JBALB Technical Guidelines Ed 2024
JBALB Technical Guidelines Ed 2024
TECHNICAL
GUIDELINES
WATER SUPPLY SYSTEMS
Edition
2024
JBALB Technical Guidelines for Water Supply System in Sarawak
Abbreviation
AC Alternating Current
API Application Programming Interface
BOMBA Fire and Rescue Department of Malaysia
BPS Booster Pump Station
BRC British Reinforcement Company
BS British Standard
CCTV Closed-Circuit Television
CI Cast Iron
CO2 Carbon dioxide
DMA/DMZ District Metering Area / District Metering Zone
DI Ductile Iron
EC Electrolytic Chlorination
H2S Hydrogen Sulfide
HDPE High Density Polyethylene Pipe
ICT Information and Communications Technology
IEC International Electrotechnical Commission
IEEE Institute of Electrical and Electronics Engineers
JBALB Rural Water Supply Department (Jabatan Bekalan Air Luar Bandar)
FIFO First-in-First-Out
FRP Fiberglass Reinforced Plastic
GI Galvanized Iron
HLT High Level Tank
HT High Tension
kVA Kilo-volt-amperes
kW Kilowatt
LT Low Tension
MCC Motor Control Centre
MCMC Malaysian Communications and Multimedia Commission
ML Mega Liter
MLD Mega Liter per Day
MoH Ministry of Health
MSB Main Switch Board
MSCL Mild Steel Cement Lining
NB-IoT Narrowband Internet of things
NDWQS National Drinking Water Quality Standard
NPSH Net Positive Suction Head
NREB Natural Resources and Environment Board
NRW Non Revenue Water
O2 Oxygen
OSHA Occupational Safety and Health Act
PLC Programmable Logic Controller
RC Reinforced Concrete
RCPM Remote Cathodic Protection Management
RF Radio Frequency
Rpm Rotational speed per minute
SCADA Supervisory Control and Data Acquisition
SESCO/SEB Sarawak Energy Berhad
JBALB Technical Guidelines for Water Supply System in Sarawak
Contents
1 WATER DEMAND AND CONSUMPTION 1
1.1 Scope of Work Supply 1
1.2 Per Capita Consumption 1
1.3 Demand Fluctuations Factors 1
1.4 Allowance in excess 1
1.5 Fire Fighting Demand 2
1.6 Design Period for Water Supply Components 2
1.7 Population and Water Demand Estimates 2
1.7.1 Population Projection 2
1.7.2 Water Demand Estimation and Projection 3
2 Pipeline 4
2.1 Types of Distribution Systems 4
2.2 Maximum system design working pressure (MSDWP) 4
2.3 Distribution and Reticulation Layout 5
2.4 Selection of Type of Pipe Material 5
2.5 Principal advantages and limitation of selected water supply pipe materials 6
2.6 Selection and Installation of Air Valve 7
3 Service Reservoir 9
3.1 Basic Components 9
3.2 Type of Reservoir 9
3.3 Design requirement for treated water reservoir 10
3.4 Installation of Altitude Valve 11
4 Raw Water Resource 12
4.1 Assessment of Raw Water Sources 12
4.1.1 Surface Water Source 12
4.1.2 Ground Water Source 12
4.2 Selection of Raw Water Intake Location 13
4.3 Raw Water Intake Structure 13
4.3.1 Pontoon Intake 14
4.3.2 Jetty Intake 14
5 Water Treatment Plant Process 15
5.1 Raw Water Quality 15
5.2 Treated Water Quality 16
5.3 Treatment Plant Location 19
5.3.1 Planning 19
5.3.2 Plant design 19
5.4 Environmental factors 20
5.5 Treatment Process 20
5.5.1 Typical Process of Treatment 21
5.5.2 Selection of Treatment Process 21
i
JBALB Technical Guidelines for Water Supply System in Sarawak
5.6 Pre-Sedimentation 22
5.7 Chemical Dosing System 23
5.8 Chemical Storage 24
5.9 Filtration 25
5.10 Operation and Maintenance Requirement 25
5.11 Layout 25
5.12 Operation Building 27
5.12.1 The Laboratory 27
5.12.2 Filter Operating Gallery 28
6 Quarters 30
7 Sludge and Wastewater Disposal 31
8 Mechanical Works 32
8.1 Parameters for Pumps Selection 32
8.1.1 Raw water pump head design 34
8.1.2 Treated Water Pump Selection 34
8.2 Pump Installation Layout 34
8.3 Mechanical Seal vs Gland Packings (Surface Pump) 35
8.4 Motor Starter Requirement 35
8.5 Variable Speed Drive (VSD) 35
8.6 Surge Suppression System 36
8.7 Cranes 37
8.8 Forklift 38
8.9 Fire Fighting Services 38
8.10 Cathodic Protection 38
8.11 Pressure Gauge 38
9 Electrical Works 39
9.1 Power Supply 39
9.2 Sizing of Motor 39
9.3 Control Panel 39
9.4 Generator 39
9.5 General Lighting and Power 41
9.6 Earthing system 41
9.7 Lightning Protection System (LPS) 41
9.8 Main Switch Board 42
9.9 Electrical Wiring 42
10 Digitalization 43
10.1 Production Digitalization 45
10.2 Distribution Digitalization 55
10.3 Consumption Digitalization 58
10.4 System Integration 61
10.5 Last Mile Internet Connection (LMIC) 63
11 Safety and Security 64
ii
JBALB Technical Guidelines for Water Supply System in Sarawak
iii
JBALB Technical Guidelines For Water Supply System In Sarawak
Note: -
* As classified under the Piawaian Perancangan Kawasan Perindustrian issued by the Jabatan
Perancangan Bandar dan Desa or Land & Survey Department Sarawak.
- Urban means communities with population exceeding 10,000 persons for design purpose.
1
JBALB Technical Guidelines for Water Supply System in Sarawak
Note: -
1. To comply with the Fire and Rescue Department of Malaysia requirement.
2. For Fire flow plus peak demand, the minimum residual pressure should be 10m head.
3. The system should be designed to provide minimum residual pressure at 20m head
for urban and 10m head for rural during the peak demand at end of the pipeline.
2
JBALB Technical Guidelines for Water Supply System in Sarawak
3
JBALB Technical Guidelines for Water Supply System in Sarawak
2 Pipeline
The water distribution system consists of transmission, distribution and reticulation pipelines,
balancing and service reservoirs and treated water pumping stations. The objective of a water
transmissions and distribution system is to convey water at a suitable pressure and the required
quantity to the consumers.
1. Transmission pipelines – gravity or pumping mains that carry water from WTP/pumping
stations to reservoirs or reservoirs to reservoirs.
2. Distribution pipelines – gravity mains that connect water from service reservoirs to
reticulation mains.
3. Reticulation pipelines – pipes of smaller sizes that carry water from distribution pipes to
water demand centres such as housing areas or factories.
4. Balancing / Service reservoirs – storage tanks that hold water for certain period of time.
5. Treated water pumping stations – pumping facilities that pump water to a higher elevation
such as reservoirs.
4
JBALB Technical Guidelines for Water Supply System in Sarawak
1. Size and maximum working and test pressure, including surge pressure.
2. Strength of pipe to withstand designed internal and external loads.
3. Durability of pipe.
4. Suitability and workability for laying and operating requirements.
5. Capital, operation and maintenance cost.
6. Extent of possible leakage.
7. Pipe material availability
8. Evaluation against environmental factors.
9. Evaluation against conveyed water quality.
10. Evaluation against soil/groundwater properties and characteristics.
5
JBALB Technical Guidelines for Water Supply System in Sarawak
2.5 Principal advantages and limitation of selected water supply pipe materials
Pipe Material Advantages Disadvantages
Ductile Iron (DI) ▪ High mechanical strength and ▪ Heavy
toughness ▪ Susceptible to corrosion if internal
▪ High fatigue resistance or external protection systems
▪ Ease of jointing damaged
▪ Flexible joint tolerates some ▪ Potential high pH problems when
defection conveying soft waters
▪ Pipe impermeable to gas and ▪ Retrospective installation of
organic contaminants fittings may be complicated on
▪ Easy to trace for detection and ungauged pipes (dia > 350mm)
location of leaks
▪ Well established methods of repair
High Density ▪ Corrosion resistant ▪ Fusion jointing requires skilled
Polyethylene ▪ Relatively light-weight installers and special equipment
(HDPE) ▪ Flexible ▪ Reliant on stable support from soil
▪ Out-of-trench jointing possible ▪ Susceptible to permeation or
degradation on prolonged
exposure to direct sunlight
▪ Pipe location difficult making
leakage detection complicated
▪ Retrospective installation of
fittings or repair complicated in
large diameters (nominal size >
335mm)
Steel ▪ High mechanical strength and ▪ Welded joints require skilled
toughness installers and special equipment
▪ High fatigue resistance ▪ Susceptible to corrosion if
▪ Flexible protection systems damaged
▪ Available in long lengths ▪ Welded joints normally required
▪ Can be welded to form a leak-free reinstatement of protection
system that will resist end load systems on site
▪ Easy to trace ▪ Cathodic protection requires
▪ Pipe impermeable to gas and regular monitoring or
organic contaminants maintenance
▪ Easy for detection and location of ▪ Potential high pH problems when
leaks conveying soft waters
▪ Reliant on stable support from soil
▪ Retrospective installations of
fittings or repair may be
problematical if non-standard pipe
size are used
Unplasticized ▪ Corrosion resistant ▪ Susceptible to impact damage
Polyvinyl Chloride ▪ Relative light-weight ▪ Susceptible to poor installation
(uPVC) ▪ Ease of jointing ▪ Reliant on stable support from soil
▪ Ultraviolet degradation on
prolonged exposure to direct
sunlight
6
JBALB Technical Guidelines for Water Supply System in Sarawak
Legend:
** Highly recommended
√ Recommended
X Not recommended
√* For steel, cathodic protection may required.
For DI, polyethylene sleeve is required.
7
JBALB Technical Guidelines for Water Supply System in Sarawak
Air valves allow excess air to escape from the pipeline while containing pipeline fluids within
the pipeline during operation. They also allow air to escape from the pipes during filling.
The valves can inject air into the pipes while they are being emptied, preventing a vacuum,
which would cause the pipe to collapse.
Kinetic type air valve so named combination air valves, triple acting air valves etc. The kinetic
air valve provides excellent protection against vacuum formation with its advanced
aerodynamics design and kinetic orifice. The design of air valve shall enable the following
functions: -
Correct Position and Installation 90° of Air Incorrect Installation (less than 90°)
Valve
8
JBALB Technical Guidelines for Water Supply System in Sarawak
3 Service Reservoir
➢ To provide a reserve of water due to breakdown
➢ To provide a reserve to meet fluctuating demand
➢ To act as a break pressure tank
➢ To provide a reserve of water for fire fighting
9
JBALB Technical Guidelines for Water Supply System in Sarawak
10
JBALB Technical Guidelines for Water Supply System in Sarawak
g. All appurtenances and regulating services should be standard water supply practices.
These include pressure regulating valves, flow measurement recorders, air and reflux
valves, altitudes valves, level indicator etc.
h. Preferable inlet pipe is located at top of the tank and outlet pipe at bottom of the tank.
i. Bypass system between inlet and outlet shall be provided.
j. Proper safety access and staircase from the ground level to tank shall be provided.
11
JBALB Technical Guidelines for Water Supply System in Sarawak
a) River Yield - safe yield based 7-day low flow for a return period of 50 years vs. estimated
future demand.
b) Raw water quality – present & future status with emphasis on existing and potential
contamination/pollution by chemical and bacteriological agents.
c) Land use and heavy impact activities surrounding raw water source.
d) Requirements for storage - location, volume, capacity of catchment areas & yields,
duration of drought & water quality due to storage and fluctuation. The capacity of the
storage will be determined by duration of drought.
e) Source protection & alarming system & raw water (quality & quantity) monitoring system.
f) Catchment details and special requirement for catchment control measures.
g) Various possible options of water sources (surface water/groundwater)
h) Environmental flow & other legal users of the source
i) Cost/Benefit analysis
12
JBALB Technical Guidelines for Water Supply System in Sarawak
a) Raw water quality & quantity & environmental considerations (geological, biological,
floodplain, debris/logs issue, riverbank conditions, erosion and deposition,
seismic/wave, safety, river navigation, etc.);
b) Silt loading, debris/log, provision for desilting, screening and isolation of intake, facility
and protection against damage, flow distribution, ease of operation and maintenance;
13
JBALB Technical Guidelines for Water Supply System in Sarawak
(o) Protection from the entry of stray animals and trespassers by the provision of fencing and
lighting.
(p) Provision of oil boom kit or other products to contain oil spillage or contamination at raw
water intake.
14
JBALB Technical Guidelines for Water Supply System in Sarawak
Table 1, Column I, National Drinking Water Quality Standards, Ministry of Health Malaysia
RECOMMENDED RAW WATER QUALITY
No Parameters Column I
Acceptable Value
mg/l (unless otherwise stated
GROUP I
1 TOTAL COLIFORM 5,000 MPN/100ml or cfu/100ml
2 TURBIDITY 1000 NTU
3 COLOUR 300 TCU
4 pH 5.5 – 9.0
GROUP II
1 TOTAL DISSOLVED SOLIDS 1500
2 BIOLOGICAL OXYGEN DEMAND 6
3 CHEMICAL OXYGEN DEMAND 10
4 CHLORIDE 250
5 ANIONIC DETERGENT MBAS 1.0
6 AMMONIA (as N) 1.5
7 NITRATE (as N) 10
8 IRON (as Fe) 1.0
9 FLUORIDE 1.5
15
JBALB Technical Guidelines for Water Supply System in Sarawak
10 HARDNESS 500
11 MANGANESE 0.2
GROUP III
1 MERCURY 0.001
2 CADMIUM 0.003
3 SELENIUM 0.01
4 ARSENIC 0.01
5 CYANIDE 0.07
6 LEAD 0.05
7 CHROMIUM 0.05
8 SILVER 0.05
9 COPPER 1.0
10 MAGNESIUM 150
11 SODIUM 200
12 ZINC 3
13 SULPHATE 250
14 MINERAL OIL 0.3
15 PHENOL 0.002
GROUP IV
ORGANOCHLORINE PESTICIDES:
1 ALDRIN/DIELDRIN 0.00003
2 DDT 0.002
3 HEPTACHLOR & HEPTACHLOR EPOXIDE 0.00003
4 METHOXYCHLOR 0.02
NON-ORGANOCHLORINE PESTICIDES:
5 HEXACHLOROBENZENE 0.001
6 LINDANE 0.002
7 CHLORDANE 0.0002
HEBRICINES:
8 2,4-D (DICHLOROPHENOXYACETIC ACID) 0.03
GROUP V
RADIOACTIVITY:
1 GROSS α 0.1Bq/l
2 GROSS β 1.0Bq/l
TOTAL 40 PARAMETERS
Table 2, Column 1, National Drinking Water Quality Standards, Ministry of Health Malaysia
DRINKING WATER QUALITY STANDARDS
No Parameters Column I
Maximum Acceptable Value
mg/l (unless otherwise stated)
GROUP I
MICROBIOLOGICAL:
1 TOTAL COLIFORM MPN METHOD/ MEMBRANE FILTRATION
METHOD: MUST NOT BE DETECTED IN ANY 100ml
SAMPLE
2 E.coli OR THERMOTOLERANT ABSENT IN 100ml SAMPLE
3 COLIFORM BACTERIA
4 FAECAL STREPTOCOCCI MEMBRANCE FILTER METHOD: ABSENT IN 100ml
SAMPLE
16
JBALB Technical Guidelines for Water Supply System in Sarawak
17
JBALB Technical Guidelines for Water Supply System in Sarawak
37 DIBROMOACETO-NITRILE 0.1
38 TRICHLOROACETO-NITRILE 0.001
39 CYANOGEN CHLORIDE (as CN) 0.07
GROUP IV
1 ALDRIN/DIELDRIN 0.00003
2 DDT 0.002
3 HEPTACHLOR & HEPTACHLOR EPOXIDE 0.00003
4 METHOXYCHLOR 0.02
5 LINDANE (BHC) 0.002
6 ENDOSULFAN 0.03
7 CHLORDANE 0.0002
8 1,2-DICHLOROPROPANE 0.04
9 1,3-DICHLOROPROPENE 0.02
10 HEXACHLOROBENZENE 0.001
11 PENTACHLOROPHENOL 0.009
12 ALACHLOR 0.02
13 ALDICARB 0.01
14 AMETRYN 0.05
15 ATRAZINE 0.002
16 BENTAZONE 0.3
17 CARBOFURAN 0.007
18 CHLOROTOLURON 0.03
19 CYANAZINE 0.0006
20 2,4-DICHLOROPHENOXYACETIC ACID (2,4D) 0.03
21 DIQUAT 0.01
22 1,2-DIBROMO-3-CHLOROPROPANE 0.001
23 1,2-DIBROMOETHANE 0.0004
24 ISOPROTURON 0.009
25 MCPA 0.002
26 METOLACHLOR 0.01
27 MOLINATE 0.006
28 PENDIMETHALIN 0.02
29 PERMETHRIN 0.02
30 PROPANIL 0.02
31 PYRIDATE 0.1
32 SIMAZINE 0.002
33 TRIFURALIN 0.02
34 2,4 DB 0.09
35 DICHLORPROP 0.1
36 FENOPROP 0.009
37 MECOPROP 0.01
38 2,4,5-T 0.009
39 TERBUTHYLAZINE 0.007
ORGRANIC SUBSTANCES:
40 CARBON TETRACHLORIDE 0.002
41 DICHLOROMETHANE 0.02
42 1,2-DICHLOROETHANE 0.03
43 1,1,1-TRICHLOROETHANE 2
44 VINYL CHLORIDE 0.005
45 1,1-DICHLOROETHENE 0.03
46 1,2-DICHLOROETHENE 0.05
47 TRICHLOROETHENE 0.07
48 TETRACHLOROETHENE 0.04
49 BENZENE 0.01
50 TOULENE 0.7
51 XYLENE 0.5
52 ETYLBENZENE 0.3
53 STYRENE 0.02
54 BENZO (A) PYRENE 0.0007
55 MONOCHLOROBENZENE 0.3
56 1,2-DICHLOROBENZENE 1
57 1,4-DICHLOROBENZENE 0.3
58 TRICHLOROBENZENE (TOTAL) 0.02
18
JBALB Technical Guidelines for Water Supply System in Sarawak
Notes: Any toxic substances not listed shall be deemed as not allowable in drinking water
5.3.1 Planning
➢ Present and future demands, direction and rate of growth of service area and potential
deterioration of source quality in future so that the site selected is flexible enough to
accommodate these changing factors.
➢ Plant site can be designed to be compatible with its surroundings which normally involve
studying the master plan for area concerned (if available) and discussions with local
authorities and principal groups who may be affected.
The site is optimally located in relation to the source of water and the area to be
served. It shall be located at strategic location and preferably with easy access. Raw
water intake shall be located as near as possible to the WTP.
Assessment towards the conservation of power costs having regards to the various
variable on pump sizes, sizes of transmission lines, service area elevations including
future service area limits to determine the optimum configuration.
Topography of site shall suit the hydraulic profile of the WTP process components
and surface drainage. A gentle and moderate slope is required, and the process
units shall be aligned down the slope rather than across, to achieve gravity flow
through the plant to avoid excessive earthworks and the need for elevated
structures.
19
JBALB Technical Guidelines for Water Supply System in Sarawak
(d) Geotechnical
(e) Flooding
Shall always be sited above the 1 in 100-year design flood level or maximum flood
levels experienced if records are insufficient for flood analysis.
(f) Access
Shall be located where power supply and telecommunication facilities are readily
available. Backup on site diesel generator shall be provided to increase in reliability
of power supply.
20
JBALB Technical Guidelines for Water Supply System in Sarawak
➢ When the characteristics and constituents of raw water do not comply to the
recommended criteria set in Table 1 of NDWQS, special treatment is required. Special
treatment includes additional process such as algae control, pre-chlorination, ozonation,
activated carbon absorption, sludge treatment etc. depending on what is needed to
achieve treated water that complies to Table 2 of NDWQS.
➢ Samples of raw water must be collected at different times to cover the range of quality
and fluctuation for physical and chemical analyses. The studies of the raw water should
be subjected to, preferably at two weeks intervals and on all days/periods of abnormal
weather, are:
21
JBALB Technical Guidelines for Water Supply System in Sarawak
a. Physical, chemical and bacteriological analysis of samples of the raw water must be
carried out. Tentative treatment process for the raw water is selected based on
preliminary results.
b. These processes are then tested out on samples of raw water using the Jar Tests to
determine the type and approximate range of chemical dosages required for pre-
chlorination (if necessary), adsorption, coagulation, disinfection and conditioning.
c. Marble or Calcium carbonate stability test must be carried out to determine the
alkalinity and pH which prevail at calcium carbonate equilibrium and thereby select
the lime/soda ash dosage required.
d. Samples of the treated water resulting from the jar and marble tests must be tested
physically, chemically and biologically for compliance to the requirements of
treated water in NDWQS Table 2.
e. The analysis in (d) above should be carried on not only on the treated water from
the jar test which appears clearest and with most rapid settling time but on the
treated water from the next three or four best tests especially during the beginning
stages of investigations to ease in the final decision making.
f. Jar test must also be used as a basis of selection of the most economical method of
treatment that will produce treated water comply to NDWQS Table 2.
g. Salinity test shall be conducted as well.
➢ The use of polymer in treatment process is to be avoided in view of the risk of filter
choking.
➢ Inclined plates or tube settlers is not preferred in the design of new WTP. They may only
be considered/recommended for upgrading works of existing plant.
5.6 Pre-Sedimentation
For raw water with high content of suspended solid, pre-sedimentation is provided.
a) Design calculations are provided to show that the proposed pre-sedimentation basins are
sized according to the treatment plant capacity and suspended solids content.
b) The pre-sedimentation basins have hopper bottom or be equipped with mechanical
moving sludge removal apparatus.
c) Have a means of dewatering the settled sediments.
d) Are designed such that the incoming water is dispersed evenly across the tank width to
prevent short circuiting.
e) There is a by-pass around each pre-sedimentation unit.
f) The pre-sedimentation basins are designed with a minimum of three (3) hours detention
time (actual detention time is to be determined through sedimentation tests).
g) Duplicate pre-sedimentation basins are provided to allow 1 unit to shut down for
maintenance.
22
JBALB Technical Guidelines for Water Supply System in Sarawak
23
JBALB Technical Guidelines for Water Supply System in Sarawak
24
JBALB Technical Guidelines for Water Supply System in Sarawak
h. All chlorine stores and dosing rooms are provided with chlorine leaks detectors with
audible alarms located outside.
i. For plants 5MLD and above capacity, a chlorine neutralization gas scrubbing system is
provided.
j. For plants below 5MLD capacity, auto-shut down valve system must be provided.
k. Ammonia solution shall be provided for detection of chlorine leakage.
11. Fluoride dosing facilities and store shall be isolated from the rest of the facilities. Fluoride
dosing shall be carried out in solution form.
5.9 Filtration
General requirement for design of filter such as filtration rate, length and breadth ratio, size
filter, tank depth, free board, water depth, head loss, media depth, pipes sizing and
recommended flow velocity of the pipe and channel, backwash system, air bower capacity shall
be provided.
5.11 Layout
(a) Layout of all treatment units, control house, chemical stores, pumping stations and other
appurtenances should be compact and to allow optimum efficiency in operation and
maintenance of the system with a minimum number of operators.
(b) A minimum of two (2) treatment trains is provided, operating in parallel.
25
JBALB Technical Guidelines for Water Supply System in Sarawak
(c) Hydraulics profile of the WTP should be such as to prevent excessive head loss and
excessive velocities and to enable gravity flow from one process unit to another wherever
possible. All connections between the various treatment units are direct and as short as
possible.
(d) A schematic diagram of the proposed system must be provided in all cases of design,
showing all levels, pipe type, sizes and lengths, hydraulics gradient, reservoirs levels and
capacities, pumping heads and capacities, the highest and lowest points of consumers
service, including all chemical feed systems.
(e) Full consideration is given to easy inspection, operation & maintenance of entire
treatment facility by locating the process units which require more attention than others
close to one another and next to operations building.
(f) Covered walkways shall be provided to connect the individual treatment units.
(g) Provision should be made for adequate isolation of individual treatment units and
adequate working area for purpose of maintenance and repairs.
(h) Access & lifting devices for removal of all major equipment are provided.
(i) Adequate walkways with safety handrail along the filters, sedimentation tanks &
flocculation basin are provided. Safety handrails are provided at all structures high above
ground.
(j) Adequate air scour and wash-water rates should be provided for thorough and effective
backwashing of filter media. Wash water lines should be provided with a rate control valve.
(k) In all cases, provisions for future expansion and augmentation of the treatment plant and
facilities shall be provided for.
(l) Due consideration should be given to the architectural design and layout of the buildings
so as to project an image of cleanliness, efficiency and reliability.
(m) Sanitary and sludge handling facilities and drains should be sited so as not to cause
contaminations.
(n) Every WTP shall install 5 units of water meters at: -
a. Raw Water Pump
b. WTP Outlet
c. For Filters Backwash use at WTP with backwash tank or supply main before
entering WTP (without backwash tank)
d. For Headworks use at service pipe
e. Discharge pipe to sludge facilities
(o) Operation units such treated water pumping station & generator house are located
separately from the main operations building to reduce noise problems.
26
JBALB Technical Guidelines for Water Supply System in Sarawak
(p) Premix access roads and service roads of adequate width and adequate parking space for
cars and motorcycles are provided.
(q) Adequate drainage facilities are provided for discharge of surface water, overflows from
the treatment facilities, wastewater flows & scour flows.
(r) Security fencing, gates, adequate external lightings and fire protection are to be provided.
(s) Signboard is to be provided at WTP and booster pump station as well as at the junction of
the access road to the plant or booster pump station. Separate signboard is to be provided
for raw water intake and reservoir, if located outside of WTP’s compound.
27
JBALB Technical Guidelines for Water Supply System in Sarawak
• Sampling pumps must be installed at places which are easy to be accessed by the plant
operator.
• Sampling pump must be installed at one duty and one standby, if there are different
treatment packages/module for the plant, sampling must be done for every
treatment module.
• Stream current detector/monitoring (with standby unit) complete with PID controller
for monitoring of raw water and automating dosing control of alum/PAC/ACH for
plant with high fluctuation in raw water quality.
• All WTPs are to be equipped with local charge analyzer (LCA).
28
JBALB Technical Guidelines For Water Supply System In Sarawak
Appendix A
No Parameter Analysis Equipment Glasswares Accessories: Reagents Remarks
1 Free Chlorine Portable Photometer and Comparator Sample cells Plastic stirring rod, test discs for Tablet DPD 1 Reagents/tablets for
comparator, standard verification kit and minimum 3 months stock
2 Total Chlorine delicate task wipers Tablet DPD 4
Test Disc Chlorine DPD Test
3 pH (4.4-6.3) Test Disc PH (4.4-6.3) Methyl Red
7 Iron Test Disc Iron (0.1-1 mg/L) Iron Low Range Tablets
8 Manganese Test Disc Manganese (0.2-4 mg/L) Manganese Low Range Tablet 1
Manganese Low Rage Tablet 2
9 Aluminium Test Disc Aluminium (0.01-0.3 mg/L) Aluminium Tablet 1
Aluminium Tablet 2
10 Turbidity Benchtop Turbidimeter and Portable Turbidimeter Sample cells Delicate task wipers
11 Colour Nessleriser (For Colour) Pair of Nessler tubes for Colour test HAZEN/APHA Disc (0-250 mg pt/l)
Delicate task wipers
12 Fluoride (if Nessleriser (For Fluoride) Pair of Nessler tubes for Fluoride test NOM DISC, Fluoride; 0-1.6mg/l Fluoride A-Z tablets Reagents/tablets for
applicable) Delicate task wipers Fluoride excess AL tablets minimum 3 months stock
13 Jar Test Jar Tester (6 Paddle) 500 ml glass beakers (6 unit) Cellulose filter paper (0.45 micron)
Adjustable Volume Micropipette (1 mL) (2 unit) 500 mL glass graduated cylinder (1 unit) Pipette tips (1ml)
Adjustable Volume Micropipette (5 mL) (2 unit) 100 mL glass graduated cylinder (1 unit) Pipette tips (5ml)
Adjustable Volume Micropipette (10 ml) (2 unit) 100 mL glass beaker (8 unit) Pipette tips (10ml)
Syringe (1ml) (2 unit) Filter funnel
Syringe (10mL) (2 unit) Funnel Holder
Laboratory Scale (Analytical Balance) Magnetic Stirrer (7mm x 30mm)
Magnetic Stirrer Plate
14 Specific Gravity Hydrometer (for Liquid polyaluminium chloride TYPE 1) (1.13-1.23 g/ml) Depend on chemicals to be
Hydrometer (for Liquid polyaluminium chloride TYPE 2) (1.18-1.35 g/ml) used.
Hydrometer (for Liquid polyaluminium chloride TYPE 3) (1.32-1.38 g/ml)
Hydrometer (for Liquid Aluminium Sulphate) (min. 1.31 g/ml)
Hydrometer (for Soda Ash Solution) (1.0-1.2 g.ml)
Hydrometer (for Aluminium Sulphate Solution) (1.0-1.2 g.ml)
Hydrometer (for Chlorine Solution) (1.0-1.2 g.ml)
15 Salinity TDS Meter (with temperature measurement) TDS calibration solution If expect saline intrusion.
29
JBALB Technical Guidelines For Water Supply System In Sarawak
6 Quarters
(a) Usually for accommodation of WTP operators working in shifts.
(b) If WTP is located near an existing community/town, the quarters may be located at/near
the community/town for social reasons.
(c) If WTP is at a remote area, quarters may have to be in the vicinity of, but outside the
compound of the WTP, with gate and fencing. Sufficient street lighting should be provided
leading from the quarters to the WTP.
(d) Quarters to be provided with electricity, lighting, water supply and internal plumbing.
Those facilities shall be separate installation from WTP. (Occupant must apply their
individual electricity connection meter with SEB/SESCO)
(e) Quarters to be designed to follow the State Pre-Approved Plant (SPAP) standard with
minimum three (3) bedrooms and floor area.
(f) Quarters to be provided with furniture as per standard furniture list.
TABLE I
Class F Quarters
Item Article Quantity
1. Easy Chairs 4
2. Occasional table 1
3. Dining table 1
4. Chairs standard 6
5. Kitchen table 1
6. Kitchen cupboard 1
7. Kitchen sink with tap 1
8. Ceiling fan 1
9. Refuse bin 1
Bedrooms No. 1 No. 2 & 3
10. Bedsteads 1 double 2 single
11. Foam rubber mattresses 1 2
12. Mosquito frames 1 2
13. Dressing table with mirror 1 2
14. Wardrobes 1 2
15. Ceiling fan 1 2
16. Washstand with tap 1
17. Toilet bowl 1
18. Shower head 1
30
JBALB Technical Guidelines for Water Supply System in Sarawak
(a) Environmental Quality Act 1974: Environmental Quality (Industrial Effluent) Regulations 2009
- shall apply to any premises which discharge or release industrial effluent or mixed effluent
other than premises as specified in First Schedule.
(b) Industrial effluent: any waste in the form of liquid or wastewater generated from
manufacturing process including the treatment of water for water supply or any activity
occurring at any industrial premises.
(c) Sludge: any deposit of particulate matter settled from any liquid, including deposit resulting
from physical, chemical, biological or other treatment of water or industrial effluent or mixed
effluent.
(d) Restriction on discharge or disposal of sludge - Clause 23. (1) No person shall discharge, or
cause or permit the discharge or disposal of any sludge generated from any production or
manufacturing process, any industrial effluent treatment system or water treatment plant
onto or into any soil, or surface of any land, or into any inland waters or Malaysian waters
without the prior written permission of the Director General.
(e) Consultant to check and comply with NREB’s requirement on sludge treatment facilities and
disposal.
(f) The options for ultimate disposal of sludge and wastewater include: -
a. To dedicated landfill
b. To municipal sanitary landfill
c. To sanitary sewer
(g) With high land costs and more restrictive measures for discharge into sanitary severs utilities
throughout the world are looking into other beneficial use programs for sludge and
wastewater, not only as a cost-effective alternative but also as a publicly acceptable
management practice. Some of the possible options for reuse of sludge/wastewater are as
follows: -
a. Commercial products
b. Co-use with biosolids
c. Land application
JBALB Technical Guidelines for Water Supply System in Sarawak
8 Mechanical Works
(s) Eccentric reducers in pump suction piping (Tapered at bottom) to prevent air-pocket.
i. Pump nozzles are smaller than inlet / outlet piping. That is why we need to use
reducers and expanders at the pump suction and discharge piping. Horizontal
surface allows hydraulic transportation of air.
(t) Separate suction lines are to be provided when pumps are operating under negative
suction heads. (Same size of pump)
JBALB Technical Guidelines for Water Supply System in Sarawak
i. The intake is located at a place from where it can draw water even during the 1 in 50-year
7-day low flow.
ii. The intake structure is located at sufficient water depth so as to be able to keep the raw
water pumps low flow (7-day Q50).
iii. Pump base should be sited at minimum low water level at Pontoon or Jetty Intake (Fixed
& Flexible Pump Mounting).
a) Supply Conditions
Alternating Current, 50 cycles (Hz), 230 volts single phase and 400 volts three phase 4
wire. (Voltage variation allowed - plus or minus 5%).
b) Up to and Including 1 HP
Single phase 230-volt motors may be used with direct-on-line starting. Starters must be
used for motors over 1/2 H.P.
c) Up to and Including 3 HP
May be three phase squirrel cage type with direct-on-line starters.
e) HP and Above
i. May be of the Auto Trans or VSD fitted with mechanical devices to prevent quick
movement of the starter switch and starting without all resistance or reactance in
circuit.
ii. In clarification of the requirements for motors of 10 HP above, motors other than
wound rotor type may be used providing the associated starting equipment limits the
starting current to not more than 200% of full load current.
f) All motors and electrical equipment to have a Power Factor of at least 0.85 but 0.9 is
preferred.
c) Complying Sarawak Electricity Ordinance The Electricity (State Grid Code) Rules, 2003 -
PC4.3 Harmonics
d) Standard Guidelines:
i. IEEE 519 1992 Harmonic Control in Electrical Power Systems
ii. Output Peak Voltage and rise time to be compatible with motors complying with
IEC 60034-17 (General purpose motors), as measured at motor terminals with
motor cable type and length specified in the tender documents.
iii. IEC Quality Assessment System for Electronic Components
iv. IEC 60146: Semiconductor converters
v. IEC 60391: Marking of insulated conductors.
vi. IEC 60529: Degree of protection provided by enclosures (IP Code)
vii. IEC 60801-2: Electronic compatibility for industrial process measurement and
control equipment. Part 2: Electrostatic discharge requirements.
viii. IEC60721-3-3: Class 3C3 High Grade conformal coated PCBs
b) Surge suppression systems with adequate air valves and vacuum relief valves along the
pipeline shall be provided to protect against surge or water hammer which may cause
damages to the pumps and pipeworks.
c) Selection of appropriate type of surge suppression system shall be done after a
comprehensive study conducted during the design stage.
d) Surge Vessel: 2 nos. of air compressors (1 duty, 1 standby) complete with air receiving
tank, control panel.
e) Surge analysis report required to be submitted.
f) Surge Anticipator Valves: combined air and vacuum relief valve
8.7 Cranes
a) All heavy equipment, including pipework shall be provided with means for installation and
removal of the equipment by appropriate lifting devices.
b) Cranes are preferably to be electrically-operated unless specified.
c) Criteria and standards as follow shall be used in determining the application of cranes: -
i. Monorail cranes are used when a single degree of movement is required and the
centre line of the equipment is in line with the entry or exit of the building
ii. The beam can be either “U’ type or “I” type.
iii. Gantry cranes are preferably to be used when two degrees of movement is required.
iv. The electrical lifting and travel for gantry cranes shall be used when the load is more
than two (2) tonnes.
d) Cranes shall be sized to withstand SPAN 1.25 times its Safe Working Load (SWL).
e) Overhead travelling cranes
i. Capacity of the crane is the maximum weight of the component to be lifted in the
pumphouse.
ii. Safe working load (SWL) shall be at least 20% greater than the individual weight of
the single pump or motor or other major equipment to be lifted.
f) For SWL less than 10 tonnes, transverse crane bridge shall be a single box girder mounted
on top of double channel end carriages.
g) For SWL of 10 tonnes and above, transverse crane bridge shall be a double box girder with
double rail crab.
JBALB Technical Guidelines for Water Supply System in Sarawak
h) Height of a plant area or the building shall be sufficient such that the largest equipment
may be lifted over or around.
8.8 Forklift
a) Forklifts shall be provided for the purposes of chemical loading and unloading within
enclosed reception areas.
b) Forklifts provided shall be battery-operated type unless specified.
c) Sufficient areas for the movement of forklift within the areas shall be considered during the
design stage.
9 Electrical Works
9.4 Generator
(a) Design capacity of the generator set shall be designed for 100% standby for full
operational of plant and systems.
(b) Standby generator set shall be designed and sized to meet the calculated standby load
requirement. The standby load shall include all equipment required for full normal
operations during power failure.
(c) The generator set rating to be selected shall be the highest calculated KVA which covering
the Maximum Demand.
(d) Generator minimum running load shall not be less than 30% of the generating rating.
JBALB Technical Guidelines for Water Supply System in Sarawak
(e) Generator house shall be provided with Acoustic Treatment (acoustic door, air intake
silencer, air discharge silencer).
(f) Generator set installation shall be completed with AMF (Auto Main Failure) Board, Control
Panel, Lead Acid Battery c/w battery charger.
(g) Genset shall be provided with safety devices such as low lub oil pressure switch, high
water temperature switch, overspeed and failure to start.
(h) Genset panel shall be provided with Auto/Manual Change Over Switch.
(i) Daily service fuel tank shall be provided for each generator set. The tank shall be
accommodated for 8 hours operation.
(j) Physical size of tank must allow for 10 - 20 % spare capacity.
(k) Diesel fuel tank shall be provided adjacent to the genset house/room. The tank shall be
sized for at least 7 days’ supply for easy access areas and 21 days for remote areas, based
on 8 hours operation.
(l) Diesel fuel tank shall be provided with mild steel tank, skid mounted c/w filling connection,
outlet connection, sight-glass level indicator, vent pipe, isolating valve, flowmeter, level
sensor etc.
(m) The tank shall be provided with easy access to facilitate loading of fuel from a fuel tanker.
(n) Where possible, the tank shall be sited on higher ground to enable the fuel to be supplied
by gravity to the engine of the generator.
(o) Preferably an electrically operated fuel transfer pump shall be provided unless specified.
(p) Genset installation shall comply with DOE requirement.
(q) Firefighting system shall be provided at Genset House/Room and comply with BOMBA
requirement.
(r) All cables and fuel lines shall be neatly arranged in trenches with galvanized chequered
plate covers and the trenches shall be well drained.
Bomba Requirement
JBALB Technical Guidelines for Water Supply System in Sarawak
(l) Electrical continuity of the reinforcing bars shall be determined by electrical testing
between the uppermost part and ground level.
(m) An additional conductor may be used to enhance the natural down conductor system if
the overall electrical resistance is greater than 0.2 Ohms.
(n) Additional conductor shall be bonded to the reinforcement bars by means of purpose
made clamps conforming to IEC 62561 at 1-meter intervals.
10 Digitalization
SCADA (or Supervisory Control and Data Acquisition) is a control system architecture comprising
computers, networked data communications and graphical user interfaces (GUI) for high-level
process supervisory management, while also comprising other peripheral devices like
programmable logic controllers (PLC) and discrete proportional-integral-derivative (PID)
controllers to interface with water treatment plant processes. This is an important control system
architecture for digitalization of water treatment plant production processes and become an
industry standard for water supply industries in the world.
SCADA monitoring is the essential part in water supply production digitalization. The main
components of monitoring are as follows:
a) Raw water intake – monitor raw water level, raw water pump condition, raw water pressure
main flow and pressure;
b) Chemical – chemical dosing pump condition and chemical dosing rate for each chemical used
for treatment processes;
c) Water quality – monitor water quality for raw water, settled water, clarified water, filtered
water and treated water;
d) Treated water – monitor treated water pump condition, treated water pumping main flow
and pressure;
e) High level tank – monitor HLT level sensor;
f) Energy monitoring – current monitoring module, load and energy consumption etc.
a) Cabling works – due to excessive vibration in the treatment house, cabling works are required
to transmit data from the sensing devices to the PLC and WTP SCADA;
JBALB Technical Guidelines for Water Supply System in Sarawak
b) Pedestal panel – a housing unit for the transmitter, surge protection and accessories required
for level sensors;
c) MCC (Motor control centre) panel – installed for monitoring of pumps, mixers and energy
monitoring.
The data from WTP SCADA will then be transmitted to Central SCADA platform which is hosted
at SAINS Data Centre. It is part of the entire Smart Water Supply System architecture which is
also monitoring distribution pipelines and also digitization of drawings.
Before Contractor carried out installation of SCADA or any production monitoring system at
JBALB WTP, a proposal with system architecture diagram must be produced first. Say, the
SCADA system is different from JBALB Central SCADA system, the system architecture between
JBALB HQ SCADA and WTP SCADA can be visualized in the following examples:
The scope of works for other WTP SCADA can range from installing PLC for Raw Water Intake,
Treated Water Pumps, Chemical Plant and Admin Building (for Water Quality). Normally, the
information will be read by the onsite SCADA workstation. The setup of JBALB Smart Water
Supply System is as follows:
GIS Data
The detailed requirement of the proposed SCADA (production digitalization) are as follows:
No. Particulars Requirement
1 SCADA ➢ SCADA architecture shall not be a proprietary ecosystem whereby all
Architecture end-to-end solution consists of only single proprietary provider. It
must consist of hardware, PLC and OPC software (OLE Process Control)
which is SCADA;
➢ SCADA system architecture and the required documents must be
provided:
• Submitted in form of A3 drawing, signed by certified professional
engineer;
• Configuration shall show essential SCADA equipment to be
provided for the entire plant;
• Typical connection between outstations (O/S) and the master
station;
• Overall concept must be distributed control system – each
individual section of the works responds automatically to local
requirements and overall work requirements;
• Provide list of equipment provided and network architecture;
• Provide HMI interface screenshot (for every page);
• Flowmeter and HLT within WTP shall form part of the SCADA;
• Each PLCs IP address and port no;
• ModBUS mapping addressing for the signal;
• Each DPM communication setting, and a set of ModBUS
addressing document;
• Substation electrical single line diagram;
• Proposed SCADA signals;
• Proposed telco for network connectivity; and
• Overall WTP process diagram
• Can be remote monitoring or automated. If automated, shall
provide sequence control functions for particular process areas at
local control panels;
• Loss of host computers and connection shall not impair process
controls;
• Any automation shall be functionally demonstrated before
implementation. Range of automation shall be made clear with
allowable customization to suit WTP operation.
• Full operational data must be communicated and available at the
Master Station;
• Master station must be located at main control room of the WTP
building;
• O/S must be PLC-based, and connected to Master Station;
• Must be fail-safe, designed for continuous 24 hours operation,
with minimum maintenance. Failure of any part of the system
JBALB Technical Guidelines for Water Supply System in Sarawak
8 Chemical Dosing • Dosing pumps must be formed as part of the SCADA system;
• Dosing pumps must be installed at the designated dosing tank, for both
pre-treatment and treatment stages, except for chlorine at clear water
well and booster station’s suction tank (if applicable);
• Dosing pumps must be installed at one duty and two standby. If they
are different treatment packages/module for the plant, dosing must be
monitored for every treatment module;
• Dosing pumps must be installed at places which are easy to be
accessed by the plant operator;
• Must monitor status for start, stop, tripped, failed, or not available;
• Usage of auto dosing modules such as stream current monitoring
(SCM) is mandatory for raw water with highly fluctuating quality and
volume, encouraged for others. However, it must have ease of
maintenance, and effective.
9 Flowmeter • Shall be battery-powered type. For flowmeters to measure raw and
treated within WTP, must be connected to power cable. Battery must
be lithium battery, last not less than 6 years, come with warranty of at
least 2 years and designed to withstand up to 60ºC;
• Can be either electromagnetic or ultrasonic;
• Accuracy must be equal or better than 0.40% of actual lamina flow
from full scale flow rate to 50% flow rate increasing progressively to
maximum of 5% of the actual flow at 10% flow rate;
• Flowmeter to measure raw and treated water within WTP must form
part of the SCADA system.
10 Transmitter/ • Signal cable must be originally manufactured for type of O/S to be
Signal Converter installed, and not through third party contractor/supplier;
(For Flowmeter) • Signal cable must be able to withstand under water.
• Transmitter/signal converter for flowmeter shall be microprocessor-
based type with function for adjustment, self-diagnostic and error
reporting. It shall incorporate hardware and software protection;
• Shall enable add on for future communication module;
• Shall be equipped with comprehensive display minimum of the
following:
• Flow rate;
• Velocity;
JBALB Technical Guidelines for Water Supply System in Sarawak
procurement procedures required; however, the tender document must ensure that system
integration is explicitly mentioned in the specification and requirements. The cost to carry out
telemetry implementation works including the required system integration must be borne by
the contract and budgeted prior to implementation of the project.
HLT
GIS Data 3G/GSM
/GPRS
Backup Server JBALB HQ HLT
SCADA Transmitter Sensor
- Backup data Workstation
in the event - Level data
- Visualization of location and - Sensor
of internet
area data;
or electricity condition data
- Alarm management
blackout. - Battery health
Digitization of Existing - Alarm notification Battery Solar Panel
Drawings Digital - Simple data analytics on level,
Drawing Data pressure, valves, battery status
architecture of SWMs which needs to be complied by the contract either using radio frequency
(RF) or NB-IOT.
The Contractor for the other SCADA project shall provide the network within the WTP. All PLCs
shall be interconnected and make available network port at WTP Admin Building office, where
the WTP SCADA workstation are located. Please ensure that PLCs are complying to MODBUS
TCP protocol. Some PLCs such as OMRON are not using MODBUS TCP Protocol, but instead,
using IP address. This is also acceptable. Other proprietary PLCs with proprietary
communication protocol (which are part of suite software and ecosystem) are not allowed to
be used.
JBALB HQ SCADA communication gateway will be installed at the same location near the WTP
SCADA workstation and sharing the plant SCADA MODBUS TCP network. For this
interconnection to work, the WTP SCADA contractor shall provide network information, such
as all equipment IP address, system architecture and detailed data mapping addressing.
The interconnection requirement for Digital Power Meter (DPM) Interfacing are as follows:
a) DPM need to be installed at the WTP main switch board (MSB) incoming and provide the
energy consumption for the plant;
b) DPM shall come with Ethernet communication port and support MODBUS TCP protocol;
c) It shall be Schneider PM5320 or equivalent model, which provide the standard address
mapping for the parameters.
WTP SCADA Contractor shall include the following signals, but not limited to:
Location Signal Signal Type
Raw Water Intake River Water Level AI
Raw Water Pump Running Status DI
Raw Water Pump Tripped Status DI
Raw Water Flowrate AI
Raw Water Totalizer AI (Double Word)
Raw Water Delivery Pressure AI
Chemical Plant Chemical Dosing Pump Running (All) DI
(Dosing) Chemical Dosing Pump Tripped (All) DI
Treated Water Treated Water Pump Running Status DI
Pumping Treated Water Pump Tripped Status DI
Clear Water Tank Water Level AI
Backwash Tank Water Level AI
Treated Water Flowrate AI
Treated Water Totalizer AI (Double Word)
Treated Water Delivery Pressure AI
Raw Water Turbidity AI
JBALB Technical Guidelines for Water Supply System in Sarawak
BPS SCADA Contractor shall include the following signals, but not limited to:
WTP SCADA contractor shall provide the following documentation for further information
related to the HQ SCADA interfacing, but not limited to:
a) Each PLCs IP address, port no.;
b) MODBUS Mapping addressing for the signal as stated in section 4;
JBALB Technical Guidelines for Water Supply System in Sarawak
c) Each DPM communication setting, and a set of the MODBUS addressing document;
d) WTP SCADA system architecture diagram;
e) Substation electrical single line diagram;
f) Proposed SCADA signals;
g) Proposed telco for network; and
h) WTP overall process diagram.
Any amendment of the configuration shall require approval from JBALB and submission of
revised documents shall be made prior to approval. SCADA contractors are required to perform
inter-connection testing to verify all MODBUS mapping address are correctly configured. Data
verification must be done and witnessed by JBALB for every testing.
Upon completion and T&C of SCADA setup at the WTP, contractor is required to hand over the
SCADA software installation CD, manual, network subscription (if applicable), together with the
required documents as above to JBALB HQ or JBALB Divisional office.
3. If liquid alum is stored in open tank, a shower/ eye wash area located in a convenient
place near to the chemical tanks as possible shall be provided.
4. The hydrogen release outlet for EC system must be installed minimum 5 m above the
ground level and ensure there is no farmable activities surround the area.
5. Chlorine detection equipment and alarms, extractor fans shall be provided at all
treatment plants.
6. A surge relief valve that protects piping and pipeline systems from pressure surge events
caused by rapid valve closure, emergency shut-down or pump trip situations shall be
provided.
7. All walkways around filters, sedimentation tanks, high level tank, opening platform etc.
where frequently accessed shall be provided with stainless steel or galvanized steel
guardrail with mid-rail either on one side or both sides depending on site conditions. The
top rail should be at least 1.0 m above the floor.
8. Vertical ladders shall be provided with safety devices, such as cage or safety straps.
9. Access ladder inside the reservoir, filter, sediment tank, coagulant tank, raw water intake
structure shall be made of rust-free material, such as aluminum.
10. Steel or Concrete staircase shall be provided for all structural buildings from ground to
top level.
11. All external stairs and ladders shall be provided with hand railings if considered
hazardous.
12. First aid equipment shall be provided in all treatment plants, booster stations and guard
houses.
13. Safety devices and equipment meeting the OSHA requirement and regulation shall be
provided,
➢ Personal Protective Equipment
➢ Safety helmet, hearing protection, eye protection, respiratory protection, glove,
safety harness, safety shoes, safety reflector vest
➢ Portable chlorine detection equipment (for treatment plant and post chlorination
plant)
14. A safety and health officer (SHO) or site safety supervisor (SSS) or Occupational Safety
and Health Coordinator (OSH-C) shall be employed for work as comply with OSHA
requirements.
JBALB Technical Guidelines for Water Supply System in Sarawak
15. Safety and Health Plan Including Safety and Health Policy, Emergency Response Plan,
Chemical Safety Data Sheet should be provided within a month after Letter of
Acceptance.
16. Monthly Safety Report shall be provided.
17. Hazard Identification, Risk Assessment and Risk Control (HIRARC) should be carried out
and recorded during contract period. Method, materials and equipment should be
selected to remove or minimize risk from work.
18. Traffic management plan documents and helps explain how risks will be managed at the
construction workplace shall be provided. Traffic control by competent person, traffic
and warning signs shall be provided.
19. Main Gate and Hoarding shall be provided at the site to stabilize entrances to a
construction site for control movement of visitors, clients, workers and vehicles, and to
ensure to safe guard the project site and maintain the safety of workers while keeping
the general public out of the construction site.
Construction site shall set up vehicle wash tank with high pressure flushing device
before exit the main entrance.
20. Temporary water supply under conditions of ensuring uninterrupted water supply shall
be allowed.
21. Safety signs shall be provided to draw attention to objects and situations which affect or
could affect health or safety.
➢ Prohibition signs
➢ Warning signs
➢ Mandatory signs
➢ Safe condition signs
22. Supply, erection and dismantle scaffolding, working platform with safety net shall be
provided.
23. Cordoning off working area and provision of public control and safety measures where
lifting operations, moving, shifting, transferring works are carried out outside the
hoarded-up area of the worksite shall be provided.
24. Measures to prevent the breeding of mosquitoes, houseflies, rats, insects and other
dangerous animals on the Site throughout the contract period shall be allowed.
25. A Confined Space entry programme with Safe Working Procedure (SWP) shall be
developed and implemented to enter a confined space.
➢ Provide an adequate and effective ventilation to always maintain the contaminants
concentration level as low as possible, and the level of oxygen within safe range.
➢ Training shall be provided in all work with confined space.
JBALB Technical Guidelines for Water Supply System in Sarawak
26. Living quarters for workers shall be provided and isolate from the construction operation
zone.
➢ Portable fire extinguishers shall be provided adequately.
➢ Provided with supply of water and electricity.
➢ Toilet and washing building shall separate from living units at least 10 m apart with
septic tank.
27. Permit-To-Work (PTW) must be obtained before any construction activity be carried out.
PTW is a formal, written, safe system of work to control potentially hazardous activities.
The permit details the works to be done and the precautions to be taken (for instance,
they may involve limiting the movement of overhead cranes, the precautions needed for
high voltage work, or they might details rescue arrangement for certain type of works).
28. Booster station should be provided with toilet facilities and office for the attendant.
JBALB Technical Guidelines for Water Supply System in Sarawak
13 Color Code
1. Quarter
(a) Roof – Bright Blue (#0096FF)
14 Reference
1. MWA Planning Guidelines and Best Practices Handbook for Water Supply Systems (Volume
1: 2021 Edition)
5. SPAN Uniform Technical Guidelines for the Design of Water Treatment Plants and Related
Water Supply System Components (First Edition, May 2021)
6. Environmental Quality Act 1974: Environmental Quality (Industrial Effluent) Regulations 2009
12. DOSH Guidelines For Public Safety And Health At Construction Sites (1st Revision: 2007)
13. Best Practice on Occupational Safety and Health in Construction Industry 2019
15. Supply System Components (Second Draft Guidelines Rev. 0-0 9 April 2021)
23. MS 2320:2010 : Drinking Water – Quality Requirements and Standard Kualiti Air Kebangsaan
24. Guidelines on Design and Planning of Water Treatment Plant and Equipment, dated
29.01.2021. By Technical Advisor Ir. WWA (PPT file)
JBALB Technical Guidelines for Water Supply System in Sarawak
25. Theory Application and Design of Air Valves along Pipelines. By Cho KM, Chief hydraulic
Engineer, 2012.
26. National Standard for Drinking Water Quality, 2nd revision January 2004, Ministry of Health
Malaysia.
JBALB Technical Guidelines for Water Supply System in Sarawak
15 Attachment
15.1 Checklist on design report for Watermain, Booster Station and Reservoir
15.2 Check list on tender drawing for Watermain, Booster Station and Reservoir
for
Name of Project:
Name of Consultant:
1
JABATAN BEKALAN AIR LUAR BANDAR
2
JABATAN BEKALAN AIR LUAR BANDAR
4
JABATAN BEKALAN AIR LUAR BANDAR
5
JABATAN BEKALAN AIR LUAR BANDAR
(H) RESERVOIR
(a) Layout plan showing the location of the
proposed reservoir site in relation to existing
and proposed water supply system provided.
(b) Layout plan of the reservoir site showing
the tank access road, drainage system, fencing,
etc. is provided and found to be acceptable.
(c) Reservoir has minimum capacity of 24 hours
storage.
(d) Calculations to determine the capacity of
the reservoir are provided and found to be in
order.
(e) Material of tank is reinforced concrete
unless otherwise approved
(f) Reservoir with capacity more than 1 ML shall
has a central partition for O & M purposes.
(g) Standby outlet is provided.
(h) Pipeworks for the reservoir are shown.
(i) Piling for the reservoir is provided.
(j) Painting works for the reservoir is provided.
(k) Level indicator is provided.
(l) Bypass system
(m) Minimum security fencing must be provided
of height at least 2.5 meter.
(n) Staircase from the ground to tank
(o) Compound light
6
JBALB Technical Guidelines For Water Supply System In Sarawak
for
Name of Project:
Tender Drawings Submitted: 1st Draft / 2nd Draft / 3rd Draft / Final (*)
Name of Consultant:
1
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
3
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
7. HYDRANTS
Pillar hydrants for the pipelines comply with the
following:
(i) provided only where there are houses,
shophouses, longhouses, office buildings or
institutions along the pipelines.
(ii) spacing interval between hydrants is not more
than 180 metres.
(iii) For high risk installations, the hydrants are
placed not more than 90 metres walking
distance from the installations.
(iv) Screw down/ sluice valve pillar hydrants are
provided at the ends of pipelines
8. WASHOUTS
(a) Washouts are located at all low points of the
pipelines.
(b) Minimum size of washouts is 100 mm.diameter
(c) Washouts are connected to the nearest drains by
HDPE pipes.
(d) Washouts are sized to give a minimum watermain
velocity of 0.8 m/s (Note: To check against design
calculations)
9. VALVE CHAMBERS
(a) All valves for buried pipelines are housed in chambers
(b) Drawings of the valve chambers are provided for the
following:
(i) sluice valves
(ii) butterfly valves
(iii) pillar hydrants
(iv) Screw down / sluice valve pillar hydrants
(v) single air valves
(vi) double air valves
(v) washouts
(vi) pressure reducing valves
(vii) reflux valves
(c) Precast concrete valve chambers are proposed for
the following:
(i) 150 mm, 200 mm. and 250 mm. diameter sluice
valves
(ii) 25 mm and 50 mm single orifice air valves
(iii) 50 mm and 80 mm dual orifice air valves
(iv) 100 mm diameter washouts
(v) pillar hydrants
(vi) sluice valve pillar hydrant
(d) Reinforced concrete or brick chambers are proposed
for the following:
(i) sluice valve of diameter 300mm and above.
(ii) butterfly valves of diameter 450mm and above
5
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
6
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
7
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
(11) Puddle pipes are used at walls for reservoir and R.C.
valve chambers.
(12) Foundation and piling details of reservoir and R.C.
valve chambers are provided.
(13) Lightning arrestor and aircraft warning light are
provided.
(14) Compound lighting at reservoir site is provided.
(15) The capacity and levels of the reservoir and the
height of the tower (where applicable) are acceptable.
(Note: To check against design report & calculations)
(16) Standby outlet pipe provided.
(17) Detailed of bypass system
(H) MECHANICAL AND ELECTRICAL WORKS
(1) Single Line diagrams are provided for the pumphouse
and generator house.
(2) Details of mechanical installation works such as soil,
sanitary and cold water systems are provided and in
order.
(3) Details of electrical installation works such as
lightings, cablings, switchboards, etc. for the pumphouse
and generator house are provided and in order.
(4) Lightning protection installations are provided for the
pumphouse and generator house and are in order.
(5) Details of fire fighting services for pumphouse and
generator house are provided and in order.
(I) TYPICAL WATER SUPPLY DETAILS
Typical water supply details are provided for the
following and are found to be in order:
(a) Thrust blocks and anchor blocks.
(b) Precast concrete chambers for air valves.
(c) Precast concrete chambers for sluice valves.
(d) Precast concrete chambers for washouts.
(e) Precast concrete chambers for pillar hydrants.
(f) Precast concrete chambers for sluice valve pillar
hydrants.
(g) R.C. chambers for sluice valves.
(h) R.C. chambers for butterfly valves.
(i) R.C. chambers for pressure reducing valves.
(j) R.C. chambers for altitude valves.
(k) R.C. chambers for electromagnetic flowmeters.
(l) culvert crossing.
(m) Drain crossings
(n) River crossings.
(o) Pipe supports at bridge crossings.
(p) Marker posts.
(q) Concrete encasement for pipes.
9
JBALB Technical Guidelines For Water Supply System In Sarawak
for
Name of Project:
Name of Consultant:
1
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
• Improvement requirements.
• Cost / benefit analysis.
(c) Comparison of the various options for the raw water
source has been carried out (should include costs
advantages & disadvantages, etc.)
(d) For the recommended option, the
reasons/justifications for selecting this option are
given.
(e) Where run of river safe yield is insufficient, adequate
impounded storage for raw water is provided.
(f) The safe yield of the recommended raw water source
satisfied the following conditions:
• Adequate to meet the maximum projected water
demand while not significantly affecting the ecology
of the water course downstream of the intake.
• Provide a reasonable surplus for anticipated growth.
• Adequate to compensate for all losses such as sitting,
evaporation, seepage, etc.
• Adequate to provide ample water for other legal
users of the source.
2. Groundwater Source
a) The following information on the proposed
groundwater source have been provided:
• Reasons for selection.
• Reliable data source & Elevations with respect to
surrounding and flood plain(s).
• Geological conditions such as characteristic of
formations, test holes, abandoned wells or
anticipated interference between proposed and
existing wells.
• Summary of source exploration (test well depths,
location, pumping rates and their duration, water
levels, specific yield, capture area and pumping radius
of influence for production wells, recharge rates, etc.
• Raw water quality report
• Sources of possible contamination such as sewerage
facilities, farming, burial ground, landfills, chemical
facilities, etc.
• Feasibility of preserving existing wells and their
effects on proposed wells.
• Depths of any known water bearing aquifers that will
reduce well yield if penetrated.
• Wellhead and aquifer protection and management
measures & issues.
3
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
4
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
17. The size of the intake structure and layout of the pumps
are designed to cater for future upgrading or addition of
pumps to cater for increase in water demand.
18. The intake structure is designed to allow the pumps to
achieve optimum hydraulic performance for all operating
conditions.
19. The intake is equipped with a coarse screen and a fine
screen, both removable.
20. The screens are readily accessible for cleaning (preferably
self-cleaning)
21. Fenders are provided to protect the intake from floating
logs, debris, etc.
22. Lifting hoist of adquate capacity is provided for installation
and maintenance of the pumps, pipes, fittings, valves, etc.
23. Piling is provided.
24. Water proof shed is provided for switchgear, lifting hoist &
other electrical equipment.
25. Switchgear & terminal box are sited above highest flood
level possible.
26. PONTOON INTAKE
The design of pontoon, intake takes into account the
following:
(i) Pontoon structure is properly designed using durable
material.
. (ii) The pumpsets can be securely mounted on the
pontoon.
(iii) The pontoon is securely anchored without risk of
overturning during changes in water level.
(iv) Where mooring ropes are used, they are long enough
and well secured to allow for changes in water level.
(v) The pump’s discharge pipe is long enough and well
secured to allow for changes in water level. Heavy duty
flexible discharge pipe of suitable material are used.
(vi) A housing is provided over the pump(s) and motors
where centrifugal pumps are used.
(vii) Coarse screens are incorporated in the design of the
pontoon to protect the pumps or foot valves from debris,
etc.
(viii) Electrical cables of sufficient length are designed to
allow for highest water level pontoon position.
(ix) Pontoon structure is properly linked with jetty
accessible for operation & maintenance, including hand
operated cart.
27. JETTY INTAKE
The design of jetty intake takes into account the following:
5
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
6
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
7
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
8
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
9
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
10
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
11
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
12
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
13
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
14
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
15
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
16
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
17
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
18
JABATAN BEKALAN AIR LUAR BANDAR SARAWAK
20
JABATAN BEKALAN AIR LUAR BANDAR (JBALB) SARAWAK
FOR
........................ DIVISION
Above requirement shall be submitted 2 weeks before T&C except FAT report:
Page | 1
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER Rev: 1
PUMPING STATION Date:
Page | 2
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER Rev: 1
PUMPING STATION Date:
The commissioning of all new Booster Pump Stations shall be carried out by designated officers
coordinated from Jabatan Bekalan Air Luar Bandar (JBALB) Headquarters. The commissioning
team shall consist of the following: -
a) Mechanical Engineer
b) Electrical Engineer
c) Civil Engineer (Related Project)
d) Chemist
e) Assistant Engineer
Team Formation
JBALB Headquarters
Testing & JBALB Divisional/Project Contractor and
Commissioning Team Team Consultant
(Refer to name list (Refer to name list detail)
detail)
Page | 3
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER Rev: 1
PUMPING STATION Date:
2.0 Methodology
DOCUMENTATION / HANDOVER
Parties involved: Divisional Office and
JBALB Headquarters
REFRESHER/ TRAINING
As per contract (external)
To be conducted by JBALB
Divisional and JBALB HQ
(recommended once every six (6)
month)
Page | 4
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER Rev: 1
PUMPING STATION Date:
i) The commissioning team will witness the testing of all items of equipment, pipework, fittings
and appurtenant (accessories) works to ensure that they are correctly installed and capable of
proper operation.
ii) The team will witness start up and running each item of equipment separately until they are
satisfied that it is capable of proper operation.
iii) After each item of equipment has been tested separately, the various items will be run
concurrently to commission the plant.
3.1 In carrying out (i) to (iii) above, the team shall ensure that: -
iv) Switchboards, control panels, alarm systems, overloads, and safety equipment are tested.
v) The alignment, mounting and configuration of pumps and drives, including the direction of
rotation are checked.
vi) The various lubrication systems and greasing systems are checked, including pump shaft
lubrication and stuffing box seal requirements.
vii) The pipework valves and gauges are correctly installed and operate satisfactorily. The
appropriate valve positions shall be determined for the different modes of operation of the
plant and documented.
viii) The chemical mixing, feeding and dosing equipment shall be tested and calibrated.
xi) All other tools and equipment necessary have been provided and are in working order.
Page | 5
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER Rev: 1
PUMPING STATION Date:
3.2 During the commissioning of the plant, the team shall ensure that: -
i) The limits of hydraulic operation of the various units of the plant are determined.
ii) The appropriate flow rate through the plant is determined to minimize “on-off” operation.
Guides on pumping rates for the raw water and treated water pumps shall be established.
iii) The clarifiers are operated with the appropriate level of coagulant to achieve a well developed
floc blanket.
v) The filters are operated sufficiently long to establish head loss characteristics and backwash
requirements.
vi) The filter backwash system and air scour are operated correctly. The correct procedure for
backwashing of the filters is determined and documented.
vii) As far as possible, the appropriate levels of dosing of chemicals for the plant are determined.
In particular, the appropriate level of post dosing for pH correction is determined.
During the commissioning of the plant, the Divisional Water Engineer (DWE), Assistant
Engineer, Assistant Technician/Technician and attendants allocated to assist the teams, will
undergo “hands on” training in preparation for accepting responsibility for operation of the plant.
This training role will be a significant aspect of the duties of the commissioning team.
Page | 6
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER Rev: 1
PUMPING STATION Date:
3.5.1 When the plant is operating satisfactorily and treated water has been supplied into the existing
reticulation system, it will be handed over to the JBALB Division staff.
3.5.2 The commissioning team will prepare four (4) copies of the commissioning report, (1) one copy
to the Regional Manager, (1) one copy to the Divisional Water Engineer and (2) two copies to
JBALB Headquarters.
3.5.3 The report shall contain as a separate section, the recommended procedure for operating the
various items of the plant including the following:
Page | 7
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER Rev: 1
PUMPING STATION Date:
METHOD STATEMENT
BOOSTER PUMP STATION PRE & POST COMMISSIONING
Page | 8
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER Rev: 1
PUMPING STATION Date:
METHOD STATEMENT
Booster Pump Station Pre & Post Commissioning
Background Information
Project Name
Contract No.
New Pipe interconnection to existing 1. JBALB Project Management Team concerned shall notify
piping system any pipe interconnection and submit method statement for
interconnection work to JBALB Divisional Office prior to
the commencement of actual work.
2. Method statement must be agreed between Project
Management Team and Respective JBALB Divisional
Office before any work can proceed.
3. Upon agreement on the interconnection Method Statement,
the affected Divisional Office (DWE/OIC) shall issue notice
of water supply interruption to the public prior to the
execution of interconnection work either via Corporate
Communication or Information Department (which ever) is
more efficient and cost effective within a weeks notice.
4. Any actual shutdown to the existing system shall be done by
representative from JBALB Divisional Office assisted by the
Contractor involved.
5. The interconnection work and any reinstatement work which
is affected by the interconnection process shall be done by
the contractor involved to the satisfaction of representative
of both Project Team and Divisional Office.
Page | 10
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER PUMPING Rev: 1
STATION
Date:
Page | 11
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER PUMPING Rev: 1
STATION
Date:
Page | 12
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER PUMPING Rev: 1
STATION
Date:
The following notes are intended as a guide to the completion of Pre-Commissioning and
Commissioning Works in a manner which will be consistent throughout all new Booster Pump
Stations.
These are checks which are required to be undertaken by the Mechanical/Electrical Sub-Contractor
and are supervised by Contractor’s staff. They are intended as a virtual 'check list’ to ensure that all
items of equipment have been installed according to manufactures/supplies requirement and have
been prepared for commissioning/operation.
These are checks which are required to be undertaken by Contractor’s staff in the presence of Jabatan
Bekalan Air Luar Bandar (JBALB) staff.
It is essential that JBALB staffs are present in order to witness measurements, readings, and
observations made during these checks. For this reason, sufficient notice should be given by
Contractor to JBALB (UPT). The contractual requirement is for 21 days’ notice. It is possible
however, to advise late changes to programme by facsimile/telephone when absolutely necessary.
Guidelines and Checklist for Commissioning are intended to be applicable to ALL Booster Pump
Stations. It is unavoidable, therefore, that certain sections will not be applicable to a particular
scheme. Inapplicable sections will normally have been crossed out or struck through before the time
of commissioning. If this is not the case, then a comment should be made by the signatories indicating
which sections have not been undertaken or witnessed.
It is absolutely essential that Mechanical and Electrical competent personnel are delegated to witness
the commissioning of Mechanical and Electrical equipment in order to avoid protracted discussions
and arguments on methods/techniques employed to generate the data.
Page | 13
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER PUMPING Rev: 1
STATION
Date:
If the reservoir is greater than 1 km-from the Booster Station, pumps are stopped by a
differential pressure switch which is operated on a decrease in flow. It may not be convenient
to wait for what could amount to several hours in order to demonstrate the correct operation
of this cut-out. All that is necessary in this case is to slowly close the pump discharge valve
and note the flow at which the pump trips.
For reservoirs less than 1 km from the Booster Station, pumps are stopped by level electrodes
which respond to the conduction of an electric current between them (when both are
immersed in water). Again, correct operation can be demonstrated by lowering the High
Level electrode into the water, or by shorting the Reference and High Electrodes
momentarily.
If a low flow trip, then re-start is by an adjustable timer. All that is necessary in this case to
demonstrate correct operation, without having to wait for an excessive time, is to temporarily
adjust the timer to a value of a few minutes.
Where trip is by electrode, re-start is also by electrodes, in this case by a break in the flow of
electric current between them. (When the water level falls below the Low Level Electrode)
Correct operation can be demonstrated in this case by raising the Low Level Electrode clear
of the water surface, or by momentarily disconnecting the connection to the Low Level
Electrode.
3. Check pumps stop when suction tank is at low level; Check pumps re-start
automatically.............
In the case of a suction tank, trip and re-set are both by electrode and the same comments
made above apply here. In some situations, however, where there is uncertainty as to the
precise details of existing water reservoirs, it will be necessary to check correct tripping by
draining or drawing down the feed reservoir.
Page | 14
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER PUMPING Rev: 1
STATION
Date:
5. Travelling Crane
The JKKP Certificate for the crane should be issued and available for record.
After the surge suppression equipment is commissioned, all that is required under this section
is to observe the maximum and minimum pressures indicated on the surge arrestor pressure
gauge on starting and stopping the pump from a position of pressure equilibrium. The JKKP
Certificate for the Surge Suppression Equipment should be issued and available for record.
7. Generating Sets
Bomba Approval on all Fire Protection System should be issued and available for record.
9. Chlorination System
Correct operation of pumps can only be assessed by mechanically competent and experienced
personnel. Manufacturers’ literature states that bearing temperature should check by hand: If a normal
person can hold a bearing cover without feeling pain, then it is highly probable that the temperature is
below 60 degree C and that the bearing is running normally.
If the bearing is running hot, this does not necessarily mean that it is defective, in nine cases out of ten
it is usually found that it has been over packed with grease, and that cleaning and repacking the
bearing will reduce its operating temperature.
‘Abnormal’ noise and vibration is a very subjective assessment and again, should be left to
experienced personnel.
Readings are taken over the operating range of the pumps. Data are calculated and graphs drawn
SUBSEQUENT to the commissioning of the booster stations. JBALB personnel/representative should
witness the readings taken. There will be one TABLE A, and one TABLE B for each pump set.
Page | 15
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER PUMPING Rev: 1
STATION
Date:
Most of the data entered onto the Acceptance Test Guidelines will be abstracted from the Pre-
Commissioning and Commissioning Guidelines. The main purpose of the acceptance test is to
demonstrate the system as a whole will function satisfactorily over a period of 14 days (or less
depending upon the operational requirements of JBALB).
All that is required is for JBALB representatives to acknowledge the period of operation defined as
the 'Acceptance Test’.
N.B. JBALB representatives are not being asked to 'accept' or takeover schemes. All that is
required of them is to witness the proceedings and if necessary, to draw up a 'snag list’ of
items considered incomplete or defective. This snag list, together with any comments
considered appropriate, should be referred to JBALB Divisional who are the agency
responsible for accepting schemes.
Page | 16
Contract No:
TESTING AND COMMISSIONING
Rev: 1
DOCUMENT FOR BOOSTER PUMPING
STATION Date:
Page | 17
Contract No:
TESTING AND COMMISSIONING
Rev: 1
DOCUMENT FOR BOOSTER PUMPING
STATION Date:
PUMP ………………………..
Location Plan
Scheme Specific
Pipeline Profiles
Booster Station Assembly drawings
Manufacturers Pump set test cert. (attached)
O&M manual (draft)
Witnessed by JBALB
2. PUMPS Checked by Consultant
Representative
a) Refer to Operation & Maintenance
Manual (2.2.5 Operating Procedure -
Booster Pump. Station)
Page | 18
Contract No:
TESTING AND COMMISSIONING
Rev: 1
DOCUMENT FOR BOOSTER PUMPING
STATION Date:
Rated Actual
d) Oil pressure switch operation kPA kPA
O O
e) Water temperature switch C C
operation
f) Engine over speed switch rpm rpm
operation
Page | 19
Contract No:
TESTING AND COMMISSIONING
Rev: 1
DOCUMENT FOR BOOSTER PUMPING
STATION Date:
(Where Surge Suppression Equipment fitted, commissioning will be carried out under section 2)
a) Pump start up: Observed
Max. Min.
pressure
Pump shut Observed
Max. Min.
down: pressure
Pressure Set Point: Bar
Level Set Point: M
7. CHLORINE DOSING SYSTEM
Check all gas pipework joints for leaks using ammonia vapor.
Manufacturers pre-start up checks complete Yes No
Page | 20
Contract No:
TESTING AND COMMISSIONING
Rev: 1
DOCUMENT FOR BOOSTER PUMPING
STATION Date:
TELEMETRY SYSTEM
TEST CRITERIA
- The PLC DI and SCADA System shall receive the signal.
- The LED status at the PLC DI module and equipment status at SCADA shall turn off when the
simulated signal is disabled.
DIGITAL SCADA
INPUT/ GRAPHIC
DESCRIPTION REMARKS
OUTPUT
ADDRESS YES NO
Page | 21
Contract No:
TESTING AND COMMISSIONING
Rev: 1
DOCUMENT FOR BOOSTER PUMPING
STATION Date:
TEST CRITERIA
- The SCADA shall give the output signal according to signal simulated.
Equip. Description :
Simulated Range : 4 – 20 mA
Input Range :
4
8
12
16
20
Commissioning complete systems ready for use.
Remarks:
Page | 22
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER PUMPING Rev: 1
STATION
Effective date: 3rd February
2020
Page | 23
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER PUMPING Rev: 1
STATION
Effective date: 3rd February
2020
Surge Vessels
Suction Tank
Reservoirs
6. Equipment used for measurement Pipelines Tanks
Flow
Range of flowmeter
Comments
Pressure
Range of instrument
Comments
Level
Comments
Page | 24
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER PUMPING Rev: 1
STATION
Effective date: 3rd February
2020
Start pumping:
Stop pumping:
* These are shift times. The pump will stop and start during this period if the Storage Reservoir
fills.
Required output: 1.1 times Average Daily Year 2000 Flow
= 1.1 x ____________ = _______________
Page | 25
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER PUMPING Rev: 1
STATION
Effective date: 3rd February
2020
10. Test conducted for 14 days/ ……… (OR as agreed with JBALB)
11. OVERHEAD CRANE
Yes No
JKKP Approval Required
If Yes, JKKP Certificate
If No, JBALB Approval At Commissioning
12. DIESEL GENERATOR SET
Yes No
D.O.E Approval
13. SURGE SUPPRESSION EQUIPMENT
Yes No
JKKP Type Approval
JKKP Installation Approval
14 CHLORINE DOSING SYSTEM Yes No
Functioning in line with booster pump
Remarks:
Page | 26
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR BOOSTER PUMPING Rev: 1
STATION
Effective date: 3rd February
2020
TABLE A
Bearing Check 40 - 60 C
Time (Every Abnormal Noise
Motor Pump Any leaks visible
Hour) and/or vibration
DE NDE DE NDE
Page | 27
TABLE B: Unless otherwise specified Tests carried out in accordance with BS5316 Part
PUMP TEST CERTIFICATE 1, Class C
PUMP TESTED:
CUSTOMER/PROJECT:
PUMP SIZE: SERIAL NO:
INLET/OUTLET
DRIVER: IMPELLER DIA: MM DIA: MM
ORIFICE PLATE
TYPE: DIA: MM
MAKE: FLOW RATE: m3/h
MODEL: RPM: HP TOTAL HEAD: M
POWER: kW AMP: I
VOLTAGE: V PHASE:
SUCTION PRESSURE GAUGE LEVEL: M
DISCHARGE PRESSURE GAUGE LEVEL: M
Page | 28
LIST OF EQUIPMENTS
Page | 29
2. Chlorination System
2.1 Vacuum Regulator
Brand/Make
Type
Model
Heater Make
Heater Type
Power Rating V/A/W
Rated Frequency Hz
2.2 Chlorinator
Brand/Make
Type
Model
Max Capacity kg/hr
Motor Make
Motor Type
Power Rating V/A/W
Rated Frequency Hz
2.3 Changeover Manifold
Brand/Make
Type
Serial No.
Range
2.4 Injector
Brand/Make
Type
Serial No.
Max Capacity kg/hr
Page | 30
3. Pressure Transmitter
Instrument Brand/Make
Instrument Model
Instrument Serial No.
Measure (i.e. pH,
NTU,mg/l)
Output current mA
Rated current A
Voltage/Phase V/Phase
Rated Frequency Hz
Class
4 Crane
Brand/Make
Type
Model
Country
Year
Equipment Serial No.
Hoist Serial No.
PMA Registration No.
Hoisting Capacity Ton
Voltage/Phase/Current V/Phase/
A
Page | 31
5. Surge Vessel (If
Applicable)
5.1 Compressor
Brand/Make
Model
Serial No.
Piston Displacement
Max Discharge Pressure Bar
Design Duty Pressure Bar
Free Air
Noise Level dB
5.2 Motor
Brand/Make
Type
Model
Serial No
Power kW
Voltage/Phase V/Phase
Rated Current A
Speed Rpm
Class
Page | 32
APPENDIX
PRE-COMMISSIONING CHECKLIST FOR BOOSTER PUMP STATION
Appendix (A)
1. VALVES
2. PUMPS
i) Manufacturers Pre-Start Up Checks (see attached PUMP PUMP PUMP PUMP
sheets) completed
ii) Alignment Checks
See manual Parallel (mm) Angular (mm)
No.
for procedure PUMP PUMP PUMP PUMP PUMP PUMP PUMP PUMP
Reading with 1
pipework 2
uncoupled
3
4
Reading with 1
pipework 2
coupled
3
4
Manufacturers tolerance: Parallel ………………… mm
Angular ………………. mm
3. ELECTRICAL
c) Polarity check
d) Earth Resistance Test for Lighting Protection System = ohms
(≤10 ohms)
ii) Switchgear Protection Setting Checked by
a) Over current protection
b) Earth leakage setting
iii) Pump Motor Insulation
Pump Pump Pump Pump
Resistance Test
R-Y
Y-B
B-R
L-N
L-E
4. INSTRUMENTATION
Yes No
a) Installation/Assembly complete and in
accordance with drawing
b) Control cables insulation check (see attached sheet D(i))
c) Isolation and Balancing Valves, bleed screws
checked for operation over full strokes
Instrument
Instrument
Instrument
Instrument
Expected Actual
Instrument 4,00 mA mA
Instrument 4,00 mA mA
Instrument 4,00 mA mA
Instrument 4,00 mA mA
If a value differs from that expected by more than 0.01 mA, reconfirm sensor range with D.P.
range stamped on D all Tube/Orifice Plate, and then refer to manufacturers operating
instructions for procedure to set zero and coarse span.
N.B. The fine span is pre-set at the factory and should not be adjusted unless there
is reason to suspect an unexpected change in calibration. A precision pressure
source is required before adjusting the fine span potentiometer.
Confirm that the Meter Factor (written on the inside of the connection compartment) matches
the settings of " switches S1, S2, S3 and S4 and link Ll.
(Details of the calibration necessary to determine the Meter Factor are contained in Appendix
A of the Manufacturers’ Instruction Manual).
5. PUMP PROTECTION
a) Low Level Probe in suction tank m
b) High Level Probe in suction tank m
c) High Level Probe in receiving reservoir m
3
d) Differential Pressure (D.P.) switch in discharge pipeline m /h
6. MOTORS
a) Check motor insulation resistance Pump Pump Pump
R-Y
Y-B
B-R
L-E
c)
b) Motor winding resistance (Ohm)
U1-U2
V1-V2
W1-W2
d) Yes No
Check thermister trip for motor over 37 kW
(by shorting thermister) PUMP
PUMP
PUMP
PUMP
Yes No
a) Tapes over breather holes removed
b) All damaged paintwork repaired
c) Alignment check Drawing
(N/A to monorail hoists) Dimension Measured Dimension Permitted Tolerances
i) Crane span at each end ±6 mm
of carriages
ii) Diagonal centres of ±6 mm
crane wheels
iii) Crane span at crane ±6 mm
rail level
Yes
d) Safe work load ______________tonnes painted on frame
8. GENERATORS
Generator Unit
a) Manufacturers pre-start checks
completed (see attached sheets)
High Low
Rated Actual Rated Actual
l) Alarm setting high/low mm mm mm mm
Stop Start
Rated Actual Rated Actual
m) Compressor settings start/stop mm mm mm mm
n) JKKP type approval Yes/No
o) JKKP installation approval Yes/No/NA
Remarks:
Site Location:
Power/Control Cables
…………………………………………………
Insulation
Cable Type of No. of Rated
Cable Name From To Resistance
Tagging Cable Cable Voltage (V)
Test (MΩ)
Remarks:
Witnessed by JBALB
Checked By Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
FOR
........................ DIVISION
Above requirement shall be submitted 2 weeks before T&C except FAT report:
Page | 1
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR WATER Rev: 1
TREATMENT PLANT Date:
Page | 2
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR WATER Rev: 1
TREATMENT PLANT Date:
The commissioning of all new JBALB water treatment plants shall be carried out by designated
officers coordinated Jabatan Bekalan Air Luar Bandar (JBALB) Headquarters. The
commissioning team shall consist of the following: -
a) Mechanical Engineer
b) Electrical Engineer
c) Civil Engineer (Related Project)
d) Chemist
e) Assistant Engineer
Team Formation
Page | 3
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR WATER Rev: 1
TREATMENT PLANT Date:
2.0 Methodology
DOCUMENTATION / HANDOVER
Parties involved: Divisional Office and
JBALB Headquarters
REFRESHER/ TRAINING
As per contract (external)
To be conducted by JBALB
Divisional and JBALB HQ
(recommended once every six (6)
month)
Page | 4
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR WATER Rev: 1
TREATMENT PLANT Date:
i) The commissioning team will witness the testing of all items of equipment, pipework, fittings
and appurtenant (accessories) works to ensure that they are correctly installed and capable of
proper operation.
ii) The team will witness start up and running each item of equipment separately until they are
satisfied that it is capable of proper operation.
iii) After each item of equipment has been tested separately, the various items will be run
concurrently to commission the plant.
3.1 In carrying out (i) to (iii) above, the team shall ensure that:-
iv) Switchboards, control panels, alarm systems, overloads, and safety equipment are tested.
v) The alignment, mounting and configuration of pumps and drives, including the direction of
rotation are checked.
vi) The various lubrication systems and greasing systems are checked, including pump shaft
lubrication and stuffing box seal requirements.
vii) The pipework valves and gauges are correctly installed and operate satisfactorily. The
appropriate valve positions shall be determined for the different modes of operation of the
plant and documented.
viii) The chemical mixing, feeding and dosing equipment shall be tested and calibrated.
xi) All other tools and equipment necessary have been provided and are in working order.
Page | 5
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR WATER Rev: 1
TREATMENT PLANT Date:
3.2 During the commissioning of the plant, the team shall ensure that: -
i) The limits of hydraulic operation of the various units of the plant are determined.
ii) The appropriate flow rate through the plant is determined to minimize “on-off” operation.
Guides on pumping rates for the raw water and treated water pumps shall be established.
iii) The clarifiers are operated with the appropriate level of coagulant to achieve a well developed
floc blanket.
v) The filters are operated sufficiently long to establish head loss characteristics and backwash
requirements.
vi) The filter backwash system and air scour are operated correctly. The correct procedure for
backwashing of the filters is determined and documented.
vii) As far as possible, the appropriate levels of dosing of chemicals for the plant are determined.
In particular, the appropriate level of post dosing for pH correction is determined.
During the commissioning of the plant, the Divisional Water Engineer (DWE), Assistant
Engineer, Assistant Technician/Technician and attendants allocated to assist the teams, will
undergo “hands on” training in preparation for accepting responsibility for operation of the plant.
This training role will be a significant aspect of the duties of the commissioning team.
Page | 6
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR WATER Rev: 1
TREATMENT PLANT Date:
3.5.1 When the plant is operating satisfactorily and treated water has been supplied into the existing
reticulation system, it will be handed over to the JBALB Divisional staff.
3.5.2 The commissioning team will prepare four (4) copies of the commissioning report, (1) one copy
to the Regional Manager, (1) one copy to the Divisional Water Engineer and (2) two copies to
JBALB Headquarters.
3.5.3 The report shall contain as a separate section, the recommended procedure for operating the
various items of the plant including the following:
Page | 7
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR WATER Rev: 1
TREATMENT PLANT Date:
METHOD STATEMENT
WATER TREATMENT PLANT PRE & POST COMMISSIONING
Page | 8
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR WATER Rev: 1
TREATMENT PLANT Date:
METHOD STATEMENT
Water Treatment Plant Pre & Post Commissioning
Background Information
Project Name
Contract No.
Page | 9
Contract No:
TESTING AND COMMISSIONING
DOCUMENT FOR WATER Rev: 1
TREATMENT PLANT Date:
Page | 10
Contract No:
Page | 11
Contract No:
Page | 12
Contract No:
The following notes are intended as a guide to the completion Pre-Commissioning and
Commissioning Works in a manner which will be consistent throughout all new Treatment Plants.
These are checks which are required to be undertaken by the Mechanical/Electrical Sub-Contractor
and are supervised by Contractor’s staff. They are intended as a virtual 'check list’ to ensure that all
items of equipment have been installed correctly and have been prepared for
commissioning/operation.
These are checks which are required to be undertaken by Contractor’s staff in the presence of Jabatan
Bekalan Air Luar Bandar (JBALB) staff.
It is essential that JBALB staffs are present in order to witness measurements, readings, and
observations made during these checks. For this reason, sufficient notice should be given by
Contractor to JBALB. The contractual requirement is for 21 days’ notice. It is possible however,
to advise later changes to programme by facsimile/telephone when absolutely necessary.
Guidelines and Checklists for Commissioning are intended to be applicable to ALL Treatment Plants.
It is unavoidable, therefore, that certain sections will not be applicable to a particular scheme.
Inapplicable sections will normally have been crossed out or struck through before the time of
commissioning. If this is not the case, then a comment should be made by the signatories indicating
which sections have not been undertaken or witnessed.
Page | 13
Contract No:
Pump Test Sheet - when recording pump performance data, it is useful if a sample check on
flow rate can be performance in order to verify the flowmeter accuracy.
Readings are taken over the operating range of the pumps. Data are calculated and graphs
drawn SUBSEQUENT to the commissioning. JBALB should witness the result taken; results
will be presented to JBALB personnel at a later date.
2. Aerators
b) The water is coming from a borehole and dissolved carbon dioxide is high.
3. Flocculators
4. Backwash Pumps
Table A: The correct operation of pumps can only be assessed by Mechanically competent
and experienced personnel. Manufacturers’ literature states that bearing temperature should
be checked by hand: if a normal person can hold a bearing cover without feeling pain, then it
is highly probable that the temperature is below 60 degree C and that the bearing is running
normally. However, if available, an electronic surface temperature meter should be used to
verify the actual temperature.
If the bearing is running hot, this does not necessarily mean that it is defective; in nine cases
out of ten, it is usually found that it has been over packed with grease, and that cleaning and
re-packing cures the problem.
‘Abnormal’ noise and vibration is a very subjective assessment and again should be left to
experienced personnel.
Table B: Readings are taken over the operating range of the pumps. Data are calculated and
graphs drawn subsequent to the commissioning of the Treatment Plant. JBALB personnel
should witness the readings taken, results will be presented to JBALB Divisional at a later
date.
Page | 14
Contract No:
If the reservoir is greater than l km from the Treatment Plant, pumps are stopped by a
differential pressure switch which is operated on a decrease in flow. It may not be
convenient to wait for what could amount to several hours in order to demonstrate the
correct operation of this cut-out. All that is necessary in this case is to slowly close the
pump discharge valve and note the flow at which the pump trips.
For reservoirs less than 1 km from the Treatment Plant, pumps are stopped by level
electrodes which respond to the conduction of an electric current between them (when
both are immersed in water). Again, correct operation can be demonstrated by lowering
the High Level electrode into the water, or by shorting the Reference and High Electrodes
momentarily.
If a low flow trip, then re-start is by an adjustable timer. All that is necessary in this case
to demonstrate correct operation, without having to wait for an excessive time, is to
temporarily adjust the timer to a value of a few minutes.
Where trip is by electrode, re-start is also by electrodes, in this case by a break in the flow
of electric current between them. (When the water level falls below the Low Level
Electrode) Correct operation can be demonstrated in this case by raising the Low Level
Electrode clear of the water surface, or by momentarily disconnecting the connection to
the Low Level Electrode.
c) Check Pumps stop when Balance tank is at low level; Check pumps re-start automatically
In the case of a balance tank, trip and re-set are both by electrode and the same comments
made above apply here.
6. Air Blowers
The un-loader valves should be permanently shut for normal operation, after initial checks are
complete.
The operation of the relief valves is checked by running the blower with the discharge valve
closed and the un-loader valve open: The un-loader valve is then slowly closed until the relief
valve lifts. The pressure can then be read from the discharge pressure gauge.
Page | 15
Contract No:
7. Sludge Tank/Pumps
After shut off at low level, the pumps require manual re-setting to re-start.
Assume top water level to be at the invert level of the overflow outlet. This ensures that the
operator consistently makes up a correct known volume of dosing solution.
Dosing solutions should always be 5% alumina content, as the flow-meter is calibrated for the
appropriate specific gravity. If the required dose rate is outside the flow-meters range and a
different dosing solution strength is necessary, then a check of actual flow rate should be
made to determine the correction factor.
To check the powder feed rate at different potentiometer settings; waits for a vibration period
to start and collect powder for 1 to 2 minutes (depending on setting). The powder collected is
then weighed and the kg/hr rate computed.
The JKKP Certificate for the crane should be issued and available for record.
After the surge suppression equipment is commissioned, all that is required under this section
is to observe the maximum and minimum pressures indicated on the surge arrestor pressure
gauge on starting and stopping the pump from a position of pressure equilibrium. The JKKP
Certificate for the Surge Suppression Equipment should be issued and available for record.
Bomba Approval on all Fire Protection System should be issued and available for record.
Page | 16
Contract No:
The JBALB operators will normally carry out the following tests:
- pH
- Turbidity
- Colour
- Aluminium
- Fluoride
This data will normally be recorded by JBALB operators but Contractor’s staff may assist if
necessary.
These calculations and tests will be carried out by Contractor’s commissioning staff. In the
event of the target pH being higher than maximum Malaysia Water Supply Quality Standard
drinking water pH, a suitable target pH will be decided in consultation with JBALB. In any
event, if daily monitoring indicates no significant change in the saturation pH, the frequency
of testing maybe decreased.
Page | 17
Contract No:
The commissioning team will instruct the operators and Contractor’s staff on the use of appropriate
test equipment.
Additionally, full instruction will be given on determination of chemical dose rates and operational
procedures to achieve them.
The Acceptance Test will normally be the responsibility of contractor’s staff, but commissioning staff
will be available for process advice when necessary.
Collection of water samples and subsequent delivery to an independent laboratory will be the
responsibility of Contractor’s staff.
It should be noted that samples for bacteriological analysis should be tested as soon as possible after
collection. Samples for chemical analysis are not so critical.
It is required is of JBALB representatives that they acknowledge the period of operation defined as
the acceptance test.
Quality based on the results must be to National Water Quality Standard for Malaysia (NWQS). What
are specified must meet the NWQS standard to achieve KPI.
N.B. JBALB representatives are not being asked to 'accept' or take over schemes. All that is
required of them is to witness the proceedings and if necessary, to draw up a 'snag list’ of
items considered incomplete or defective. This snag list, together with any comments
considered appropriate, should be referred to JBALB Regional Office/JBALB Divisional who
is the agency responsible for accepting schemes.
Page | 18
Contract No:
Page | 19
Contract No:
Remarks:
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 20
Contract No:
AERATOR
1. With system in operation, check weir levels under dynamic conditions.
Unit No. Top Mid Lower
North
East
South
West
Yes No
Remarks:
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 21
Contract No:
Page | 22
Contract No:
Yes No
Commissioning complete, system ready for use.
Remarks:
Page | 23
Contract No:
FLOCCULATOR/CLARIFIERS/SEDIMENTATION TANK
Yes No
Within tolerance ±3mm
2. Check drainage line adequacy during conditions of unit
draindown and overflow. Satisfactory
Remarks:
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 24
Contract No:
Page | 25
Contract No:
Yes No
Commissioning complete systems ready for use.
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 26
Contract No:
BACKWASH PUMPS
1. Run each pump for 10mins to check current consumption.
Measured Full Load Current
Unit Rated Full Load Current (FLC) (A) (FLC) (A)
R B Y
Pump
Pump
Pump
Page | 27
Contract No:
Remarks:
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 28
Contract No:
Unit Rated Full Load Measured Full Load Current (FLC), (A)
Current
(FLC),(A) R Y B
Pump
Pump
Pump
Pump
Pump
Pump
3. Run each pump for 2 hours or until Bearing/Gland temperature is constant. Check motor and pump for
uncharacteristic noises or vibration. Adjust gland leakage.
Satisfactory Unit Yes No
Pump
Pump
Pump
Pump
Pump
Pump
Page | 29
Contract No:
Performance satisfactory
7. Check pump/motor speeds
Unit Pump Pump Pump Pump Pump Pump
Rated speed (RPM)
Measured speed (RPM)
Commissioning complete; system ready for use Yes No
Remarks:
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 30
Contract No:
AIR BLOWERS
1. Manufacturers start-up procedure complete Unit Yes No
Blower
Blower
Yes No
Satisfactory
3. Blower Speed Unit Rated Flow Rate (m3/h) Actual Flow Rate (m3/h)
Blower
Blower
4. Remote start checked Yes No
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 31
Contract No:
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 32
Contract No:
SLUDGE TANK
1. Manufacturer pre-start checks complete Yes No
3. Run pumps to low level in order to check automatic shut off; level at shut off.
4. Check pump discharge capacity by volumetric method
Pump Pump
Time Interval hours hours
Draw down volume m3 m3
3 3
Estimated flow rate m /h m /h
Yes No
Commissioning complete, system ready to use.
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 33
Contract No:
Remarks:
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 34
Contract No:
Page | 35
Contract No:
Remarks:
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 36
Contract No:
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 37
Contract No:
3. Vertical deflection test of crane bridge caused by hoist plus Safe Working Load (SWL) in
central position.
Span
Permitted maximum deflection (span – 750)
Measured deflection To Be Inspected by JKKP
4. Load hook through full travel with Safe Working Load
5. Crane travelled full length with Safe Working Load
Yes No
6. JKKP type approval
7. JKKP installation approval & Certificate (See Attached
Certificate)
Remarks:
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 38
Contract No:
GENERATORS
Yes No
1. Manufacturers test certificate attached
2. D.O.E Application
Rated Actual
3. Oil pressure switch operation kPA kPA
o o
4. Water temperature switch operation C C
5. Engine over-speed switch operation rpm rpm
6. Trip-on control circuit voltage failure
7. Noise measured (in dBA) North South East West
Measured 3 m from exhaust
Measured 3 m from outer wall
Yes No
8. Test generator over six consecutive starts
Remarks:
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 39
Contract No:
Yes No
Remarks:
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 40
Contract No:
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 41
Contract No:
TEST CRITERIA
- The PLC DI and SCADA System shall receive the signal.
- The LED status at the PLC DI module and equipment status at SCADA shall turn off when the
simulated signal is disabled.
DIGITA
L INPUT SCADA GRAPHIC
DESCRIPTION /OUTPU REMARKS
TADDR YES NO
ESS
Page | 42
Contract No:
TEST CRITERIA
- The SCADA shall give the output signal according to signal simulated.
Equip. Description :
Simulated Range : 4 – 20 mA
Input Range :
Simulated Range
Desired Value Displayed Value Remarks
(mA)
4
8
12
16
20
Page | 43
Contract No:
Page | 44
Contract No:
Record head loss due to progressive clogging, and turbidity, commencing immediately after
an extended backwash (to ensure clean media). See data sheet attached.
Design Recommended
Air Scour Duration minutes minutes
Backwash Duration minutes minutes
Backwash Flow m3/hr m3/hr
Design Recommended
Air/Water Scour Duration minutes minutes
Air/Water Scour Flow m3/hr m3/hr
Wash Water Duration minutes minutes
Wash Water Flow m3/hr m3/hr
Page | 45
Contract No:
Check filters bank performance under conditions of increased unit flow due to filter washing
in progress.
Page | 46
Contract No:
Page | 47
Contract No:
Best Selection
Comment :
Witnessed by JBALB
Checked by Contractor Certified by Consultant
Representative
Name
Signature
Designation
Date
Page | 48
Contract No:
Pump Tested:
Bearing Check 40 -60 C
Motor Abnormal Noise
Time (Every Hour) Pump Any leaks visible
and/or vibration
DE NDE DE NDE
Remarks:
Note:
DE – Drive End
NDE – Non Drive End
Page | 49
Contract No:
Page | 50
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
LIST OF EQUIPMENT
Page | 51
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
LIST OF EQUIPMENTS
Pump Brand/Make
Pump Model
Pump Serial No.
Pump Head m
Design Flow Rate m3/hr
HP
Power kW
Rated current A
Voltage/Phase V/Phase
Motor Brand/Make
Motor Model
Motor Serial No.
Motor Speed rpm
Motor Frequency Hz
Class
Page | 52
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Pump Brand/Make
Pump Model
Pump Serial No.
Pump Head m
Design Flow Rate m3/hr
HP
Power kW
Rated current A
Voltage/Phase V/Phase
Motor Brand/Make
Motor Model
Motor Serial No.
Motor Speed rpm
Motor Frequency Hz
Class
4. Air Blower
Blower Brand/Make
Blower Model
Blower Serial No.
Blower Capacity m3/hr
Page | 53
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
5. Sampling Pump
Sample Type
Pump Brand/Make
Pump Model
Pump Serial No.
Pump Head m
Design Flow Rate l/min
Power kW
Rated current A
Voltage/Phase V/Phase
Motor Speed rpm
Motor Frequency Hz
Class
7. Agitator/Mixer
Chemical Type
Brand/Make
Model
Serial No.
Motor Brand/Make
Motor Model
Motor Power kW
Motor Rated current A
Voltage/Phase V/Phase
Motor Speed Rpm
Motor Frequency Hz
Gear Model
Gear Speed Rpm
Page | 54
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
8. Monitoring Instruments
Parameter monitored
Instrument Brand/Make
Instrument Model
Instrument Serial No.
Measure (ie pH, NTU,mg/l)
Output mA
Rated current A
Voltage/Phase Voltage/Pha
se
Rated Frequency Hz
Class
9. Chlorination System
9.1 Vacuum Regulator
Brand/Make
Type
Model
Heater Make
Heater Type
Power Rating kW
Voltage/Frequency/Current V/Hz/A
9.2 Chlorinator
Brand/Make
Type
Model
Max Capacity kg/hr
Motor Make
Motor Type
Power Rating kW
9.3 Changeover Manifold
Brand/Make
Type
Serial No.
Range
9.4 Injector
Brand/Make
Type
Serial No.
Max Capacity kg/hr
Page | 55
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
12 Crane
Brand/Make
Type
Model
Country
Year
Equipment Serial No.
Hoist Serial No.
PMA Registration No.
Hoisting Capacity Ton
Page | 56
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Page | 57
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Appendix
Contract No:
Appendix (A)
Page | 58
Contract No:
General Yes No
1. Installation/assembly complete and in accordance with drawings
2. Forebays and sumps free from construction debris
3. Screens cleaned
Lifting Gear
1. Safe Working Load painted on lifting gear ……………….Tonnes
2. Chain lubricated
Pump A
Pump A
Pump A
Yes No
1. Motor winding thermister checked
2. Pump/motor rotation check: (CCW/CW) Pump
Pump
Pump
Pump
3. Earth conductivity tests carried out ( see attached data sheets)
Above checks satisfactorily completed
Witnessed by JBALB
Checked Sub-Contractor Supervised by Consultant
Representatives
Name
Signature
Designation
Date
Page | 60
Contract No:
AERATOR Yes No
1. Installation/assembly complete and in accordance with drawings.
2. Aerator channels and chambers cleared of construction debris and
flushed through.
3. Aerator inlet and drain valves operated over full travel.
4. Leakage test completed.
5. Check dosing points in accordance with drawings.
Above checks satisfactorily completed.
Witnessed by JBALB
Checked Sub-Contractor Supervised by Consultant
Representatives
Name
Signature
Designation
Date
Page | 61
Contract No:
Page | 62
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
10. Motor Insulation Resistance checks (≥20 MegaOhm) R (MΩ) Y (MΩ) B (MΩ)
Unit No. Flocc G/bx A
Flocc G/bx B
Scraper G/bx
Unit No. Flocc G/bx A
Flocc G/bx B
Scraper G/bx
Yes No
11. Rotation correct (CCW/CW) Unit No. Flocc G/bx A
Flocc G/bx B
Scraper G/bx
Unit No. Flocc G/bx A
Flocc G/bx B
Scraper G/bx
Unit No. Flocc G/bx A
Flocc G/bx B
Scraper G/bx
Above checks completed satisfactorily :
Unit No.
Unit No.
Unit No.
Remarks:
Page | 63
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
FLOCCULATOR/CLARIFIERS Yes No
Remarks:
Page | 64
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Weir length % Filter No. Filter No. Filter No. Filter No. Filter No. Filter No.
0
33
67
100
Yes No
Within tolerance +3 m
9. Inlet penstock weir level checked
10. Air blower delivery rate ( from manufacturers cert.)
Page | 65
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Witnessed by JBALB
Checked Sub-Contractor Supervised by Consultant
Representatives
Name
Signature
Designation
Date
Page | 66
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Pipework Pump / /
uncoupled
Pump / /
Pump / /
Witnessed by JBALB
Checked Sub-Contractor Supervised by Consultant
Representatives
Name
Signature
Designation
Date
Page | 68
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Yes No
Values within manufacturers range
Page | 69
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
MOTORS
1. Motor insulation resistance check (≥20Megaohm) R (MΩ) Y (MΩ) B (MΩ)
Pump .
Pump .
Pump .
Pump .
2. Switchgear over current set Unit Current (A)
Pump
Pump
Pump
Pump
Pump
Pump
3. Pump/motor rotation check: Clockwise (CW) Counter
clockwise (CW)
Pump
Pump
Pump
Pump
Pump
Pump
Yes No
4. Earth continuity checks carried out (see attached data sheet )
5. Low level shut-off probes checked (by shorting)
Page | 70
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Page | 71
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Page | 72
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Page | 73
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Page | 74
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Lifting Gear
1. SWL..................................painted on lighting gear
2. Chain lubricated
3. Load hook operated over full travel
4. Sludge pumps removed and re-installed
5. Paint work made good
Pumps
1. Pump manufacturers pre-start up checks complete (see attached Pump
sheets)
Pump
Pump
2. Adequate water level in tank
3. LLS electrode checked (by shorting link)
Motors
1. Motor insulation resistance check (≥20 MegaOhm):
Unit R (MΩ) Y (MΩ) B (MΩ)
Pump
` Pump
Pump
Page | 75
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Page | 76
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Yes No
10. Earth continuity checks carried out (see attached data sheet..........)
Page | 77
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Page | 78
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Page | 79
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Page | 80
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Page | 81
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Completed
Page | 82
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Page | 83
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Page | 84
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Page | 85
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
If a value differs from that expected by more than ±0,01 mA, reconfirm sensor range with D.P. range
stamped on Dall Tube/Orifice Plate, then refer to manufacturers operating instructions for procedure to
set zero and coarse span.
Page | 86
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
N.B. The fine span is pre-set at the factory and should not be adjusted unless there is reason to
suspect an unexpected change in calibration. A precision pressure source is required before adjusting
the fine span potentiometer.
If a measured value differs from that expected by more than ± 0,01 mA, refer to the
manufacturers’ operating instructions for the procedure to adjust the zero.
N.B. Integral transducer/transmitters such as model no. SH3102 have no provision for zero
adjustment, they are supplied pre-calibrated.
4. Check span of primary loop element:
With tank full, and with transducer lowered to the bottom of the tank such that the depth of water
above the transducer is as specified on the Instrument Data Sheet (............................................),
measure the loop current.
Page | 87
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Expected Actual
Backwash tank 20,00 mA mA
Contact/balance tank 20,00 mA mA
If a measured value differs from that expected by more than ± 0,02 mA, refer to the manufacturers
operating instruction for the procedure to adjust the span (range)
N.B. Integral transducer/transmitters such as model no. SH3102 have no provision for span
adjustment, they are supplied pre-calibrated.
Page | 88
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Sample Pumps
FW
TW
3. Switchgear over current protection set at: Unit Amps
RW
SW
FW
TW
4. Pump/motor rotation checks carried out correct. Clockwise Counterclock
Unit (CW) wise (CCW)
RW
SW
FW
TW
Page | 89
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Page | 90
Contract No:
TESTING AND COMMISSIONING
PLAN FOR WATER TREATMENT Rev: 1
PLANT Date:
Site Location
Power/Control Cables
Rated Rated Voltage
Cable Resistance Loading
Cable Tag From To Voltage Current Drop
Type (Ω) (kW)
(V) (A) (V)
Page | 91