Ms - Htar Htar Soe
Ms - Htar Htar Soe
By
Nationality: Myanmar
Yangon, Myanmar
Thailand
December 2015
i
ACKNOWLEDGEMENTS
Firstly I am grateful to all the teachers who came and taught us from AIT for the lectures
concerning with project management in construction. Specially thank to Dr. Hardikusumo for
guiding and supervision on this paper, giving reference books and helping us along the
training period.
Secondly I would like to be grateful to Director Daw Mie Mie Tin (DUHD) who assigned me
as a project representative official in "51 st public housing redevelopment project", Director
Daw San San Aye(DUHD) who advised me to attend this class, Director U Myint
Naing(MOC) who gave me the chance to attend this class and Director General U Min
Htein(DUHD) for the encouragement of attending the class.
ii
ABSTRACT
There are two types of relocation implemented by DUHD. These are relocation for slums and
squatter families and for public tenants from old buildings to new modernized ones. In
relocation projects, the strategy in each stage such as inception stage, feasibility study, pre-
construction, construction, commissioning, hand over and project close out stage are all
important because the project is related to public.
In real practice, public tenants are more difficult to negotiate and communicate than housing
unit purchasers. For this reason, selection for designers, contractors and quality consultants are
very important and these team members must be skillful and qualified in the related
professionals.
This project is the first one in public housing relocation project in Yangon among (10) public
rental housing which have been running since 50-60 years ago. The project development
strategy include two parts, strategy for executing construction works and strategy for public
negotiation in order to implement successfully for the housing relocation project. Although
there have been facing some problems during construction and public negotiation, the project
is an evidence of a great success in relocation executed by DUHD.
Key words: relocation, public tenants, strategy, rental housing, implement
iii
TABLE OF CONTENTS
Title Page i
Acknowledgements ii
Abstract iii
Table of Contents iv- vi
List of Tables vii
List of Figures viii
List of Abbreviations i×
1.0 Introduction
1.1 General Background 1
1.2 Problem Statement 1-2
1.3 Objectives of Study 2
2.0 Literature Review for Housing Development Project
2.1 Inception Stage 3
2.2 Feasibility Stage
2.2.1 Feasibility Study 3
2.2.2 Aiming to Sustainable Development 3-4
2.2.3 Aerial Restrictions and Site Selecting 4
2.2.4 Land Acquisition 4
2.2.5 Project Execution Plan 4
2.3 Strategy for Housing Development
2.3.1 Housing Development Activities 5
2.3.2 Project Organization Structure 6-7
2.3.3 Selecting the Members of Project Team 7
2.3.4 Cost Planning and Control 7-8
2.3.5 Relationship Between Cost and Quality 8
2.3.6 Project Scheduling 8
2.4 Pre-Construction Stage
2.4.1 Interlinking with Strategy 8-9
2.4.2 Design Delivery 9
2.4.3 Project Meetings 9
2.4.4 Risk Mitigation Planning 9
2.5 Construction 9-10
2.6 Handover 10
2.7 Project Review after Completion 10
3.0 Case Study for 51st Public Housing Redevelopment Project
3.1 Case Description 11-12
3.2 Project Development
3.2.1 Feasibility Study
(a) Environmental Impact Assessment 13-14
(b) Business Case 14
(c) The Risks of the Project 16
3.2.2 Land Acquisition 17
iv
3.2.3 Project Execution Plan 17
3.2.4 Conceptual Design
(a) Basic Characteristic 18
(b) DUHD’s Restrictions 18
(c) YCDC’s Rules and Regulations 18-19
(d) Factors Required for Fire Brigade Department 19
(e) Factors Required for YESC 20
(f) Schedule for Conceptual Design 20
(g) Quality Management for Design 20-21
(h) Problems Detail for Design Phase 21
3.2.5 Demolishing Process 21
3.2.6 Construction
(a) Pre Construction Works 21-22
(b) Foundation Works 24-25
(c) Superstructure Works 25
(d) Architectural Works 26
(e) M&E Works 26
(f) Infrastructure Works 26
3.2.7 Handing Over 26-27
3.3 Analysis of Strengths, Weakness and Recommendations
for Improvement
3.3.1 Strength of the Project
(a) Strength of PPP Project 27
(b) Location of the Project 27-28
(c) Near to Network Infrastructure 28
(d) Get Favor for Permit (BCP) 28
(e) Having Good Consultants 28-29
(f) Regular Visit of Authorized Persons 29
(g) Good for Safety and Health 29
3.3.2 Weakness of the Project
(a) Problems Between two Companies 29
(b) Weakness Concerning with Quality Control
Consultant 30
(c) Construction Technology 30
(d) Weakness in Health and Safety Issue 30-31
(e) Lack of Discussion with Relocated People
During Construction Period 31
3.3.3 Recommendation 31-32
3.4 Lesson Learnt from the Project 32-33
3.5 Develop a Framework for Housing Project Development
Strategy
3.5.1 Inception Stage 33-34
3.5.2 Feasibility Study 34
3.5.3 Pre-Construction Works
(a) Tendering for Designs 34
(b) Tendering for Construction 34-35
(c) Contractual Stage for Construction 35
v
3.5.4 Construction Stage
(a) Strategy Related to Quality 35-36
(b) Strategy Related with Time 36
(c) Strategy Related to Cost 36
(d) Strategy Related to Safety and Health 36-37
3.5.5 Commissioning 37
3.5.6 Hand Over 37
3.5.7 Project Close out 37
4.0 Conclusion 40
References
1. Managing Residential Construction Project written by Derek Graham.
2. Code of Practice for Project Management for Construction and Development
(Fourth Edition) written by Wiley-Blackwell.
3. Myanmar Times Journal of 18 March 2015
Appendix
Appendix 1 Three dimensional project view and location plan
Appendix 2 Old buildings photographs and floor plan
Appendix 3 Comparing old buildings plan and new ones and
Profit sharing ratio between DUHD and construction companies
Appendix 4 Architectural photos for relocation buildings
Appendix 5 Floor plan for relocation buildings
Appendix 6 Architectural photo and floor plan for 15-1/2 storey building
Appendix 7 Work schedule for relocation buildings
Appendix 8 Photographs of present conditions for relocation buildings
vi
LIST OF TABLES
TABLE TITLE Page No.
Table (3) Table for Comparison of Existing and Proposed Improvement 38-39
vii
LIST OF FIGURES
FIGURE TITLE Page No.
viii
LIST OF ABBREVIATIONS
JV Joint Venture
RC Reinforced Concrete
ix
Chapter (1)
Introduction
2
Chapter (2)
Literature Review for Housing Development Project
3
good drainage system, sufficient open spaces with adequate green areas, etc. Most clients and
government departments are proactively engaged and committed to securing such kind of
sustainable development.
On the other hand, carbon emission must be reduced during construction period by selecting
construction materials, construction technology and transportation. For example, concrete
batching plants should be placed in the site area or the place as near as possible to reduce
transportation. Sustainable development in terms of design and construction is responsible for
all parties involved on the entire project from start to end.
4
2.3 Strategy for Housing Development
2.3.1 Housing Development Activities
The strategy for housing development must include the forming of project organization,
determining the strategies for procurement and delivery (cheaper, faster and better quality and
risk management), commissioning issue until completion and close out of the project. The task
and activities for feasibility study and housing strategy are interrelated to each other in order to
achieve both processes. The sequences of activities for housing development projects are
commonly as follows;
Feasibility
Study
Inception
Stage
PPlana Strategy
Development
Pre-Construction
Construction
Commissioning
Hand-over
O&M
5
2.3.2 Project Organization Structure
A project organization structure is set out clearly and must include the detail functions and
performance of all parties concerning with the project. It is updated depending on
circumstances during the lifetime of the project. Under the project organization structure,
project manager plays in a crucial role for the success of the whole project. Project is usually
carried out under the overall direction and supervision of a project manager. Project
organization structure normally comprises the following separate teams.
Client's internal team ( suitable representatives)
Project manager (either from client's organization or appointed from outside)
Design team consisting architects, ( buildings and landscape), engineers
(structural, civil, electrical and mechanical), and technological specialists
Consultants to cover the field of legal, financial, quality, safety and health, etc.
Contractors and subcontractors
The most common project organization structure for the housing development project is as
follows;
Client
Consultants
- land acquisition
Project Manager
- legal
- financial
- public relation
Subcontractor Subcontractor
6
In order to have effective project management, it must have all provisions for quality
assurance, time and financial control, health and safety and, access environmental protection.
A suitable deputy for each team member should be identified to be sufficiently familiar with
the project in order to act as replacement whenever it is needed. Apart from the above stated
abilities, team members should have the following people skills in order to get smooth relation
among project team members and develop the project successfully.
Ability to genuinely empathize with people
Willingness to admit mistake whenever it has done.
Appreciate to other people's feelings and respect basically to them
Have open-minded and patiently listen to other people what they want to say
Communicate smoothly to people with different culture and social nature
Tolerate to people who do not fit the ideal
As for the project manager, who is the most important person to run the project efficiently and
get success effectively, should have one more skill that is "Information and Communication
Technology". Because it is usual for extensive use of computer applications as a tool to assist
most project management functions. The main purpose of applying ICT is to support efficient
working practices and enable knowledge circulation. The researchers discovered that (95) %
of construction and manufacturing companies believed that chief executive officer was
essential to initiate changes to ICT system.
7
or other specialist advisors. A budget study is undertaken by the determination of total costs
and expected return of the project.
The objective of cost control is to manage project delivery within the approved budget. Only if
all the project team members have correct attitude to control the cost, effective cost control
can be achieved. Moreover, the current budgetary, cost situation and, up-to-date and accurate
cost reports must be informed to the client regularly in order to achieve effective cost control.
8
Project manager is responsible person to review and update project handbook by monthly or
suitable regular time interval.
2.5 Construction
Construction business is not an individual, it is a people business and thus communication is
the key to succeed a project. The project manager's responsibilities in this stage involve
heading up the professional design and construction team and, building trust between all
parties. The bonding between all parties can be developed by holding regular meetings and
workshops. During this stage, the project team must be hand on to resolve and eliminate any
issue hindering the smooth of construction process. The major issue of construction process is
9
to ensure that contractors and subcontractors receive regular payments for their works.
Normally, the contractor makes a monthly claim for the payment. The quantity surveyor
values the work, contract administrator certifies it and the client pays for it during the period
written in the contract.
2.6 Handover
Completion and handover are interlinking to each other. This is the final stage of work
implemented by contractors and consultants in order to accept facilities by the client. In this
stage, client commissioning is carried out by the client's personnel, assisted by the consultants
as required. It is also stated as substantial completion for which AIA (American Institute of
Architects) definition of (A 201:9.8.1) defined as follows;
Substantial Completion is the stage in the progress of the Work when the Work or
designated portion thereof is sufficiently complete in accordance with the Contract
Documents so that the Owner can occupy or utilize the Work for its intended purpose.
(A201: 9.8.1)
After substantial completion, the next step is final completion. The items which are
substantially complete and only require for minor adjustments are listed as a punch list. Final
completion and handover to client must include the following documents.
Completion of punch list
Release of lien waivers for 100% of the contract value
Sign-offs for all controlled inspections
Temporary or permanent certificate of occupancy
10
Chapter (3)
Case Study for 51st Public Housing Redevelopment Project
(a PPP approach in Myanmar)
11
According to the conceptual design, the project consists of (2) no of 12-½ storey buildings and
(2) no. of 15-½ storey buildings. The former ones are to relocate the old tenants. The profit
sharing ratio will be described in Appendix-3. The reasons for building 12-½ storey are to get
BCP faster by reducing one step for submittals. According to YCDC’s rules and regulations,
all building designs above 12- ½ storey have to submit CQHP to get design approval and then
YCDC will issue BCP. It will take more time about six months depending on the designer's
quality.
There are totally (10) public rental housing projects which were executed and managed by
DHSHD. All these housing estates are needed to make redevelopment by relocating. But there
are some difficulties and challenges to implement and only two projects can be carried out.
Among these two, this project is the first one and nearly finished, and will be hand over to all
the tenants on 1st November 2015. Some families have already accepted and lived in their
rooms since 1st July 2015.
12
Photograph for Public Meeting before the Project was Started
13
responsible to reduce the impacts to the environment during construction period as well as for
the smooth operation and easy maintenance of the building facilities in the long run.
14
Figure (3) Functional Steps of Relocation Project
No Yes
Re discussion
Tendering
Design & Build
No
No
Fire Brigade
YESC YCDC
Department
No Yes
Yes
Yes
15
(c) The Risks of the Project
The developers cannot construct the buildings in time and cannot give additional rental
charges because of appearing financial problems.
Labour shortage appears because of other construction projects such as “Haul Group
from Vietnam is running a huge construction project in Yangon by paying more labour
charges to obtain many labours”.
Quality problems can appear because of shortage of skill labours and the relocated
people cannot satisfy the finished quality of their new units.
If something happen for safety problems, the project is under the watch of public and
easy to describe in media.
In order to mitigate these risks, DUHD made risk mitigation plan. In conditions of the
contract, the amount of penalty for delay is expressed clearly. In clause no. (18) of the contract
between the DUHD and contractor, “the contractor must finish the work done as the schedule
attached in this contract. For the delay of the first (6) months, the second (6) months, the third
(6) months, the developer must pay 20,000,000 Kyats for each six months delay. Moreover, if
the finished date is over (6) months, the owner can take all these constructed properties
without paying any charges.” Before the contract was signed, the developers have to keep
performance guarantee that is 3% of total project cost in the Construction and Housing
Development Bank (CHDB) until the project is hand over.
As for the quality of each unit, the architectural specifications are stated in the conditions. In
which all rooms hand over to DUHD must contain kitchen counter with (8)ft length including
steel sink, toilet with EWC pan set, floor tiles in kitchen, bath, rest rooms and verandah, wall
tiles are (7)ft for kitchen and (5)ft for bath & w/c, each unit must include (200) galloon
overhead water tank, etc. Other materials such as door and window accessories and painting
standards are specified in the contract as well. The third party inspection team has been
checking and inspecting along the construction period until the project is hand over. In
addition to this, the responsible engineers from DUHD also check occasionally.
As for the safety, DUHD has given pressure to the developers to keep a full time safety officer
in the site and wearing PPE to the workers, and check the working conditions and working
environment to get safety. These safety activities are kept as a record and giving preference in
the evaluation of the bidders in the next projects.
16
3.2.2 Land Acquisition
The land area is totally (2.486) Acre including infrastructure yard. Because the land is
originally owned by DUHD, there is no problem concerning with land acquisition. The
problems appeared only the people living on this land as tenants. They did not want to lose
their opportunity to live for a long period as before only with small amount of rental charges.
In this project, DUHD implemented joint venture system with private developers.
The project includes (4) buildings and sharing units is done in each building. According to the
condominium law(which is still submitting in people's congress) of Myanmar, the buyers or
owners of living units in condominium will have chance to own partially the land on which the
building is constructed, and the building have to register as a condominium, and must be
perfect with the characteristic of condominiums.
In these new buildings, the relocated units are owned by DUHD, the relocation families will
be tenants and cannot concern with land acquisition. Apart from these units, DUHD will get
other sharing units and will be sold out to public after hand over. In Myanmar, especially in
Yangon, developers are used to run the management activities for operation and maintenance
of the condominium which they constructed for about (5) years. And then Estate Management
Committee is set up in this estate with the participants from the living families and is handed
over by the construction company.
17
3.2.4 Conceptual Design
(a) Basic Characteristic
Conceptual design is one of the important items in bidding competition. It must be compliance
with DUHD’s restrictions and YCDC’s rules and regulations. Moreover, the conceptual design
must be creative, innovative, buildable, and easy for operation and maintenance in the long
term, cost effective, efficient for land use and will be erect as a land mark in the future.
18
Water Supply
The whole project requires (150,000) galloon per day for the total usage and developers must
connect YCDC’s water supply piping network by their own expense. Actually developers
wanted to draw water from underground (tube well) because it is much cheaper than piping
connection cost. But DUHD did not allow to take huge amount of water from underground
because it can effect sustainable environment and the life span of the buildings as well.
Drainage System
For the storm water, developers have to draw drainage system design and submit to YCDC.
YCDC will check their design and if needed, they give guide lines to mend it. In this project,
after approval from YCDC, (3) no. of box culvert crossing nearby street and (1) big box
culvert (56)ft long crossing main road is necessary together with brick drains to dispose storm
water until reaching Yangon river.
19
(e) Factors Required for YESC
For electricity supply, the developers have to comply with Yangon City Electricity’s Supply
Corporation. All external cables must be connected underground system. 66/11KV electricity
substation must be built and installed in the project area. But the station is not only for this
project, must share the usage with other housings nearby area and the cost for this station must
be shared as well.
Figure (4) Bar Chart for Conceptual Design Schedule (in the year 2013)
In the tendering stage, to control the design quality which include all designs such as
conceptual design, architectural design, structural design, M&E design, the contractor need to
bring all design professionals ( the leader of each team) to the presentation for tender
competition. Design team organization chart and the qualification of team members for each
design team have to present. According to the marking system of technical evaluation in the
tendering process, the marks of the company depends on how strong in technically of design
team which the contractor choose because the tender selection system is QCBS (Quality and
Cost Based System).
After the design team was chosen, in the pre-construction stage, the designers must submit
DUHD for the approval documents of concerning department such as YCDC, YESC, Fire
Brigade Department, CQHB, etc. And then, all the design sheets were checked sheet by sheet,
by holding design meetings together with all the designers, quality consultants, and
responsible site engineers from construction companies in order to run smoothly in the
construction process.
20
In the construction stage, shop drawings were distributed in time to the contractors by the
designers not to get delay. DUHD and quality consultant team usually gave reminder to the
designers if the shop drawings cannot get to the site a week before the works were started.
21
3.2.6 Construction
(a) Pre Construction Works
Before construction started, the two contractors and their engineers had to come to MOC,
office no(11), Naypyitaw and explain their structural designs, M&E designs, construction
methods, the use of construction materials concerning with their buildings to the Minister,
Deputy Ministers, Director General of DUHD, and other responsible officials. Minister and
Deputy Ministers asked questions to get the commitments and gave necessary guide lines.
In this stage, Inspection Company to inspect and check the construction works of this project
was appointed by Minister. In which TOP engineering and consultant group was chosen to do
quality control works, and the fee is (1%) of total project cost. This fee must be paid by the
developer. One of the important activities in pre-construction phase is to plan for master
schedule for construction which is described as follows;
Sp = Sub program
Sp 5 Drainage System
Sp 8 Landscaping
Time Frame
22
Before the construction phase was started, it is needed to set up project organization perfectly
and this organization chart must be placed in the project office.
MOC
DUHD
Sub-Contractor
Sub-Contractor Civil works Water Supply& Sanitation
Sub-Contractor Sub-Contractor
Electrical Civil Works Water Supply&
Works Sub-Contractor Sub-Contractor Electrical Works
Sanitation
Functional step
Communication function
23
(b) Foundation Works
Although the two 12-1/2 storey relocated buildings are the same in architectural design, the
structural design, especially foundation designs are totally different. The two developers were
competitive to each other and their communication is not good. It can effect some problems to
DUHD, but the advantages is better in quality and faster in construction works by comparing
their work progress and quality.
The two developers are Maha-Nawarat-Myay Construction Company and Triple Aung
Construction Company. The structural designers of Maha-Nawarat-Myay built the foundation
with 14”x14” RC precast pressed pile (1219 no.) and pile cap. Triple Aung built foundation
with 12”x12” RC precast pressed pile (1054 no.) and mat foundation.
According to the nature of high-rise building construction, foundation is the most difficult to
do and take longer period. The two companies need to made pile load test and reported the test
result to DUHD.
Because the two companies were working foundations with different design, they submitted
their own schedule. Nevertheless, DUHD did not accept it and held meeting with chief
engineers from these two companies and determined the exact finished date of foundation
works. This date must be correspond with the master schedule attached in the contract. This
work schedule for these two 12-1/2 storey buildings is described in appendix-7.
Foundation works especially piling works are executed by the same subcontractor named
"Myanmar V-pile Company". Separate work schedule for foundation works including piling
works are as follows;
1. Site Clearing
3. Piling Works
4. Pile Cap/Mat Foundn.
The quality for foundation works was carefully checked by quality consultants. Precast
reinforced concrete piles were tested by rebound hammer whether it has sufficient concrete
strength or not. Destructive tests for concrete and mild steel was done regularly by quality
consultant and reported to DUHD. Contractors have to send sample of mild steel to test for
every brand before they use in the RC works. Slump test were done for every batch of
concrete and also took cube mould for testing strength. Although batching plant cannot be
24
placed in the site area, ready mixed concrete was purchased from the nearest plant to reduce
travel time. Concrete for pile cap or mat foundation were placed mostly in the morning in
order to reduce temperature during concreting. DUHD's engineers also made counter check to
quality consults in order to get safe quality foundation for the buildings.
During foundation works, the major risks are;
Cube test results are not conforming to the design strength although the concrete works
have already finished and corrective action will cause delay.
Heavy rain appears unexpectedly and the site becomes flooded and difficult to
continue foundation works and causes delay.
Land slide happens because of not enough sheet pile and cannot control media and
effect the reputation of the site, contractors and DUHD as well.
Although these major risks were registered and made risk mitigation plan, some problems
appeared during foundation works. These problems are;
YCDC water supply pipe (2"Ф) caused a lot of leakage and land slide happened in 51 st,
but neighborhood people thought that problems raised because of the construction site.
The people living near the construction site did not accept to do overtime because of
the noise of machine and difficult to make catch up program whenever delay appears.
The people living in the building (eight storey ) located on the opposite site of 50 th
street made problems by the reasons that their building caused vibration, whenever
piling works were done although the designers were using pressed pile.
25
(d) Architectural Works
According to work schedule, architectural works were started on 15 May 2014 that is after
removing scaffolding under reinforced concrete slabs and beams. These works include brick
walling, plastering, doors and window works, painting, tiling, etc. The developers prepared
one simple unit for relocation and approved by Inspection Company and DUHD for the
standard quality and the use of materials. Inspection Company and DUHD check it and give
guide lines if something needed.
Every relocation units must include kitchen counter with (2)ft width and (8)ft length
containing steel sink of medium size by medium class, floor tiles for kitchen, bath, w/c room,
verandah and outside ventilation space, wall tile with(7)ft height for kitchen and (5)ft height
for bath and w/c rooms. The tiles and other materials for architectural works must be made in
Thailand, and do not allow to use the materials made in China. Other countries’ product such
as Korea and Hong Kong are also allowed to use.
26
want to make decoration, they have to inform to the contractor who built the building and
must pay the charges for decoration depending on what they want. The tenants are not allowed
to hire outside decoration contractor not to damage internal piping and other M&E works.
Another strength point of PPP project is that employees from DUHD especially engineers can
learn the construction technology by inspecting weekly as a counter check to the project.
28
(f) Regular Visit of Authorized Persons
Because this is the first project for relocation, every stakeholder is interested in the
implementation works. The project has been progressing in line with work schedule because
the authorized persons (Ministers or Deputy Ministers for Construction) visit the site and held
a meeting with the two companies and consultant group in every two weeks. The authorized
persons were used to ask the problems and difficulties facing in the site and gave supportive
directions. Although the delay happened for one or two weeks because of labor problems and
some other construction problems, the contractors have to submit catch up programs not to
delay the whole building schedule and also the whole project.
30
When the structural works finished, only a few workers wear PPE and this PPE is only helmet
and coat.
3.3.3 Recommendation
The following facts are recommended in order to get successful housing relocation projects;
Separate tenders for design and construction should be made instead of Design Build
system because the project is related to public and need to make discussion in design
stage for their relocation units.
The inspection fee for QC/QA consultants should not be paid directly from contractors
although it is expensed by contractors. Contractors install to DUHD account and
DUHD charges to QC/QA consultant depending on finished work done.
The scope of work should be written clearly in the contract for inspection works.
Quality control and quality assurance should be made not only for structural works, but
also for architectural works and M&E works as well, until the project is handed over.
31
The construction technology must be updated in the next relocation project in order to
save time and cost. Conventional brick walling have impact to sustainable
environment.
Triangle meeting with DUHD, public tenants and contractors should be held three or
four times during construction period and must explain them the conditions of
construction works and ask their desire and try to fill within the scope of contract.
Health and safety program should be encouraged by giving bonus or incentives for the
obedient of safety rules and restrictions in the construction sites.
There are ten lessons learnt from this project for the implementation in the future project.
1) The Design Build procurement technic is not good enough in this kind of relocation
project. Because of this tendering system, there are many factors including profit sharing
ratio to consider for choosing contractor in the tendering stage and cannot get a good
architectural design for the building. Therefore separate tender for design and
construction is better to get good design and for user satisfaction.
2) Although architectural designs for the two relocation buildings are the same, the finished
buildings are a little bit different in some ways because of building by two different
contractors with different ideas. Instead of choosing two contractors, only one contractor
is better by writing clear statements in the contract concerning with specification, quality
and reward for defects , penalty for delay, etc.
3) Among the contractors, one contractor did not want to use good quality materials in
architectural works such as door & window accessories, tiling works, etc. Because of
DUHD’s enforcement and the competitiveness between the two contractors, good quality
materials are used. In order to improve the quality of buildings and related infrastructure,
the share for the owner should be reduced instead as of 52% unit floor area share.
4) The quality consultant was chosen with appointing system by MOC( Ministry of
Construction) and there are some weak points in the quality consultant team such as delay
for reporting, only took responsible for structural works , etc. Therefore choosing quality
consultant by competitive tendering system (QCBS ) is more effective than appointing.
5) In this project, each contractor holds their weekly meeting by oneself without inviting
DUHD and quality consultants. Because of this reasons, some problems relating to the
whole project are delay to solve and can solve only when the authorized persons from
MOC such as Minister or Deputy Ministers visited to the site. In the future project,
32
weekly meetings should be led by DUHD by inviting quality consultant contractors and
designers (if necessary) and distribute meeting minutes regularly.
6) No contractor want to construct electricity substation because of the cost is high around
1800 million Kyats. This costs has to share with nearby housing projects located in this
area in which some projects are under the management of DUHD and some are private
projects. It took long period to collect the cost of their share. DUHD had to requested to
YESC to give temporary electricity supply for the relocation units. Therefore sharing
costs for electricity substation should be done in the early stage of the project although the
substation has not constructed yet. If so temporary installation of electricity will not be
needed.
7) The quality consultant defines their scope of work by themselves and only done for
structural works. The result is that DUHD found the differences only when the works are
finished. Therefore not only the quality check for structural works, architectural
designer’s check and approval for his design is also necessary at least twice a month when
the architectural works start and this fees should be added in the design fee request.
8) Because public tenants were met only when the works were finished, they have no chance
to know the site condition in advance. Therefore tri-party meetings with DUDH,
contractors and public tenants, must be done three or four times during construction
period.
9) DUHD assigned a representative official to this project. Therefore only one person knows
about the project. The entire junior engineer’s group should be affiliated with senior one
to study construction and QC inspection works from practical construction site.
10) In all JV projects, inspection fee is given by contractor’s side. Because of this reason,
inspectors felt hesitate to take action in some cases. Therefore the quality consult’s fee
should be paid by DUHD (owner’s expense) by making budget allocation or in some
other financial ways.
33
The public tenants should be explained not only one plan, at least two plans as plan A and plan
B. If only one plan is explained, only the result for this plan will always be considered in their
mind and difficult to change depending on conditions.
34
Directors from Ministry of Construction. The number of person in Jury Board is (5) to (7)
depending on project size. The marking system for huge project including at least (4)no. of
high-rise buildings are as follows;
Financial condition of the contractor (10) point
Construction experience in high-rise building (20) point
The program for internal QA/QC (15) point
Required heavy machineries and equipment possession
and resources for qualified engineers (15) point
The plan for investment and fund flow (10) point
Plan for master schedule (construction period) (10) point
Unit sharing ratio for finished buildings (20) point
Total (100) point
35
(b) Strategy Related with Time
Because Project Master Schedule has already prepared in the pre-construction stage, separate
schedule with detailing for each work package and also short interval plan is needed to prepare
in the construction stage. When delay appears in some activities, catch up program must be
drawn as soon as possible by holding meetings with related persons such as sub-contractors,
supervisors, material suppliers, etc.
Weekly meeting should be held in the site office during weekdays especially between Tuesday
and Thursday in the morning. Meetings should be held by two portions, one for design
meeting and another for construction meeting and the project participants have to attend only
to the related meeting. Meeting minutes for each meeting must be distributed to the attendees
not later than coming Monday.
36
3.5.5 Commissioning
Commissioning must be made for electrical and mechanical machines and equipment when
the building is finished and before handover. The responsible engineers from Construction
Company or material supplier must explain the practical operation with the manual guide
book. The client's representative or resident engineer must note down the operation works,
maintenance procedures and avoidance. In relocation projects, the representative on behalf of
public tenants has to invite to involve in the commissioning process.
3.5.6 Handover
In normal construction project, the building is handed over from the contractor to the client as
the substantial completion. Copies of manual guide books for M&E installation works are
transferred to the client. Defects or some works which the client or user do not satisfied must
be repaired within the scope. In relocation project, contractors have to hand over to owner and
owner hands over to the public tenants systematically.
The most important documents for this stage is BCC (Building Completion Certificate) to
hand over from contractor to client or unit purchaser. Without BCC no one can occupy in this
residential building and if stay without BCC, fine or penalty have to pay by per diem rate. The
rate is mostly 10000 Kyats per day for one unit. The contractor has to take responsibility for
getting this document (BCC). Although it is an understanding in the residential construction
work, it should be written clearly in the construction contract.
37
Table (3) Comparison for Existing and Proposed Improvement
Feasibility study Do not have proper feasibility Should do proper feasibility study
study, only for network with the intention of sustainable
infrastructure and market environment for the people living
price of the finished units. this region.
Tendering Although the winner for A firm contract should be done for
for Design architectural design is chosen the quality improvement of every
and the awarded price is design concerning with the project.
given, there is no proper
contract between designer &
owner
Tendering Two envelops systems is used Good enough in current project
for construction by choosing QCBS in starting in 2015.
tendering for contractors.
Contractual Include only penalty for delay, Should also include more detail in
Stage general for scope of work in scope of work, reporting system,
for Construction the contract. quality standard, rework for defect
etc.
Construction Weakly project meetings are Weekly meetings should be held
Stage held separately by the with the guidance of DUHD
contractors, without inviting together with the contractors,
DUHD. quality consultants and designers
(if necessary)
Meeting with public tenants Tri-party meetings between
are only held before and after DUHD, contractors and public
the construction. tenants should be held three or
four times during construction
period.
There are no enforcement for Safety and Health program should
Safety and Health issue by the be made enforcement to reduce
authorized organizations. accident and near miss.
Commissioning The responsible engineers It is good enough for current
from construction company or projects.
material suppliers explain the
practical operation with
manual guide book.
38
Stage Existing Proposed Improvement
Hand-over Manual guide book for M&E Copies of manual guide book for
installation works are kept in M&E installation are transferred to
contractors. the client.
Project Project review is done just a Project review should be done
Close out little by contractors only in systematically and thoroughly by
some project. the project team for every project
to get lessons learnt for the next
projects.
39
Chapter (4)
Conclusion
In the construction industry, there have been many projects implemented successfully for
commercial, residential and mixed used. But only few projects are executed for the purpose of
relocation. The project team needs to manage carefully in this kind of project because of
relating to public. Actually public tenants are not owners, but sometimes they want to get more
opportunities than the one who purchased the units. Although the purchaser can be negotiated
and they can be patient for a few month delays, the tenants cannot be patient and they are used
to want more market rental charges to stay outside for delay. If they do not satisfy and inform
to president office or Yangon region chief minister office or journalist, the project team will
get busy for the explanation of real condition.
Because construction is a dynamic business and plays many people with specific professionals
such as architects, engineers, contractors, material suppliers, management people, labours, etc.
Therefore, the pace of all these members must have balance to complete the successful
housing project.
In conclusion, not only for project management strategy, communication and negotiation
strategies are also necessary in order to develop the successful public housing relocation
project.
40
Appendix
Appendix 1
41
Appendix 2
42
Appendix 3
43
Appendix 4
44
Appendix 5
45
Appendix 6
46
Work Schedule for Relocation Buildings Appendix 7
1 Knocking Down
2 Site Claning
3 Pile Work
4 Foundation Work
Program
Progress
19 Mansonary
20 Chowket
21 Electrical
22 Sanitary
23 Painting
24 Tiling
25 Aluminium
26 Steel
27 Ceiling
28 Lift
29 Iron Grill
30 Transformer
31 Generator
32 Landscaping
33 Apron & Drain
Program
Progress
47
Appendix 8
48
Appendix 8
49
Appendix 8
50
Appendix 8
51
Appendix 8
52
Appendix 8
53