Internship Report
Internship Report
Summary5
General introduction............................................................7
List of tables
Table 1: Human resources of the company ..................................................................................10
Table 1.1The Lambert coordinates of the origin and the end of the project14
Table 1.2: Average rainfall values of the province of Kelaat Mgouna.......................16
Table 1.3: Variation in the temperature of the Kelaat Mgouna region.........................................16
Table 2.1: The geometric characteristics of the non-category.
Table 2.2: Structure of the roadway for the rectified sectionss....................................................20
Table 2.3: Characteristics of watershedst r a n s l a t e d Te x t ...........................................................................23
Table 2.4: Value of coefficient k depending on the nature of the surfacee ......................................24
Table 2.5: Runoff coefficient value....................................................................................25
Table 2.6: Debits retained by empirical formulas .................................................................27
Table 2.7: Summary table of the works...............................................................................28
RESUME
Our work focuses on the study of the execution project for a section of the rural road at PK 14+000.
at PK 26+000 in the province of Tinghir. We focused our work on the detailed study
the first 12 kilometers of this road which present at certain points situations
singularities related to the succession of a series of very small turns that do not respond to the
road design standards.
Our contribution was mainly focused on the preparation of the execution file that addresses
to the objectives of the required improvements for this road. In this approach, we took into
consideration of all the imperatives related to this road taking into account the estimate
project cost. As with civil engineering constructions, the construction of this road requires
preliminary studies. This concerns topographic studies (planimetry and altimetry of
terrain), traffic studies, and geotechnical studies, which led to the determination of the
basic project data.
We opted for the use of the software 'Piste 5' for road design; as a result, it
once the design is finished, the floor plans, the long profiles, the cross profiles and the
volume of pavement and earthworks materials. The preliminary measurement of the planned works has
permission to estimate the quantity of sanitation and rainwater drainage elements at
achieve. We have thus determined the quantification of the preliminary measurements of the works, of the
roadway and earthworks and the value of this project.
5
LIST OF ABBREVIATIONS
BV Watershed.
EB Bituminous Coating
ED Definition Study
PE Execution Project
PK Kilometric Point
Rr Rural route
6
INTRODUCTION
This graduation thesis is part of the preparation for the specialized Master's in Engineering.
and Project Management of Buildings and Public Works. It corresponds to the report of an internship
4 months completed in a design office that operates in the fields of civil engineering and
public works. Our work focuses on the study of the execution project of a section of the road
rural PK 14+000 to PK 26+000, in the province of Tinghir. It allowed us to
familiarize with the real contexts of a road project and closely monitor all the stages of
design and implementation of this road field.
Indeed, the construction of this road network is considered one of the effective means of
promote the economic development of a country. Infrastructure in general and the
Road transport infrastructures in particular undeniably represent the elements
drivers of economic development. This is within the framework of the development of these
road infrastructures that the provincial direction of equipment and transport of Tinghir has been.
initiated by the realization of this project.
This is part of the policy for the modernization of the road network and its adaptation.
with the evolution of traffic and in the development strategy of the Southeast provinces of
Morocco. Indeed, the construction of a road communication system is participating
Significantly in the socio-economic development of a country. The functions that are ensured by the
there are indeed multiple routes, both in the social and economic fields:
- On a social level: the road facilitates exchanges between different regions of a country, and
participate in socio-cultural and administrative exchanges.
In economic terms: the road is a means of collecting and distributing goods by
excellence. It ensures direct contact between producing and consuming populations;
In agreement with the design office, we have focused our work on the detailed study of the
twelve kilometers of this road encompass all the realities that exist over the twenty-six kilometers.
The recommendation of these twelve kilometers relates to the specific nature of this segment which
presents in certain places unique situations related to the succession of a series of turns
very limited that do not meet road design standards.
During this internship, we were led to work in a group with the entire technical team of this
research office and to participate in the various ongoing operations of these activities. However,
Our contribution has mainly focused on the preparation of the execution file that meets
to the objectives of the required improvements for this road. In this approach, we took into
consideration of all the imperatives related to this road taking into account the estimate
Project cost. Two steps were taken before arriving at its estimate:
However, like any civil engineering construction, the construction of this road cannot be
do without prior studies. These studies mainly concern topographic studies.
(planimetry and altimetry of the terrain), traffic studies and geotechnical studies, which have
led to the determination of the project's basic data.
We chose to use the software 'Track 5' for road design; due to the fact that it
give, once the design is finished, the plan drawings, the long profiles, the cross profiles and the
volume of pavement and earthworks materials. The preliminary measurement of the proposed works has
permission to estimate the quantity of sanitation and rainwater drainage elements at
to achieve.
PRESENTATION OF THE STUDY OFFICE
SOGETRAP SARL: General company for studies and public works with limited liability
MOHAMED OUHADDACH
600,000.00 dirhams
Registered office address of the company: RUE RAHAL BEN AHMED 40000 GUELIZ
MARRAKECH
Affiliated with the CNSS under No: 7828968
Registered in the trade register of (locality): Marrakech under no.: 34055
5398377
HUMAN RESOURCES
2011 4 2 - 6
2012 4 4 - - 8
2013 4 5 - 1 10
2014 5 6 - 3 14
2015 6 6 - 3 15
2016 6 7 3 16
Chapter 1
I. Introduction
During my internship, the main objective is to create a general design for a road project.
During the first month we tried to read and understand the different elements and the
software that is part of the study of a road project. Then, we started with a small
project of an essay in which we will see the different elements that are part of the projects
truck drivers.
The project is focused on the study of a 2km road layout in a rural area. We are
called to conduct the road study of the route and this project will clearly present our activities
which consists of establishing:
• Sizing of structures.
The plan layout of a road is the orthogonal projection of all points on a horizontal plane.
which is generally a topographic map or a situation plan where the relief of the terrain is
represented by contour lines.
The plan layout is a succession of straight alignments and circular arcs connected by
successive connection curves.
The dimensional layout rules in plan aim, on one hand, to ensure conditions of
relatively homogeneous comforts along a road axis, and adapted to each category of road;
by setting minimum characteristics in particular. On the other hand, to ensure good conditions
of safety, notably through principles of sequencing the different elements of the layout and
the principles related to visibility.
The main goal of the long profile is to ensure continuity in space for the driver.
the road in order to allow him to anticipate the evolution of the route and a good perception of the points
singular.
In order to avoid significant earthworks, a correction of the red line will be carried out while
respecting the technical conditions for road development.
The cross profile of a road is the cross-section of this roadway along a vertical plane
from this latest one following a vertical plane perpendicular to its axis.
It is a basic document drawn up in the projects for new roads or road development.
existing.
It contains all the constructive elements of the future road, in all situations (in embankment,
excavated). or mixed
5. Earthworks
Digging a trench, a ditch, or more generally modifying the ground's relief represents in itself a
earthworks.
6. Plate
Field of land occupied by the roadway, it includes the shoulders; the ditches and
the total clutter of the works.
7. Showcase
Part of the land belonging to the community, designated for the road and its dependencies, which coincides
with the public domain.
8. Causeway
Surface of the road designed for vehicle traffic. In structural terms, it is the whole
layers of materials that support the passage of vehicles.
Platform
Clearing route: The platform extends to the edge of the ditch on the roadside if there is no ditch,
it extends to the foot of the delay bank.
10. Shoulders
Lateral zones that border the roadway externally. The shoulders are "lowered" if they are
at the same level as the roadway. They are "elevated" otherwise.
In the second month of my internship, after reading the documents related to road design.
we started a new project located in the Ouarzazate region which aims to
conduct a technical study on 6.5 km and understand the study software (Track and AutoCAD).
The project in question is located to the west of the city of Kellat Mgouna, 45 km away;
take respectively the origin and the end at pk 14 and pk 26 of the Rr that passes through Amjgag.
The Lambert coordinates of the beginning and end of the project are as follows:
Table 1.1: The Lambert coordinates of the origin and the end of the project
DESIGNATION X Y
ORIGIN OF PROJECT 420295.0723 99828.7686
END OF PROJECT 416912.6438 105297.6584
Figure 1.2: Project location plan
The studied route develops from its origin at PK14 on flat and hilly terrain at PK
20 then it develops in rugged mountainous areas.
The terrain morphology has an irregular topographical aspect with flat reliefs,
hilly then steep, particularly the mountainous section of Imgoune.
The entire route is located between the coasts 2027.4 and 3015.05 relative to the general level of
Morocco.
V. Climate Context
The climate of the study area is arid, hot in summer and cold in winter.
The precipitation in the municipality is relatively low, characterized by its rarity and
The irregularity. The average annual rainfall is about 143.2 mm.
The average recorded temperature is around 22°C with significant temperature variations.
In summer, the temperature can reach 42°C, and in winter it drops to -2°C.
Precipitation
ie mm
35
30
25
20
Rainfall...
15
10
5
0
Sep Oct Nov Dec Jan Feb Mar Apr May June July August
Figure 1.3: Histogram of the variation of the average rainfall in Kelaat Mgouna.
2. Temperature
A significant thermal gap between winter and summer, the average temperature varies from -2°C in
February, which is the coldest month of the year (2013), up to 42°C in July, the hottest month.
hot. The daily maximum temperatures are recorded in July and the minimums in
January.
Month Sep Oct Nov Déc Jan Fév Mars Avr Mai Juin Juill About
38.20 32.4 25,7 23,2 20,8 27,3 27.2 31.3 32.9 37.9 42 41.2
maximum temperature (°C)
3. Evaporation
The measurement of evaporation from a free surface is an essential climatic data for
appreciate the evaporating power of the atmosphere when it is not possible to proceed with some
measures of other more precise parameters such as saturation deficit, solar radiation and
temperature gradients.
Vent
The prevailing winds mainly blow from the North, Northeast, and Southwest. The winds from the North sector
are most often humid, while those in the Southeast are dry (chergui type). Their intensities
are averages, they vary from 15m/s to 29m/s.
The local geology of the project is characterized by the presence of Lower Proterozoic terrains.
made up of mica schists, gneiss, and magmatites. The whole is intersected by dykes.
of dolerite. The series of quartzites and limestones attributed to the Middle Proterozoic crops out in the north
Locally, the encountered formations are made up of clayey gravel in the form of tuffs.
gypsum, fine tuffs or gravelly.
During the first month of my internship in the technical office, I learned and I gained confidence.
several things about road design in Morocco in general, namely:
Presentation of the tasks accomplished during the last two months of the internship
I- Current outline
At its origin 14+000, at the entrance of the ALMOU NZI agglomeration, the route develops on
flat and hilly land up to RUTA DE DADES at km 20+000, offering the possibility of
project very satisfactory geometric characteristics. Beyond that, the drawing begins to grimace
the mountain until arrival at pk26+000 over a length of 6 km. Along this section,
the current geometric characteristics are very poor and are presented in the form of a
a succession of curves with very shallow radii. The slopes are very steep in some places.
sections but do not exceed 12%. The main characteristic of this section is that it
has a rocky character.
The traffic supported by the tracks is very low, at around 40 to 50 vehicles per day.
The results shown from the graph indicate that the measurements are moderate.
regular and homogeneous between the year 2008 and 2013.
The construction of the runway will generate an expected T4 class traffic according to the catalog.
Moroccan standardized road structures. In the sense of the new catalog, traffic corresponds to
TPL1.
The formula chosen for traffic calculation reflects an exponential growth of traffic.
which is presented as follows:
With:
Average daily traffic of year n.
Project lifespan.
III- Geometric aspects
The current geometry of the project as a whole is acceptable; it corresponds to the outside.
category in the sense of the Instruction on the geometric characteristics of open countryside. Thus the
The alignment of the plan and the longitudinal profile of the project will be carried out in accordance with the following principles:
Choice of category
The rural road is part of the structuring axes whose development is essential and allows for a
easy access to the Southeast regions through a high-level service road infrastructure and
security.
The projected geometric characteristics are those recorded in the instruction on the
geometric characteristics of roads in rural areas of the non-category.
According to REFT standards, the rays satisfying these two conditions are given in relation to the
base speed and category, for bidirectional choice and for a base speed
Vr=40Km/h on a :
Table 2.1: The geometric characteristics of the non-category
CHARACTERISTICS STANDARDS
TRACE ON PLAN
Curvature radius:
Minimum normal 30
Absolute minimum 15
SIDE PROFILE
Ramp:
Maximum normal 7%
Corner connection:
Corner connection:
The platform will be widened and homogenized in parts of the route with the construction of a
platform.
A cross slope of 2.5% will be adopted for the roadway and 4% for both shoulders.
1m 4m 1m
RS (double layer)
15 cm
15 cm
15 cm
The platform will have a width of 6.00m, with triangular ditches of 1.20m open mouth.
and 0.50m deep.
The slopes of the embankments in excavation will be determined by the geotechnical study according to the formations.
of soils encountered.
The slopes of the embankment slopes adopted are equal to 3/2 (3 horizontal for 2 vertical).
In a curve, the slope will be:
4% for the minimum free and normal.
7% for the absolute radius, this slope can be reduced to 4% for excessive edges.
road or to facilitate the connections of slopes.
i. Sanitation:
The platform is flanked laterally by a collection and drainage system.
constituted by a ditch. This ditch also receives runoff water from the
talus.
2/3 0.50
1/1 1/10.50
0.50
These cross-sectional works are placed at the outlets of the watersheds and at the level
low points for sanitation.
ii. Protection :
The protections are located at the crossings of the chaabas.
IV- HYDROLOGICAL AND HYDRAULIC STUDY
1. Introduction
2. Hydrological study
a. Delimitation of watersheds
b. Definition
A watershed is an area defined by a boundary within which every drop that
Rainwater must imperatively go into the main thalweg after passing through one of the thalwegs.
secondary.
Figure 2.4: represents the delimitation of the respective watersheds of the project.
Table 2.3: characteristics of watersheds
Considering the nature of the road and their service objective, it is not possible for...
economic and financial reasons, to anticipate works that must face all the
climatic events and therefore to all floods. It is necessary to accept a certain risk that a
the structure may be damaged; this risk varies from one project to another.
In all rigor, the choice of the return period of a flood should be the subject of an analysis.
comparing the investment cost of the work with the consequences of an overflow
water for the user, the residents and the structure.
Given the importance of this project, we opt for a long centennial payback period, the cost
The investment is high and its maintenance will be moderate.
The determination of an input flow takes into account several factors reflecting the parameters.
of climatic and morphological orders, relating to the contributing basin and the watercourse
draining.
As a result, the input flow rate is estimated using empirical formulas commonly used.
in the field of road crossing structures.
K Coefficient related to the nature of B, V and varying between 0.11 and 0.43
3.2.Burki-Ziegler formula
C Runoff coefficient
Q=C.I.S/3.6
I Average intensity of rain with frequency F in mm/h during the concentration time
Tc ;
C Runoff coefficient.
Brick:
Tc=1/52x[L/P0.5]0.77
Turraza:
Tc = 60 x 0.108 x (S.L)^(1/3) / Sp
Spanish
Tc=60x0.30x(L/P1/4 )0.77 ,
Ventura
Tc=76.32x[S/(100xP)]1/2
Californian
Tc=60x0.1452.(L/ P1/2)0.77,
With:
slope in m/m
3.4.MALLET-GAUTHIER FORMULA:
Q(T)=2K.log(1+A.H)xS/L0.5x(1+4xlog(T)-log(S))0.5
T Payback period;
K: coefficient variant from 0.5 (for large B.V with low slope) to 5.0; (For small B.V)
strong slope). Let K=2.
T Return period
We take N=85
4.Retained flows
The inflow rates retained for the sizing of the structures are presented as follows
next:
Table 2.6: Flows retained by empirical formulas
E- Fuller II - - Yes
F- Regional - - Yes
The main function of such a structure is to allow the passage of a watercourse underneath a
fill and support the loads that solicit it, its design therefore involves
hydraulic and structural considerations. Among the considerations related to hydraulics, the
The passage of water must be carried out without causing flooding or flow conditions.
inadmissible.
5.1.DELORME Method
This is a simple and the most widely used method for the sizing of hydraulic structures.
The flow rates capable of the structures are given by flow rates that correspond to the critical flow rates.
determined by the Delorme formula
In which:
Qc: Critical discharge evacuated in m3/s
buses dalots
No. Flow
No OH Profile No. PK Observations
BV of contribution diameter
number long Number Long High Rare
On a relational level
Group work.
V- Project Estimation
Our work focuses on service level roads and road networks and on its
this that the Ministry of Equipment and Transport, in its Development policy, has initiated
the construction of road infrastructure to open up the southeast of the country and increase its
road network and its adaptation to the evolution of traffic and in the development strategy of
It should be noted that the rural road is an integral part of the development axis of the south.
going from Kelaat Mgouna to Azilal. It is therefore a tourist route that crosses Amjgag.
In our study, we have thus determined the quantification of the preliminary estimate.
works, of the roadway and earthworks and the value of this project.
BIBLIOGRAPHY