Example of Scrum Report
Example of Scrum Report
Development of a Web Application for the Newport Institution Implementing the SCRUM Methodology
Table of contents
1. Introduction. 2
1.1 Purpose. 2
2. General Overview of the Methodology. 2
2.1 Foundation. 2
2.2 Work values. 2
3. People and roles of the project. 3
4. Artifacts. 3
4.1 Increase. 4
4.2 Burn Down Chart. 4
4.3 Meeting to generate the Product Backlog. 4
4.4 Meeting for generate the Sprint planning. 5
4.5 Meeting of Work. 7
1 | Page
1. Introduction
This document describes the implementation of the SCRUM work methodology in the
Newport Institute Web Application Development Project.
Include along with the description of this iterative and incremental life cycle for the project,
the artifacts or documents used to manage the tasks of acquisition and supply:
requirements, monitoring and tracking of progress, as well as the responsibilities and
commitments of the participants in the project.
1.1 Purpose
Report the way of working that was adopted by the team for the implementation of the methodology.
Scrum and to describe the process that followed in the development and control of the first sprint.
Team autonomy
Respect in the team
Responsibility and self-discipline
Focus on the task
Transparency and visibility information.
2 | Page
3. Project personas and roles
Role Member
Scrum Master Martha Leticia Sánchez López
Product Owner Maria Esmeralda Pérez Piñón
Analyst/Documenter Diana Fernanda Díaz León
Designer Jurhiata Joel Ibarra Garnica
Programmer Miguel Ángel Rodríguez Guzmán
Programmer Ignacio Alan Moreno Álvarez
Programmer Antonio Abraham Ochoa Avalos
Tester Celeste Álvarez Aguirre
Programmer Miguel Ángel Ramírez Rodríguez
o Responsible for carrying out the necessary work to deliver the increase of the
project.
o Updated knowledge and understanding of the product stack
o Sprint backlog creation.
o Auto-assignment of work.
4. Artifacts
Product Backlog
Sprint Backlog
Sprint
Increase
3|Page
Work Meetings
4.1 Increase
Part of the application that was produced in a sprint and delivered to the client completely.
finished and operational.
4.2 Burn Down chart
Effort chart
Pending Effort
16
14
12
10
8
6
4
2
0
Meeting to determine the functionalities or user stories that will be included in the Sprint.
Generated by the Product Owner Esmeralda, Scrum Master Martha, and the development team.
This meeting took place on Friday, October 3, 2014
Where was it determined which are the most important modules for the client? What are the stories?
What will be part of each of the modules and what is their priority?
Follow-up that was done that day:
- The Product Owner (Esmeralda) mentioned to the rest of the Scrum team what the
general project requirements as well as what matters most to the client.
- The product owner writes down these requirements on the whiteboard, subsequently the team members of
team gave their opinion on which ones have higher priority than others, in the cases
that not everyone agreed on the priority, an explanation was requested as to why it is considered that.
of higher or lower priority, ending their explanation, the rest said because they were
agree or not, in cases where they did not yield their opinion, it was determined by majority
voting.
- The team members self-assigned themselves to the responsible parties for each H.U according to the
skills that each individual has and taking into account the roles they perform.
- Scrum acted as a moderator in this decision-making process.
- This is how the activity of gradually generating the entire product backlog was carried out until it was completed.
4 | Page
4.4 Meeting to generate the Sprint planning
The purpose of Sprint planning is to provide the team with enough information so that
determine how they will work during the 2 weeks that the sprint lasts.
A Sprint goal
Work with commitment and responsibility in order to deliver on time and in the correct manner the first
sprint of the Database Design thus satisfying the client's requirements.
Member Dedication
Martha Leticia Sánchez López 100%
Maria Esmeralda Perez Pinon 100 %
Diana Fernanda Díaz León 95%
Jurhiata Joel Ibarra Garnica 95%
Miguel Ángel Rodríguez Guzmán 85%
Ignacio Alan Moreno Álvarez 85%
Antonio Abraham Ochoa Avalos 85%
Celeste Álvarez Aguirre 85%
Miguel Ángel Ramírez Rodríguez 85%
A Product Backlog
It is a prioritized list of requirements, or stories, or functionalities (that the client wants, where it is used)
terminology).
Product Backlog
5 | Page
This consists of breaking down the user stories into tasks that the team will develop in the iteration.
Sprint 1
Sprint Start Duration
1 06/10/2014 2 Weeks
Sprint Backlog
6 | Page
Antonio
Create a query to verify the existence of the Ignacio
005 T
user Miguel A
Miguel
Antonio /
Ignacio
005 Create session validation file T
Miguel A
Miguel
Antonio
Ignacio
005 Create interface to terminate connection T
Miguel A
Miguel
Fig. 2 Sprint Backlog Deployment Format
Where the Scrum Master supervises the meeting and notes the needs or impediments that I can.
detect the equipment.
Place: room J4
Time: 11:00 am to 2:00 pm
Day: Friday
A Work Structure
Communication within the team will be informal, through email, social media and
face-to-face dialogue.
This aims to develop the sprint activities in which the whole team participates.
Scrum.
Follow-up that was given:
The Scrum Master takes attendance at the agreed time, noting delays and absences of
team members.
Subsequently, the sprint planning is illustrated, where the order of the activities is observed.
elaborate.
The activities were carried out according to the planning, taking into account the planned hours.
but in case it does not reach, the dedication time will be extended.
The Scrum Master is responsible for providing everything necessary to ensure that there are no impediments.
to work and to record the conflicts or obstacles present for the completion of any activity.
In case not all activities of that day are completed, another workday is proposed or if each
individually responsible performs their task but with a due date.
7 | Page
Meeting October 10, 2014
Assistance
Delay
faults
1
0
Miguel Miguel Celeste Anthony Jurhiata Maria Martha Diana Ignacio
Angel Angel Alvarez Abraham Joel Ibarra Esmeralda Leticia
Fernanda Alan
Rodriguez Ramirez Aguirre Ochoa Garnica Perez Sanchez Diaz Leon Moreno
Guzman Rodriguez Avalos Pine nut Lopez Avila
8 | Page