Ppi Earth Movement
Ppi Earth Movement
Version: 01
INSPECTION LEVEL
TYPE OF REGISTER OF
ITEM N° ACTIVITY INSPECTION POINTS REFERENCE DOCUMENT ACCEPTANCE CRITERION INSPECTION FREQUENCY MEP RESPONSIBILITY
INSPECTION CONTROL
MEP SUPERVISION CLIENT
1.1. Material tests: Material with the following characteristics. In each Common Fill material Control Formats
Modified proctor P ASTM D1557 of Quality Quality E R T
Standard proctor P ASTM D698
Moisture Content P ASTM D2216
Liquid Limit P ASTM D4318
Plasticity Index P ASTM D4318
Grain Size Analysis P ASTM D422 / D5519 / D136
According to procedure
JU-001-06-0523-0000-08-02-0007
1 Common Filling
1.3. Tests after Compaction: According to Technical Specification: 101946-ES- - The densities (Di) must be at least 95% of - Varies according to the area as per Table 12 Frequency in Control Formats
Density P 0301_0 Earth Movement. the density obtained in the Proctor test. compaction tests of Technical Specification: of Quality Production / Quality E R T
According to procedure Final layer thickness 0.20m. 101946-ES-0301_0 Earthworks
JU-001-06-0523-0000-08-02-0003 The working humidity should not vary by ±1.0% with
regarding the Optimal Moisture Content, obtained with
the Modified Proctor.
Mass Filling
(Prior to the start of the
activity will take place
2 the test fill essay
for approval by
part of CQA /
Ausenco 2.2. Tests after Compaction: The densities must be at least 90% of the It varies according to the area according to Table 12 Frequency in Control Formats
Density P According to Technical Specification: 101946-ES- density obtained in the panel test. compaction tests of Technical Specification: of Quality Production / Quality E R T
0301_0 Earth Movement. Humidity +1.0%, -2.0% of the OCH. 101946-ES-0301_0 Earth Movement
According to procedure Final layer thickness 1.00m.
JU-001-06-0523-0000-08-02-0003 -
According to procedure
JU-001-06-0523-0000-08-02-0006
JU-001-06-0523-0000-08-ITP-0002 . 01 . 16/10/2018 Uncontrolled Document. Please consider the environment before printing this document. Page 1 of 4
16/10/2018
Version: 01
INSPECTION LEVEL
TYPE OF REGISTRATION OF
ITEM N° ACTIVITY INSPECTION POINTS REFERENCE DOCUMENT ACCEPTANCE CRITERION INSPECTION FREQUENCY MEP RESPONSIBILITY
INSPECTION CONTROL
MEP SUPERVISION CLIENT
According to Technical Specification: 101946-ES-0301_0 According to Technical Specification: 101946-ES-0301_0 Topographic format
- According to Technical Specification: Earth Movement. Earth Movement.
101946-ES-0301_0 Earthworks. According to the Plan
2.3. Topographical Control I Production/ Topography E R T
According to procedure
JU-001-06-0523-0000-08-02-0001
3.1. Tests on the material: Material with the following characteristics: In each Selected Fill Material Control Formats
Modified proctor P ASTM D1557 of Quality Quality E R T
Moisture Content P ASTM D2216
Liquid Limit P ASTM D4318
Plasticity Index P ASTM D4318
Grain Size Analysis P - ASTM D422 / D5519 / D136
According to procedure
JU-001-06-0523-0000-08-02-0007
Filling
3
Seleccionado
3.3. Tests after Compaction: According to Technical Specification: 101946-ES- - The densities must be at least 100% of the - Varies according to area as per Table 12 Frequency in Control Formats
Density P 0301_0 Earth Movement. density obtained in the Proctor test compaction tests of Technical Specification: of Quality Production / Quality E R T
According to procedure - La humedad +1.0%, -1.0% del OCH. 101946-ES-0301_0 Earth Movement
JU-001-06-0523-0000-08-02-0003 Final layer thickness 0.30m.
4.1. Tests on the material: In each sand bed material Control Formats
of Quality Quality E R T
Moisture Content P ASTM D2216 - IP < 8.00%
Liquid Limit and Plastic Limit P ASTM D4318 Matrix permeability (size smaller than 19 mm)
Plasticity Index P ASTM D4318 > 1x10-1 cm/s.
Granulometric Analysis P ASTM D422 / D5519 / D136 The corrected point load index (minimum average)
Permeability P ASTM D2434 It must have a value greater than 2 N/mm2.
Point Load P ASTM D5731 Granulometry according to the table:
According to procedure
JU-001-06-0523-0000-08-02-0007
4 Sand Bed
JU-001-06-0523-0000-08-ITP-0002 . 01 . 16/10/2018 Uncontrolled Document. Consider the Environment before printing this document. Page 2 of 4
16/10/2018
Version: 01
INSPECTION LEVEL
TYPE OF REGISTRATION OF
ITEM N° ACTIVITY INSPECTION POINTS REFERENCE DOCUMENT ACCEPTANCE CRITERION INSPECTION FREQUENCY MEP RESPONSIBILITY
INSPECTION CONTROL
MEP SUPERVISION CLIENT
4.3. Tests after Compacting: Final layer thickness of 0.10m. Control Formats
Density P of Quality Production / Quality E R T
- -
According to Technical Specification: 101946-ES-0301_0 According to Technical Specification: 101946-ES-0301_0 topographic format
- According to Technical Specification: 101946-ES- Earth Movement. Earth Movement.
0301_0 Earth Movement. According to the plan According to plans
1.4. Topographic Control I Production/Topography E R T
According to procedure
JU-001-06-0523-0000-08-02-0001
5.1. Testing the material: The structural fill material may always be used and Control Formats
Grain Size Analysis P when sizes greater than 75 mm are removed (3 In each Anchor Trench material of Quality Quality E R T
- ASTM D422 / D5519 / D136
inches).
According to the procedure
JU-001-06-0523-0000-08-02-0007
5.3. Tests after Compaction: According to Technical Specification: 101946-ES- Layers not greater than 0.30m. According to Table 12 Frequency in compaction tests Control Formats
Density P 0301_0 Earth Movement. - Densities must be at least 95% of the Technical Specification: 101946-ES-0301_0 of Quality Production / Quality E R T
Standard Proctor According to procedure density obtained in the Proctor test Earth Movement.
Trench Fill Moisture content JU-001-06-0523-0000-08-02-0003 The working humidity should not vary by ±2.0% with
5
of Anchorage regarding the Optimal Moisture Content, obtained with
the Modified Proctor.
According to Technical Specification: 101946-ES-0301_0 According to Technical Specification: 101946-ES-0301_0 topographic format
According to Technical Specification: Earth Movement. Earth Movement.
101946-ES-0301_0 Earth Movement. According to Plan According to plans
5.4. Topographical Control I Production/ Topography E R T
According to procedure
JU-001-06-0523-0000-08-02-0001
6.1. Tests on the material: Excess material from the 0.075mm sieve must have the Control Formats
Standard Proctor P ASTM D698 following features: Liquid limit 28% max, IP 8% In each Base material for roads. of Quality Quality E R T
Moisture Content P ASTM D2216 max, and 4.5% maximum linear contraction.
Liquid Limit P ASTM D4318 The minimum acceptable CBR value for the gravel of
Plasticity Index P ASTM D4318 The pavement is at 80%.
Grain Size Analysis P - ASTM D422 / D5519 / D136 The grain size must match the spindle.
CBR P -ASTM D4429-09a granulometric table:
Abrasión of the Angels P ASTM C131 and C535
According to procedure
JU-001-06-0523-0000-08-02-0007
According to Technical Specification: 101946-ES-0301_0 According to Technical Specification: 101946-ES-0301_0 Topographic format Production/ Topography
According to Technical Specification: 101946-ES- Earthworks. Earth Movement.
0301_0 Earth Movement. According to Plan According to Plans
6.3. Topographic Control I E R T
According to procedure
JU-001-06-0523-0000-08-02-0001
JU-001-06-0523-0000-08-ITP-0002 . 01 . 16/10/2018 Uncontrolled Document. Consider the Environment before printing this document. Page 3 of 4
16/10/2018
Version: 01
LEVEL OF INSPECTION
TYPE OF REGISTRATION OF
ITEM NO. ACTIVITY Inspection Points REFERENCE DOCUMENT ACCEPTANCE CRITERION INSPECTION FREQUENCY MEP RESPONSIBILITY
INSPECTION CONTROL
MEP SUPERVISION CLIENT
7.1. Tipo de Inspección: According to Technical Specification: 101946-ES- Stable foundation, free from water outcrops, Control Formats
Visual 0301_0 Earth Movement. consistent as natural ground, according to the plans Each time it reaches Foundation level of Quality Quality E R T
According to procedure of construction.
I JU-001-06-0523-0000-08-02-0002
EXCAVATION AND
7
FOUNDATION
According to Technical Specification: 101946-ES-0301_0 - According to Technical Specification: 101946-ES-0301_0 Topographic Format Production / Topography
According to Technical Specification: 101946-ES- Earth Movement. Earthworks.
0301_0 Earth Movement. According to Plan According to plans
7.2. Topographic Control I E R T
According to procedure
JU-001-06-0523-0000-08-02-0001
8.1. Type of Inspection: According to Technical Specification: 101946-ES- dense and stable surface, conditioning of Control Formats
Visual 0301_0 Earth Movement. humidity, The compacted surface must be Each time the subgrade is approved. of Quality Quality E R T
I
According to procedure trimmed to adjust the levels of
JU-001-06-0523-0000-08-02-0002 design, without agrientamientos.
PREPARATION OF
8 According to Technical Specification: 101946-ES-0301_0 According to Technical Specification: 101946-ES-0301_0 Topographic format Production/ Topography
SUB RASANTE According to Technical Specification: 101946-ES- Earth Movement. Earth Movement.
0301_0 Earth Movement. According to Plans
8.2. Topographic Control I According to the Plan E R T
According to procedure
JU-001-06-0523-0000-08-02-0001
E: Executes (responsible for executing and preparing the inspection format) I: Inspection
R: Review (inspection level referring to reviewing the documentation: test records, inspection records, test report, certificates) Test and/or Essay
Witness (inspection level to be a witness of an inspection, test or trial. Inspection staff is notified and the activity can begin without their presence)
H: Waiting Point (level of inspection required to wait. Work cannot continue until the inspection, test, or trial has been approved)
JU-001-06-0523-0000-08-ITP-0002 . 01 . 16/10/2018 Uncontrolled Document. Please consider the environment before printing this document. Page 4 of 4