RESS Li-Ion Battery Installation Guide V1.0
RESS Li-Ion Battery Installation Guide V1.0
This guide provides guidance on the safe and effective installation and operation wall mounted
Li-ion batteries. It also provides information on how to safely connect multiple batteries in parallel 1
1 Unpacking Inspection
2 Mechanical Installation
(Max. 6), as well as how to charge and discharge the batteries.
1. Unpack the battery and visually inspect the appearance. If any shipping damage is found,
CAUTION notify the carrier immediately. 2.1. Wall mounted for 5KWH
Due to the regulations governing the transportation of Lithium Ion cells and batteries 2. Press ON/OFF button to active the battery, the SOC and RUN indicator will be light.
Take out wall mounted accessories which include bracket and screws,
internationally. The battery is only 50% SOC during transport. Please charge battery turn on MCB to measure the output voltage by multimeter, For parallel application, the
fully in the first use. voltage difference should less than 500mV. Fix the bracket on the battery and remove the floor mounted part on the
Before connecting any electrical cable, turn OFF all the switches and breakers and turn 3. Press ON/OFF button to shutdown the battery, the indicator light will turn off. bottom of battery.
OFF the batteries by press the ON/OFF button.
.Avoid any fall or collision during the installation process.
Do not remove the battery components. The maintenance of the battery should be
carried out by a professional engineer.
2 4. Check the accessories which should include: Drill 4 pcs Φ10 *110mm holes on the wall, fix wall mounted part on the wall
and fasten the screw head of the expansion bolts
System Introduction
- + Accessories for floor mounted (prevent tilt) Accessories for wall mounted
Bracket for floor mounted Bracket for wall mounted
ON
- + ON
2 pcs outer hexagon inner cross combination bolt _M6X16mm 4 pcs stainless steel expansion screws M8*100mm
ADD
screws
ON/OFF OFF 2 pcs outer hexagon inner cross combination bolt _M8X16mm
ADD screws
CAN RS485 LINK-IN LINK-OUT
ON/OFF OFF
Ÿ Use a proper hammer to fit the expansion bolt into the holes. The screw
head protruding too long may interfere with the battery cabinet.
ON mode
By press ON/OFF button to active BMS to enter into working mode, if the
MCB is also ON, the battery voltage will can be measured by terminal. 2 pcs power cable -Black, Red. 1pc 1pc Optional Part Optional Part Optional Part
100A Version Communication User manual RS485-USB device Wall mounted type parallel parts for
25 mm2 high flexible wire, distribution box-300A floor mounted
Even if the button is at ON mode, The BMS will enter into dormancy mode SC25-8 & SC25-8, L=1500mm
cable-
Only for install engineer 2 pcs outer
150A Version 586B,CAT5e, and after-sale engineer. For several batteries or hexagon inner
after 24 hours when there are no charge, no discharge and no 35 mm2 high flexible wire, 2m inverters in parallel cross combination
SC35-8 & SC35-8, L=1500mm bolt _M6X16mm
communication. it can be activated again by charge or communication or 200A Version 2pcs RJ45
screws
50 mm2 high flexible wire, terminal.
repress ON/OFF button. SC50-8 & SC50-8, L=1500mm
Take out wall mounted accessories which include bracket and screws, For floor mounted parallel connection, it supports to install as below:
Drill 8 pcs Φ10 *110mm holes on the wall, fix wall mounted part on the wall and fasten the screw head
of the expansion bolts.
COM cable
ON ON
ADD
4 Cable Connection
ON ON
Step 4. Make sure the inverter had be The length of power cable should be the same.
Note: installed correctly.
Ÿ Remember that the battery is heavy (96Kg) ! Please be careful when doing operation. Step 5. Press ON/OFF button to active
the battery BMS and connect ON
Ÿ Use a proper hammer to fit the expansion bolt into the holes. The screw head protruding too long battery to PC by BMS PC
may interfere with the battery cabinet. software, select inverter protocol
ADD
- +
on BMS (detail operation refer to ON/OFF OFF
user manual)
2.4. Floor mounted for 10KWH
Step 6. Turn on battery breaker and the
RS485 to USB cable
inverter will be activated, set the ON
inverter (battery type and CAN RS485 LINK-IN LINK-OUT
protocol). 1 2 3 4 OFF
ADD
Note:
Ÿ For 1pcs 5KWH battery and 10KWH-100A , it max support 5KVA inverter or the real load
ON
power consumption is less than 5KW. ON
Ÿ For 1pcs 10KWH-200A battery , it max support 10KVA inverter or the real load power
consumption is less than 8KW.