar y and relevant labo rat or y t est s o n select ed so il samp le
limit ed t o fo llowing.
a) S ieve Analysis
e) Specific Gravit y
f) Vo id Rat io
Analys is o f t est result and submiss io n of report g iving all t he t est dat a alo ng
wit h so il pro file and reco mmendat io n regard ing t yp e and t he dept h of
fou nd at io ns for t he propo sed st ruct ure and sugg est ed net safe/ allo wable bear ing
capacit ies.
AEs
3
CHAPTER 3.0
FIELD INVESTIGATION:-
The t est ing equip ment and personnel fo r carr ying o ut t he requ isit e fie ld work were
mo bilized t o t he sit e. These wer e shift ed fro m one t est lo cat io n to ano t her
lo cat ion dur ing t he course of field wo rk and demobilized on sat isfact o ry
co mp let io n of t he ent ire field wo rk.
Locat ion & RL o f bore ho les wer e pro vided at t he sit e by t he concer ned Eng ineer in
charge o f t he pro ject sit e .
St andard penet rat ion t est were conduct ed in t he bo re ho le at regu lar / desired
int er vals as per IS: 2131 – 1981. The bore was cleaned up to t he desir ed dept h.
St andard split spoon sampler at t ached t o lo wer end o f ‘A’ s ize dr ill rods was
dr iven in t he bo re ho le by means o f st andard hammer o f 63.5 Kg. Falling freely
fro m a heig ht o f 75 cm. The samp ler was dr iven 45 cm and t he number o f blo ws
requir ed for t he first 15 cm. penet rat io n were no t t aken in t o acco unt . This was
co nsid ered as seat ing dr ive. T he nu mber of blo ws for last 30 cm penet rat ion were
designat ed as SPT ‘N’ value.
So il samples obt ained fro m st andard split spoo n samp ler for all abo ve st andar d
penet rat io n t est s were co llect ed in t he po lyt hene bag s o f su it able size. T hese
samples were properly sealed, labe led, recorded and carefu lly t ransport ed to t he
labo rat o ry for t est ing.
AEs
4
Undist urbed so il samples were a lso co llect ed fro m t he bo re ho les at regu lar
int er vals as per IS: 2131 – 1986 in t hin walled samp ling t ubes o f 100 m m
diamet er and 450 mm lengt h. These sampling t u bes aft er ret r ieval fro m t he bore
ho les were properly waxed and sealed at bo t h ends. These were carefully labele d
and t ransport ed to t he labo rat ory fo r t est ing.
Two no s. wat er sample each ( i.e. fo r dr ink ing purpose & chemical t est )along wit h
t hree nos. so il sa mples fro m t he bo re ho les has been co llect ed and proper ly sealed
sample sent t o t est ing laborat o ry fo r chemical examinat io n as per relevant IS
spec ificat io n.
The grou nd wat er t able in t he boreho les is generally measured aft er 2 4 ho urs o f
t he bo r ing aft er st abilizat io n. However t he sub so il wat er at t he pro ject sit e was
obser ved at 3.70 m to 4.0 m dept h belo w exist ing G. L. in t he var iou s bore ho le s
in t he mo nt h of Ap ri l-2024. The proposed project sit e is located at App rox. 8.20
KM a way from Shive River. As per lo cal enqui ry, it wa s reported th at th e
observed water table m ay further ri se up to/or above the existing g round surfa ce
during flood in River Shi ve or in rainy season du ring heavy t o very heavy rain s
in m onsoon season.
Disclaimer:- so met imes t he measured sub so il wat er t able may r ise abno r mall y
depend ing upo n heavy t o ver y heavy rainfall o r due t o lo cal recharge scheme s
such as Rain wat er har vest ing o r any o ther scheme in t he part icular area. The
abnor mal r ise in wat er t able will have imp act on t he reco mmended bear in g
capacit y hence t his po int must be int imat ed t o us if obser ved dur ing act ua l
const ruct ion act ivit y. It is also suggest ed t o re-ver ify t he su b so il wat er lev e l
before st art of const ruct io n act ivit y.
AEs
5
CHAPTER 4
LABORATORY TESTS:-
The fo llowing labo rat ory t est s were co nduct ed on select ed so il samp le
reco vered fro m t he bore ho le lo cat ion:-
a) S ieve Analysis
e) Specific Gravit y o f So il
f) Void Rat io
The abo ve laboratory t est were carr ied out as per relevant Ind ian st andard co de o f
pract ice. The result of laborat ory t est s are sho wn in bore lo g sheet 1 to 6. All t he
so il samp le were ident ified and classified a per IS: 1498 – 1970. Tri-a xial and
direct shea r tests on few sa mp les were conducted under con solidated un-
dra ined/d rain ed test condition. The pressu re app lied on these sa mp les
initially wa s 0.6 K g/cm 2 to minimi ze sa mp le loo sening du ring ext ruding. Many
sandy samples were slipped dur ing dr illin g hence t he shear t est s are per fo r med o n
t he remo uld ed as well as or iginal samp le depend ing upo n t he ext ract ion fro m t he
UDS t ube pro cured.
AEs
6
CHAPTER 5
TEST RESULTS AND INTERPRETATIONS
5.1 SOIL PRO FILE
AEs
7
d) The obser ved field SPT ‘N’ values at t his sit e var ies fro m 6 to 27 wit hin 1 5.0
m dept h. The sub so il layer s shows lo o se to med iu m dense/ st ick y nat ure o f
st rat a in ent ir e dr illing dept h.
e) No vo id s, organic mat t er et c. have been o bser ved fro m t he sample co llect ed
dur ing dr illing o perat io n in t he su b so il.
f) The part icle size gradat io n cur ve sho ws well grad ed sub so il st rat a (i.e.
Ino rganic silt y cla y/sandy silt y so il) up t o 6.0 m-9.0 dept h and 1 2.0 m-12.5 t o
15.0 m dept h below EGL. However po orly graded sub so il st rat a o f fine sand y
so il has been obser ved wit hin 6.0 m-9.0 m t o 12.0 m-12.5 m d ept h belo w EGL
in BH-1 t o BH-6. The majo r port ion o f t he so il fract io n in silt y cla ye y so i l
(almo st 90 % to 97 %) co nsist s o f part icles finer t han 75 micro n sieve siz e
(silt and cla y fract ion).
The u nifor mit y coeffic ient (Cu=D60/D10)=0.5526 to 1.334 9 and co efficient
of cur vat ures (Cc=(D 3 0 ) 2 /(D 6 0 XD 1 0 )=5.71 43 to 7.2381 o f sub so il wit hin 15.0
m dept h are wit hin r ange o f well graded as per IS 1498-1970. The grain size
analys is shows clay fract io ns var ying from Nil ( i. e. 0%) t o 13.12%, silt size s
var y fro m 18.0 % t o 81.73 %, fine sand var y fro m 2.99 % t o 78.59 % and
mediam sand sizes var y fro m 1.31% t o 3.18% respect ively.
g) As per t he seis mic zonat ion map, t he pro po sed sit e at Siddart h Nag ar in t he
dist r ict , Utt ar Pradesh is sit u at ed in seismic zo ne IV. The liquefact io n
analys is based on co -relat io ns present ed in IS 1893 (Part -I):2016 clau se 3.12
and 6.3.5.3 (Annexure F) on t he basis of SPT values shows that the sub soil
stra ta is liquefiable within 12.0 m depth below EGL in BH-1 to BH-6
location s. The liqu efaction analysis is ca rried out fo r ea rthqua ke Moment
Magnitude of 7.5, max/peak g round a cceleration of 0.24g and sub soi l
water tab le at 3.70 m to 4.0 m depth b elow EG L. The fact or o f safet y o f
liqu efact io n resist ances o f t he su b so il st rat a against shear st ress induced due
to earthquake in Sei smic Zone IV is less t han unit y wit hin 12.0 m dept h and
mo re t han u nit y beyo nd 12.0 m t o 15.0 m below EGL at t he var io u s bo re ho le
lo cat ions.
AEs
8
a) In view o f nat ure of propo sed mult ist or ied bu ild ing ( i.e. st ilt /ground flo o r wit h
one t o four and six addit io nal st o rey st ruct ures wit hout basement ) and su b so il
paramet er obt ained fro m t he bo reho les alo ng wit h liquefiable st rat a up to 12.0
m dept h belo w EGL, t he safe bear ing pressure values fo r shallow fo ot ing ( i.e.
iso lat ed square foot ing & raft fou ndat io n) is analyzed but fo und inap pro pr iat e
as per sit e cond it io n. The bo red cast in sit u p ile fou ndat io n is analyzed &
reco mmended for execut io n at t he pro ject sit e.
5.2 TYPE AND DEPTH O F FO UNDATION: -
Based on t he result s of fie ld invest igat io n, labo rat o ry t est resu lt and det ails o f
pro po sed mult ist o r ied st ruct ures ( i.e. bu ildings having st ilt /ground flo or wit h
o ne t o four and six addit io nal st orey st ruct ures wit hout basement ) and su b so il
paramet er obt ained fro m t he boreho les alo ng wit h liquefiab le st rat a up to 12.0
m dept h belo w EGL, t he allo wable bear in g capacit y is calcu lat ed for sha llo w
foo t ing ( i.e. Iso lat ed square fo o t ing & raft fo undat ion) ar e no t feasib le as per
sit e co ndit io n. The bored cast in sit u pile fo undat io n is analyzed and
present ed below.
.
AEs
9
CHAPTER-6
RECOMMENDATION
Based on field invest igat io n, laborat ory t est resu lt s, sub so il par amet er
obser ved and pro posed mult ist or ied st ruct ures ( i.e. bu ild ing s having st ilt /gro und
flo or wit h o ne t o fo ur and six add it io nal st oried st ruct ures wit hout basement ), The
bored cast in sit u pile foundat ion is analyzed & reco mmended belo w.
In view o f loo se & liquefiable st rat a up to 12.0 m d ept h be lo w EGL, t he shallo w
foo t ing ( i.e. iso lat ed squar e fo ot ing & raft found at io n) is no t feasib le fo r the
propo sed st ruct ure.
The load carrying capacit y of bored cast in situ pile is analyzed & recom m ended
for execution at site.
The sub so il wat er level at t he project sit e was o bser ved at 3.70 m to 4.0 m dept h
belo w exist ing G.L. in pre mo nsoon seaso n dur ing dr illing per io d in t he mo nt h o f
May-2024. As per local enqui ry, it was repo rted that the observed water table m a y
further rise up to/or abo ve the exi stin g ground su rface du ring flood in nearby
River or in rainy season during heavy to very heavy rain s in m onsoon sea son.
The lo ad carr ying capacit y o f bo red cast in sit u p ile fo u ndat io n is at t ached for read y
refer ence & must be adopt ed fo r t he proposed st ruct ure.
The provisio n o f Eart h quake co nsid erat ion shall be t aken as per relevant clau se o f
IS 1893-2002.
6.1 PILE FOUNDATIONS
NORMAL BORED CAS T – IN – SITU PILE FOUNDATIONS.:-
No rmal bo red cast –in-sit u RCC pile fo und at io ns fo r t he pro posed mult ist o r ied
st ruct ures ( i.e. st ilt / ground floo r wit h o ne t o four and six add it io nal st orey
st ruct ures wit hout basement ) has been analyzed & t he safe load carr ying capacit y is
det er mined in co mpress io n and uplift as per IS 2911,(Part – I/ sect io n – 2) – 1979.
The effect ive lengt h o f pile has been co nsidered belo w t he cut t o ff level. T he cut t
off level o f pile has been co nsidered at 1.0 m below exist ing gro und leve l
co nsid er ing pile cap et c depending upon st ruct ural requirement .
Normal bored cast – in – situ RCC piles having stem dia. equal to 45.0 cm to 75.0 cm of lengths
14.00 m to 20.0 m were selected.( In view of limited depth of investigation, the sub soil parameter of
15.0 m to 20.0 depth is generalized with the results of shallow depth.)
AEs
10
The value o f safe lo ad carr ying capacit ies o f p ile based o n so il pro pert ies in
co mpressio n & uplift has been t abu lat ed belo w.
AEs
12
quality of piles. These test should also be carried out by those agencies who have sufficient
experience in the area and have properly calibrated equipment.
9.Structural designer may take into account the affect of seismic loading also.
6.3 CHEMICAL ANALYSIS O F WATER AND SOIL SAMPLE.
Two nu mbers wat er & t hree number s samples has been co llect ed fro m t he bo re ho les
at d ifferent dept hs and examined fo r chemical co nt ent . The t est result s are t abu lat ed
as per fo llo wing.
SOIL CHEMICAL ANALYSIS OF SOIL SAMPLE,
PROJECT:-CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION HEAD QUARTERS
(BN. H.Q.) AT SIDDARTH NAGAR, UTTAR PRADESH.
SL LOC Depth PERMISSIBLE LIMIT
NO ATI of
ONS Samp
BH le
NO Below
EGL(
m)
Chlor Sulphat Calciu Mag Total Potassiu Sodi Nitra pH
ide as e as m (as nesiu Alkali m (as um te (as as
CL SO4% Ca) m (as nity, K) (as N2O Per
% by by Mass Mg) as Na) 3) IS
Mass (Gravim CaC 272
(Volh etric) O3 0Pt
ards 26
Meth
od)
<0.05 <0.04% Max Max Max 0.30- (0.30 (0.03 >6.
% 75 30 200 0.70 - 0- 0
Meq/10 0.70) 0.070
0g Mg/ ) %
Kg
1 BH- 1.50 0.022 0.02 37.0 12.0 85 0.44 0.37 0.048 6.81
1
2 BH- 3.00 0.020 0.018 35.0 10.0 82 0.40 0.35 0.045 6.74
3
3 BH- 4.50 0.019 0.016 34.0 8.0 78 0.38 0.33 0.041 6.67
6
AEs
13
CHEMICAL ANALYSIS OF WATER SAMPLE,
PROJECT:-CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION HEAD QUARTERS
(BN. H.Q.) AT SIDDARTH NAGAR, UTTAR PRADESH.
SL NO LOCA DEPTH pH Chloride SULPHATE MG/L
TION (M) VALUE MG/L
(BH S
No)
ACCEPEP >6 500 MG/L 400 MG/L
TING
CRITERI
A AS PE
IS 456-
2000.
1.0 BH-3 7 6.73 75.60 46.68
2.0 BH-6 9 6.52 76.80 45.10
Remark:-The chemical examination of soil and water samples was conducted as per IS
specification. It is found that water samples confirms the provision of IS:456-2000.
6.4 CHEMICAL ANALYSIS O F WATER FOR DRINK ING QUALITY
(POTABILITY):-
Desirable
S. Microbiological
Units Methods Resultes of Limits (IS
No. Parameters
Analysis 10500:2012)
Not
3
1 Total Bacterial Count cfu/ml IS 3025 Part 35:1988 Reaff. 2019 5.3x10 specified
cfu/100 Not Not
2 Coliform ml Detectable Detectable
IS: 15185:2016
cfu/100 Not Not
3 Escherichia Coli ml Detectable Detectable
Remarks:–Based on above t est ed paramet er, t he wat er samp le has been examined fo r
pot abilit y/dr ink ing qualit y as per IS 10500:2012 & t he cont ent s are wit hin Accept able
limit hence wat er is fit for dr ink ing purpo se. Ho wever it is reco mmended t o ext ract
t he wat er fro m deep well & mu st be valid at ed/ check ed fro m t he local Mu nic ip a l
aut hor it y before any do mest ic use. The wat er fro m shallow dept h will not be used fo r
dr inking purpose which is vulner able t o be cont aminat ed easily due t o ext ernal
fact or.
6.5 TERMITE TEST IN SOIL:-
Termit es are key so il biot ur bat o rs in t rop ical eco syst ems. Apart from mo und nest s
co nst ruct ed by so me ad vanced lineages, mo st of t he species use t heir faces, o ra l
secret io ns, debr is, or soil aggreg at es to prot ect t hemselves fro m predat ors and
desiccat io n when t hey go out t o fo rage.
Remark:-T he so il samp le does no t co nt ain t he t ermit es in it .
SPECIFIC GRAVITY
LIMITS gm / cm3 UCC,TXL
MAX MOISTURE
PARAMETER
MDD GM/CC/OMC %
SWELL PRESSURE
SOIL SIEVE ANALYSIS
CONTENT (%)
DISCRIPTION
VOID RATIO
COHESION (C)
DEPTH (m)
PLASTICITY
COMPRESSION
SHRINKAGE
AND
ANGLE (O)
RELATIVE
FRICTION
DENSITY
DENSITY
DENSITY
PLASTIC
CLASSIFICATION
MEDIUM
GRAVEL
COARSE
LIQUID
(KG/CM2)
INDEX
LIMIT
LIMIT
LIMIT
BULK
INDEX
FINE
DRY
1234567890
1234567890
GL 1234567890
1234567890
1234567890 Light brownish colour
1234567890
1234567890
1234567890 Inorganic sandy silt
SPT 1.50 1234567890
1234567890 10 14
1234567890 of low plasticity
1234567890
1234567890 (ML) DST
1234567890
1234567890
UDS 2.00 1234567890 Light brownish colour 0 1 1 1 97 31.86 20.63 11.23 1.80 1.57 14.91 2.67 0.40 7.5 0.70 0.105
1234567890
1234567890
1234567890 Inorganic silty clay
SPT 3.00 1234567890
1234567890 7 8
1234567890 of low plasticity
1234567890
1234567890 (CL)
1234567890
1234567890
SPT 4.50 1234567890 8 9
1234567890
1234567890
1234567890 Light brownish colour DST
UDS 5.00 1234567890
1234567890 0 1 2 25 72 1.83 1.58 15.46 2.66 0.02 28.0 0.68
1234567890 Inorganic sandy silt
1234567890
1234567890 of low plasticity
1234567890
1234567890
SPT 6.00 1234567890 (ML) 10 10
1234567890
1234567890
1234567890
1234567890
SPT 7.50 1234567890
1234567890 Light brownish colour 13 13
1234567890
1234567890 Inorganic silty clay 0.05 29.5 DST/CUT
1234567890
1234567890
UDS 8.00 1234567890 of low plasticity 1 1 1 2 95 32.41 21.15 11.26 1.86 1.57 18.42 2.67 0.75 6.5 0.70 0.098
1234567890
1234567
9.00 1234567
1234567890
1234567890
1234567890
(CL) UUT/TXL
1234567
SPT 15 14 1.45 0.0 UCT
SPT
1234567 Light/Dark
10.50 1234567 Brownish colour 17 15
1234567
11.00 1234567
Inorganic fine silty sand Remoulded DST
UDS 1234567
1234567
of non plasticity
(SP-SM)
2 1 2 75 20 1.78 1.59 12.00 2.65 0.00 31.5 0.67
12.00 1234567
SPT
1234567
1234567890
1234567890
1234567890
21 17
1234567890
1234567890
SPT 13.50 1234567890 18 15
1234567890
1234567890 Blackish colour
1234567890 0.05 30.5 DST/CUT
1234567890
1234567890 Inorganic silty clay
UDS 14.00 1234567890 2 2 1 2 93 33.65 20.15 13.50 1.92 1.55 23.68 2.67 0.90 5.5 0.72 0.091
1234567890
1234567890 of low plasticity
1234567890 UUT/TXL
SPT 15.00 1234567890
1234567890 (CL) 17 14
1234567890 1.60 0.0 UCT
1234567890
1234567890
1234567890
1234567890
15.45 1234567890
16
ALLIED ENGINEERS SOIL
SOIL INVESTIGATION FOR WATER TABLE LOCATION
BH-2
CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION HEAD QUARTERS SHEET-2
JOB NO. M-5/2024-25/3179 PROFILE
(BN. H.Q.) AT SIDDARTH NAGAR, UTTAR PRADESH.
3.70 (M) N:-28°22'18.9"
E:-77°33'18.1"
SPECIFIC GRAVITY
LIMITS gm / cm3 UCC,TXL
MAX MOISTURE
PARAMETER
MDD GM/CC/OMC %
SWELL PRESSURE
SOIL SIEVE ANALYSIS
CONTENT (%)
DISCRIPTION
VOID RATIO
COHESION (C)
DEPTH (m)
PLASTICITY
COMPRESSION
SHRINKAGE
AND
ANGLE (O)
RELATIVE
FRICTION
DENSITY
DENSITY
DENSITY
PLASTIC
CLASSIFICATION
MEDIUM
GRAVEL
COARSE
LIQUID
(KG/CM2)
INDEX
LIMIT
LIMIT
LIMIT
BULK
INDEX
FINE
DRY
1234567890
1234567890
GL 1234567890
1234567890 Light brownish colour
1234567890
1234567890 Inorganic silty clay
1234567890
1234567890
SPT 1.50 1234567890 (CL) 9 12
1234567890
1234567890
1234567890
1234567890
DST
UDS 2.00 1234567890
1234567890 Light brownish colour 0 1 2 27 70 1.78 1.61 10.65 2.66 0.02 27.5 0.65
1234567890
1234567890 Inorganic sandy silt
1234567890
1234567890
SPT 3.00 1234567890 of low plasticity 6 7
1234567890
1234567890
1234567890 (ML)
1234567890
1234567890
SPT 4.50 1234567890 7 8
1234567890
1234567890 Light brownish colour
1234567890 0.05 27.5 DST/CUT
1234567890
1234567890 Inorganic silty clay
UDS 5.00 1234567890 0 1 1 2 96 32.68 21.57 11.11 1.81 1.55 16.52 2.67 0.55 5.5 0.72 0.100
1234567890
123456789 (CL) UUT/TXL
123456789
123456789
SPT 6.00 123456789 Light brownish colour 10 11 1.00 0.0 UCT
123456789
123456789 Inorganic sandy silt
1234567890
123456789
1234567890
123456789
SPT 7.50 1234567890 (ML) 12 12
1234567890
1234567890
1234567890 Light brownish colour 0.05 28.5 DST/CUT
1234567890
1234567890
UDS 8.00 1234567890 Inorganic silty clay 2 2 1 2 93 31.96 20.10 11.86 1.85 1.57 17.96 2.67 0.80 5.0 0.70 0.095
1234567890
1234567890 of low plasticity
SPT 9.00
123456
1234567890
1234567890
123456
1234567890 (CL) 17 16 1.55 0.0
UUT/TXL
UCT
123456
123456 Light/Dark
SPT 10.50 123456
123456 Brownish colour
20 17
Remoulded
123456
DST
Inorganic fine silty sand
UDS 11.00
123456
123456
of non plasticity
2 1 2 76 19 1.80 1.60 12.50 2.65 0.00 32.5 0.66
17
ALLIED ENGINEERS SOIL INVESTIGATION FOR WATER TABLE LOCATION
SOIL CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION HEAD QUARTERS BH-3 SHEET-3
JOB NO. M-5/2024-25/3179 PROFILE 4.00 (M) N:-27°16'10.1"
(BN. H.Q.) AT SIDDARTH NAGAR, UTTAR PRADESH. E:-83°02'07.8"
SPECIFIC GRAVITY
LIMITS gm / cm3 UCC,TXL
MAX MOISTURE
PARAMETER
MDD GM/CC/OMC %
SWELL PRESSURE
SOIL SIEVE ANALYSIS
CONTENT (%)
DISCRIPTION
VOID RATIO
COHESION (C)
DEPTH (m)
PLASTICITY
COMPRESSION
SHRINKAGE
AND
ANGLE (O)
RELATIVE
FRICTION
DENSITY
DENSITY
DENSITY
PLASTIC
CLASSIFICATION
MEDIUM
GRAVEL
COARSE
LIQUID
(KG/CM2)
INDEX
LIMIT
LIMIT
LIMIT
BULK
INDEX
FINE
DRY
1234567890
1234567890
GL 1234567890
1234567890
1234567890
1234567890
1234567890
1234567890
SPT 1.50 1234567890
1234567890
8 11
1234567890
1234567890 0.04 25.5 DST/CUT
1234567890
1234567890 Light brownish colour
UDS 2.00 1234567890 0 0 1 2 97 31.75 20.25 11.50 1.77 1.54 14.75 2.67 0.38 7.0 0.73 0.096
1234567890
1234567890 Inorganic silty clay UUT/TXL
1234567890
1234567890
SPT 3.00 1234567890 of low plasticity 6 7 0.75 0.0 UCT
1234567890
1234567890 (CL)
1234567890
1234567890
SPT 4.50 1234567890
1234567890 7 8
1234567890
1234567890
1234567890 0.05 26.5 DST/CUT
1234567890
1234567890
UDS 5.00 1234567890 0 1 1 2 96 32.81 21.28 11.53 1.80 1.54 16.81 2.67 0.50 5.0 0.73 0.092
123456 1234567890
1234567890
6.00 123456
1234567890 UUT/TXL
SPT 123456
123456 Light/Dark
9 9 0.90 0.0 UCT
18
ALLIED ENGINEERS SOIL INVESTIGATION FOR WATER TABLE LOCATION
SOIL BH-4 SHEET-4
CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION HEAD QUARTERS N:-27°16'04.6"
JOB NO. M-5/2024-25/3179 PROFILE 3.80 (M)
(BN. H.Q.) AT SIDDARTH NAGAR, UTTAR PRADESH. E:- 83°02'00.8"
SPECIFIC GRAVITY
LIMITS gm / cm3 UCC,TXL
MAX MOISTURE
PARAMETER
MDD GM/CC/OMC %
SWELL PRESSURE
SOIL SIEVE ANALYSIS
CONTENT (%)
DISCRIPTION
VOID RATIO
COHESION (C)
DEPTH (m)
PLASTICITY
COMPRESSION
SHRINKAGE
AND
ANGLE (O)
RELATIVE
FRICTION
DENSITY
DENSITY
DENSITY
PLASTIC
CLASSIFICATION
MEDIUM
GRAVEL
COARSE
LIQUID
(KG/CM2)
INDEX
LIMIT
LIMIT
LIMIT
BULK
INDEX
FINE
DRY
1234567890
1234567890
GL 1234567890
1234567890
1234567890
1234567890
1234567890
1234567890
SPT 1.50 1234567890 Light brownish colour
1234567890
1234567890
8 11
1234567890 Inorganic silty clay 0.04 24.5 DST/CUT
1234567890
1234567890 of low plasticity
UDS 2.00 1234567890
1234567890 0 0 1 1 98 31.80 20.66 11.14 1.75 1.53 14.50 2.67 0.35 6.5 0.75 0.095
1234567890 (CL)
1234567890
1234567890
UUT/TXL
SPT 3.00 1234567890
1234567890 5 6
1234567890 0.70 0.0 UCT
1234567890
1234567890
1234567890
1234567890
Light brownish colour
SPT 4.50 1234567890 7 8
1234567890 Inorganic sandy silt
1234567890
1234567890 DST
1234567890 of low plasticity
UDS 5.00 1234567890
1234567890 (ML) 0 1 2 26 71 1.82 1.57 15.65 2.66 0.02 29.5 0.69
1234567890
SPT 6.00
123456
123456
1234567890
1234567890
1234567890 11 12
123456
SPT 7.50 123456
123456 12 12
123456
8.00 123456
Remoulded DST
UDS
123456
123456
Light/Dark 1 1 2 72 24 1.74 1.56 11.25 2.65 0.00 30.5 0.69
SPT
123456 of non plasticity
10.50 123456 21 17
123456 (SP-SM)
11.00 123456
Remoulded DST
UDS 123456
123456
2 1 2 74 21 1.77 1.58 12.00 2.65 0.00 31.5 0.68
19
ALLIED ENGINEERS SOIL
SOIL INVESTIGATION FOR WATER TABLE LOCATION
BH-5 SHEET-5
CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION HEAD QUARTERS N:-27°16'05.2"
JOB NO. M-5/2024-25/3179 PROFILE 4.00 (M)
(BN. H.Q.) AT SIDDARTH NAGAR, UTTAR PRADESH. E:-83°01'58.7"
SPECIFIC GRAVITY
LIMITS gm / cm3 UCC,TXL
MAX MOISTURE
PARAMETER
MDD GM/CC/OMC %
SWELL PRESSURE
SOIL SIEVE ANALYSIS
CONTENT (%)
DISCRIPTION
VOID RATIO
COHESION (C)
DEPTH (m)
PLASTICITY
COMPRESSION
SHRINKAGE
AND
ANGLE (O)
RELATIVE
FRICTION
DENSITY
DENSITY
DENSITY
PLASTIC
CLASSIFICATION
MEDIUM
GRAVEL
COARSE
LIQUID
(KG/CM2)
INDEX
LIMIT
LIMIT
LIMIT
BULK
INDEX
FINE
DRY
1234567890
1234567890
GL 1234567890
1234567890
1234567890
1234567890
1234567890
1234567890
SPT 1.50 1234567890
1234567890 7 10
1234567890
1234567890
1234567890
1234567890 Light brownish colour DST
UDS 2.00 1234567890 0 1 2 25 72 1.74 1.58 10.25 2.66 0.02 25.5 0.69
1234567890
1234567890
Inorganic sandy silt
1234567890
1234567890 of low plasticity
SPT 3.00 1234567890
1234567890 6 7
1234567890 (ML)
1234567890
1234567890
SPT 4.50 1234567890
1234567890
1234567890 6 7
1234567890
1234567890
1234567890 DST
UDS 5.00 1234567890
1234567890
1234567890 0 1 2 27 70 1.78 1.58 12.96 2.66 0.02 26.5 0.69
1234567890
SPT 6.00 123456
123456
1234567890
7 7
123456
7.50 123456
SPT
123456
123456 Light/Dark
8 8
Remoulded
8.00 123456 Brownish colour
DST
UDS
123456
123456Inorganic fine silty sand
1 1 2 74 22 1.72 1.55 11.00 2.65 0.00 29.5 0.71
SPT 9.00 123456 of non plasticity
123456 11 11
10.50 123456
(SP-SM)
SPT 123456
123456
16 15
11.00 123456
Remoulded DST
UDS
123456
123456
2 1 2 77 18 1.76 1.57 11.75 2.65 0.00 31.5 0.68
1234567890
1234567890
SPT 12.00 1234567890 19 16
1234567890
1234567890
1234567890
1234567890
SPT 13.50 1234567890
1234567890 17 15
1234567890
1234567890
1234567890 Blackish colour 0.05 30.0 DST/CUT
UDS 14.00 1234567890
1234567890 Inorganic silty clay
1234567890 2 1 1 2 94 33.41 20.18 13.23 1.93 1.56 23.85 2.67 0.95 4.5 0.71 0.090
1234567890
1234567890 of low plasticity
1234567890 UUT/TXL
SPT 15.00 1234567890
1234567890 (CL) 1.75 0.0 UCT
1234567890 21 16
1234567890
1234567890
15.45 1234567890
1234567890
20
ALLIED ENGINEERS SOIL
SOIL INVESTIGATION FOR WATER TABLE LOCATION
BH-6 SHEET-6
CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION HEAD QUARTERS N:-27°16'14.4"
JOB NO. M-5/2024-25/3179 PROFILE
(BN. H.Q.) AT SIDDARTH NAGAR, UTTAR PRADESH.
4.00 (M)
E:-83°02'19.5"
SPECIFIC GRAVITY
LIMITS gm / cm3 UCC,TXL
MAX MOISTURE
PARAMETER
MDD GM/CC/OMC %
SWELL PRESSURE
SOIL SIEVE ANALYSIS
CONTENT (%)
DISCRIPTION
VOID RATIO
COHESION (C)
DEPTH (m)
PLASTICITY
COMPRESSION
SHRINKAGE
AND
ANGLE (O)
RELATIVE
FRICTION
DENSITY
DENSITY
DENSITY
PLASTIC
CLASSIFICATION
MEDIUM
GRAVEL
COARSE
LIQUID
(KG/CM2)
INDEX
LIMIT
LIMIT
LIMIT
BULK
INDEX
FINE
DRY
123456789
123456789
GL 123456789
123456789
123456789
123456789
123456789
123456789
SPT 1.50 123456789
123456789
123456789 7 10
123456789
123456789
123456789 Light brownish colour DST
UDS 2.00 123456789
123456789 0 1 2 26 71 1.76 1.59 10.85 2.66 0.02 27.5 0.68
123456789
123456789
Inorganic sandy silt
123456789
123456789 of low plasticity
SPT 3.00 123456789 9 11
123456789
123456789 (ML)
123456789
123456789
SPT 4.50 123456789
123456789
123456789 8 9
123456789
123456789 DST
UDS 5.00 123456789
123456789
123456789 0 1 2 28 69 1.77 1.56 13.25 2.66 0.02 25.5 0.70
123456789
SPT 6.00
123456
123456789
123456789
123456
123456789
123456
123456
6 6
SPT 7.50 123456
123456
17 16
UDS 8.00 123456
123456
Light/Dark
Brownish colour 1 1 2 73 23
Remoulded
1.75 1.57 11.50 2.65 0.00 31.5
DST
0.69
123456
123456
Inorganic fine silty sand
123456
SPT 9.00 of non plasticity 19 17
SPT 10.50
123456
123456
(SP-SM)
123456
123456
19 16
Remoulded DST
UDS 11.00 123456
123456
2 1 2 76 19 1.79 1.59 12.25 2.65 0.00 32.0 0.66
123456789
123456789
SPT 12.00 123456789 26 19
123456789
123456789
123456789
123456789
SPT 13.50 123456789 23 17
123456789
123456789
123456789
123456789 Blackish colour 0.04 31.0 DST/CUT
UDS 14.00 123456789
123456789 Inorganic silty clay
123456789 2 3 2 3 90 33.91 20.60 13.31 1.95 1.57 24.48 2.67 0.80 5.5 0.70 0.092
123456789
123456789 of low plasticity UUT/TXL
SPT 15.00 123456789
123456789
123456789 (CL) 27 19 1.55 0.0 UCT
123456789
123456789
123456789
123456789
15.45
21
STANDARD PENETRATION TEST
N VALUES (I.E. NO OF BLOWS PER 30.0
25.0
20.0
CM PENETRATION)
15.0
10.0
5.0
0.0
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0
DEPTH (M)SPT (BH-1),
PROJECT:-CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION HEAD
QUARTERS (BN. H.Q.) AT SIDDARTH NAGAR, UTTAR PRADESH.(OBESRVED
VALUES, ▲ CORRECTED VALUES)
25.0
30.0 CM PENETRATION)
20.0
15.0
10.0
5.0
0.0
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0
25.0
20.0
CM PENETRATION)
15.0
10.0
5.0
0.0
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0
25.0
30.0 CM PENETRATION)
20.0
15.0
10.0
5.0
0.0
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0
25.0
20.0
CM PENETRATION)
15.0
10.0
5.0
0.0
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0
30.0
25.0
CM PENETRATION)
20.0
15.0
10.0
5.0
0.0
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0
DEPTH (M)SPT (BH-6),
PROJECT:-CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION HEAD
QUARTERS (BN. H.Q.) AT SIDDARTH NAGAR, UTTAR PRADESH.(● OBESRVED
VALUES, ▲ CORRECTED VALUES)
GRAIN SIZE DISTRIBUTION CURVE
Client CHIEF ENGINEER, CONSTRUCTION MANAGEMENT UNIT-III, WAPCOS LTD.
CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION HEAD QUARTERS (BN. H.Q.) AT SIDDARTH NAGAR, UTTAR
Project PRADESH.
Location Date 18/6/2024
BH. NO. 1 DEPTH IN (M) 5.00 M-5.30 M IS:2720 (PT-4)1985
RANGE Clay (µ) Silt (µ) Fine Sand (µ) Mediam CoarseSand Gravel Cobbel Boulder
Sand (mm) (mm)
0.001 <0.002 <0.075 <0.425 <2.0 >2 >4.75 >75 >300
CLAY % 2 SILT% 70 SAND% 28 GRAVEL% 0
100
90
80
70
Percentage Passing
60
50
40
30
20
10
0
0.000 0.001 0.010 0.100 1.000
100
90
80
70
Percentage Passing
60
50
40
30
20
10
0
0.000 0.001 0.010 0.100 1.000
100
90
80
70
Percentage Passing
60
50
40
30
20
10
0
0.000 0.001 0.010 0.100 1.000
0.51 1.29 0.02 0.46 0.26 -1.68 0.1860 7.50 0.240 -0.066 0.008 0.993 1.000 0.155 1.201 Non-Liquefiable
0.56 0.98 0.01 0.20 0.09 -1.92 0.1461 7.50 0.240 -0.152 0.017 0.979 1.000 0.153 0.957 Liquefiable
0.57 0.92 0.01 0.17 0.07 -1.96 0.1402 7.50 0.240 -0.252 0.029 0.963 1.000 0.183 0.766 Liquefiable
0.57 0.96 0.01 0.19 0.08 -1.94 0.1440 7.50 0.240 -0.364 0.041 0.945 1.000 0.203 0.711 Liquefiable
0.56 0.96 0.01 0.19 0.08 -1.93 0.1447 7.50 0.240 -0.487 0.055 0.926 1.000 0.215 0.672 Liquefiable
0.53 1.13 0.02 0.31 0.15 -1.81 0.1640 7.50 0.240 -0.618 0.069 0.906 1.000 0.224 0.731 Liquefiable
0.49 1.41 0.03 0.60 0.38 -1.58 0.2050 7.50 0.240 -0.756 0.084 0.885 1.000 0.232 0.882 Liquefiable
0.47 1.60 0.03 0.88 0.63 -1.41 0.2430 7.50 0.240 -0.898 0.100 0.863 1.000 0.238 1.022 Non-Liquefiable
0.49 1.43 0.03 0.62 0.39 -1.57 0.2071 7.50 0.240 -1.042 0.116 0.840 1.000 0.240 0.862 Non-Liquefiable
0.46 1.62 0.03 0.91 0.66 -1.40 0.2475 7.50 0.240 -1.185 0.131 0.818 1.000 0.241 1.025 Non-Liquefiable
LIQUIFACTION POTENTIAL OF SUB SOIL STRATA
PROJECT:-CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION HEAD QUARTERS (BN. H.Q.) AT SIDDARTH NAGAR, UTTAR
PRADESH.(MOMENT MAGNITUDE 7.50, MAX GROUND ACCELARATION 0.240 g)
16.00
14.00
DEPTH BELOW GL (M) ,(SPT-1)
12.00
10.00
8.00
6.00
4.00
2.00
0.00
0.0 1.0 2.0 3.0
FACTOR OF SAFETY (I.E. RATIO OF LIQUFACTION RESISTANCES OF THE SUB SOIL STARTA TO
SHEAR STRESS INDUCES DUE TO EARTHQUAKE)
PROJECT:-CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION HEAD QUARTERS (BN. H.Q.) AT SIDDARTH NAGAR, UTTAR PRADESH.
CONSOLIDATION TEST
PROJECT:-CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION HEAD QUARTERS (BN.
H.Q.) AT SIDDARTH NAGAR, UTTAR PRADESH.
Location BH-5 Depth: 14.00 m
Ht of The Sample = 2.0 cm Diameter of the sample = 6.0 cm
Initial Void Ratio 0.72
Applied Pressure Void Ratio (e)
Kg/cm2
0.05 0.7200 Cc 0.090
0.10 0.7000
0.20 0.6950
0.40 0.6870
0.80 0.6740
1.60 0.6500
3.20 0.6230
6.40 0.5955
e-Log-p Curve
0.80
0.70
VOID RATIO(E)
0.60
0.50
0.01 0.10 1.00 10.00
LOG P (Kg/cm2) BH-5, DEPTH-14.00 M
SEMI LOG PLOT OF PRESSURE VOID RATIO RELATIONSHIP
PROJECT:-CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION HEAD QUARTERS
(BN. H.Q.) AT SIDDARTH NAGAR, UTTAR PRADESH.
PROJECT:-CONST. OF BH-1 DEPTH-
INFRASTRUCTURE AT S.S.B. 14.00 M DIRECT SHEAR TEST
BATTALION HEAD 1.40
y = 0.579x + 0.049
SIDDARTH NAGAR, UTTAR 1.00 R² = 0.997
PRADESH. 0.80
Normal Proving shear Angle of Cohesion (c ) 0.60
stressσ ring stress shear Kg/cm2 0.40
Kg/cm2 divisions kg/cm2 (phi) 0.20
0.5 23 0.32
0.00
1.0 46 0.64 30.00 0.05 0 0.5 1 1.5 2
1.5 67 0.94 NORMAL STRESS (Kg/cm2) BH-5, DEPTH-14.00 M
PROJECT:-CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION HEAD
2.0 85 1.19
QUARTERS (BN. H.Q.) AT SIDDARTH NAGAR, UTTAR PRADESH.
PROJECT:-CONST. OF MODIFIED FAILURE BH-1 DEPTH-
TRIAXIAL SHEAR TEST (UU)
INFRASTRUCTURE AT ENVELOPE 14.00 M
1.24
S.S.B. BATTALION
1.22
HEAD QUARTERS (BN.
H.Q.) AT SIDDARTH 1.20
NAGAR, UTTAR 1.18 y = 0.098x + 0.899
PRADESH. 1.16
1.14
(σ1-σ3)/2
Cell Deviator Deviato (σ1+σ3 (σ1- Tan d'=c'( Angle of Cohesion 1.12
Pressur Stress r Stress )/2 σ3)/2 ψ'=(Sin CosØ' shear (c'=d'/Co 1.10
e σ3 divisions σd (σ1- Ø') ) (Ø'=Sin- sØ' ) 1.08
Kg/cm2 σd(σ1- σ3)kg/c 1(Tanψ' Kg/cm2 1.06
σ3) m2 ) 1.04
0.5 70.0 2.10 1.55 1.05 0.00 1.00 2.00 3.00 4.00
1.0 74.0 2.22 2.11 1.11 0.0958 0.896 5.50 0.90 (σ1+σ3)/2 BH-1, DEPTH-14.00 M
PROJECT:-CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION
2.0 81.0 2.43 3.22 1.22 HEAD QUARTERS (BN. H.Q.) AT SIDDARTH NAGAR, UTTAR
PRADESH.
+
PROJECT:-CONST. OF MODIFIED FAILURE BH-3 DEPTH- TRIAXIAL SHEAR TEST (UU)
INFRASTRUCTURE AT ENVELOPE 2.00 M 0.80
S.S.B. BATTALION
0.70
HEAD QUARTERS (BN.
H.Q.) AT SIDDARTH 0.60
NAGAR, UTTAR 0.50
PRADESH. y = 0.122x + 0.375
0.40
(σ1-σ3)/2
1.14
1.12
Cell Deviator Deviato (σ1+σ3 (σ1- Tan d'=c'( Angle of Cohesion 1.10
Pressur Stress r Stress )/2 σ3)/2 ψ'=(Sin CosØ' shear (c'=d'/Co
e σ3 divisions σd (σ1- Ø') ) (Ø'=Sin- sØ' ) 1.08
Kg/cm2 σd(σ1- σ3)kg/c 1(Tanψ' Kg/cm2 1.06
σ3) m2 ) 0.00 1.00 2.00 3.00 4.00
0.5 72.0 2.16 1.58 1.08 (σ1+σ3)/2 BH-5, DEPTH-14.00 M
PROJECT:-CONST. OF INFRASTRUCTURE AT S.S.B. BATTALION
1.0 75.0 2.25 2.13 1.13 0.078 0.947 4.50 0.95 HEAD QUARTERS (BN. H.Q.) AT SIDDARTH NAGAR, UTTAR
2.43 3.22 1.22 PRADESH.
2.0 81.0
PROJECT NAME : CONST. OF INFRASTRUTURE AT SASHASTRA SEEMA BAL Legend
➤
N
Image © 2024 Airbus 1000 ft
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Volume-II
FINANCIAL PROPOSAL
WAPCOS LIMITED
CONSTRUCTION MANAGEMENT UNIT- III
1st Floor, NPCC, BUILDING, PLOT NO. 148,
SECTOR-44, GURUGRAM-122003, HARYANA
August 2025
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
TABLE OF CONTENT
SECTION – X
FINANCIAL PROPOSAL
Letter of Transmittal for Financial Bid
Total Cost of Works
Terms of Payment
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Sub: Financial Bid for the work ----- (Name of Work /Project)
Dear Sir,
With reference to this NIT document, I/we, having examined the Bidding Documents and
understood their contents, hereby submit my/our Bid for the aforesaid Project. The Bid is
unconditional and unqualified.
1. I / We acknowledge that the WAPCOS will be relying on the information provided in the
BID and the documents accompanying the BID for selection of the Contractor for the
aforesaid Project, and we certify that all information provided in the Bid are true and
correct; nothing has been omitted which renders such information misleading; and all
documents accompanying the BID are true copies of their respective originals.
2. The BID percentage rate / price has been quoted by me / us after taking into consideration
all the terms and conditions stated in the NIT, format of Contract Agreement, our own
estimates of costs and after a careful assessment of the site and all own the conditions
that may affect the project cost and implementation of the project.
3. I/ We acknowledge the right of the Authority to reject our BID without assigning any reason
or otherwise and hereby waive, to the fullest extent permitted by applicable law, our right
to challenge the same on any account whatsoever.
4. In the event of my/ our being declared as the Selected Bidder, I/we agree to enter into a
Agreement in accordance with the format of Contract Agreement. We agree not to seek
any changes in the aforesaid format of Contract Agreement and agree to abide by the
same.
5. I / We shall keep this offer valid as period specified in the NIT.
6. I / We hereby submit our FINANCIAL BID and offer Price excluding GST as filled in BoQ
excel sheet “BoQ1” for undertaking the aforesaid Project in accordance with the Bidding
Documents and the Agreement.
Yours faithfully,
SUMMARY OF COST
Sl. No.
Total Quoted Cost
Description
(Rs.)
Note:-
The Performa for filling the rate is given in Microsoft excel sheet. Bidder shall fill the
rate only up to two decimal places in soft format. The bidder will upload same filled
rate quote in soft Microsoft Excel copy during uploading of financial bid.
The Bidder shall quote rate up to two decimal only in bill of quantity of tender.
Prices quoted by the Bidder shall include all Materials, Tools & Plant, labour, supervision,
profit; other levies together with all general risks, liabilities and obligations set out or implied
in the contract, applicable Labour Cess, cost of insurance to this contract, all applicable tax
liabilities like Income Tax & Surcharges, etc. Any other taxes /cess as per Government
directives shall be deducted from each bill paid to the Contractor, from time to time. GST
shall be payable extra as per prevailing rates.It is mandatory to bidders to deposit GST within
time limit framed by Govt. of India, if applicable. The Goods and Services Tax (GST) shall
be reimbursed to the Agency only after uploading of bills by Contractor on GST Portal to
avail Input benefit of GST
The Contractor shall issue Tax Invoices to the Employer showing (i) Basic amount (ii) GST
amount separately in each bill. It is mandatory to bidders to deposit GST within time limit
framed by Govt. of India, if applicable. The Goods and Services Tax (GST) shall be
reimbursed to the Agency only after uploading of bills by Contractor on GST Portal “to avail
Input benefit of GST”.
The company shall be performing all its duties of deduction TDS and other deduction on
payment made to the contractor as per applicable legislation in force on the date of
submission of bid or to be newly / amended introduced during the execution of the Contract.
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
Terms of Payment
TENDER NO: WAP/CMU-III/2025-26/SSB/Siddarthnagar/11
TERMS OF PAYMENT
The Stage wise payments shall be made in Percentage of the Agreed Cost of works as quoted by
the bidder/contractor. The “STAGE OF CONSTRUCTION” for each component shall be as per the
details below. The Payment will be made after completion of particular “STAGE OF
CONSTRUCTION” in all respect as per the detail in Section of Scope of Work in compliance of all
the conditions mentioned in the Tender Document.
It is mandatory that contractor shall submit stage wise bills along with the Test Reports of the
materials used in the works and the photographs of the complete stage of construction as well as
periodically photographs taken during execution. The photographs shall be taken from the Digital
camera showing the date and time on the photograph, nothing extra shall be payable to the agency
on this account. The frequency of Test of materials will be as per the standard norms and conditions
in tender document.
The works mentioned in column no. 2 of Stage of Construction, are milestone for progress of work
and payment purpose only. The main scope of work for each component shall be governed as
detailed in “SECTION: ‐ SCOPE OF WORK” of the tender document and final payment shall be
made accordingly to the Contractor.
If any works mentioned in column no. 2 of Stage of Construction do not execute or is executed
partially due to any reason, then the payment will be deducted on pro‐rata basis over % mentioned
and in column no.3 for particular stage of construction.
The final 100% payment depicts the total cost of work as per the scope of work and in compliance
with all conditions mentioned in tender document.
CONSTRUCTION & DEVELOPMENT OF INFRASTRUCTURE WORKS AT BATTALION
HEADQUARTERS SSB, SIDDARTHNAGAR, UTTAR PRADESH ON EPC MODE-I
PAYMENT SCHEDULES
Percentage of
S.No. DESCRIPTION
Quoted Cost
1 Architectural and Structural Drawings 1.00%
2 Construction of Admin Block/Training Block and Offices (G+2) 19.00%
3 Construction of 01 No. 128 Men Barrack (G+2) 14.00%
4 Construction of Residential Quarters Type-II/48 Nos. (3 Blocks) (G+3) 22.00%
5 Construction of Residential Quarters Type-III/16 Nos. (1 Block) (G+3) 8.00%
6 Construction of Residential Quarters Type-IV/6 Nos.(1 Block) (S+3) 5.00%
7 Construction of Residential Quarters Type-V/2 Nos. (2 Blocks) (G) 3.00%
8 Construction of Boundary Wall, Gate and Guard Room 5.00%
9 Site Development Works 11.00%
10 Construction of Sewage Treatment Plant 2.00%
11 External Electrical Works 3.50%
12 Construction of Water Tank and Pump Room 1.00%
13 Issuance of NOCs by all relevant Local Bodies and GRIHA Certificate 1.50%
Handing over of the project with full satisfaction of Engineer in-charge and
14 4.00%
submission of completion certificate, provided by the Engineer-in-charge
GRAND TOTAL 100.00%
PAYMENT SCHEDULE No. 1
ARCHITECTURAL AND STRUCTURAL DRAWINGS
S.No. Stages of Construction Percentage Breakup
1.0 ARCHITECTURAL AND STRUCTURAL DRAWINGS
On submission & Approval of Geo-Technical and Topographical Survey
1.1 0.15%
Report
On submission & Approval of Draft Layout Plans, Floor Plans and 3D
1.2 0.15%
Views of the Building (Soft and 3 Hard copies)
On submission & Approval of Final Layout Plan of the Project (Soft and 4
1.3 0.10%
Hard copies)
On submission & Approval of Final Floor plans of Buildings, Detail
1.4 Architectural Drawings including 3D view from each side, Sectional 0.15%
elevation etc. (Soft and 4 Hard copies)
On submission & Approval of Detailed Civil, Electrical and plumbing work
1.5 Specification of each component of the Building, External development & 0.10%
other works involved in the project. (Soft and 4 Hard copies)
1.6 On registration of Project with GRIHA for 3 Star GRIHA Certification 0.10%
On submission & Approval of IIT vetted Final Structural design and
1.7 0.10%
drawings (Soft and 7 Hard copies)
1.8 On Submission & Approval of as built drawings. 0.15%
GRAND TOTAL 1.00%
PAYMENT SCHEDULE No. 2
CONSTRUCTION OF ADMIN BLOCK/TRAINING BLOCK AND OFFICES
Percentage
S.No. Stages of Construction
Breakup
1.0 CIVIL WORKS
On Completion of Site Clearance / Jungle Clearance, Filling and levelling
1.1 2.50%
of site as per Scope of Work
On Completion of RCC Piles, RCC Pile Cap and Pile Load Test as per
1.2 5.00%
Scope of Work
1.3 On completion of all works upto Plinth level as per Scope of Work 2.50%
On casting of columns in Ground Floor & allied works of Building as per
1.4 2.00%
Scope of Work
On casting of Ground Floor Beams and Slab & allied works of Building as
1.5 3.00%
per Scope of Work
On casting of columns in First Floor & allied works of Building as per
1.6 2.00%
Scope of Work
On casting of First Floor Beams and Slab & allied works of Building as per
1.7 3.00%
Scope of Work
On casting of columns in Second Floor & allied works of Building as per
1.8 2.00%
Scope of Work
On casting of Second Floor Roof Beams and Slab & allied works of
1.9 3.00%
Building as per Scope of Work
On casting of columns upto Mumty & parapet wall and allied works of
1.10 1.50%
Building as per Scope of Work
On casting of Mumty Roof Beams and Slab & allied works of Building as
1.11 1.00%
per Scope of Work
On completion brick work of Ground floor along with provision of lintel etc.
1.12 and providing and fixing door & window frames & allied works of Building 2.50%
as per Scope of Work
On completion brick work of First floor along with provision of lintel etc. and
1.13 providing and fixing door & window frames & allied works of Building as 2.50%
per Scope of Work
On completion brick work of Second floor along with provision of lintel etc.
1.14 and providing and fixing door & window frames & allied works of Building 2.50%
as per Scope of Work
On completion brick work in parapet walls and Mumpty along with
1.15 provision of lintel etc. and providing and fixing door & window frames & 1.50%
allied works of Building as per Scope of Work
1.16 On completion of internal plastering of Ground floor of Building 3.00%
1.17 On completion of internal plastering of First floor of Building 3.00%
1.18 On completion of internal plastering of Second floor of Building 3.00%
1.19 On completion of External Plastering of Building including parapet wall 3.00%
1.20 On completion of flooring in staircase of Building 3.00%
On completion of flooring in rooms, toilets, common area and wall tiles etc.
1.21 3.00%
in Ground floor of Building
On completion of flooring in rooms, toilets, common area and wall tiles etc.
1.22 3.00%
in First floor of Building
On completion of flooring in rooms, toilets, common area and wall tiles etc.
1.23 3.00%
in Second floor of Building
1.24 On fixing railing in staircases, balcony, corridors etc. of Building 2.50%
On providing and fixing door, window shutters, cupboard shutters,
1.25 3.00%
ventilators, hardware fixtures & fittings, etc. of Building
CONSTRUCTION OF ADMIN BLOCK/TRAINING BLOCK AND OFFICES
Percentage
S.No. Stages of Construction
Breakup
1.26 On completion of Over- head Tanks in all Respect of Building 1.50%
1.27 Terrace water proofing & allied works & testing thereof of Building 1.50%
External finishing work of the building alongwith Plinth Protection of
1.28 3.00%
Building
Sub-Total (1) 72.00%
2.0 ELECTRICAL WORKS
2.1 Internal Wiring complete in all respects 2.00%
2.2 Telephone Wiring and Conduits complete in all respects 1.00%
2.3 Light, Fans, exhaust fans and their Fixtures complete in all respects 3.00%
2.4 Earthing complete in all respects 2.00%
2.5 Lightning Protection System complete in all respects 2.00%
2.6 Safety Accessories complete in all respects 1.00%
2.7 Distribution Board (Ready Made MCB DB) complete in all respects 2.00%
Sub-Total (2) 13.00%
3.0 PHE WORKS
On providing and laying of pipes for internal/external sanitary, Waste, etc.
3.1 2.00%
in position of all floors of Building
On Supply and installation of all plumbing and sanitary fittings in the
3.2 2.00%
Building of Building
Sub-Total (3) 4.00%
4.0 FIRE PROTECTION WORKS
4.1 On Completion of Fire Extinguishers Work 0.50%
4.2 On Completion of Fire Downcomer System with Piping System 1.50%
4.3 On Completion of Automatic Fire Alarm System 1.00%
Sub-Total (4) 3.00%
5 Finishing and Handing Over
Final coat of internal/external painting, polishing on each required surface,
5.1 4.00%
testing / commissioning of services prior to handing over of Building
Final fixing of all complete sanitary fitting, lighting, fans, final fixtures, and
5.2 other fittings etc. as detailed in scope of work prior to handing over of 4.00%
Building
Sub-Total (5) 8.00%
GRAND TOTAL 100.00%
PAYMENT SCHEDULE No. 3
CONSTRUCTION OF 01 NO. 128 MEN BARRACK
Percentage
S.No. Stages of Construction
Breakup
1.0 CIVIL WORKS
On Completion of Site Clearance / Jungle Clearance, Filling and levelling
1.1 2.50%
of site as per Scope of Work
On Completion of RCC Piles, RCC Pile Cap and Pile Load Test as per
1.2 5.00%
Scope of Work
1.3 On completion of all works upto Plinth level as per Scope of Work 2.50%
On casting of columns in Ground Floor & allied works of Building as per
1.4 2.00%
Scope of Work
On casting of Ground Floor Roof Beams and Slab & allied works of
1.5 3.00%
Building as per Scope of Work
On casting of columns in First Floor & allied works of Building as per
1.6 2.00%
Scope of Work
On casting of First Floor Roof Beams and Slab & allied works of Building
1.7 3.00%
as per Scope of Work
On casting of columns in Second Floor & allied works of Building as per
1.8 2.00%
Scope of Work
On casting of Second Floor Roof Beams and Slab & allied works of
1.9 3.00%
Building as per Scope of Work
On casting of columns upto Mumty & allied works of Building as per
1.10 2.00%
Scope of Work
On casting of Mumty Roof Beams and Slab & allied works of Building
1.11 2.00%
as per Scope of Work
On completion brick work of Ground floor along with provision of lintel
1.12 etc. and providing and fixing door & window frames & allied works of 2.50%
Building as per Scope of Work
On completion brick work of First floor along with provision of lintel etc.
1.13 and providing and fixing door & window frames & allied works of Building 2.50%
as per Scope of Work
On completion brick work of Second floor along with provision of lintel
1.14 etc. and providing and fixing door & window frames & allied works of 2.50%
Building as per Scope of Work
On completion brick work in parapet walls and Mumpty along with
1.15 provision of lintel etc. and providing and fixing door & window frames & 1.00%
allied works of Building as per Scope of Work
1.16 On completion of internal plastering of Ground floor of Building 3.00%
1.17 On completion of internal plastering of First floor of Building 3.00%
1.18 On completion of internal plastering of Second floor of Building 3.00%
1.19 On completion of External Plastering of Building 3.00%
1.20 On completion of flooring in staircase of Building 3.00%
On completion of flooring in rooms, toilets, common area and wall tiles
1.21 3.00%
etc. in Ground floor of Building
On completion of flooring in rooms, toilets, common area and wall tiles
1.22 3.00%
etc. in First floor of Building
On completion of flooring in rooms, toilets, common area and wall tiles
1.23 3.00%
etc. in Second floor of Building
1.24 On fixing railing in staircases, balcony, corridors etc. of Building 2.50%
On providing and fixing door, window shutters, cupboard shutters,
1.25 3.00%
ventilators, hardware fixtures & fittings, etc. of Building
1.26 On completion of Over- head Tanks in all Respect of Building 1.50%
CONSTRUCTION OF 01 NO. 128 MEN BARRACK
Percentage
S.No. Stages of Construction
Breakup
1.27 Terrace water proofing & allied works & testing thereof of Building 1.50%
External finishing work of the building alongwith Plinth Protection of
1.28 3.00%
Building
Sub-Total (1) 73.00%
2.0 ELECTRICAL WORKS
2.1 Internal Wiring complete in all respects 2.00%
2.2 Light, Fans, exhaust fans and their Fixtures complete in all respects 3.00%
2.3 Earthing complete in all respects 2.00%
2.4 Lightning Protection System complete in all respects 2.00%
2.5 Safety Accessories complete in all respects 2.00%
Distribution Board (Ready Made MCB DB) complete in all respects
2.6 2.00%
Sub-Total (2) 13.00%
3.0 PHE WORKS
On providing and laying of pipes for internal/external sanitary, Waste,
3.1 1.50%
etc. in position of all floors of Building
On Supply and installation of all plumbing and sanitary fittings in the
3.2 1.50%
Building of Building
Sub-Total (3) 3.00%
4.0 FIRE PROTECTION WORKS
4.1 On Completion of Fire Extinguishers Work 0.50%
4.2 On Completion of Fire Downcomer System with Piping System 1.50%
4.3 On Completion of Automatic Fire Alarm System 1.00%
Sub-Total (4) 3.00%
5 Finishing and Handing Over
Final coat of internal/external painting, polishing on each required
5.1 surface, testing / commissioning of services prior to handing over of 4.00%
Building
Final fixing of all complete sanitary fitting, lighting, fans, final fixtures, and
5.2 other fittings etc. as detailed in scope of work prior to handing over of 4.00%
Building
Sub-Total (5) 8.00%
GRAND TOTAL 100.00%
PAYMENT SCHEDULE No. 4
CONSTRUCTION OF RESIDENTIAL QUARTERS TYPE-II (3 BLOCKS)
Percentage
S.No. Stages of Construction TOWER-1 TOWER-2 TOWER-3
Breakup
1 CIVIL WORKS
On Completion of Site Clearance / Jungle Clearance, Filling
1.1 0.80% 0.80% 0.90% 2.50%
and levelling of site as per Scope of Work
On Completion of RCC Piles, RCC Pile Cap and Pile Load
1.2 1.60% 1.70% 1.70% 5.00%
Test as per Scope of Work
On completion of all works upto Plinth level as per Scope of
1.3 0.80% 0.80% 0.90% 2.50%
Work
On casting of columns in Ground Floor & allied works of
1.4 0.50% 0.50% 0.50% 1.50%
Building as per Scope of Work
On casting of Ground Floor Roof Beams and Slab & allied
1.5 0.80% 0.80% 0.90% 2.50%
works of Building as per Scope of Work
On casting of columns in First Floor & allied works of
1.6 0.50% 0.50% 0.50% 1.50%
Building as per Scope of Work
On casting of First Floor Roof Beams and Slab & allied works
1.7 0.80% 0.80% 0.90% 2.50%
of Building as per Scope of Work
On casting of columns in Second Floor & allied works of
1.8 0.50% 0.50% 0.50% 1.50%
Building as per Scope of Work
On casting of Second Floor Roof Beams and Slab & allied
1.9 0.80% 0.80% 0.90% 2.50%
works of Building as per Scope of Work
On casting of columns in Third Floor & allied works of
1.10 0.50% 0.50% 0.50% 1.50%
Building as per Scope of Work
On casting of Third Floor Roof Beams and Slab & allied
1.11 0.80% 0.80% 0.90% 2.50%
works of Building as per Scope of Work
On casting of columns upto Mumty & allied works of Building
1.12 0.30% 0.35% 0.35% 1.00%
as per Scope of Work
On casting of Mumty Roof Beams and Slab & allied works
1.13 0.60% 0.70% 0.70% 2.00%
of Building as per Scope of Work
On completion brick work of Ground floor along with
1.14 provision of lintel etc. and providing and fixing door & window 0.60% 0.70% 0.70% 2.00%
frames & allied works of Building as per Scope of Work
3 Guard Room 5%
GRAND TOTAL 100.00%
Note: The Successful bidder shall submit the Payment Schedule for the Gate and Guard Room
upon award of work for appproval
PAYMENT SCHEDULE No. 9
SITE DEVELOPMENT WORKS
Percentage
S.No. Stages of Construction
Breakup
On completion of external development works like raising of site, road,
1 Water Supply, Sewerage network, , footpath, Storm water drains, Rain
water Harvesting other necessary allied development works.
1.1 Raising of Ground level for Roads and Buildings (Levelling) 40.00%
1.2 Cement Concrete Pavement with Vacuum Dewatered Concrete 19.00%
1.3 Footpath with PCC Base, 60 mm thick Paver blocks and Kerb stone edging 1.00%
1.4 External Sewerage Network 7.00%
1.5 Water Supply Network 4.00%
1.6 Storm Water Drains Network 20.00%
1.7 Rain Water Harvesting 3.00%
1.8 External Service Connections 6.00%
GRAND TOTAL 100.00%
Note: The Successful bidder shall submit the Payment Schedule for the above works upon award of
work for appproval
PAYMENT SCHEDULE No. 10
CONSTRUCTION OF SEWAGE TREATMENT PLANT
Percentage
S.No. Stages of Construction
Breakup
1 SEWAGE TREATMENT PLANT AND PLANT ROOM
Design, Supply, Installation, testing and Commissioning of STP of
1.1 appropriate Technology inlcuding Civil works (excluding Plant room), 87.00%
tertiary treatment etc. for the Campus - 150 KLD Capacity
1.2 On completion of Plant Room for STP as per Scope of Work 13.00%
GRAND TOTAL 100.00%
Note: The Successful bidder shall submit the Payment Schedule for the above works upon award
of work for appproval
PAYMENT SCHEDULE No. 11
EXTERNAL ELECTRICAL WORKS
Percentage
S.No. Stages of Construction
Breakup
1 External Electrical Works
Supplying, installation, testing and commissioning of 33 kV/0.433 kV or
11 kV/0.433 kV substation equipment comprising HT panel, dry type/Oil
type transformers, HT cable, bus trunking from transformer to LT panel,
LT panels, automatic power factor correction panel, active harmonic
1.1 filters, TVSS (transient voltage suppression system), SPD (surge 33.00%
protection system), essential panel, earthing, required inter-
connections, substation safety equipments including LT cabling from
substation to the buildings fed by the substation. - 630 kVA Capacity