The document outlines the construction project G+0 Resifence in Dire Dawa, detailing the costs associated with various substructure and superstructure works. Key components include excavation, masonry, concrete, block work, and finishing tasks, with a total estimated cost of 153,216.05. Several items are marked as '#NAME?' indicating missing data that needs to be addressed for a complete financial overview.

Uploaded by

tadessee165
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views3 pages

DR Tesfaye

The document outlines the construction project G+0 Resifence in Dire Dawa, detailing the costs associated with various substructure and superstructure works. Key components include excavation, masonry, concrete, block work, and finishing tasks, with a total estimated cost of 153,216.05. Several items are marked as '#NAME?' indicating missing data that needs to be addressed for a complete financial overview.

Uploaded by

tadessee165
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Project Name: G+0 Resifence

Client :
Location: Dire Dawa
Consultant:
Summary
A/SUB STRUCTURE
1 Excavation and Earth work 3,888.00
2 Masonry works 32,064.00
3 Sub structural Concrete Works #NAME?
Sub Total A #NAME?
B/SUPPER STRUCTURE
1 Super structural concrete Works 45,344.00
2 Block work 24,000.00
3 Roofing #NAME?
4 Steel Structure #NAME?
5 Carpentry and Joinery #NAME?
6 Aluminium Works #NAME?
7 Plastering and Finishing #NAME?
8 Glazing 38,905.84
9 Painting #NAME?
10 Sanitary instalation #NAME?
11 Electrical instalation #NAME?
12 Mechanical instalation 9,014.21
Sub Total B #NAME?
Total (A+B) #NAME?
VAT(15%) #NAME?
Grand Total #NAME?
Item Description Unit Quantity Price Amount 1 To hide zero values, click on the downw
A. SUBSTRUCTURE 1
1. EXCAVATION & EARTH WORK 1
1.60 Trench excavation for masonry foundation wall to an average depth of 1000mm from reduced level
in ordinary soil m3 12.96 300.00 3,888.00 #REF!
SUB TOTAL CARRIED TO SUMMARY 3,888.00 1
3. MASONRY WORK 1
3.10 Basaltic or equivalent stone masonry foundation bedded in cement sand mortar (1:4) #REF!
a) Below N.G.L. m3 4.45 3,200.00 14,240.00 1
3.20 Fair faced chiseled or dressed natural stone masonry foundation bedded in cement same mortar
(1:4), The price includes pointing work #REF!
a) above N.G.L. m3 5.57 3,200.00 17,824.00 1
SUB TOTAL CARRIED TO SUMMARY 32,064.00 1
1. CONCRETE WORK 1
1.10 C-25 concrete casts into Formwork and vibrated around Rod Reinforcement with 420 kg
cement/m3 : "type of cement to be PPC" #REF!
a) Columns m3 0.84 5,000.00 4,200.00 1
b) In Beams m3 1.48 5,000.00 7,424.00 1
1.30 Steel Reinforcement bars according to structural drawing. Prices shall include cutting, bending,
Tying wires and placing in position #REF!
a) 6mm def bars Kg 12.00 175.00 2,100.00 1
b) 10mm def bars Kg 85.00 175.00 14,875.00 1
c) 12mm def bars Kg 74.00 175.00 12,950.00 1
form work for column,beam m2 25.30 150.00 3,795.00
SUB TOTAL CARRIED TO SUMMARY 45,344.00 1
2/ BLOCK BRICK AND MASONRY WORK 1
2.10 20 cm thick Class "C" HCB wall bedded in cement mortar (1:3) m2 24.00 1,000.00 24,000.00 1
SUB TOTAL CARRIED TO SUMMARY 24,000.00 1
7. FINISHING #REF!
Finishing work shall include all surface pre cleaning, preparation and application of finishing and
cleaning at the end of finishing work. #REF!
7.1 Apply two coats of plastering with cement mortar (1:3) Mortar for grooves recessed by 5 mm
between beams and walls, columns and walls. #REF!
a) to internal wall surface m2 27.50 452.00 12,430.00 1
b) to external wall surface m2 27.60 452.00 12,475.20 1
c) to exposed beams, columns m2 24.45 452.00 11,050.50 1
7.3 Apply pointing to 1
a)external exposed stone masonry wall in cement mortar (1:3) m2 19.27 153.11 2,950.15 1
SUB TOTAL CARRIED TO SUMMARY 38,905.84 1
9. PAINTING #REF!
9.10 Prepare the surface and apply three coats of plastic emulsion paint to all internal plastered wall
surface nifas silk or equivalent paint. m2 54.60 127.68 6,971.33 #REF!
9.20 Ditto item 9.1 but to plastered beams and columns m2 16.00 127.68 2,042.88 1
SUB TOTAL CARRIED TO SUMMARY 9,014.21 1
Ground Total Summary 153,216.05