The document outlines the concept designs and submission requirements for MEP (Mechanical, Electrical, and Plumbing) systems for villas, detailing productivity rates for various stages. It includes HVAC, plumbing, and electrical design elements, along with specific requirements for authority submissions and tendering drawings. Each section specifies locations, calculations, and drawings necessary for compliance and project execution.

Uploaded by

manarosamagaberr
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
65 views5 pages

Mep Design Stages

The document outlines the concept designs and submission requirements for MEP (Mechanical, Electrical, and Plumbing) systems for villas, detailing productivity rates for various stages. It includes HVAC, plumbing, and electrical design elements, along with specific requirements for authority submissions and tendering drawings. Each section specifies locations, calculations, and drawings necessary for compliance and project execution.

Uploaded by

manarosamagaberr
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

1ST - MEP CONCEPT DESIGN

Productivity: 10 Villas / Week

HVAC CONCEPT DESIGN

Ref: CD_HVAC_XXX_R00

1. Indoor unit location


2. Outdoor unit location
3. Pool cooling unit location (If any)
4. Extract fans location
5. Duct routing
6. Proposed Machine schedule

PLUMBING CONCEPT DESIGN

Ref: CD_PLU_XXX_R00

1. Location of water meter


2. Location of FIC
3. Location of water tanks, pumps
4. Location of solar heaters or Electrical heaters
5. Location of sump pump (If any)
6. Location of condensate tank (If any)
7. Location of gray water tank (If any)
8. Schematic diagram for water supply system
9. Equipment schedules for heaters, tanks, pumps,..for type, capacity and qty.

ELECTRICAL CONCEPT DESIGN

Ref: CD_ELEC_XXX_R00

1. Meter Cabinet location


2. MDB location
3. Elec DBs locations
4. Etisalat DB locations
5. HA DB location (If any)
6. Rack location (If any)
7. Car charger location (If any)
8. Load estimation
2ND - MEP DESIGN DRAWINGS
Minimum Requirements for Authority submission and building permit

Ref: DD_ELEC_XXX_R00

Ref: DD_HVAC_XXX_R00

Ref: DD_PLUM_XXX_R00

DM SUBMISSION

Productivity: 8 Villas / Week

1. U-Value and
2. Solar heaters calculation, WS roof plan
3. Drainage drawings
4. Etisalat drawings
5. Electrical drawings

NAKHEEL SUBMISSION

Productivity: 20 Villas / Week

1. Daily water consumption calculation


2. Daily waste water discharge calculation
3. Drainage site plan with FIC

TRAKHEES SUBMISSION

Productivity: 8 Villas / Week

1. Water supply drawings


2. AC drawings
3. Ventilation drawings
4. Thermal load calculation/Equipment schedule
5. HAP calculation
6. Indoor lighting plan
7. Outdoor lighting plan
8. Elec site plan & Load Estimation for Elec NOC
9. Water supply site plan for water NOC
DDA SUBMISSION

Productivity: 8 Villas / Week

M-00-XXX

D-00-XXX

P-00-XXX

1. Mechanical, legend & symbols


2. General notes and details
3. Schedule of Equipment
4. Building AC thermal summary sheet
5. Building glazed schedule
6. Building U value calculation
7. HVAC setting out plan
8. HVAC Floor plans
9. HVAC Schematics raiser diagram
10. Elec site plan & Load Estimation for Elec NOC
11. Water supply site plan for water NOC
3RD CIVIL TENDERING DRAWINGS
MEP builder works only for sleeves and containment works
Productivity: 15 Villas / Week

Ref: MEP_BW_XXX_R00

1. Boundary walls builder works


2. Floor slabs builder works
3. Underground pump room/Underground tanks builder works
4. Electrical containment plans (With PVC pipes provisions for Light, Wifi, HA, Sound,..)
5. Descoped MEP works or BOQ with provisional sum amount.

4TH IFC DRAWINGS & MEP TENDERING


Final MEP set coordinated with ID, Landscape, Exterior lighting, Client requirements
Productivity: 5 Villas / Week

Ref: IFC_ELEC_XXX_R00

Ref: IFC_ETS_XXX_R00

Ref: IFC_HVAC_XXX_R00

Ref: IFC_PLUM_XXX_R00

1. HVAC detailed design drawings


2. Drainage detailed design drawings
3. Water supply detailed design drawings
4. Electrical detailed design drawings
5. Etisalat detailed design drawings
6. MEP BOQ