0% found this document useful (0 votes)
6 views2 pages

CM Mock Paper

Uploaded by

t.a.240802
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views2 pages

CM Mock Paper

Uploaded by

t.a.240802
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Final Examination, Summer 2025

Course: Constraint Management (MGT 340)


Time: 1 hour
Full Marks: 20

Instructions:

1. Answer any TWO questions from Part-A


2. Answer the COMPULSORY question from Part-B

Part – A (Answer any TWO questions, 5 marks each)

1. Theory of Constraints (TOC):


a) Define TOC
b) How can organizations relate operational measures to its financial measures through
TOC?

2. Bottleneck:
a) Define bottleneck
b) Show a bottleneck and maximum time consumption by an imaginary example

3. Line Balancing:
a) Define precedence diagram and explain its importance in assembly line design (2
marks)
b) Differentiate between cycle time and throughput time (3 marks)
Part – B (COMPULSORY, 10 marks)

4. A garment factory produces shirts through these work elements:

Work Element Time (min) Predecessor(s)


A (Cut fabric) 4 None
B (Sew collar) 6 A
C (Sew sleeves) 5 A
D (Assemble) 8 B, C
E (Inspect) 3 D
F (Package) 2 E

Required:
Draw the precedence diagram

5. A pizza shop makes pizzas through these steps:

Work Element Time (min) Predecessor(s)


A (Make dough) 5 None
B (Add toppings) 3 A
C (Bake) 8 B
D (Package) 2 C

Required Calculations:
a) Cycle Time: Calculate when demand is 10 pizzas/hour
b) Theoretical Minimum Stations
c) Idle Time: For 2 workstations