ANOH Gas Processing Company Limited
Security Classification: Restricted
AGP-ALC-ANOGP-E05-0033
ANOH GAS PLANT PROJECT
(AGPP)
ITP for Centrifugal Horizontal Pump
May, 2021
Rev Date Description Issued by Checked by Approved by
A01 25-08-21 Issue for Approval Bassey Samuel 'Stalian Iordache Abdul Adewale
A01 AGP-ALC-ANOGP-E-05-0033 PAGE 1 OF 4
Document No. AGP-ALC-ANOGP-E-05-0033 Rev. A01
Document Title Inspection and Test Plan for Centrifugal Horizontal Pump Page Page 2 of 4
Client : AGPC .
ITP No. : ITP-M-002 / E Rev. 0 .
Item : Installation of Centrifugal Horizontal Pumps INSPECTION & TEST PLAN
Page: 1 of 3 .
Discipline: Mechanical .
ANOH GAS PLANT PROJECT
Procedure / Reporting Inspection By
No Activity Description Frequency Inspection / test requirement Remarks
Spec. Format ALCON AGPC
1 Equipment Verification Each delivery Relative - Verify the packaged items are clearly identified to Inspection W M
Inspection Drawing packing list etc. report
- Check the following by visual inspection. supplied
. Equipment tag No. and Qty on packing list by Vendor
. Dents, flaws, Damage and Paint scratch.
2 Installation of Equipment
2.1 Chipping Each Unit Reference - Check foundation surface prepared and weak N/A M M
Drawing concrete removed by chipping
2.2 Visual & Dimension insp. Each Unit Reference - Check the location, plumb, level and dimension of N/A M M
before setting of Equip. Drawing all foundations on which equipment is to be
mounted.
- Check the Level pad/ plate elevation and pocket HSFP-
sizes CHP-01 W M
- Check all scale, dirt, grease and foreign matter is
thoroughly cleaned from the contacted surface of
the skid frame and top surface of foundation
2.2 Setting of Equipment Each Unit Reference - Check orientation and level of the equipment. HSFP- S/W S/W
Drawing - Check the foundation bolts are freely hang in their CHP-02
Pockets with between two and four threads
projecting above their nuts.
2.3 Grouting of Anchor Bolts Each Unit Reference - During grouting the bolts shall be moved up and N/A S/W M
Drawing down so as to ensure the exclusion of voids and
air pockets.
- Ensure grout mix ratio & sample test performed.
- Ensure the grout is protected and cured as per the
requirement.
- Check pump and motor shaft free to drive.
A01 AGP-ALC-ANOGP-E05-0033 Page 2 of 4
This Document is Controlled Electronically and Uncontrolled if Printed
Document No. AGP-ALC-ANOGP-E-05-0033 Rev. A01
Document Title Inspection and Test Plan for Centrifugal Horizontal Pump Page Page 3 of 4
* Legend : S/W : Spot Witness, W : Witness Point, H : Hold Point, R : Review Point, M : Monitoring, I : Random Inspection,
SCS : Standard Construction Specification
Client : AGPC .
Item : Installation of Centrifugal Horizontal Pumps
INSPECTION & TEST PLAN ITP No. : ITP-M-002 / E Rev. 0 .
Page: 2 of 3 .
Discipline : Mechanical . ANOH GAS PLANT PROJECT
Procedure / Reporting Inspection By
No Activity Description Frequency Inspection / test requirement Remarks
Spec. Format ALCON AGPC
2.4 Final Installation Each Unit Construction - Check final dimension and adjustments to ensure HSFP- W W
Inspection Drawing that the equipment is plumbed and leveled within CHP-02
tolerances.
2.5 Final grouting Each Unit Construction - Check the foundation bolts/nuts are firmly tightened “ W M
Drawing After the grouting material has cured.
- Check pump and motor shaft free to drive.
3 Coupling alignment Each Unit Reference - Check that coupling hubs are correctly installed HSFP- W S/W
(Preliminary check) Drawing before alignment checks. CHP-03
- Check the distance between shaft ends and /or
distance between hubs.
- Check shaft alignment in conjunction with driven
equipment
4 Connection of pipe to Each Unit Reference - Verify nozzle pipe work clean and free of foreign N/A M M
equipment nozzle Drawing material.
- Pipe installation - Check pipe supports, stops, gauges, anchors,
spring cans and supports for proper settings.
- Verify no strain on piping connection with dial
indicators, if required by Vendor Manual.
- Check all permanent gaskets, spacers, spectacle
blinds bolting etc. complete for piping connection
Reference
5 Coupling alignment Before start-up Drawing See para.3 above HSFP- W S/W
(final) CHP-03
A01 AGP-ALC-ANOGP-E05-0033 Page 3 of 4
This Document is Controlled Electronically and Uncontrolled if Printed
Document No. AGP-ALC-ANOGP-E-05-0033 Rev. A01
Document Title Inspection and Test Plan for Centrifugal Horizontal Pump Page Page 4 of 4
Client : AGPC .
ITP No. : ITP-M-002 / E Rev. 0 .
Item : Installation of Centrifugal Horizontal Pumps INSPECTION & TEST PLAN
Page: 3 of 3 .
Discipline : Mechanical .
ANOH GAS PLANT PROJECT
Procedure / Reporting Inspection By
No Activity Description Frequency Inspection / test requirement Remarks
Spec. Format ALCON AGPC
6 Final inspection Each Reference - Ensure the pump inside is clean and no foreign HSFP- W W
(Mechanical complete Equipment Drawing particles. CHP-04
check) - Check rotary direction and manual rotation of
motors, pumps and engines.
- Check all interconnection piping completed.
- Check all electrical and instrumentation
connections completed.
- Check the pump and motor are running without
noise.
- Check the mechanical seals are in good condition.
- Ensure the coupling alignment between pump
& motor completed and coupling guard in place.
Paint
7 Touch-up paint Each unit procedure Check and ensure all damaged paint area cleaned HSFP- M M
and re-painted as per original paint spec. CHP-04
A01 AGP-ALC-ANOGP-E05-0033 Page 4 of 4
This Document is Controlled Electronically and Uncontrolled if Printed