1ST - MEP CONCEPT DESIGN
Productivity: 10 Villas / Week
HVAC CONCEPT DESIGN
Ref: CD_HVAC_XXX_R00
1. Indoor unit location
2. Outdoor unit location
3. Pool cooling unit location (If any)
4. Extract fans location
5. Duct routing
6. Proposed Machine schedule
PLUMBING CONCEPT DESIGN
Ref: CD_PLU_XXX_R00
1. Location of water meter
2. Location of FIC
3. Location of water tanks, pumps
4. Location of solar heaters or Electrical heaters
5. Location of sump pump (If any)
6. Location of condensate tank (If any)
7. Location of gray water tank (If any)
8. Schematic diagram for water supply system
9. Equipment schedules for heaters, tanks, pumps,..for type, capacity and qty.
ELECTRICAL CONCEPT DESIGN
Ref: CD_ELEC_XXX_R00
1. Meter Cabinet location
2. MDB location
3. Elec DBs locations
4. Etisalat DB locations
5. HA DB location (If any)
6. Rack location (If any)
7. Car charger location (If any)
8. Load estimation
2ND - MEP DESIGN DRAWINGS
Minimum Requirements for Authority submission and building permit
Ref: DD_ELEC_XXX_R00
Ref: DD_HVAC_XXX_R00
Ref: DD_PLUM_XXX_R00
DM SUBMISSION
Productivity: 8 Villas / Week
1. U-Value and
2. Solar heaters calculation, WS roof plan
3. Drainage drawings
4. Etisalat drawings
5. Electrical drawings
NAKHEEL SUBMISSION
Productivity: 20 Villas / Week
1. Daily water consumption calculation
2. Daily waste water discharge calculation
3. Drainage site plan with FIC
TRAKHEES SUBMISSION
Productivity: 8 Villas / Week
1. Water supply drawings
2. AC drawings
3. Ventilation drawings
4. Thermal load calculation/Equipment schedule
5. HAP calculation
6. Indoor lighting plan
7. Outdoor lighting plan
8. Elec site plan & Load Estimation for Elec NOC
9. Water supply site plan for water NOC
DDA SUBMISSION
Productivity: 8 Villas / Week
M-00-XXX
D-00-XXX
P-00-XXX
1. Mechanical, legend & symbols
2. General notes and details
3. Schedule of Equipment
4. Building AC thermal summary sheet
5. Building glazed schedule
6. Building U value calculation
7. HVAC setting out plan
8. HVAC Floor plans
9. HVAC Schematics raiser diagram
10. Elec site plan & Load Estimation for Elec NOC
11. Water supply site plan for water NOC
3RD CIVIL TENDERING DRAWINGS
MEP builder works only for sleeves and containment works
Productivity: 15 Villas / Week
Ref: MEP_BW_XXX_R00
1. Boundary walls builder works
2. Floor slabs builder works
3. Underground pump room/Underground tanks builder works
4. Electrical containment plans (With PVC pipes provisions for Light, Wifi, HA, Sound,..)
5. Descoped MEP works or BOQ with provisional sum amount.
4TH IFC DRAWINGS & MEP TENDERING
Final MEP set coordinated with ID, Landscape, Exterior lighting, Client requirements
Productivity: 5 Villas / Week
Ref: IFC_ELEC_XXX_R00
Ref: IFC_ETS_XXX_R00
Ref: IFC_HVAC_XXX_R00
Ref: IFC_PLUM_XXX_R00
1. HVAC detailed design drawings
2. Drainage detailed design drawings
3. Water supply detailed design drawings
4. Electrical detailed design drawings
5. Etisalat detailed design drawings
6. MEP BOQ