Assignment 2
Assignment 2
The observed total streamflow hydrograph ordinates (including base flow) at 2-hour intervals are:
Time(hr) 0 2 4 6 8 10 12 14 16 18
Discharge(m3/s) 25 60 140 210 260 200 140 90 50 25
Find effective Rainfall (Runoff Estimation) and Direct Runoff Hydrograph (DRH).
Solution:-
Time interval = 2 hr
=10,200,000m3
where i is the rainfall intensity (mm/hr) and Td is the storm duration (minutes).
Answer
The peak outflow occurs at any of the two conditions
i- A long, gentle storm (45 min) that covers the entire 20-hectare catchment.
ii- A short, intense storm (15 min) that only covers the 5-hectare commercial area
(as the park area would not be fully contributing yet).
First condition
Condition 2
Therefore, the critical Time of Concentration to use for the final design is 45 minutes, and
the design peak discharge is 0.461 m³/s.
Hydrology Assignment
Abdul Qayyom
B230728CE
Qn, The inflow hydrograph tabulated in Table through a river for which x = 0.2 and K =
10 hours is given. Determine the peak outflow at hour 30 by using the Muskingum
channel routing method, if the initial outflow is 22 m³/s.
Time(hours) Inflow(m^3/s)
00 12
05 15
10 22
15 32
20 10
25 08
30 17
Ans,
C2 =(5+2×10×0.2)/(2×10(1-0.2)+5)=0.4285
C3 =(2×10(1-0.2)-5)/(2×10(1-0.2)+5)=0.5238
Routing Table
ABDUL SANAD
B230729CE
CE01
Sl no. :3
Question:
In a river reach, the Muskingum parameters are given as:
K = 10 hours, X = 0.25, and Δt = 5 hours.
The inflow and outflow data for the reach are as follows:
0 50 50
5 100 70
10 ? 110
15 ? 160
20 250 200
25 180 190
30 100 150
Estimate the missing inflows at 10 hours and 15 hours using the Muskingum method.
Solution:
The Muskingum equation is given by:
C3 = (K - KX - 0.5Δt) / (K - KX + 0.5Δt)
At time 15 hr:
200 = 0.5I_15 + 80
At time 10 hr:
160 = 0.5I_10 + 55
0 50 50
5 100 70
10 210 110
15 240 160
20 250 200
25 180 190
30 100 150
Time 0 6 12 18 24 30 36 42 48 54
(h):
Inflow 10 20 50 60 55 45 35 27 20 15
(m³/s):
Perform flood routing using the Muskingum method for two reaches in series with the
following parameters:
Reach 1: K₁ = 8 hr, x₁ = 0.25
Reach 2: K₂ = 6 hr, x₂ = 0.3
Δt = 6 hr
Compute the outflow hydrograph for both reaches, Plot both the inflow and final outflow
hydrographs on the same graph.
Answer:
Δt = 6 hr
Reach 1: x₁ = 0.25, K₁ = 8 hr
Reach 2: x₂ = 0.3, K₂ = 6 hr
Muskingum coefficients
Reach 1:
0 10
Both Reach 1 and Reach 2 are in series; the outflow of Reach 1 will be the inflow of Reach 2.
Reach 2:
0 10 10
PROBLEM STATEMENT
For the given 3-hour unit hydrograph derive the Direct runoff hydrograph
for 3 cm excess rainfall using which get the flood hydrograph with
baseflow 5 m3./s.
Derive the ordinate of 6-hour unit hydrograph using s-curve method
using above obtained data.
TIME 0 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48
UH
(m^3/ 0 27 52 83 128 163 188 175 163 116 68 38 23 14 9 2 0
s)
Sol:
First obtaining the direct runoff hydrograph for 3 cm excess rainfall using given 3-
hour unit hydrograph.
S curve ordinates for 6-hour unit hydrograph obtained from flood hydrograph
ENGINEERING HYDROLOGY ASSIGNMENT
The total length of main channel is 1.8 km and the difference in elevation between the most
distant point and the outlet is 15 m.
where L = channel length (m), S = slope (H/L), find the peak discharge (Q) for the basin
using the Rational Method.
Solution:
Q = 0.278 × C × i × A
Question:
A river gauging station has recorded the annual maximum flood discharge (in m³/s) for the
past 10 years as follows:
YEAR 1 2 3 4 5 6 7 8 9 10
DISCHARGE(m^3/s) 210 275 190 330 290 410 360 280 440 390
1. Rank the data in descending order ,calculate P using the Weibull formula and calculate Fn
and yt
Weibull formula:P = m / (n + 1)
2. Compute the return period (T) for each discharge using T = 1 / P.
3. Estimate the flood discharge for a return period of 25 and 50 years using the Gumbel
distribution method.
Solution:
The discharges are ranked in descending order and plotting positions are calculated using
Weibull formula.
P =m/(n+1)
Fn =1 – P
yt = -ln[-ln(0.96)] = 3.1985
Final Answer
Estimated 25-year flood discharge = 546.64 m^3/s
Estimated 50-year flood discharge = 605.28 m^3 /s
ENGINEERING HYDROLOGY
ASSIGNMENT
NOVEMBER 1, 2025
ADITYA CHAUDHARY
B230761CE
Question
The table below shows the rainfall hyetograph (incremental rainfall) for a storm event
over a catchment. The total direct runoff volume measured from the catchment outlet
for this storm is 480,000m3. The catchment area is 4.5km2.
(a) Calculate the total observed runoff depth (in cm) over the catchment.
(b) Using the φ-index method, determine the value of φ (in cm/hr) for this storm.
Time (hr) 3 6 9 12 15 18 21 24
Incremental
Rainfall 3.0 4.5 6.0 7.5 5.4 3.6 2.4 1.5
(cm)
Solution
So,
R=10.67cm
Therefore,
total observed runoff depth (in cm) over the catchment is R = 10.67 cm
(b)
Time (hr) 3 6 9 12 15 18 21 24
Incremental
Rainfall 3.0 4.5 6.0 7.5 5.4 3.6 2.4 1.5
(cm)
Intensity
1.0 1.5 2.0 2.5 1.8 1.2 0.8 0.5
(cm/h)
Given, Total rainfall (P) = (3 + 4.5 + 6 + 7.5 + 5.4 + 3.6 + 2.4 + 1.5)cm
P = 33.9 cm
Infiltration = ( P – R ) / t [ R = 10.67cm ]
= (33.9 – 10.67) / 24
= 0.968 cm/h
R=∑(I–φ)∆t [ ∆ t = 3 hr ]
10.67 = ( 10 - 6φ ) * 3
10.67 = 30 - 18φ
φ = ( 30 – 10.67 ) / 18
φ = 1.0738cm/h
Intensity
1.0 1.5 2.0 2.5 1.8 1.2 0.8 0.5
(cm/h)
Again using formula, R=∑(I–φ)∆t
10.67 = ( 9 - 5φ) * 3
10.67 = 27 - 15 φ
Φ = ( 27 - 10.67 ) / 15
Φ = 1.0887 cm/h
Therefore,
Problem statement
A catchment has an area of 1.8 km² has 50%
impervious surfaces (C=0.85) and 50% pervious
surfaces (C=0.35). The time of concentration is 22
minutes. A rainfall event with a uniform intensity of 65
mm/hr occurred for the duration of the time of
concentration. It has been noted that only 80% of the
total precipitation is effective rainfall that reaches the
surface. This is because 20% is lost to interception,
initial abstractions, and surface storage. Using the
Water Budget Equation, first calculate the net rainfall
available for runoff. Then,
(a) Use the Rational Method to find the peak runoff
from the net rainfall.
(b) Now the given 22 minute unit hydrograph has a
peak flow of P m^3/s for 1 cm net rainfall.It is observed
that the Unit Hydrograph’s peak flow 𝑃 is exactly 10%
less than the peak runoff for the same net rainfall.
Find the value of P and find the direct runoff at t=11
minutes for the actual net rainfall.(If the UH ordinate at
t=11 min is 60% of the peak)
Solution:
STEP 1- Calculate Effective Rainfall using the water
budget equation .
Given,
Rainfall intensity , i=65mm/hr
Duration = 22 min = 0.367 hr
Only 80 % is effective (20% is lost).
TIME(h) 0 6 12 18 24 30 36 42 48 54
6h UH 0 11 18 25 30 28 21 16 7 0
Ans:
S Curve
TIME(h) 6h UH Interpolated Lag by 3h (S_A-S_B)*2
(S_A)
0 0 0 0 0
3 5 0 10
6 11 11 11 5 12
9 19 11 16
12 18 29 29 19 20
15 41 29 24
18 25 54 54 41 26
21 68 54 28
24 30 84 84 68 32
27 99 84 30
30 28 112 112 99 26
33 123 112 22
S Curve
TIME(h) 6h UH Interpolated Lag by 3h (S_A-S_B)/2
(S_A)
39 142 133 18
45 154 149 10
51 156 156 0
Problem Statement
During the July 2020 Brahmaputra floods, severe inundation occurred near Kaziranga National Park,
causing widespread damage. The Central Water Commission (CWC) recorded annual maximum
discharges (m³/s) for a 15-year period at a gauging station upstream of the park. The channel routing
parameters determined from past calibration are K = 5 hours and X = 0.25. The storage–outflow relation is
approximately linear and can be expressed through the Muskingum method. Tasks include: 1. Flood
Frequency Analysis (Gumbel’s Method): Peak discharge for a 50-year return period flood. 2. Design Flood
Estimation: SPF and PMF for 100-year flood. 3. Channel Routing (Muskingum Method): Design inflow
hydrograph for the 50-year flood.
Inflow Hydrograph Data
2013 7500
2014 7700
2015 8150
8600
2016
9050
2017
9750
2018
10400
2019
2020
Solution
Conclusion: The estimated 50-year flood peak is approximately 12,150 m³/s, while the 100-year SPF
is 12,922 m³/s and the PMF is 19,383 m³/s. The Muskingum method routing results indicate a peak
outflow of about 9,094 m³/s at 8 hours.
Submitted By
Adwaith.R
B230766CE
NAME: Aishwarya Ramohan
DATE: 27/10/2025
HYDROLOGY ASSIGNMENT
Ques on:
1. Route the flood hydrograph through a reservoir of surface area 10800 m² based on the
following data:
Ini ally, (at t=0), the rainfall intensity is measured to be 1666.7 mm/h. The ini al eleva on of
the water level in the reservoir is 200.33 m.
Plot the:
a. Inflow – ou low hydrograph.
b. Eleva on – me graph.
c. Graph to obtain the storage – ou low rela onship.
Use the Levelpool methodology.
0 1.6667 200 0
3 3.3333 200.5 16
6 9.0000 201 38
9 19.3333 201.5 66
12 34.0000 202 110
15 30.3333 202.5 160
18 24.0000
21 17.6667
24 13.3333
27 10.3333
30 8.3333
Answer:
Given, the area of the reservoir is 10800 m². Then, the storage of the reservoir for each respec ve
eleva on would be:
Then:
With these points, the graph to obtain the storage – ou low rela onship can be plo ed:
Outflow Q (m³/s)
202.5
202
Elevation (m)
201.5 2S/Δt + Q
Outflow
201
200.5
200
199.5
400.00 420.00 440.00 460.00 480.00 500.00 520.00 540.00 560.00 580.00
2S/Δt + Q (m³/s)
We know that, using the Levelpool method,
Then,
110
100
90
80
70
60
Q (m³/s)
50 Inflow
Outflow
40
30
20
10
0
0 3 6 9 12 15 18 21 24 27 30 33
Time t (h)
b. Eleva on – Time graph:
202.00
201.80
201.60
201.40
Elevation (m)
201.20
201.00
Elevation
200.80
200.60
200.40
200.20
0 3 6 9 12 15 18 21 24 27 30 33
Time t (h)
HYDROLOGY ASSIGNMENT
Q. A catchment area consists of three different types of land uses — a railway track, an airport runway, and a
parking lot. The corresponding runoff coefficients (C) and areas are given in the table below. The peak discharge (Qₚ)
observed from the catchment during a storm of intensity 50 mm/hr is 14.5 m³/s. determine the area of the airport
runway (in hectares).
Solution:
𝑖 = 50 mm/hr
0.4×0.80+0.9(𝐴)+0.6×0.60
𝐶=
1.4+𝐴
𝐶×𝑖×𝐴𝑟𝑒𝑎
𝑄𝑝 =
3.6
Substituting,
1 0.4×0.80+0.9(𝐴)+0.6×0.60
14.5 = 3.6 × ( ) × 50 × (1.4 + 𝐴)
1.4+𝐴
Solving,
𝐴 = 0.4 km2
HYDROLOGY ASSIGNMENT
Q. A newly developed township spreads across 2.8 km² of mixed land use. The area is divided as follows:
SOLUTION —
1) Time of concentration (Tc)
Kirpich formula: Tc = 0.0195 × L^0.77 × S^-0.385 L = 2.1 km = 2100 m; S = 1.6% = 0.016
(m/m).
Compute L^0.77 = 361.500462
Compute S^-0.385 = 4.913758
Therefore, Tc = 0.0195 × 361.500462 × 4.913758 = 34.64 minutes.
Compute I:
I = 950 / (34.64 + 18)^0.45 = 159.638 mm/hr
3) Weighted runoff coefficient (Cw)
Formula: Cw = (Σ Ci × Ai) / (Σ Ai)
Numerator = 0.70×1.2 + 0.85×0.8 + 0.35×0.8 = 1.8000
Total area = 2.80 km²
Cw = 1.8000 / 2.80 = 0.6429
***************************************
ALOK G C
B230158CE
CE01
In a rural area of 200 ha, 60% is reserve forest, 30% is cultivated land with sandy loam soil and the
rest is residential area. The distance between the two extreme points in this region in 1300 m and
there is an elevation difference of 12 m between these. An irrigation canal is being constructed in
this region. The runoff coefficients from a survey that happened 10 years ago is given below.
But due to the densification of forest from the past 10 years, there is a 15% reduction in the runoff
value due to interception loss.
Duration (min) 10 20 30 40 50 60
Depth of rainfall 11 20 27 34 39 45
(mm)
SOLUTION
t = 29.5437 min
C= ΣCiAi/A
C = Runoff/Precipitation = (R – 0.15R) /P
= 0.85R/P
C = 0.085
C = 0.156
Qp = CiA/3.6
12 + 0.4 = 12.4
=0.1656
Problem Statement:
A large, flat parking lot (Area = 2 Hectares) acts as a temporary detention basin during a
storm. The inflow to the parking lot is from a storm drain. The outflow from the lot is over a
broad-crested weir along one edge, and the outflow rate is governed by the equation O = 1.5
* H^(3/2), where O is in m³/s and H is the depth of water (in meters) above the weir crest.
Time(hr) 0 1 2 3 4 5 6
Solution
Now, K = dS / dO
K = d/dO [15,260 * O^(2/3)] = 15,260 * (2/3) * O^(-1/3)
K ≈ 10,173 / O^(1/3)
K is not a constant! It depends on the outflow O. For routing, we need an initial estimate.
Let's assume an average outflow for the event. The peak inflow is 2.5 m³/s. Let's estimate a
peak outflow of around 1.5 m³/s.
K ≈ 10,173 / (1.5)^(1/3) ≈ 10,173 / 1.145 ≈ 8,885 seconds.
Converting to hours:K ≈ 8885 / 3600 ≈ 2.47 hours.
K = 2.5 hours.(Approx)
Given:
· Δt = 1 hour
· K = 2.5 hours
·X=0
0 0.0 0.000
The outflow hydrograph has been calculated. Notice the characteristic peak attenuation and
time lag. The inflow peak was 2.5 m³/s at t=2 hrs, while the outflow peak is 1.21 m³/s at t=4
hrs.
HYDROLOGY ASSIGNMENT
AMAN AGRAWAL (B230794CE)
Question:
A₁ 1.2 0.40
A₂ 1.8 0.55
A₃ 2.0 0.70
tc = 30 min.
(a) Determine the equivalent runoff coefficient (Ceq) for the basin.
(b) Estimate the rainfall intensity for the basin time of concentration.
(c) Compute the peak discharge (Q) in m³/s using Rational Method.
Solution:
Ceq = (Σ Ai Ci) / Σ Ai
Ceq = 0.574
i = 850 / (50)^0.7
i = 54.96 mm/hr
Q = 43.7 m³/s
A storm of 8-hour duration occurred over a catchment area of 150 km² and produced the following
rainfall record:
The observed total streamflow hydrograph ordinates (including base flow) at 2-hour intervals are:
Time(hr) 0 2 4 6 8 10 12 14 16 18
Discharge(m3/s) 25 60 140 210 260 200 140 90 50 25
Find effective Rainfall (Runoff Estimation) and Direct Runoff Hydrograph (DRH).
Solution:-
Time interval = 2 hr
=10,200,000m3
4 140 115
6 210 185
8 260 235
10 200 175
12 140 115
14 90 65
16 50 25
18 25 0
Amna Sharin
B230111CE
ENGINEERING HYDROLOGY
ASSIGNMENT
Answer:
S-curve ordinate for 2h intervals:
Time(h) 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28
S(2h-UH) 0 5 10 25 40 52.5 65 74 83 88 93 95.5 98 98 98
Time(h) 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28
S(t) 0 5 10 25 40 52.5 65 74 83 88 93 95.5 98 98 98
S(t-d) 0 0 5 10 25 40 52.5 65 74 83 88 93 95.5 98 98
UH 0 10 10 30 30 25 25 18 18 10 10 5 5 0 0
ENGINEERING HYDROLOGY
ASSIGNMENT
Anamika K V
B230172CE
CE01
Q.Given the ordinates of 2hr unit hydrograph at the upstream. Derive the ordinates of direct runoff
hydrograph from a 6cm excess rainfall and find the outflow hydrograph at the downstream level
using Muskingum routing method. Find out the peak flow at downstream.
K=2.5hr,X=0.15,Δt=2hr,Initial Q=15m3/s,Base flow=20m3/s
Time 0 2 4 6 8 10 12
2h UH 0 20 80 120 70 15 0
UH ordinates 0 2 8 12 7 3 0
DRH 0 12 48 72 42 18 0
ordinates
Storm 20 32 68 92 62 38 20
hydrograph
ANSWER:
100
80
Q(m3/s)
60
40
20
0
0 2 4 6 8 10 12 14
time (hr)
Inflow Outflow
Question:
A watershed is made of three zones:
Other data:
Maximum flow length, L = 1.2 km (1200 m)
Average slope, S = 0.008
Return period: 10 years
Solution:
Rainfall Intensity:
Interpolating for 23.8 minutes between (20, 32) and (30, 42):
D = 32 + ((42 - 32)/(30 - 20)) × (23.8 - 20) = 35.8 mm
I = (35.8 × 60) / 23.8 = 90 mm/hr
Final Answers:
Time of concentration (tc): 23.8 min
Weighted runoff coefficient (C): 0.33
Rainfall intensity (I): 90 mm/hr
Peak discharge (Q): 6.6 m³/s
Temporary storage volume (V): 3420 m³
NAME : ANANTHU VR
CE01
B230810CE
HYDROLOGY ASSIGNMENT
Q.The NIT Calicut campus has a total area of 300 hectares, with the following land-use
details:
The maximum length of flow from the farthest point in the campus to the outlet is 2.5
km and the difference in elevation between them is 20 m.
From the regional rainfall data, the 25-year return period rainfall for different
durations is given below:
0.5 4.5
1.0 6.8
2.0 9.2
2. The peak runoff (Qₚ) from the campus using the Rational Method.
Solution
Given Data
𝑖 = 6.1 cm/hr
HYDROLOGY ASSIGNMENT
Q. A 4-hour unit hydrograph for a catchment area of 250km2 is given below by
the ordinates:
1. Derive a 6hr unit hydrograph using the S-curve method.
2. And calculate the equilibrium discharge.
Time(hr) 4-hr UH Ordinate(m^3/s)
0 0
4 20
8 55
12 80
16 60
20 35
24 15
28 5
32 0
The annual maximum flood discharges (in m³/s) recorded at a gauging station for 10 years are as follows:
2014 220
2015 340
2016 280
2017 410
2018 370
2019 450
2020 500
2021 390
2022 420
2023 470
Using Gumbel’s Extreme Value Type-I distribution, estimate the flood discharge corresponding to a return
period of 50 years (Q₅₀). Also, determine the return period of a flood of 480 m³/s.
Answer
1. Question Explanation
The inflows due to a flood in the Sonali River are given every 6 hours.
Given data:
K = 11 hours
X = 0.13
Initial outflow (O₀) = 10 m³/s
We need to perform flood routing using the Muskingum method to compute the outflow hydrograph.
The Muskingum method relates storage (S), inflow (I), and outflow (O) as:
S = K [ X·I + (1 − X)·O ]
where
S = storage in the reach
K = storage time constant (hours)
X = weighting factor (0 ≤ X ≤ 0.5)
I = inflow
O = outflow
By combining and discretizing for a time step Δt, the outflow at the next time step is given by:
3. Given Data
K = 11 hours
X = 0.13
Δt = 6 hours
O₀ = 10 m³/s
(Assume inflow at time 0 = 0)
Denominator:
D = 2K(1 − X) + Δt
D = 2(11)(0.87) + 6 = 25.14
Check: C₀ + C₁ + C₂ = 1.000 ✔️
5. Apply Routing Equation
Step-by-step calculations:
Time 0 hr:
I₀ = 0, O₀ = 10 (given)
At 6 hr:
O₆ = 0.1249(10) + 0.3524(0) + 0.5227(10) = 6.48
At 12 hr:
O₁₂ = 0.1249(30) + 0.3524(10) + 0.5227(6.48) = 10.66
At 18 hr:
O₁₈ = 0.1249(68) + 0.3524(30) + 0.5227(10.66) = 24.64
At 24 hr:
O₂₄ = 0.1249(50) + 0.3524(68) + 0.5227(24.64) = 43.09
At 30 hr:
O₃₀ = 0.1249(40) + 0.3524(50) + 0.5227(43.09) = 45.14
At 36 hr:
O₃₆ = 0.1249(31) + 0.3524(40) + 0.5227(45.14) = 41.56
At 42 hr:
O₄₂ = 0.1249(23) + 0.3524(31) + 0.5227(41.56) = 35.52
At 48 hr:
O₄₈ = 0.1249(10) + 0.3524(23) + 0.5227(35.52) = 27.92
6. Outflow Hydrograph
The flood wave took about 12 hours to travel through the river reach.
During routing, the flood peak decreased (from 68 to 45.14 m³/s) — this is called attenuation, and the delay of
12 hours is the lag time.
Final Answers
Assignment 2
Time (h) 0 3 6 9 12 15 18 21 24 27
Discharge 10 20 52 60 53 43 32 22 16 10
(m³/s)
Since the value of spillway Crest is at elevation of 300.2 , so starting with the
another table acc to the relation of Level pool routing:-
By using several codes , I am finding graphical values such that (2S / Δt)+Q at
300.2 elevation and similarly for all,
And the code is like :-
Final Table:-
The average slope of the catchment is 0.006 and the maximum length of the
catchment is 1.5km. For a 25 year return period, the maximum depth of rainfall
observed for various durations is as follows
Duration(min) 10 20 30 40 50 60
Depth of Rainfall(mm) 24 37 48 55 60 63
.
= D=54.634mm-
.
Intensity = . = 83.035mm/hr
Given Data:
30 years 40000
90 years 45000
Answer:
xₜ = x̄ + Kₜσₜ
40000 = x̄ + K₃₃σₜ
45000 = x̄ + K₃₃σₜ
NAME : ARUNKRISHNAN K
ROLL NO: B230205CE
BATCH: CE01
Q). For a small catchment area of 12 km², the annual maximum 1 hour rainfall (mm) for
the past 10 years are:
78, 95, 105, 82, 110, 97, 123, 115, 88, 102.
(a) Using Gumbel’s method, estimate the 25 year return period rainfall.
(b) Assuming that the design storm duration is 1 hour and the runoff coefficient C =
0.75, compute the design flood peak (m³/s) using the Rational formula.
Ans).
NAME : ARVIND YADAV
B230842CE
CE01
HYDROLOGY ASSIGNMENT
QUS
DERIVE 1 HOUR UNIT HYDRO GRAPH FROM 3 HR UNIT HYDROGRAPH HAVING A TIME INTERVAL
OF 1 HOUR GIVEN IN TABLE AND FROM THE SAME 1 HOUR UNIT HYDROGRAPH FIND THE FLOOD HYDROGRAPH
FOR 3 CM OF RAINFALL . TAKE THE BASE FLOW OF 10 CUMECS
solution :
given D=3HR
T=1HR
SO , D/T = 3
3 HR UH
TIME
(CUMEC Sa Sb (Sa-Sb)/3
(HRS)
)
0
0 0
1 3 3 0 1
2 12 15 3 4
3 8 23 15 8/3
4 6 29 23 2
5 3 32 29 1
6 0 32 32 0
7 32 0
GRAPH
FLOOD
TIME 1 HR UH DRH (3CM)
HYDROGRAPH
0 0 0 10
1 4 12 22
2 8/3 8 18
3 2 6 16
4 1 3 13
5 0 0 10
6 0 0 10
Aswin Sunil
B230853CE
CE-01
The maximum length of the main flow path (L) = 5.2 km and average slope (S) = 0.004.
where:
• i = rainfall intensity (mm/hr)
• t_c = time of concentration (min)
• T = return period (years)
Tasks:
1. Compute the time of concentration using Kirpich’s formula:
t_c = 0.0195 × L^0.77 × S^-0.385 (L in meters, t_c in minutes)
2. Determine the composite runoff coefficient (C) for the entire catchment.
3. Using the Rational Method, compute the peak discharge (Q) for return periods T = 10, 25, 50,
and 100 years.
Q = 0.278 × C × i × A
4. Plot a frequency curve (Q vs. T) and comment on the growth pattern of design floods.
Solution
Total A = 820 ha
Σ(A×C) = 225 + 180 + 112 = 517
The rainfall intensity i (mm/hr) for each return period (T) is obtained from the IDF equation:
i = (2500 × T^0.2) / (t_c + 20)^0.85
10 81.3 11.2
25 93.7 12.9
50 103.6 14.3
Hence, as the return period increases, rainfall intensity and peak discharge also increase.
This indicates a moderate increase in design flood with increasing return period—typical for
urban basins with mixed land use.
10 11.2
25 12.9
50 14.3
100 15.8
Thus, the Rational Method combined with frequency analysis provides an efficient approach for
estimating design discharges for urban catchments.
Avanthika Pradeep
Engineering Hydrology
B230859CE
Question:
The following table gives the ordinates of a 4-hour unit hydrograph for
a particular catchment:
Time (hr) 0 4 8 12 16 20
Discharge
0 40 150 260 310 270
(m³/s)
Time(hr) 24 28 32 36 40
Discharge
200 130 80 40 20
(m³/s)
Time(hr) 24 28 32 36 40
Discharge
200 130 80 40 20
(m³/s)
Q=UH8 × 6.78
Assignment
Time(hrs) Inflow(m3/s)
0 15
6 25
12 58
18 92
24 75
30 64
36 52
42 38
48 27
54 18
60 12
∗ ∗ .
C2 = ( )
= 0.446
∗ .
∗ ( . )
C3 = ( )
= 0.544
∗ .
Routing Table
Determine:
(i) The transmissibility of the aquifer.
(ii) The drawdown in the pumped well assuming R = 300 m.
(iii) The specific capacity of the well.
Solution
Given:
Q = 2000 lpm = 0.0333 m³/s
r1 = 12 m, r2 = 36 m
Static head H = 40 m
Drawdowns: s1 = 1.4 m, s2 = 0.6 m
Hence,
h1 = H − s1 = 40 − 1.4 = 38.6 m
h2 = H − s2 = 40 − 0.6 = 39.4 m
Substitute:
0.0333 = [πK(39.4² − 38.6²)] / [2.303 × 10³ log10(36/12)]
39.4² − 38.6² = 78.0 × 0.8 = 62.4
(i) Transmissibility:
T = KH = 1.87 × 10⁻⁴ × 40 = 7.48 × 10⁻³ m²/s = 648 m²/day
(ii) Drawdown in the pumped well:
Q = [2.72 T (H − hw)] / [log10(R/rw)]
0.0333 = [2.72 (7.48 × 10⁻³) (40 − hw)] / log10(300/0.15)
log10(300/0.15) = 3.301
Final Answers:
Submitted
by
B. KALYA
N
B230249CE
DEPARTMENTOOFOCIVILOENGINEERING
NATIONAL INSTITUTE OF TECHNOLOGY CALICUT
Kozhikode – 673 601, Kerala, India
August 2025
This method is one of the most widely used hydro river routing
techniques employed to estimate the outflow hydro graph from a channel
reach given the inflow hydro graph. This report presents a detailed
theoretical background, derivation of governing equations, step-by-step
computation procedure, and a solved example following the notations and
formulations used in K. Subramanya’s ‘Engineering Hydrology’.
INTRODUCTION TO HYDROLOGIC
ROUTING
Hydro routing is a procedure to determine the temporal and spatial
variation of flow in an open channel or river reach. It relates inflow,
outflow, and storage within the reach over time. There are two main types
of routing methods: (i) Hydro routing and (ii) Hydraulic routing. Hydro
routing utilizes the continuity equation and a storage–discharge
relationship, while hydraulic routing employs full dynamic equations of
unsteady flow.
Time(hr) Inflow,I(m3/s)
0 20
2 50
4 100
6 160
8 200
10 160
12 100
14 60
16 40
GIVEN PARAMETERS :
Solution
∴ x̄ = 239.00 / 20 = 11.95
Calculation for standard deviation (Sx)
Sx = √[ (Σ(xi − x̄ )²) / (N − 1) ]
N − 1 = Degrees of freedom = 19
Sx = √(104.53 / 19)
= √5.5016 = 2.346
Mean x̄ = 11.95
Standard deviation Sx = 2.346
Here, N = 20
x̄ = 11.95 cm
Sx = 2.346 cm
T = 50
γ = √6 × Sx / π
= (2.4495 × 2.346) / 3.1416
= 1.8305
γ = 1.8305
Design Intensity
i = (X50 × 10) / tc
= (18.0348 × 10) / 6
i = 30.058 mm/h
Peak Discharge
Qp = (1 / 3.6) × C × i × A
Problem:
A mountainous watershed drains into a reservoir and consists of three distinct
sub-catchments with the following characteristics:
Sub-Catchment Land Use Type Area (km²) Runoff Coefficient (C) Max Flow Length (km) H (m)
1 Rocky slope 1.8 0.75 2.2 95
2 Agricultural field 2.7 0.45 3.1 70
3 Dense forest 1.5 0.30 2.6 60
Then:
1. Compute tn for each sub-catchment.
2. Compute the weighted time of concentration for the entire catchment.
3. Using that tc, determine rainfall intensity (i) from IDF equation.
4. Determine the equivalent runoff coefficient (Ce).
5. Compute the peak discharge using the rational method.
Solution:
Step 1: Convert flow length L (km m)
L(m)=2200 m, L(m)=3100 m, L(m)=2600 m
BHUKYA MAHENDER
CE01,B230881CE
QUESTION:
A 600 ha watershed has the following land use/cover and corresponding runoff
coefficients:
The maximum flow length in the watershed is 3500 m, and the difference in elevation
between the highest and lowest points is 30 m.
The maximum rainfall intensity-duration-frequency relationship is given by:
7.20 𝑇 0.18
𝑖=
(𝐷 + 0.6)0.92
where
𝑖= rainfall intensity in cm/hr,
𝑇= return period in years, and
𝐷= duration of rainfall in hours.
Estimate:
(i) The 25-year peak runoff from the watershed.
(ii) The 25-year peak runoff if the forest area reduces to 100 ha and the cultivated land
expands such that the total watershed area remains 600 ha.
Solution:
𝑡𝑐 = 0.01947(𝐾𝑡 )0.77
𝐿3
𝐾𝑡 = √
Δ𝐻
(3500)3
𝐾𝑡 = √ = 37748
30
𝑡𝑐 = 0.01947(37748)0.77 = 0.01947 × 5521 = 107.5 min = 1.79 h
Rainfall intensity 𝑖
Peak discharge
1
𝑄𝑝 = (𝐶 𝑖 𝐴)
3.6 𝑒
1
𝑄𝑝 = (0.192 × 5.99 × 600)
3.6
1
𝑄𝑝 = (690.5) = 191.8 m3 /s
3.6
Modified Condition
Substituting the storage equation and rearranging yields the Muskingum routing
equation:
𝑂2 = 𝐶0𝐼2 + 𝐶1𝐼1 + 𝐶2𝑂1
where
−𝐾𝑋 + 0.5Δ𝑡
𝐶0 =
𝐾 − 𝐾𝑋 + 0.5Δ𝑡
𝐾𝑋 + 0.5Δ𝑡
𝐶1 =
𝐾 − 𝐾𝑋 + 0.5Δ𝑡
𝐾 − 𝐾𝑋 − 0.5Δ𝑡
𝐶2 =
𝐾 − 𝐾𝑋 + 0.5Δ𝑡
Q. A river reach has the following inflow hydrograph during a flood event. Using
Muskingum equation derive the routing coefficients and compute the outflow
hydrograph and plot the hydrograph.
Given parameters:
𝚫𝒕 = 𝟐 hr, 𝑲 = 𝟒 hr, 𝑿 = 𝟎. 𝟐𝟓
−4(0.25)+1 −1+1
Ans. 𝐶0 = = =0
4−4(0.25)+1 4−1+1
4(0.25)+1 2
𝐶1 = = = 0.5
4−4(0.25)+1 4
4−4(0.25)−1 2
𝐶2 = = = 0.5
4−4(0.25)+1 4
Time (hr) Inflow I Outflow O
(m3/s) (m3/s)
0 40 40
2 90 0(90)+0.5(40)+0.5(40)
= 40
4 160 0(160) + 0.5(90) +
0.5(40) = 65
6 210 0(210) + 0.5(160) +
0.5(65) = 112.5
8 260 0(260) + 0.5(210) +
0.5(112.5) = 161.25
10 210 0(210) + 0.5(260) +
0.5(161.3) = 210.6
12 150 0(150) + 0.5(210) +
0.5(210.6) = 210.3
14 100 0(100) + 0.5(150) +
0.5(210.3) = 180.1
16 60 0(60) + 0.5(100) +
0.5(180.1) = 140.1
18 40 0(40) + 0.5(60) +
0.5(140.1) = 100.1
Hour (hr) Rainfall (mm) Effective Rainfall (mm) Effective Rainfall (cm)
0–1 25.0 16.250 1.625
1–2 45.0 29.250 2.925
2–3 30.0 19.500 1.950