Power Transformer - Rev 6.1
Power Transformer - Rev 6.1
May 2022
Engineering Department
WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED
1. SCOPE:
2. GENERALREQUIREMENT:
The Transformer shall be multi-winding, oil immersed complying as per Specific Technical
parameters and suitable for outdoor installation.
Rated Capacity and Voltage of the Transformers shall be guided by the respective Tender
Documents. The specificationcovers for the following transformers as per present requirement
of thecompany:
c) 132/66 KV Auto Transformer with unloaded stabilizing winding having two terminals taken
out.
Type Test: The transformers should be Type Tested as per IS 2026 or IEC 60076 in
conjunction with their relevant Part. Necessary test documents shall have to be submitted
with thebid.
For400kVClassAutotransformer:
Bidder should have successfully carried out Dynamic Short Circuit test on offered t
rans former or similar transformer (as defined in IS 2026 part-5) as on the date of NIT and
shall enclose the relevant Test Report and certificate along with bid. Otherwise their bid shall
be considered technically non responsive .This shall be applicable for 400kV class Auto
transformerofMVAratingsimilartoorhigherthanthetenderedtransformer.
Sweep Frequency Response Analysis (SFRA/FRA) shall have to be carried out as special
test for each transformer at manufacturer’s premises in presence of representative of
WBSETCL free of cost. Test result shall have to be handed over to WBSETCL. Before
commissioning of the Transformer at site, the same SFRA/FRA test will have to be carried by
the test engineers of the manufacturer in presenceof customer’s representative for comparing
the results to take the decisions of the commissioning. The Testing Engineers &FRA kit for
such pre-commissioning site testing shall have to be arranged by the manufacturer free ofcost.
Guaranteed Technical Particulars: The Bidder shall furnish all guaranteed technical
particulars as called for in this specification along with each copy of Bid submission. Bids
lacking information in this respect may not beconsidered.
Core Materials: Core materials should be directly procured from either the manufacturer or
their accredited reputed marketing organization and not through any agencies.
3. STANDARD:
The Power Transformer covered under this specification shall comply with the requirements
ofthe latest edition of theStandards.
4. DEVIATION:
Normally the offer should be as per Technical Specification without any deviation. But any
deviation felt necessary to improve performance, efficiency and utility of equipment must be
mentioned in the 'Deviation Schedule' with reasons, duly supported by documentary evidences
and advantages of such Deviation shall be mentioned. Such deviations suggested may or may
not be accepted. But deviations not mentioned in Deviation Schedule will not be considered.
a) The Transformer and accessories shall be designed tofacilitate easy inspection, cleaning
and repairs. All fittings and accessories shall be designed to ensure satisfactory
operation underworst conditions of load and voltage as may be met under working
conditions in thesystem.
b) All materials used shall be of best quality and of the class most suitable for working
under the conditions specified. It shall withstand the variations of temperature and
atmospheric conditions without undue stressing etc. i.e. not affecting the
workability/durability of the various parts of thetransformer.
c) All outdoor fittings and accessories, including bushings insulators with their mounting, shall
be so designed as to avoid pockets in which water can collect. All electrical connections
shall be of ample cross sections for carrying the specified currents continuously without
undue heating. All fixing bolts and screws shall be reliable under worst conditions of
operations.
e) Transformer with tertiary winding and all its accessoriesincluding Bushing CTs etc. shall
be design to withstand without injury, the mechanical and thermal effects and any external
short circuit to earth and of short circuits at the terminals of any winding. Transformer
shall be capable of withstanding thermal and mechanical stresses caused by symmetrical or
asymmetrical faults on anywinding.
f) The short circuit level of the HV & IV System to which the transformers will be
connected is asfollows:
• 400kV system - 63kA for 1 sec (sym, rms, 3 phase fault)
• 220kV system - 50 kA for 1 sec / 40 kA for 3 sec (sym, rms, 3 phasefault)
• 132kV system - 40 kA for 1 sec / 31.5 kA for 3 sec (sym, rms, 3 phasefault)
• 66kV system - 31.5 kA for 3 sec (sym, rms, 3 phasefault)
• 33kV & 11kV system - 25 kA for 3 sec (sym, rms, 3 phasefault)
i) Transformer shall be designed for full lightning impulse voltage as well as chopped and
reducedchoppedimpulsevoltageasperrelevantclausesofIS:2026(Pt.-III)/IEC:60076-3
6. TERTIARYWINDINGS:
The 400/220/33KV and 220/132/33 KV transformers shall be provided with delta connected
loaded tertiary windings of 33 KV voltage class and shall be suitably rated to withstand the
stresses due to short circuit in the system. Transformer with 3-windings shall be of loaded
tertiary design.
This stabilizing winding shall be capable of carrying continuously the rated load as specified
under S.T.P. The design of the stabilizing winding shall be such that to take care of the effect
of transfer surge. Tertiary winding shall be designed to withstand mechanical and thermal
stresses due to dead short circuit on itsterminals.
7. TEMPERATURERISE:
Each Transformer shall be capable of operating continuously at its normal rating without
exceeding temperature rise and hot spot limits.
a) The tank and cover shall be fabricated from low- carbon mild steel plate of adequate
size and suitable for welded construction. The tank so welded shall be reinforced by
stiffener of structural steel for general rigidity. Each tank cover shall be of adequate
strength and shall not distort whenlifted.
b) The tank shall be designed to have sufficient strength to withstand without
distortion-
(i) Under full vacuum at an internal pressure. of 3.33KN/sq.mm. absolute (25 torr) for
one hour and permanent deflection of flat plate after the vacuum has been
releasedshall notexceedthevaluesspecifiedbelow:
(ii) Transformer tank of each size, its radiator, conservator vessel and other fittings
together or separately shall be subjected to a pressure corresponding to twice the
normal head of oil or to the normal pressure plus 35 KN/m2 whichever is lower
measured at the base of the tank and maintained for one hour. The permanent
deflection of flat plates after the excess pressure has been released shall not exceed
the figures specified under vacuum test aboveand
(iii) The tank shall be designed to have sufficient strength to withstand mechanical shock
duringtransport.
c) The internal and external surface including structural steel work and oil filled
chambers are to be painted after removing all rust and scale of foreign adhering matter
or grease by sand blasting or other approved method. All steel surfaces in contact
with insulating oil shall be painted with two coats of heat resistant oil insoluble
insulatingpaint.
d) All steel surface exposed to weather shall be given a primary coat of zinc chromate
and shall be applied immediately after cleaning. The second coat shall be of an
oil and weather resisting nature and of shade or colour easily distinguishable from
the primary. The final coat shall be of epoxy paint of minimum thickness of 80 microns
and weather resisting non-fading paint of shade No. 631 ofIS:5.
Any other valves & plugs other than those mentioned above, are also to be
provided as perrequirement.
k) ForTwowindingTransformer4no.thermometerpocketshouldbeprovidedforWTI&
2 no. for OTI. Amongst 4 no. pocket for WTI, Two (2) will be used for direct
connection with the WTI in MK of Transformer. Balance Two (2) shall beprovided
l) Design shall be such that Tank cover can be lifted independently without lifting active
part of core, windingetc.
m) Astepladdershallbeprovidedwitheachtransformertostepintothetopofthetank.
10. CORE:
The magnetic circuit shall be core type. Each limb shall be joined with top and bottom
yokes. The laminations shall be made from high grade non-ageing cold rolled grain
oriented silicon alloy of HI -B or its equivalent grade steel. The insulation of lamination
shall be coated with oxide/silicate/phosphate coating or any coating inert to the action of
hottransformeroil.Thecoreshouldbebottommounted.
The core shall be of stepped cross-section. The yokes shall be clamped by means of end
frames and yoke bolts and limbs shall be clamped by means of clamp plates. Sufficient
number of lifting lugs is to be provided on end frames so that core with windings can be
lifted whenrequired.
The design of magnetic circuit shall be such as to avoid static discharges, development of
short circuit paths within itself or to theearthed clamping structure and production of
fluxcomponentat rightanglestotheplaneoflaminationwhichmaycauselocalheating.
The insulation for the core to bolts and core to clamps shall be such as to withstand a test
voltage of 2 (two) KV rms at 50 Hz for one minute.
The maximum flux density in any part of the core and yoke at the rated MVA, voltage &
frequency shall be such that less than 10% continuous over voltage condition does not
exceed 1.9Tesla.
For consideration of over fluxing, the transformer shall be suitable for continuous
operation for values of over fluxing at (i) 110% (ii) one minute for 125% and (iii) 5 seconds
for 140% of ratedvoltage.
The prime core materials are only to be used. Bidder’s should furnish following document as
applicable as a proof towards use of prime Core material to be submitted before the
stageinspection:
(a) Invoice ofsupplier
(b) Mill’s testcertificate
(c) PackingList
(d) Bill oflading
(e) Bill of entry certificate byCustom.
(f) Description of material, electrical analysis, physical inspection, certificate for surface
defects,thicknessandwidthofthematerials.
(g) Place of cutting of corematerials
The transformer shall give full load output on all taps. The transformer shall operate
withoutdangeronanyparticulartappingattheratedMVAwithinavoltagevariationof
±10% of the rated nominal voltage.
For 132/33KV, 132/66KV & 220/33 KV transformer ON LOAD TAP CHANGER with bi-
directional power flow shall be provided on the 132KV voltage winding & 220KV winding
respectively. The tapping range shall be +10% and –10% in 1.25% equal steps. Remote
TapChangerPanelshallalsobeprovidedtobeinstalledatourControlRoom.
For 132/66KV, 220/132/33 KV & 400/220/33KV Auto Transformer Tap coil with bi-
directional power flow shall be provided at 1 3 2 K V , 132 KV and 400 KV sides respectively
of the transformer. The tapping range shall be + 10% and –10% in 1.25% equal steps.
Transformers with constant ohmic impedance characteristics are preferred.
However,tomatchwithexistingsystemothertypemayhavetobesupplied.
Remote Tap Changer Panel shall also be provided to be installed at our Control Room. In Tap
Position Indicator sufficient terminals are to be provided for sending inputs for SCADA/SAS.
This shall be designed suitable for remote control operation from RTCC Panel in the control
room to be supplied by the manufacturer in addition to being capable of local manual as
well as local electricaloperation.
The on-load tap changer shall include the following :-
a) An oil immersed tap selector and arcing switch or arc suppressing tap selector, provided
with reactor or resistor for reduction of make and break arcing voltages and short
circuits.
b) Motor drivenmechanism
c) Control and protectiondevices
d) Local/Remotetapchangerpositionindicator
e) Manual/Electrical operatingdevice.
The on-load tap changer shall be designed so that the contacts do not interruptarc within the
main tank of the transformer. The tap selector and arcing switch or arc suppressing tap
selector switch shall be located in one or more oil filled compartments. The compartment
shall be provided with Oil Surge relay. Those compartments shall be designed so as to
prevent the oil in tap selector compartment from mixing with the oil in the transformer
maintank.
An oil surge relay with trip float arrangement shall be provided for the OLTC unit.
The tap changer shall be capable of permitting parallel operation with either existing or
futuretransformersofthesametypeasMasterorFollower.
The manual operating device shall be so located on the transformer that it can be operated
by a man standing at the level of the transformer track. It shall be strong and robust in
construction.
The control scheme for the tap changer shall be provided for independent control of the tap
changers when the transformers are in independent service. In addition, provision shall
be made so that under parallel operation the tap changer will give alarm and visual
indication for becoming out of step. Visual indication during the operation of motor shall
also be incorporated. The tap change control must ensure step by step operation under all
operatingconditions.
Necessary interlock blocking independent control when the units are in parallel shall be
provided.
Under parallel operation, as may occur if the contactor controlling one tap changer sticks, the
arrangement must be such as to switch off supply to the motor so that an out of step
condition is limited to one tap difference between the units. Details of out of step protection
providedforthetapsshouldbefurnishedinthebid.
The contactors and associated gear for the tap change driving motors shall be housed in a
local kiosk mounted on the transformer. The motors shall be suitable for operationwith
3-phase 400 volts, 50 cycle external power supply.
RTCC Panel:
The supplier shall furnish, in addition to the equipment above, the following accessories
mounted in a separate Remote Tap Changer Control (RTCC) panel to be installed in each of
theWBSETCL’sControlRoomforremoteoperation.
a) Bay Control Unit (IED should be latest IEC61850 compliant having rear port)–
i) BCU shall be provided for data acquisition and control of Power Transformer.The
Complete particulars of the tap changing gear and capacity of the motor shall be stated in
GTP. An under voltage relay shall be incorporated to monitor the AC control circuit voltage
of tap changer. Audible Alarm and annunciation shall be provided for failure of control
circuit supply, failure of 400 V AC supply to the motor. All the relays requisite for remote tap
changeoperationshallbeprovidedinRTCCpanel.TheOLTCshouldhavebeenTypeTested.
In case of parallel operation or 1-Phase Transformer unit banks, OLTC out of step alarm shall
be generated for discrepancy in the tap positions.
Oil for first filling together with 5% extra oil shall be supplied with each transformer. The oil
shall comply in all respect with the provisions of the latest edition IS:335 (as amended up-to-
date) of specification for New Insulation oils for transformers and switchgears. Particular
attention shall be taken to deliver the oil free from moisture having uniform quality
throughout in non-returnable steel drums. The quantity of oil for first filling of each
transformershallbe statedintheoffer.
SL.
NO. CHARACTERISTICS REQUIREMENT
After site processing through filtration and before commissioning, the moisture content
shall be as follows :
15. CONSERVATORVESSEL:
a) The conservator is a vessel for oil preservation. The oil level in the conservator shall not
be below the level of theH.V. bushing caps unless the bushings are of oil sealed type
construction. The size of the conservator tank shall have adequate capacity with highest
and lowest visible level to meet the requirement of expansion of total cold oil volume in
the transformer and cooling equipment from minimum ambient temperature to100oC.
b) The conservator shall have one filter valves at suitable location, in addition to the valve
specified in the accessories for the main tank. The conservator with sump shall also have
asmalldrainvalveandsamplingcock,thelattersoarrangedasnottointerferewithoil
16. BUSHING:
Bushing shall have high factor of safety against leakage to groundand shall be so located as
to provide adequate electrical clearances between bushing and grounded parts. Bushings
of identical voltage rating shall be interchangeable. All bushings shall be equipped with
suitable terminals of approved type and size and shall be suitable for bimetallic connection, if
necessary. The insulation class of thehigh voltage neutral bushing shall be properly
coordinated with the insulation class of the neutral of thehigh voltage winding.
All main windings, tertiary windings and neural leads shall be brought out to outdoor
through bushings which shall be so located that the full flashover strength will be utilised
and phase to phase and phase to earth clearance shall be more than minimum value
specifiedbelow.LocationandarrangementofbushingshallfollowIndianStandards.
145(HV) 800
36(LV) 2000
36(Neutral) 2000
The minimum withstand value of cantilever load of bushings for 60 sec. shall be as follows
(refer IS:2099-1986 Cl. 5.5)
420KV - 2500N
245KV - 1600N(for 315MVA Tr.) & 1250N (for 200/160MVA TR).
145KV - 1250N
72.5KV - 3150N
52KV - 3150N
36KV - 1250N/2000N
If specifically mentioned in BOQ, Transformer will be fitted with cable end box
suitable for cable termination as per required size of cable. Cable box arrangement
shallbewithsuitabletypeofbushinganddrytypeterminationofsuitablesize&runforHVand LV of
Transformer. The cable box entry shall be of suitable type and shall be designed such that it
shall be able to withstand without any deformity the electrical, thermal and mechanical
stresses & forces developed due to rated short circuit current during any terminal fault inside
the cable box. The flange joints of cable boxes shall be secured with suitable & proper sized
and nos. of stainless steel HTS nuts andbolts.
18. TERMINALCONNECTOR:
i) The bushing shall be equipped with suitable terminals for connector as specifiedherein.
ii) Each terminal (including the neutral) shall be distinctly marked on both the primary and
secondary side in accordance with the diagram of connection supplied with the
transformers.
iii) Vertical/horizontal/universal type bi-metallic, rigid connector for bushing stud shall be
provided.
iv) Clamp and connector shall be made from Cold forged Aluminum Alloy Plate i.e Extruded
AluminumClampandConnectorshallbeprocessedthroughColdforgingfor220KV,132KV,
19. COOLINGSYSTEM&COOLERGROUP:
Type of cooling for this transformer (as per capacity rating) under this specification shall be as
follows:
a) Three winding transformer (220/132/33 KV of 200/160 MVA Tr. & 400/220/33KV 315MVA)
capacity transformer shall employ ONAN/ONAF/OFAF type cooling. ONAN rating shall be
about 60% of OFAF rating. ONAF rating shall be 80% of OFAF rating and OFAF shall be
100% rating of capacity oftransformer.
b) Two winding transformer (132/33KV) of 50MVA Capacity transformer & 220/33KV of
80/50MVA capacity transformer shall employ ONAN/ONAF/OFAF type cooling. ONAN rating
shall be about 60% of OFAF rating. ONAF rating shall be 80% of OFAF rating and OFAF
shall be 100% rating of capacity oftransformer.
c) Two winding/Auto transformer (132/33KV & 132/66KV) of 20MVA & 31.5MVA capacity
transformer shall employ ONAN/ONAF type cooling. ONAN rating shall be about 65% of
ONAFrating.
The whole cooler plant shall be grouped as indicated below:
For ONAN/ONAF cooling: 2×50% cooling banks consisting of radiators & fans. 1(one) standby
fan for each bank shall be provided.
For ONAN/ONAF/OFAF cooling: 2 x 50% cooling banks consisting of radiators, adequate no.
of fans and oil pumps. There shall be at least one stand by pump and fan for each bank of
radiators. There would be 2 x 100% oil pumps and motors for cooling and one such oil pump
shall feed both the radiator banks. The other pump would remain asstandby.
20. RADIATORS:
The transformers up to 50 MVA Capacity shall have body mounted radiators, whereas
transformers above 50 MVA capacity shall have separate plinth &structure mounted radiator and
all transformers shall be fitted with detachable radiator consisting of a series of separate
circular/elliptical/rectangular, etc. tubes or fins, welded at their top and bottom into headers
which in turn are connected to the tank by means of bolted, oil tight, flanged joints. There
shall be indicating butterfly or similar valves fitted in between the tank and the headers,
which can be kept in open or closed position. There shall also be filter valves for
circulationofoil,ateachoftopandbottomheader.Oneairreleaseplugatthetopheader
The bid shall clearly specify the time limit for operation of a transformer carrying full load
without forced cooling. The motor operated fans shall be provided for AF rating and oil
circulation pumps for OF rating.
All Power transformers shall be installed at new/old substation of WBSETCL anywhere in West
Bengal.For50MVAtransformers,radiatorassemblyshallbeplacedalongthe bushingsides
(preferably on HV sides only) . For transformers above 50 MVA rating, in case of separate
plinth &structure mounted radiators, actual orientationof radiatorbank shall be finalised
during approval of drawings based on site condition and related approved drawings.
a) The radiator stacks shall be provided with A.C.3 Phase Motor driven Fans for Forced
Air cooling. The fan motors shall be suitable for continuous operation. Blades shall be
suitably painted for outsideuse.
b) The fans shall operate without any abnormal noise. They shall be fitted with guards of
close mesh-wire-netting for safety. The terminal connections and the greasing caps of
thefanmotorsshallbeaccessiblewithouttheneedofremovinganyfanguard.
c) Fanshallbesolocatedsothattheyarereadilyaccessibleforinspectionandrepair.
d) Cooling fans shall not be directly mounted on radiator bank to avoid undue vibration on
the same. These shall be located in such a manner as to prevent ingress of rain
water. The exhaust air flow from cooling fan shall not be directed towards the main
tank in anycase.
Each cooler unit shall consist of a totally enclosed, oil immersed motor- pump, and a
forced air cool heat exchanger. Motor & pump shall be enclosed in an oil tight container
with motor leads brought through hermetically sealed bushings. Moving parts of motor &
pump shall be readily removable without dismantling of cooler and with minimum spillage
of oil. Pump shall have open type impeller to permit oil circulation when pump is idle. Heat
exchangers,fansandoilpumpsshallbecompletelyinterchangeable.
Radiators shall be connected to the tank by machined steel flanges welded to Radiator
Bank and to the tank through proper gaskets. At each such connection there shall be
provided on the tank an indicating shut off valve which can be fastened in either open or
closedposition.
An oil flow indicator with alarm contacts shall be furnished with each pump assembly to
indicate normal pump operation and direction of oil flow. An indication shall be providedin
theflowindicatortoindicatereverseflowofoil/lossofoilflow.
23. COOLERCONTROL:
a) Cooler units shall be suitable for operation with a 400 volts, 3 phase, 50 Hz. A.C.
power supply Main and standby power supply shall be given for cooler control and source
selected throughcontactor.
b) Cooler control equipment for oil pump and fan motors shall be mounted in a marshalling
cabinet adjacent to the transformer and shall include necessary MCB with automatic
controlandannunciationequipmentandswitchesforremoteandlocalcontrol.
c) Main 400 Volt, 3- phase supply for control of cooler banks shall be taken to cooler control
cabinet through a MCB of suitable rating. The supply to cooler fans and oil pumps motors
shall be made through individual MCB with overload trip arrangements. The control
scheme for the cooler shall be so designed to ensure satisfactory operation of cooler
groupsasspecifiedinthespecification.
d) The switching in or out of the cooling equipment shall be controlled by winding
temperature and there shall be provision for automatic switching in or out at
predetermined temperature differences which should be capable of adjustment and
settingatwill.Huntingofthetransformercoolingequipmentshouldbeavoided.
e) The bidder shall specify the loading of the transformer in case of failure of one or more
set of fans orpumps.
f) Remote control of cooling equipment and its alarm and indicating devices shall beprovided
in the RTCC panel. Indication for operation of individual fan group and oil pump
shallalsobeprovidedintheRTCCpanel.
Necessary provision for incorporating fire prevention and extinguishing system by Nitrogen
injectiondrain&stirsystem-NIDS(alsoreferredasNitrogeninjectionfirepreventionsystem-
NIFPS)shallbeprovided.Theflanges/gatevalvesshallbeprovidedwithblankingplates.
Sufficient quantity of valves, flanges, pipelines shall have to be provided to protect the whole
portion of transformer & surroundings from fire hazard. Details of location & size of the
flanges, valves, dummy pipe and other pipelines for incorporating the NIDS / NIFPS shall be
finalizedduringdetailedengineering.Theexactdetailsincludingsizeofadditionaloutlet/inlet pipes,
valve with flange and other features like provision of non-return valve in conservator,
spare‘NO’contactinPRVetc.,forthefireprotectionsystemshallbehavetobeconsidered.
a) One dial type gas thermometer ( having 150 º scale, with accuracy of 1.5% of FSD)of
robust design andin weather proof casing shall be provided for temperature indication
of oil of all type power transformers shall be housed in the ground mounted marshalling box to
indicate the hot oil temperature. Both alarm and trip contacts shall be provided. Maximum oil
temperature indicating pointer shall also be provided. Remote indication of oil temperature
shall be provided in RTCC and as such the oil temperature indicatorshallbesuitableforthesame.
b) Indicating type winding temperature indicator: All transformers shall be provided with a
device for indicating the combination of top oil temperature and heating by winding
current calibrated to follow the hottest spot temperature of the transformer winding. The
device shall have a dial type indicator, and in addition a indicating pointer to register the
h o t t e s t temperature reached. The temperature indicator shall be connected to CT
secondary current in one phase of each winding of the transformer. It s h a l l have
sufficient contacts for switching in and switching out the cooling employing
ONAF/OFAF system with Alarm as well as trip contacts.
c) For 315MVA, 400/220/33KV and 200/160MVA, 220/132/33KV transformers having three
separate winding temperature indicator shall be provided each with potential free contacts
for control, indication, alarm and trip with independent facility for setting the contacts at
any temperature over the whole working range of 20oC to 150oC Each mercury contact /
micro switch shall have adjustable 10oC overlapping (between ON & OFF ) to prevent
hunting of cooling fans and/or forced oil pump motors.The winding temperature
indicator shall be connected to one phase of each winding of HV/IV/LV windings. Those
temperature indicators shall be housed in ground mounted marshalling box. The Accuracy
Class of WTI shall be ± 1.5% or better temperature indicator diashall have linear
gradationstoclearlyreadatleastevery2°C.
d) Two separate winding temperature indicators with potential free mercury contacts / micro
switches for control, indication, alarm & trip shall be provided in two winding transformer
with independent facility for setting the contacts at any temperature over the whole working
range of 20°C to 150°C. Each mercury contact / micro switches shall have adjustable 10°C
overlapping (between ON & OFF) to prevent hunting of cooling fans and/or Oil pump motors.
Boththe Windingtemperatureindicatorshallbehousedingroundmountedmarshallingboxfor all
two winding transformer shall be connected to one phase of each HV & LV windings. The
accuracy class of WTI shall be ±1.5% or better temperature indicator did shall have
lineargradationtoclearlyreadatleastevery2°C.
e) In addition to WTI & OTI, optical sensors are to be used for hotspot temperaturemeasurement:
1. Adequate no of optical temperature sensors of at least 14 numbers with the unit as
specified below:
Two winding transformer: 7+7 spares (1+1 spare in each phase of HV & LV winding & 1+1
spare in topoil)
For Auto Transformer: 7+7 spares (1+1 spare in each phase of HV & IV winding & 1+1
spare in topoil)
Number of channels in display box shall be minimum 7.
2. Probes shall be all silica, Teflon jacketed fiber with perforation/slits in outer jackets to allow
complete filling. The probes shall not get damaged / affected during filtration of the
transformer. The fiber with Teflon jacket shall be strong enough to withstand the severe
conditions prevailing inside an EHVTransformer.
3. This optical sensors measuring system shall be of direct measurement non calibrating
type. Temperature range of the system should be – 30oC to + 200oC & accuracy of+/- 2o C.
26. VALVES:
(i) TwoNos.oil inletvalveslocatedinsuitablelocations
(ii) Oneoildrainvalveeachsuitablylocatedattopandbottom
(iii) Onefiltervalvesuitablylocatednearthetopofthetank
(iv) Onefiltervalvesuitablylocatednearthebottomofthetank
(v) Onevalveeachforoilsamplingsuitablylocatedatbottomandtop
vi) Radiatorshutoffvalveattopandbottom.
vii) Buchholzrelayandoilsurgerelayshut-offvalvesatbothendsoftherelays
viii) MainConservator–filter,drain,samplevalve,airreleasevalve,airreleaseplug.
ix) OLTCConservator–Oilfillingvalve,Drainvalve,Suctionvalve
x) One drain valve forOLTC
xi) One oil inletvalve
xii) Oneno.BleedvalvewithpetcockforBuchholzrelay.
xiii) Any other valves other than those mentioned above for improvement of operation
and maintenance facility if required & pointed during drawing approval stage shall
alsobewithinthescopeofsupplyofmanufacturer.
28. GROUNDINGTERMINALS/EARTHINGARRANGEMENT:
a. Two grounding terminals capable of carrying for 3 (three) seconds the full short circuit
current of the transformer shall be provided at positions close to the bottom at two
corners of the tank for bolting the earthing terminals to the tank structure to suit local
condition.
b. Neutral Earthing Arrangement: The neutral terminal of auto-transformer & two
winding transformer shall be brought to the ground level by adequate sized brass/tinned
copper grounding bar (considering the system fault level as stated in STP) supported
from the tank by using porcelain insulators. The end of the tinned copper bar shall be
brought to the bottom of the tank at the convenient point for making bolted connection
to two nos. galvanized steel grounding flat connected to sub-station groundingmat.
29. RATING,DIAGRAMANDPROPERTYPLATES:
The following plates shall be fixed to the transformer tank at an average height readable from
the transformer base level.
a) A rating plate bearing the data specified in the appropriate clauses of IS:2026
b) A diagram plate showing the internal connections and also the voltage vector relationship of
the several windings in accordance with the IS and in addition, a plan view of the
transformer giving the correct physical location of the terminals. No load voltage shall be
indicated in each tap. The winding temperature C.T. and the thermometer pocket shall also
be indicated in the saidplate.
c) A plate showing the location and function of all valves and air release plugs and plate
material preferably in stainlesssteel.
d) An indoor cubicle for remote control of coolers, position of tap, alarm and indicating devices
with the help of control equipments, annunciation, relays, indicating instrument,etc.
e) A separate rating plate embossing different losses obtained after relevant test for each
transformer is to be provided.
f) A rating plate for each type of bushing shall be provided and to be fixed at the base of the
bushing.
a. A suitable weather proof cubicle for housing the control, equipment, terminal block etc.,
made of 3 mm sheet steel, shall be provided for each transformer. The box shall
accommodate all (i) winding and oil temperature indicators and (ii) control and
protection equipment for coolingplant.
b. All terminal blocks for cable connection shall be located in this box. Terminal blocks shall
be of 1100 Volt grade “Elmex/Connectwell” make and have continuous rating to carry
the maximum expected current on the terminals. The terminal block shall be fully
enclosed with removable covers of transparent, non-deteriorating type plastic material.
Insulating barrier shall be provided between the terminals. The terminal blocks shall
have locking arrangement to prevent its escape from the rails. 20% spare terminals are
to be provided. These spare terminal blocks shall be uniformly distributed on all the
terminal block column. All terminal blocks shall be numbered for easy identification.
Terminal blocks shall be arranged with at least 100 mm clearance between two sets of
terminalblock.
c. The marshalling box shall be provided with cubicle lamp with door switch, space heater
with differential thermostat and removable cable gland plate etc. Cable shall enter from
the bottom of thebox.
d. Marshalling box of each type shall be tested for IP-55 in accordance withIS:13947.
e. All internal wiring shall be carried out with 1100 Volt grade PVC insulated stranded
copper conductor of 2.5 sq. mm or larger size as per schemerequirement.
31. WIRING:
All control, alarm and indicating devices provided with the transformer shall be wired up to the
terminal blocks in the marshalling box.
Wiring from transformer to the cubicle shall be done with PVC wires in conduit or by PVC
2
armoured cable of 1100 V grade. Minimum wire size shall be 2.5mm copper. Not more than
two wires shall be connected to a terminal. 20% spare terminals shall be provided.
All devices and terminal blocks within the marshalling box shall be identified by marking
corresponding to the circuit in schematic or wiring diagram. All fuses shall be of cartridge type
and IS marked.
Phase marking on each terminal bushing (including neutral) shall be distinctly made on both
the primary, secondary and tertiary winding side in accordance with the connection diagram of
thetransformer.
Interconnection of wires in between transformer and marshalling box will be in the scope of the
contractor.
Labels shall be provided for all apparatus such as relays, switches, fuses contained in any
cubicle or marshalling kiosk.
Descriptive labels for mounting indoor or inside cubicles and kiosks shall be of material that
will ensure permanence of the lettering. A mat or stain finish shall be provided to avoid dazzle
from reflected light. Labels mounted on dark surfaces shall have white lettering on a black
background Danger notices shall have red lettering on a white background. All plates shall be
of material which will not be corroded. Labeling shall be clear, concise andadequate.
Labels for mounting outdoors shall be weather and corrosion proof formed by etching to
ensure permanence.
Labels shall be attached to panels with brass screws or with steel screws which have received
rust preventive treatment.
Labels should have lettering sizes of at least 1 to 1.5mm stroke width and 3 to 6mm height.
After placement of P.O., six copies of following drawings ,manuals and literatures shall be
submitted to the Chief Engineer, Engg. Deptt., BidyutVhaban (9thfloor), Salt Lake, Kolkata -
700091.
Drawings of Transformer:
(i) General outline drawing showing front, side elevation, plan of the transformer and
accessories with detailed dimensions and detailedlegend.
(ii) Detailed foundationplan.
(iii) Drawing of each type of bushings, lifting dimensions, clearance between Terminals of
different voltage level and ground, quantity of insulation oil, name plate, detailsetc.
(iv) Operation and maintenance guide for transformer and ON LOAD TAPCHANGER.
(v) Transport OutlineDrawing
(vi) Valve SchedulePlate
(vii) Measured LossPlate
Four (04) copies of approved drawings and literatures for each transformer along with soft
copy shall be submitted for our record and distribution to site.
Instruction Manuals:
Six (06) copies of operation, maintenance and erection manuals in English language shall be
supplied for each transformer against each P.O. The manuals shall be bound volumes and
shall contain the drawings and information required for erection, operation and maintenance
of the power transformer. The manuals shall include amongst other, the followingparticulars.
a) Marked erection prints identifying the components parts of the power transformers as
dispatched, with assemblydrawings.
b) Detailed dimensional drawings, assembly and descriptions of all thecomponents.
One copy of each drawings incorporating the following particulars along with one set of
complete type test report on similar transformer carried out as per IS & IEC in Govt.
Recognized Test House or Laboratory/NABL accreditated Laboratory shall be submitted by
each bidder with each copy the bid to the Purchaser for the purpose of evaluation of bid as
follows:
General outline drawing showing dimensions, net weights of transformers, tap changing gear,
marshalling box and their shipping weights.
Sectional views showing the general construction features and disposition of various
fittings andaccessories.
Bushing drawing showing full details of construction of HV/LV/Tertiary condenser
bushing and other technical data, weight of bushing assemblyetc.
Dimension of the largest part to be shipped and the position in which these are to be
transported.
Technical literature on tap changing control, cooling system, relays meters and general
construction feature for winding temperature indicators, Buchholz relays, oil temperature
indicator, Oil pumps, pressure release device (where required) etc.
Transformer similar to offered one should have type tested as per relevant IS.
Stage inspection will be carried out by the customer on Core, Coil & Tank during the
manufacturing stages of the transformer. The manufacturer will have to call for the stage
inspection and shall arrange the inspection at manufacturer’s premises or manufacturer’s
bidders premises free of cost. Stage inspection of core and coil will be carried out on 1 (one)
number Transformer against each Purchase order or a particular design. On the basis of
satisfactory Stage Inspection, manufacturer will proceed further. The following stage
inspection shall be carried in oneinspection.
Prior to stage inspection following documents shall have to be submitted by
manufacturer forverification:
1) Document related to prime core, procurement establishing traceability vide relevant Cl.
of Technical Specification of PowerTransformer.
2) Documents for coil establishingtraceability.
Following tests have to be carried out in stage inspection.
I. On Core
1) Flux density checking of assembled core (without having any insulating tape etc. rapped
around the core) vis-à-vis measurement of step thickness, lamination widthetc.
2) Window height, leg center dimension, core diameter of assembledcore.
3) Physical verification of core in respect of lamination thickness, bend, camber and
wavinessetc.
4) Carlite test, Watt loss and ageing test on the sample of prime core. (Core sample shall be
selected during stage inspection and sent to any NABL accredited laboratory for tests
under Sl.No.4)
5) Loss measurement of Prime core(Loss/Kg).
6) 2KV test between core and Yokeclamps.
II. On Coil
1) Physical verification of HV, IV and LV wound coil for 160MVA,200 MVA and
315MVA Power Transformer (without any outerinsulation).
2) Measurement of resistance of each finished coil (HV, IV &LV).
3) Measurement and current density calculation of eachwinding.
4) Copper purity test (after cutting from finished coil offered forinspection).
Calibration Certificates of all measuring instrument to be used during stage and final
inspection shall be produced and that will be in conformity to our relevant Clauses of
GCC/TechnicalSpecification.
III. OnTank
All Routine and Acceptance tests at manufacturer’s works shall be carried out in presence of
WBSETCL’s representative in compliance with IS: 2026/ IEC 60076 (as amended up-to- date)
on the transformers. The entire cost of acceptance test, routine test and special test as follows
that are to be carried out as per relevant IS shall be treated as included in quoted price of
transformer.
1. The Contractor shall offer the transformer for final testing with at least 15 (fifteen) days
prior to the actual date when the tests will be carriedout.
2. Internal test report of each transformer and test reports of prime core and coil from NABL
accredited laboratory shall be submitted at least 7(seven) day prior to date of testing.
Offer for final test shall be accepted after receiving abovedocuments.
3. After final testing 6 (six) copies of test reports of each transformer along with soft copy and
soft copy of final drawing shall be submitted to the Chief Engineer, Engg. Deptt. prior to
issuance of formal MICC & DIletter.
The following tests are to be carried out as a part of routine tests as per IS:2026 / IEC 60076
and as per our standard requirement:
The following Type tests are to be carried out for at least on one of each type of transformer
against each purchase order without any price implication:
42. TOLERENCES
As per the clause of the IS 2026/ IEC 60076 tolerances will be applicable to certain
guaranteed values as depicted in the followingtables:
SL Item Tolerance
2 Voltage ratio on other tapings, same pair To be agreed, but not less than the lesser of
the values in a) and b)above
3 Voltage ratio for further pairs To be agreed, but not less than the lesser of
the values in a) and b)above
NOTE - For certain auto-transformers and booster transformers the smallness of their impedance
justifies more liberal tolerance. Transformers having large tapping ranges, particularly if the range
is asymmetrical, may also require special consideration. On the other hand, for example, when a
transformer is to be combined with previously existing units, it may be justified to specify and
agree on narrower impedance tolerances. Matters of special tolerances shall be brought to
attention at the tender stage, and revised tolerances agreed upon between manufacturer
andpurchaser.
NOTE - 'Declared value' should be understood as meaning the value declared by the
manufacturer.
All the Tests shall be conducted after complete Drying out at the works. The transformer shall be
despatched complete after being dried out under vacuum and filed with inert gas, ready to be put
into commission, without further drying out at site.
The MANUFACTURER shall arrange for the services of their Supervisor/Engineer from the
manufacturer during erection, testing and commissioning of the equipment at sites at free of cost
as many time as required by WBSETCL.
A) A tentative I/O signal list of BCU of RTCC is mentioned in the technical specification.
However the detail exhaustive I/O signal list will be finalized during detail Engineering.
All ICD files should be ready and configured based on the final I/O signal list before
offering final inspection of the transformer.
Outdoor Type
6 Type of Transformer For All Rating
Interconnection Power
Transformer
7 Tertiary winding voltage (KV) for 160 MVA,200 MVA& 33
315MVA
i) 1.2×50 micro-
Insulation level of HV(N) 95
16 second Lightning impulse
winding
(KVp)
ii) Power Frequency
18 withstand(KVrms) 38
80MVA/50MVA/31.5/20 YNd1
31.5 MVA 132/66 KV Auto YNa0
Transformer
400KV(1 Sec) 63
220KV(3 Sec) 40
23 Short circuit level (KA)
132 KV (3 Sec) 31.5
66 KV (3 Sec) 31.5
33KV (3 Sec.) 25
400KV 13020
220 KV 7595
400 KV 1425
400 KV 630
220 KV 460
Insulating level of bushing:
35 One minute Power frequency 132 KV 275
withstand voltage
(KVrms)(dry 66 KV 155
& wet).
33 KV 70
Tertiary 33 KV 95
HV Neutral 70
400 KV 10500
220 KV 6125
132 KV 3625
Minimum Total Creepage
36
distance (mm) forBushing 66 KV 1815
33 KV 900
Tertiary 33 KV 1300
HV Neutral 900
Transformers similar to a reference transformer can be identified by comparison using the following
non-exclusive list of critical features:
3. Same type of main windings for example, helical, disc, layer, pancake, as the referenceunit.
5. Axial forces and relative winding stresses (ratio of actual stress to critical stress) at short-
circuit not exceeding 120% of those in the referenceunit;
6. Same type of winding conductors, for example, aluminum, aluminum alloy, annealed or
hardened copper, metal foil, wire, flat conductor, continuously transposed conductors and
epoxy bonding, if used, as the referenceunit;
9. Same conceptual design, for example dry-type, oil-immersed type, core type with concentric
windings, sandwich type, shell type, circular coils, non-circular coils as the referenceunit.
Sl Description No Core Application Current Output ISF Accuracy Min Knee Max CT Max
. . No. Ratio Burden (<) Classas point excitation
N of (VA) at per IS Voltage Secy current at
o Co Lower 2705 (V) Winding Knee point
re Ratio Resistance Voltage
i) 400KV side, 220KV 1 1 Protection 1600/1A PS Class 1600V 4.0 30 at Vk/2
side & Neutral of 500
MVA, 400/220/33KV
Transformer
ii) 400KV side, 220KV 1 1 Protection 1000/1A PS Class 1000V 2.5 30 at Vk/2
iv) 220KV side, 132 KV 1 1 Protection 800/1A PS Class 1000V 2.5 30 at Vk/2
side & Neutral of
vi) 220KV side & Neutral 1 1 Protection 400/1A PS Class 800V 1.5 30 at Vk/2
of 80MVA / 50MVA
viii 132KV side & Neutral 1 1 Protection 150/1A PS Class 600 1.5 30 at Vk/2
of 31.5MVA /20MVA
ix) 33KV side of1 1 Protection 800/1A PS Class 400 2.5 30 at Vk/2
31.5MVA /20MVA
xiii Tertiary
200MVA
winding of 1 1 Protection 1200/1A PS Class 1200 2.5 30 at Vk/2
SL DESCRIPTION SUBMISSION
b Country of Origin
e Number of Phase
i Vector Group
j Type of Cooling
3 Thermal Data
4 Impedance Data
5 Guaranteed Loss
h c) At Full Load
7 Core
a Number of Winding
a Rated KV
10 Insulation Level
11 Bushings
a Manufacturer of HV/IV/Tertiary/HV
Neutral/LVNeutral
12 Tap Changer
a Manufacturer
b Type
13 TANK
g
Approximate weight : Windings (in Kg)