Project: ETAP Page: 1
Location: 19.0.1C Date: 25-04-2025
Contract: SN:
Engineer: Revision: Base
Study Case: SM
Filename: UGHELLI EAST FIELD POWER NTWK Config.: Normal
Short-Circuit Summary Report
3-Phase, LG, LL, LLG Fault Currents
Bus 3-Phase Fault Line-to-Ground Fault Line-to-Line Fault *Line-to-Line-to-Ground
ID kV I"k ip Ik I"k ip Ib Ik I"k ip Ib Ik I"k ip Ib Ik
Bus16 0.400 7.660 11.075 7.642 6.505 9.405 6.505 6.505 6.633 9.591 6.633 6.633 7.268 10.509 7.268 7.268
All fault currents are in rms kA. Current ip is calculated using Method C.
* LLG fault current is the larger of the two faulted line currents.
Project: ETAP Page: 2
Location: 19.0.1C Date: 25-04-2025
Contract: SN:
Engineer: Revision: Base
Study Case: SM
Filename: UGHELLI EAST FIELD POWER NTWK Config.: Normal
Sequence Impedance Summary Report
Bus Positive Seq. Imp. (ohm) Negative Seq. Imp. (ohm) Zero Seq. Imp. (ohm) Fault Zf (ohm)
ID kV Resistance Reactance Impedance Resistance Reactance Impedance Resistance Reactance Impedance Resistance Reactance Impedance
Bus16 0.400 0.02945 0.01163 0.03166 0.02945 0.01163 0.03166 0.04565 0.01648 0.04853 0.00000 0.00000 0.00000
Project: ETAP Page: 3
Location: 19.0.1C Date: 25-04-2025
Contract: SN:
Engineer: Revision: Base
Study Case: SM
Filename: UGHELLI EAST FIELD POWER NTWK Config.: Normal
Sequence-of-Operation Event Summary Report
Symmetrical 3-Phase Fault at Bus16.
Time (ms) ID If (kA) T1 (ms) T2 (ms) Condition
140 CB08 7.642 80.0 140 Phase
200 CB03 7.642 140 200 Phase
1543 Relay2 0.095 1543 Phase - OC1 - 51
1563 CB02 20.0 Tripped by Relay2 Phase - OC1 - 51