Sanral Interim Preferential Procurement Policy
Sanral Interim Preferential Procurement Policy
1
Contents
1. SANRAL INTERIM PREFERENTIAL PROCUREMENT POLICY ............................................. 3
2. POLICY STATEMENT ............................................................................................................... 3
3. PURPOSE ................................................................................................................................. 3
4. OBJECTIVES AND DEFINITIONS ............................................................................................ 3
5. REGULATORY FRAMEWORK FOR PREFERENTIAL PROCUREMENT POLICY ................. 6
6. REQUIREMENTS OF SANRAL’S SCM POLICY ...................................................................... 6
7. STANDARD PREFERENTIAL PROCUREMENT STRATEGIES .............................................. 9
ANNEXURE 1: ENGINEERING: CONVENTIONAL PROJECTS FOR CONSTRUCTION WORKS
13
ANNEXURE 2: ENGINEERING: ROUTINE ROAD MAINTENANCE (RRM) PROJECTS FOR
CONSTRUCTION WORK ............................................................................................................... 14
ANNEXURE 3: ENGINEERING CONSULTANTS: CONVENTIONAL, RRM, COMMUNITY
DEVELOPMENT, CTROM, TCC, ORT, ORS AND OTHER CONSTRUCTION RELATED
SERVICES ...................................................................................................................................... 15
ANNEXURE 4: COMMUNITY DEVELOPMENT PROJECTS ........................................................ 16
ANNEXURE 5: ENGINEERING: SITE MATERIAL LABORATORY ............................................... 18
ANNEXURE 6: NON-ENGINEERING – GOODS AND SERVICES................................................ 19
2
1. SANRAL INTERIM PREFERENTIAL PROCUREMENT POLICY
To give effect to the procurement policy contemplated in section 217(2) of the Constitution and as
prescribed in Section 2 of the Preferential Procurement Policy Framework Act (PPPFA), 2000 (Act
No. 5 of 2000).
2. POLICY STATEMENT
South African National Roads Agency SOC Limited (SANRAL) vision is to ensure the national road
transport system delivers a better South Africa for all. In order to achieve this vision SANRAL aims
to:
2.1 Ensure value for money through efficient and cost-effective procurement;
2.2 Promote a fair, equitable, transparent and competitive procurement process and engagement
with prospective bidders and suppliers;
2.3 Develop, support and promote social equity and socio-economic transformation objectives
through Broad-Based Black Economic Empowerment (“B-BBEE”), PPPFA, the implementation
of the SANRAL Transformation Policy and Supplier Development initiatives;
2.4 Ensure that at all times applicable legislation and good practice is followed in the procurement
of goods and services at SANRAL;
2.5 Ensure that procurement policy and processes promote innovative and cost-effective solutions
in achieving SANRAL’s vision; and
2.6 Drive transformation objectives within SANRAL through its procurement.
3. PURPOSE
3.1 SANRAL recognises the critical role it plays in the built environment, construction and related
industries. SANRAL is mindful of the impact that its procurement policies and practices have
on the lives of South Africans and the transformation of the construction industry and the
country’s economy.
3.2 The policy details the preferential procurement system that ensures effective procurement
and promotes the realisation of government’s transformation agenda. This will allow
SANRAL to contract with persons or categories of persons who were, historically
disadvantaged by unfair discrimination on the basis of race, gender or disability as envisaged
in the PPPFA.
3
a) Engineering services, Construction works, Operations and other Construction related
Services.
b) Non-engineering goods and services.
This policy provides guidance for transformation and preferential procurement decisions in the
development of specification for quotes (where applicable) and tenders for the various
categories of procurement.
4.2 The Framework for Infrastructure Delivery and Procurement Management (FIDPM) serves as
the reference for all technical requirements relating to Engineering services, Construction
works and construction related services.
4.3 A key objective is to:
- provide for categories of preference in the allocation of contracts;
- protection and advancement of persons, categories of persons, disadvantaged by unfair
discrimination;
- promote standardisation;
- promote standardisation and ensure responsibility and accountability for procurement
decisions that subscribe to the overall transformation of the economy and industries from
which SANRAL procures its goods or services.
4.4 The policy also underpins SANRAL’s efforts in the prevention of unfair and unlawful
procurement practices by adopting standardised preferential procurement strategies. For this
purpose, this policy must be read in conjunction with the SCM Policy for an understanding of
the various controls that have been established to identify and avoid any unlawful
procurement practices.
4.5 In addition to the above, this policy provides for a governance control framework within which
sector transformation strategies are enabled for implementation, monitoring and evaluation.
4.6 Definitions:
4.6.1 “black people” is a generic term which means Africans, Coloureds and Indians.
4.6.2 “BEC” is the Bid Evaluation Committee.
4.6.3 “BSC non-engineering” is the Bid Specification Committee responsible for approving tender
documents for non-engineering tenders.
4.6.4 “BSC engineering / PG2” is the Procurement Gate 2 as referenced in the FIDPM, and
includes Procurement Gate 1 (PG1), responsible for approving the broad scope of work
and the financial estimates, preferential targets, local content and production.
4.6.5 “Contract value”
4.6.5.1 Means the approved tender amount including Value Added Tax (VAT) and Provisional
Sums and / or Prime Cost (PC) sums (where applicable), but excluding Contract Price
4
Adjustments, Construction Industry Development Board (CIDB) levy (where applicable) and
contingencies.
4.6.5.2 “for engineering consultants” means the approved tender amount including VAT and the
provision for site staff salaries (and the respective Mark-up if any), but excludes all other
Provisional Sums and Prime Cost Sums (and the respective Mark-up if any).
4.6.6 “Consultants” means an entity appointed by SANRAL to carry out the following activities:
Planning, design and construction monitoring in the built environment including operation
and maintenance, advisory and compliance services.
4.6.7 “Contractor” means an entity appointed by SANRAL to conduct construction project
activities that include, civil engineering, electrical engineering, power transmission, general
building and specialist construction works as per the CIBD grading, also referred to as
“Main Contractor”.
4.6.8 “Community Development projects” are SANRAL projects that provide direct development
support to communities through road or other infrastructure improvement projects within the
community that create an appropriate balance between access and mobility whilst
enhancing road safety. The ultimate beneficiaries are the communities that actively
participate in the delivery of improved infrastructure facilities and through the community
project are uplifted with business skills, construction skills and the ability to provide
sustainable business opportunities due to the imparting of knowledge into the community.
4.6.9 “CTROM” means Comprehensive Toll Road Operations and Maintenance.
4.6.10 “EME” means Exempted Micro Enterprise.
4.6.11 “FIDPM” is the Framework for Infrastructure Delivery and Procurement Management.
4.6.12 “MBAC” is the Management Bid Adjudication Committee.
4.6.13 “ORT” means Open Road Tolling.
4.6.14 “ORS” means Open Road Service.
4.6.15 “PDRC/PG 3 (Procurement Gate 3) ” is the Procurement Gate 3 as referenced in the
FIDPM and includes PG 4 (Procurement Gate 4) and is responsible for approval of tender
documents to be issued and confirm there is sufficient cash flow to meet financial
obligations of the contract.
4.6.16 “Price” means an amount of money tendered for goods or services and includes all
applicable taxes less all unconditional discounts.
4.6.17 “Procurement Gate” means a control point at the end of a process where a decision is
required before proceeding to the next process or activity.
4.6.18 “QSE” means Qualifying Small Enterprise.
4.6.19 “RBAC” is the Regional Bid Adjudication Committee.
4.6.20 “Service provider” means an entity appointed by SANRAL to provide services.
4.6.21 “Supplier” means an entity appointed by SANRAL to deliver goods.
4.6.22 “TCC” means Traffic Control Centre.
5
4.6.23 All reference to prices and value thresholds for procurement in this document are deemed
to be inclusive of VAT and provisional sums and prime cost sums where the service
provider will procure services / goods under the contract provisions.
4.6.24 All references to Targeted Enterprises refer to either an EME or QSE that is more than 51%
black owned with a BBBEE status level of either 1 or 2. A main contractor or consultant is
not permitted to have any equity shareholding in a Targeted Enterprise.
5.1 This Policy aligns to the requirement of the following prescripts relating to preferential
procurement and the transformation agenda of Government as legislated in:
• Constitution of the Republic of South Africa, 1996.
• Preferential Procurement Policy Framework Act, 2000 (Act No. 5 of 2000).
• Broad-Based Black Economic Empowerment Act, 2003 (Act No. 53 of 2003).
• Construction Industry Development Board Act, 2000 (Act No. 38 of 2000), and associated
regulations, standards and practice notes.
• Promotion of Administrative Justice Act, 2000 (Act No. 3 of 2000)(PAJA).
• Promotion of Access to Information Act, 2000 (Act No. 2 of 2000) (PAIA).
• Prevention and Combating of Corrupt Activities Act, 2004 (Act No. 12 of 2004).
• Companies Act, 2008 (Act No. 71 of 2008).
• Competitions Act, 1998 (Act No. 89 of 1998).
• Public Finance Management Act, 1999 (Act No. 1 of 1999).
• Military Veterans Act, 2011 (Act No. 8 of 2011).
• SCM instruction / practice note / circular issued by the National Treasury.
The integrated Supply Chain Management (SCM) process as published by National Treasury and
depicted below, requires the SANRAL to implement all components of an integrated SCM system,
namely:
• Demand Management;
• Acquisition Management;
• Logistics Management; and
• Disposal Management.
6
6.1 Acquisition Management
In the acquisition of goods, services and works, SANRAL will apply categories of preference in
the allocation of contracts and the protection or advancement of persons or categories of
persons disadvantaged by unfair discrimination as envisaged in the PPPFA,2000. The policy
shall be applied when procuring goods, services and works through quotations, competitive /
limited bidding process, pre-qualification of bidders and two-stage bidding.
SANRAL may, before the award of a tender, cancel a tender invitation if:
a. due to changed circumstances, there is no longer a need for the goods/services specified in
the invitation;
b. funds are no longer available to cover the total envisaged expenditure;
c. no acceptable tender is received; or
d. there is a material irregularity in the tender process.
The decision to cancel a tender invitation must be published in the same manner in which the
original tender invitation was advertised.
The local production and content requirements as designated by the Department of Trade, Industry
and Competition (DTIC) shall be applied on all SANRAL tender documents based on the
Instruction Notes issued by the National Treasury, as a condition of award and not an eligibility
criterion. The applicable designated items applicable on a specific tender / project will be listed in
the tender document.
8
7. STANDARD PREFERENTIAL PROCUREMENT STRATEGIES
The standard preferential procurement strategies outline the different preferential targets for the
subcontracting percentage (%) targets per category.
7.1 Subcontracting
SANRAL’s policy is to ensure that all projects have a subcontracting or site material laboratory’s
joint venture requirement of at least 30%. The rule is that subcontracting may apply across all
categories of procurement above R10 million. The requirement for subcontracting is based on the
principle of identifying and creating opportunities to support the development of Targeted
Enterprises. The minimum subcontracting work must be clearly defined and specified in the tender
document, including how the sub-contractor will be involved throughout the project cycle. There
must be evidence of conscious consideration of the skills and capabilities for the local community
when finalising the scope of the main construction tender document.
For these reasons, the following key requirements must be adhered to:
a) For RRM contractors the minimum of 30% subcontracting provisions will apply as a
contractual obligation.
b) For conventional contractor the minimum of 30% subcontracting provisions will apply as a
contractual obligation.
- For contract value less than R10 million (category 1) – no subcontracting
required for EMEs.
- For contract value R10 – R60 million (category 2) – no subcontracting required
for EMEs.
c) For Community Development projects (construction), subcontracting provisions will apply as
a contractual obligation:
- The Scope of the Work and the Bill of Quantities for CD Projects consists of 3 schedules:
i. Schedule A describes and provides for the Training and Construction Management of
the project a minimum of 30% subcontracting provisions will apply as a contractual
obligation.
ii. Schedule B describes and provides for the (labour enhanced) Construction of the
Works a minimum of 30% subcontracting provisions will apply as a contractual
obligation. The percentage may be increased based on the scope of the project.
iii. Schedule C describes and provides for the Stakeholder and Community Liaison a
minimum of 30% subcontracting provisions will apply as a contractual obligation.
d) For RRM consulting and Ad-hoc consulting, subcontracting is not a requirement.
e) For Conventional Consulting (including Community Development, CTROM, TCC, ORT, ORS,
and other related service), the minimum of 30% subcontracting provisions will apply as a
contractual obligation.
9
- For contract value less than R6 million (category 1) – no subcontracting required
for EMEs.
- For contract value R6 – R25 million (category 2) – no subcontracting required for
EMEs and QSEs.
f) For site material laboratory, the minimum of 30% joint venture provision will apply as an
eligibility requirement in the conditions of tender.
g) For non-engineering procurement (goods and services) the minimum of 30% subcontracting
provisions will apply as a contractual obligation.
h) Except where there are valid reasons acceptable to SANRAL, the appointed Service
provider, Supplier, Main Consultant or Contractor must pay the sub-consultant/contractor
within seven days of receipt of payment from SANRAL.
i) Where a case is made for specific contracts, that the subcontracting may not be feasible, the
PG3 / BSC (non-engineering) may allow a tender to be let for a lower percentage. The
PG3/BSC (non-engineering) may only allow this after Board approval.
j) The tender documents must state that sub-contractors and / or suppliers and / or service
providers procured by the successful bidder must be registered on the National Treasury’s
Central Supplier Database (CSD) and in the applicable CIDB grades where required and
must meet all other compliance requirements as well viz Tax Complaint Status, COIDA, etc.
k) Any additional work over and above the contracted amount must be divided between the
Main Contractor/Consultant and sub-contractor/consultant as per the
subcontracting/consulting percentage attached to the award.
l) Community Development projects must not be included as part of the main contract or as a
replacement for subcontracting targets.
m) In terms of Annexures 1-6, the subcontracting or site material laboratory's joint venture
subcontracting will be for entities that are either an EME or QSE that is more than 51% black
owned with a B-BBEE status level of either 1 or 2.
n) The minimum level of subcontracting or site material laboratory's joint venture requirements
may be increased on a project specific basis and approved by the BSC non-engineering /
PG3.
7.4.1 The preferential targets as contracted must be monitored by SANRAL for the duration of the
contract to ensure compliance and fulfilment of the transformation objective.
11
ANNEXURES
STANDARD PREFERENTIAL
PROCUREMENT STRATEGIES
12
ANNEXURE 1: ENGINEERING: CONVENTIONAL PROJECTS FOR CONSTRUCTION WORKS
ENGINEERING: CONVENTIONAL PROJECTS FOR CONSTRUCTION WORK
ESTIMATED CONTRACT VALUE (INCLUDING VAT) INSTRUCTION NOTES
CATEGORY 1 CATEGORY 2 CATEGORY 3
Contract value < R10 M Contract value R10M < R60M Contract value >R60M
CIDB GRADE 1-5 CIDB GRADE 6&7 CIDB GRADE 8 & 9
PREFERENTIAL SUBCONTRACTING REQUIREMENTS
The following subcontracting The following subcontracting The following subcontracting a) If the minimum subcontracting requirements cannot be applied BSC engineering (PG2)
provisions may apply: provisions may apply: provisions may apply: / NDRC or PDRC/PG3 / BSC non-engineering may condone this criterion, on condition
that that prior written approval by Board has been obtained in terms of DOA.
b) The idea is to make small value projects unattractive to the higher graded contractors;
• QSE and Generic entities: minimum • QSE and Generic entities: • Minimum 30% subcontracting
impose incrementally higher levels of subcontracting requirements according to the size
30% subcontracting provisions minimum 30% subcontracting provisions applies. of the project.
applies. provisions applies. c) Subcontracting may include suppliers; calculation of points for subcontracting will be as
• No mandatory subcontracting • No mandatory subcontracting per Std for CPG’s – October 2017 (Gazette 41237).
requirements for EME. d) CPG Targets may apply in addition to subcontracting provisions.
requirements for EME.
JOINT VENTURES
JVs to be encouraged where at least JVs to be encouraged where at JVs to be encouraged where at a) JVs to be encouraged on a project specific basis where market analysis indicates no
one partner must be from the least one partner must be from least one partner must be from supply side capacity for the designated sector(s) exists.
designated groups. the designated groups. the designated groups. b) JVs must be aligned to CIDB prescriptions.
i. The lead partner must have a contractor grading designation of not lower than one level
below the required grading designation in the class of construction works specified in the
tender document.
ii. Any discrepancy in information relating to ownership in terms of the joint venture
verification certificate, the joint venture agreement and the CIDB grading information will
be reported to National Treasury for possible fronting.
TRANSFORMATION PROVISIONS
• Application of clause 6.1.7 of the a) Clause 6.1.7: Where necessary, SANRAL shall provide direct development support, or
Transformation Policy. through its partners, to emerging contractors, professionals and suppliers in the generic
• Application of clause 6.1.12 of the CIDB grades of 1-4 or other equivalent benchmarks to ensure that their status and
Transformation Policy. prevailing conditions are not a barrier to entry to opportunities created by SANRAL.
b) Clause 6.1.12: SANRAL shall award contracts exclusively to black contractors,
professionals and suppliers in the generic CIDB Grades 1-4, or equivalent benchmarks
in all community development projects in compliance with the provisions of the PPPFA.
c) Provision (b) above is for nurturing and growing small contractors / consultants /
suppliers.
General Notes
1. The table represents the standard (Pro Forma) requirements for Conventional Projects.
2. NDRC = National Documentation Review Committee.
3. PDRC = Project Documentation Review Committee.
13
ANNEXURE 2: ENGINEERING: ROUTINE ROAD MAINTENANCE (RRM) PROJECTS FOR
CONSTRUCTION WORK
ENGINEERING: ROUTINE ROAD MAINTENANCE (RRM) FOR CONSTRUCTION WORK
ESTIMATED ANNUALISED VALUE OF CONTRACT (INCLUDING VAT)
INSTRUCTION NOTES
CATEGORY 1 CATEGORY 2 CATEGORY 3
Contract value < R10 M Contract value R10M < R60M Contract value > R60M
CIDB GRADE 1-5 CIDB GRADE 6&7 CIDB GRADE 8
PREFERENTIAL SUBCONTRACTING REQUIREMENTS
The following subcontracting The following subcontracting The following subcontracting a) Subcontracting will be applied as a condition of contract.
provisions may apply: provisions may apply: provisions may apply: b) Subcontracting based on Management Contractor Model.
c) Subcontracting based on annualised contract value (includes VAT).
• Minimum 30% subcontracting • Minimum 30% subcontracting • Minimum 30% subcontracting d) Subcontracting may include suppliers.
provision applies. provision applies. provision applies. e) CPG Targets may apply in addition to subcontracting provisions.
JVs to be encouraged where JVs to be encouraged where JVs to be encouraged where at a) JVs to be encouraged on a project specific basis where market analysis indicates no supply side
at least one partner must be at least one partner must be least one partner must be from capacity for the designated sector(s) exists.
from the designated groups. from the designated groups. the designated groups. b) JVs must be aligned to CIDB prescriptions.
i. The lead partner must have a contractor grading designation of not lower than one level below the
required grading designation in the class of construction works specified in the tender document.
ii. Any discrepancy in information relating to ownership in terms of the joint venture verification
certificate, the joint venture agreement and the CIDB grading information will be reported to National
Treasury for possible fronting.
TRANSFORMATION PROVISIONS
• Application of clause 6.1.7 of a) Clause 6.1.7: Where necessary, SANRAL shall provide direct development support, or through its
the Transformation Policy. partners, to emerging contractors and suppliers in the generic CIDB grades of 1-4 or other
• Application of clause 6.1.12 of equivalent benchmarks to ensure that their status and prevailing conditions are not a barrier to entry
the Transformation Policy. to opportunities created by SANRAL.
b) Clause 6.1.12: SANRAL shall award contracts exclusively to black contractors and suppliers in the
generic CIDB Grades 1-4, or equivalent benchmarks in all community development projects in
compliance with the provisions of the PPPFA.
c) Provision (b) above is for nurturing and growing small contractors / consultants / suppliers.
General Notes
1. Due to the application of the Management Contractor Model, contract value for Routine Road Maintenance (RRM) Projects are based on annualized cost of project.
2. Subcontracting may include suppliers.
3. The table represents the standard (Pro Forma) requirements for RRM Projects.
4. NDRC = National Documentation Review Committee.
5. PDRC = Project Documentation Review Committee.
14
ANNEXURE 3: ENGINEERING CONSULTANTS: CONVENTIONAL, RRM, COMMUNITY
DEVELOPMENT, CTROM, TCC, ORT, ORS AND OTHER CONSTRUCTION RELATED SERVICES
ENGINEERING CONSULTANTS: CONVENTIONAL AND RRM PROJECTS INCLUDING COMMUNITY DEVELOPMENT, CTROM, TCC, ORT, ORS AND OTHER CONSTRUCTION RELATED SERVICES
15
ANNEXURE 4: COMMUNITY DEVELOPMENT PROJECTS
Contract Value < R10m Contract Value R10 ≤ R60m Contract Value > R 60m
The following subcontracting The following subcontracting The following subcontracting As per PPP Annexure 2:
provisions may apply: provisions may apply: provisions may apply:
a) Subcontracting will be applied as a condition of contract.
b) Subcontracting based on Management Contractor Model.
• Minimum 30% subcontracting
EME entities: EME entities: c) Subcontracting based on annualised contract value (incl. VAT).
provisions will apply as a contractual
obligation.
• No mandatory subcontracting • No mandatory subcontracting
As per PPP Annexure 1:
requirements. requirements.
d) If the minimum subcontracting requirements cannot be applied, BSC
engineering (PG2) or NDRC or PDRC (PG3) or BSC non-engineering may
QSE and Generic entities: QSE and Generic entities: condone this criterion, on condition that that prior written approval by Board
has been obtained in terms of DOA.
• Minimum 30% subcontracting • Minimum 30% subcontracting e) The idea is to make small value projects unattractive to the higher graded
provisions will apply as a provisions will apply as a contractors; impose incrementally higher levels of subcontracting
contractual obligation. contractual obligation. requirements according to the size of the project.
f) Subcontracting may include suppliers; calculation of points for subcontracting
will be as per Std for CPG’s – October 2017 (Gazette 41237).
g) CPG Targets may apply in addition to subcontracting provisions.
PREFERENTIAL SUBCONTRACTING (as per PPP Annexure 2)
The following subcontracting The following subcontracting The following subcontracting As per PPP Annexure 2:
provisions may apply: provisions may apply: provisions may apply:
a) Subcontracting will be applied as a condition of contract.
b) Subcontracting based on Management Contractor Model.
16
• Minimum 30% subcontracting c) Subcontracting based on annualized contract value (incl. VAT).
provisions will apply as a contractual d) Subcontracting may include suppliers.
• Minimum 30% subcontracting • Minimum 30% subcontracting obligation. The percentage may be e) CPG Targets may apply in addition to subcontracting provisions.
provisions will apply as a provisions will apply as a increased based on the scope of the
contractual obligation. The contractual obligation. The project.
percentage may be increased percentage may be increased
based on the scope of the project. based on the scope of the project.
JOINT VENTURES (as per PPP Annexures 1 and 2)
JVs to be encouraged where at JVs to be encouraged where at least one JVs to be encouraged where at least As per PPP Annexures 1 and 2:
least one partner must be from partner must be from the target groups. one partner must be from the target
the target groups. groups. a) JVs to be encouraged on a project specific basis where market analysis
indicates no supply side capacity for the target sector(s) exists.
b) JVs must be aligned to CIDB prescriptions.
i. The lead partner must have a contractor grading designation of not lower
than one level below the required grading designation in the class of
construction works specified in the tender document.
ii. Any discrepancy in information relating to ownership in terms of the joint
venture scorecard, the joint venture agreement and the CIDB grading
information will be reported to National Treasury for possible fronting.
TRANSFORMATION (as per PPP Annexures 1 and 2)
1. Due to the application of the Management Contractor Model, the contract value for Community Development Projects (CDP) are based on annualised cost of the project.
CD Project Specific Notes:
2. Subcontracting for Schedules A and C may include suppliers and professional service providers.
3. Subcontracting for Schedule B is earmarked for Trainee Targeted Enterprises.
4. The table represents the standard (Proforma) requirements for Community Development Projects.
As per PPP Annexures 1 and 2:
17
ANNEXURE 5: ENGINEERING: SITE MATERIAL LABORATORY
ENGINEERING: SITE MATERIAL LABORATORY
TRANSFORMATION PROVISIONS
• Application of clause 6.1.7 of the Transformation Policy. a) Clause 6.1.7: Where necessary, SANRAL shall provide direct development support, or through its partners, to
• Application of clause 6.1.12 of the Transformation Policy. emerging contractors, professionals and suppliers in the generic CIDB grades of 1-4 or other equivalent
benchmarks to ensure that their status and prevailing conditions are not a barrier to entry to opportunities
created by SANRAL.
b) Provision (a) above is for nurturing and growing small contractors / consultants / suppliers.
General Notes
1. The table represents the standard (Pro Forma) requirements for Site Material Laboratory Projects.
2. NDRC = National Documentation Review Committee.
3. PDRC = Project Documentation Review Committee.
18
ANNEXURE 6: NON-ENGINEERING – GOODS AND SERVICES
NON-ENGINEERING: GOODS AND SERVICES
ESTIMATED CONTRACT VALUE (INCLUDING VAT) INSTRUCTION NOTES
CATEGORY 1 CATEGORY 2
Clause 6.4.3: SANRAL shall target and allocate all opportunities below R100m to black real
estate and property development entities.
• Application of Clause 6.5.3 of the Transformation Policy for tenders in the ICT sector
• Application of Clause 6.6.2 of the Transformation Policy for tenders in the Finance and audit sector b) Finance and audit
Clause 6.6.2 SANRAL shall limit opportunities for tendering to one service area, i.e. (audit or
non-audit) per firm, to ensure that opportunities for black participation are maximised.
• Application of Clause 6.7.2 and 6.7.3 of the Transformation Policy for tenders issued for Legal Services c) Legal
i. Clause 6.7.2 SANRAL shall promote joint ventures in all SANRAL-issued legal tenders in
order to maximize the participation of black business.
ii. Clause 6.7.3 Legal services provided to toll concessions and toll operations shall be
required to include black business participation plans before any contract extensions or
renewals are considered.
• Application of Clause 6.8.3, 6.8.4 and 6.8.5 of the Transformation Policy for tenders issued for Legal d) Marketing, Advertising and Communications services
Services i. Clause 6.8.5 SANRAL will allocate a minimum thirty percent (30%) of its media spend for
community and small-scale media owners.
19