TDBL HS C S 002 Risk Management Procedure - V 1.0
TDBL HS C S 002 Risk Management Procedure - V 1.0
TDBL-HS-C-S-002
Page 1 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
CONTENTS
Para Page
1 Purpose 4
2 Scope 4
3 Terminology 5
4 Key Responsibilities 6
4.1 TAQA T&D HSE Business Partner 6
4.2 OpCo Executive Directors and Directors 6
4.3 OpCo Division Managers 6
4.4 OpCo Department Managers 6
4.5 OpCo HSE Managers 6
4.6 OpCo HSE (Senior) Engineers 6
4.7 OpCo Section Managers and (Senior) Engineers 7
Table
Addendum
V 1.0 Page 2 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
Glossary
References
V 1.0 Page 3 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
1 Purpose
According to TAQA Global HSSE policy:
“No operational priority is more important than protection of the health, safety and
security of our people and our communities and respecting our environment”.
TAQA Commitment to Operational Excellence (COE), the TAQA HSSE Management
System, clearly defines what TAQA expects from our OpCo's around the world.
Element 5 – Hazard Identification & risk assessment establishes Group Expectations
that must be adhered to by all TAQA OpCo’s. According to Element 5, TAQA OpCo’s
must ensure a comprehensive risk assessment process identifies, assesses, and
appropriately manages the risks arising from operations.
TAQA T&D Risk Management Procedure establishes the expectations from all its
employees - from Line Managers to Executive Directors, to ensure that HSSE hazards
are identified, and risks associated with our activities are assessed. This must be
followed by appropriate actions to account for acceptable risks, and prevent or reduce
unacceptable risks to people, the environment, and the integrity of TAQA T&D’s
assets.
The objectives of this procedure are to:
• Ensure that roles and responsibilities for Risk Management process are clearly
defined and assigned;
• Ensure that day-to-day risks at TAQA T&D’s assets/OpCo’s are reduced to As Low
As Reasonably Practicable (ALARP);
• Ensure all risks at TAQA T&D’s assets/OpCo’s and the respected remedial action
have been communicated to all relevant stakeholders; and
2 Scope
This procedure covers all domains of the TAQA T&D, including sites, facilities and
offices. This procedure applies to the entire TAQA T&D HSSE Management System,
all associated and related documentation, including the HSSE Manual, and HSE
Policy, procedures and appendices.
This procedure applies to all employees, contractors, visitors and relevant interested
parties within TAQA T&D offices, operations and activities. Adherence of this
procedure will ensure compliance to the requirements of our HSSE Management
Syste, OSHAD-SF, and Environment Agency Abu Dhabi (EAD) including all applicable
legislation, international standards (ISO 45001, 14001 and OHSAS 18001) and
industry best practices within all required areas of our organization pertaining to risk
management.
V 1.0 Page 4 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
3 Terminology
The following terminology is used throughout all TAQA Management System (TMS)
documents.
Must Mandatory
Legislative requirement, standard or TAQA’s Safety Rules.
Shall Mandatory
Minimum requirement.
Should Strongly Recommended
Best practice or recommended/
preferred option.
May Suggested
Possible course of action.
V 1.0 Page 5 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
4 Key Responsibilities
V 1.0 Page 6 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
V 1.0 Page 7 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
Section
TAQA OpCo OpCo OpCo All workforce
TAQA OpCo Division Department Manager /
Task T&D HSE EDs or HSE HSE (Sr.) (incld.
T&D ED MD Manager Manager (Sr.)
BP Directors Manager Engineer Contractors)
Engineer
Review/Upgrade Risk
A R I C/I
Management Procedure
Provide required resources
to manage risk to ALARP A R R I R/C
level
Track procedure
I A I I I R R I
implementation effectiveness
Identification of HSE
A C R C
Hazards
Evaluation & Classification of
A C R
HSE Hazards
Decide on the required
I A C R C
control measures
Approve the risk assessment I A R R R I I
Record the risk assessment A C R R
Review the risk assessment A R R
Verify risk mitigation I A R I C
Communicate risks &
A I R I
controls
V 1.0 Page 8 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
6 Standard
6.1 Principles
This procedure is based on the principles that HSE Risk Management:
• Is an integral part of the way that TAQA T&D manages its business risk;
• Is a management responsibility;
• Risk assessments shall be documented and key HSE risks arising shall be
transferred to TAQA T&D Business Line HSE risk registers.
• Managers are ultimately responsible for ensuring that risk assessments are
performed, documented, recorded and managed in the areas of their responsibility.
However, workers also have a responsibility for their own health and safety thus
ensuring that they are not exposed to potential hazards and risks.
A team approach / consultation process is adopted to conduct risk assessment
(RA) – as a minimum, the team conducting the risk assessment should include:
o Section Manager
o (Senior) Engineers (Operations & Maintenance)
o HSE Representative
o Engineering Services / Asset Management Representative (Technical Expert)
o Technicians (as needed)
V 1.0 Page 9 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
• The respective manager forms the RA team, nominates a team leader, and ensures
that the process is in accordance with this procedure and is in line with relevant
OSHAD, and EAD legislation and requirements.
• Risk assessment teams shall have the required experience, knowledge and
training and be led by a competent team leader.
• Hazard Identification - Identifying hazards that have the potential to cause harm.
• Risk Analysis – calculating the risk value if and when the hazard materialises.
• Risk Evaluation – comparing the calculated risk value with some sort of criteria i.e.
a judgement regarding its acceptability.
• Risk Treatment – deciding what to do with the risk by identifying available options,
and Implementation of Risk Reduction Measures – application of ALARP concept
Note: The term “risk assessment” covers the first three elements above; Hazard
Identification, Risk Analysis and Risk Evaluation whereas “Risk Management” extends
risk assessment to include the last element; Risk Treatment and Implementation of
Risk Reduction Measures.
The HSE risk management process is shown in Figure 1 (as determined in ISO 31000
Risk Management Standard) and is defined in the following five steps.
V 1.0 Page 10 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
• Defining the activity, process, function, project, product, service or asset in terms
of time and location as well as its goal and objectives;
• Defining responsibilities for the risk management activities;
• Identifying and specifying the decisions that have to be made and the resources
required; and
• Defining the company requirements, local and/or international legal requirements
and industry standards applicable.
Required Output:
Determining the scope of the hazards and risks and possible outcomes should
allow users to select the correct risk assessment technique.
V 1.0 Page 11 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
• Risk assessment can be conducted against industry specific code of practices and
guideline which are developed by competent authorities;
• Locally and internationally acceptable standards can also be referred to as
guidance standards. For example, have OSHAD RF/ Technical Guidelines and
ISO standards i.e., 31000 (Risk Management) and 45001 (Occupational Health
and Safety Management System) Standards available in Abu Dhabi;
• Both qualitative and quantitative risk assessment studies rely on experience based
judgement. The result or outcome of the risk assessment may vary from person to
person based on the experience and knowledge of the particular industry whose
risk are being assessed;
Some of the key processes/studies used for identification of hazards are described
below.
V 1.0 Page 12 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
• Layout review
• Constructability review
• Installation assessment
• Hazard and Constructability Review (HAZCON)
V 1.0 Page 13 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
V 1.0 Page 14 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
V 1.0 Page 15 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
• Qualitative
• Semi-Quantitative
• Quantitative
When HSE hazards are identified, qualitative risk assessment shall be used initially to
identify risk levels and determine whether a more comprehensive (quantitative)
assessment is required. For most situations, a qualitative or semi quantitative
assessment of risk is sufficient. Table-2 below is a guide to the types of risk
assessment and their applicability:
V 1.0 Page 16 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
HSE risk assessment is a lifecycle process and must be adopted from project
inception and throughout the lifecycle of the project including decommission. Since
risk is dynamic, risk assessments must be re-evaluated regularly to confirm their
continued adequacy and that controls remain sufficient to mitigate the risk.
Required Output:
All directorates and divisions shall ensure that risks are assessed across all
operations and that these assessments are maintained up-to-date as the activity
progresses and at regular planned intervals.
.
V 1.0 Page 17 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
The qualitative approach uses the TAQA T&D risk assessment matrix as a guide in
determining risk potential. Risk is categorized in risk levels (Extreme, High, Moderate
or Low Risk). Hazards identified during audits, inspections, reviews, accident/incident
investigation, HAZID, TRA, qualitative risk assessment are assessed using this non-
numerical data risk assessment matrix.
HAZIDs and TRAs are examples of qualitative risk assessment.
V 1.0 Page 18 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
Depending on the level of complexity, Bowtie diagrams may also be integrated with
semi-quantitative analysis techniques (e.g. HAZID studies).
All existing facilities and activities at TAQA T&D with potential for Major Accident
Hazards and all new projects with potential for Major Accident Hazards will be
subjected to Bowtie Analysis.
V 1.0 Page 19 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
V 1.0 Page 20 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
Environment Slight impact – Minor Impact - Considerable Local (AD) National (UAE)
clean- clean-up impact – clean-up impact – impact - major
up operation by operation required by significant clean-up operation
local by the specialist waste clean- by specialist waste
team. No public company. contractor. No long up operation by contractor. Long
concern Some local term negative specialist waste term negative
public effect on the contractor. effect
concern environment. Possible long on the
Adverse stance of term negative environment.
local government. effect on the Extensive
environment. measures
Adverse stance required to restore
of environment.
local Adverse stance of
government. national
Regional public government and
concern. public
Total Cost of Financial loss Financial loss Financial loss Financial loss Severe financial
Impacts or (compensation, (compensation, (compensation, (compensation, penalties or legal
fines, fines, cost to fines, cost to fines, cost to liabilities. Financial
Incident Event cost to repair, repair, repair, repair, plant & loss
plant & plant & plant & environment (compensation,
environment environment environment damage) of fines, cost to
damage) damage) of damage) of AED500,000 – repair,
of less than AED5,000 – AED50,000 – 5m plant &
AED5,000 50,000 500,000 environment
damage) of
greater
than AED5m
Production Incident event Production Production loss or Production loss Loss of license to
Loss without loss or delay delay up to one or operate or ability
causing up to one week to one delay for over to produce
production week month onemonth indefinitely
loss
V 1.0 Page 21 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
Table 4 – Likelihood
Initial risk ranking involves comparing the level of risk found during the analysis
process with risk categories identified in the risk matrix above. In practical terms this
means that:
• Red zone (Extreme Risk) - activity cannot commence / continue until further
control measures are identified and implemented in order to remove the risk from
the red zone;
• Orange zone (High Risk) – risk rating must be reduced by applying the hierarchy
of controls (refer to section 3.4) and implementing those additional measures
before the activity to continue;
• Yellow and green zones (Moderate and Low Risk) – this requires that all risk
controls identified in the JSAs are implemented.
Required Output:
On completion of the analysis and evaluation of risks, findings are entered into
the risk register. Each OpCo is required to maintain its own risk register.
V 1.0 Page 22 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
Risk assessment must never be just a paper exercise; the entire process will have
been a waste of time if the findings are merely noted, but no action taken as a result.
Risk assessment is a fundamental part of TAQA T&D’s HSEMS and leads to the
development of plans for improvement.
Risk treatment involves a cyclical process of assessing a risk treatment; deciding
whether residual risk levels are tolerable or not; if not tolerable generating a new risk
treatment; and assessing the effect of that treatment until the residual risk is As Low
as Reasonably Practicable (ALARP).
The process must ensure that whenever possible hazards and risks are eliminated.
When elimination is not possible then mitigation factors including substitution,
engineering controls, administrative controls are considered to reduce / control
hazards and risks. Administrative controls shall include the determination of Safe
Systems of Work and Safe Operating Procedures (SOPs). Administrative controls
alone will not reduce the HSE impact, only the likelihood will and all sections and
divisions are required to demonstrate that residual risk levels are valid, based on
application of sound controls.
V 1.0 Page 23 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
V 1.0 Page 24 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
Action plans are documented and implemented to ensure that the mitigation factors
identified are effectively processed to ensure the reduction of hazards and risks as
required. Controls as identified in the action plans are evaluated and reviewed by the
risk assessment team leader at determined intervals.
The approach to Risk Assessments is to reduce risk As Low as Reasonably
Practicable (ALARP). Note that a residually ‘red’ risk in the TAQA T&D risk matrix is
automatically intolerable, but does allow prioritisation of actions to control the risk to
ALARP as given in the following diagram:
• For residual ‘red’ risks: These can never be ALARP and therefore cannot
commence or continue. The issue needs to be escalated to the executive
committee for further action.
• For residual ‘orange’ risks: A JSA alone is unlikely to demonstrate ALARP. It
should be at this point where the need for semi-quantitative or quantitative risk
assessment techniques are considered to determine sufficient additional controls
to reduce high risks to acceptable levels. If after further detailed risk assessment,
residual risk remains in the orange zone then the risk level must be agreed by the
responsible director through consultation with HSE department.
• For residual ‘yellow’ & ‘green’ risks: Risks in these zones should be continually
monitored and any further opportunities for risk reduction should be assessed.
The general concept is that any further risk controls must be implemented unless
the level of cost and effort becomes grossly disproportionate to the benefit. The
need to continually review the JSAs is therefore very important to identify these
opportunities for risk reduction.
V 1.0 Page 25 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
Required Output:
All sections, divisions and directorates in TAQA T&D OpCos shall demonstrate
that risks identified in their HSE risk registers are reduced to ALARP through
application of a variety of risk control measures. The continued adequacy of
these controls shall be verified at regular intervals through self-assessment and
on-going assurance (audit) of the HSE risk register.
All extreme and high risks shall be escalated to the TAQA T&D corporate risk
register.
When risk cannot be reduced to ALARP or if risk is residually extreme, these will
be escalated to top management.
Residual risk levels shall be recorded in the HSE risk register and residual risk
re- assessed regularly.
• Changes which may affect the risk level or introduce new risks
• Introducing new plants, equipment, materials, or substances
• After incidents, audits and inspections
• When applicable legislative obligation changes
• Any other change affects the HSE risk/impacts
• Ensuring that risk controls are effective and efficient in both design and operation;
• Obtaining further information to improve risk assessments;
• Analysing and learning lessons from events (including near-misses), changes,
trends, successes, and failures;
• Detecting changes in the external and internal context, including changes to risk
criteria and the risk itself which can require revision of risk treatments and
priorities; and
• Identifying emerging risks.
V 1.0 Page 26 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
• General;
• Power;
• Projects;
• Water;
• Combined High Risks.
Risk registers are owned and controlled by the respective directorate, division and /
or department. Additional controls, when defined, shall be effectively dealt with and
closed out in the respective JSA and risk register.
The HSE department shall conduct periodic reviews to ensure that the quality of risk
registers being produced are of high quality and meet expectations. They must also
assist and provide guidance as required in ensuring suitable action is taken to ensure
effective close-out of additional controls when identified.
6.11 Follow up
Section and Department Managers shall ensure that a follow-up process is
implemented to ensure that risk reduction recommendations are implemented
satisfactorily and within the identified timescales. In some cases, this may be prior to
commencement of the activity giving rise to the risk.
KPIs relating to the effective implementation of this procedure should be agreed upon
between TAQA T&D HSE BP, TAQA T&D OpCo MDs, & TAQA T&D OpCo HSE
Managers. These shall then be tracked by the HSE Department in each OpCo and
reported to Division Managers and Managing Directors. A consolidated view for the
T&D Business Line shall also be reported to TAQA T&D Executive Director.
V 1.0 Page 27 of 33
TDBL-HS-C-S-002
TAQA RISK MANAGEMENT PROCEDURE
Residual risk
Impact Current risk Additional controls, (after
Possible
S. Activity/ Hazard / Existing Category (with Controls) if required additional
Consequences / Responsible Target Date
No. Condition Aspect Controls (Personnel, (Recommended controls)
Effects
Env, Financial) C L R Actions) C L R
Completed by: Designation: Signature: Date: Approved by: Designation: Signature: Date:
V 1.0 Page 28 of 33
TDBL-HS-C-S-002
TAQA RISK MANAGEMENT PROCEDURE
Possible
Step Additional Controls if Required
Job step Hazard(s) Consequences / Existing Controls Responsible Target Date
No. (Recommended Actions)
Effects
Plant, Equipment & Tools Needed: Maintenance Checks Required: PPE Required:
Reviewed by: Designation: Signature: Date: Approved by: Designation: Signature: Date:
V 1.0 Page 29 of 33
TDBL-HS-C-S-002
TAQA RISK MANAGEMENT PROCEDURE
V 1.0 Page 30 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
Glossary
Abbreviations
Terms
Contractor All parties working for the company either as direct contractors or as
subcontractors.
Roles Positions that have an expected set of expectations attached to them
HSE Risk Assessments Register for recording HSE Risk Assessments
Register
Risk Assessment (RA) A process for identifying hazards and aspects, evaluating the risk(s)
arising from a hazard(s) taking into account the adequacy of any
existing controls and deciding whether the risk is acceptable or not
Top Management Managing Director, Directors, Division and Department Managers or
similar, and be the person in charge of a particular department or
division.
Responsibilities A duty or obligation to satisfactorily or complete as task (assigned by
someone or created by one’s circumstances) that one must fulfil and
which consequent penalty for failure.
Roles Positions that have an expected set of expectations attached to them
Corrective Action Steps that are taken to remove the causes of an existing non-
conformity or undesirable situation. The corrective action process is
designed to prevent any recurrence of non-conformities or undesirable
situations.
Hazard / Aspect Any substance, physical effect or condition with potential to harm
people or property.
Risk Risk is the measure of the likelihood of occurrence of an undesired
event and the potential adverse consequences which this event may
have upon people – injury or harm to physical or psychological health.
Inherent (Initial) Risk Initial Risk (considering initial consequence severity and initial
likelihood) that is established the first time the risk is identified and
assessed without any controls to mitigate the risk
V 1.0 Page 31 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
Current Risk Risk having considered the existing controls in place (current
consequence severity and current likelihood) that exist at this current
point in time with controls actively influencing the risk rating
Residual Risk Risk established after accounting for any additional controls (beyond
the existing controls). It will be the same as the current risk if no
additional controls are identified
Tolerable Risk Risk that has been reduced to a level that can be tolerated by the
organisation having regard to its legal obligations and its own HSE
policy
V 1.0 Page 32 of 33
TDBL-HS-C-S-002
TAQA Risk Management Procedure
References
(1) OSHAD-SF - Technical Guideline Process of Risk Management – Version 3.0 – July 2016
(2) Abu Dhabi Emirate Environment, Health and Safety Management System Framework
(OSHAD-SF) Version 3.1 – March 2017 - Element 4 – Communication and Consultation
(3) ISO 45001:2018 – Occupational Health and Safety Management System
(4) OSHAD-SF – CoP 15.0 Electrical Safety - Version 3.0 – July 2016
(5) OSHAD-SF – CoP 53.0 OSH Management during Construction Work - Version 3.0 – July
2016
(6) ISO 31000 Risk Management
V 1.0 Page 33 of 33