Design of Switchyard - NWA
Design of Switchyard - NWA
TYPE OF SWITCHYARDS
AIR INSULATED (CONVENTIONAL) GAS INSULATED SWITCHGEAR (GIS) HIGH VOLTAGE POWER ELECTRONIC SUB-STATION (HVDC) FLEXIBLE AC TRANSMISSION SUBSTATION (FACT)
This arrangement involves one main bus with all circuits directly connected to Bus Reliability Low, Entire substation is lost in case of a fault on the bus-bar or any bus-bar isolator and also in case of maintenance thereof One of the methods for reducing the number of circuits lost in case of a fault is to sectionalise the bus Additional by-pass isolators are provided to permit a circuit breaker to be taken out for maintenance without switching out the associated feeder.
Comparison of Configurations
Configuration Reliability Cost Available Area Single bus Least reliable - single failure can cause complete outage Least cost (1.0) fewer components Least area fewer components
Main bus and transfer Least reliable same as single bus, but flexibility in operating and maintenance with transfer bus. Moderate cost (1.76) fewer components Low area requirement - fewer components
Double bus, single breaker Moderately reliable depends on arrangement of components and bus Moderate cost (1.78) more components. Moderate area - more components Ring bus High reliability single failure isolates single component Moderate cost (1.56) more components. Moderate area increase with number of circuits Breaker-and-a-half Highly reliable single circuit failure isolates single circuit, bus failures do not affect circuits. Moderate cost (1.57) breaker and a half for each circuit Greater area - more components per circuit
No deterioration of active parts from air, moisture, contamination, etc GIS is more reliable, less maintenance than AIS SF6 is used in GIS at 4 to 6 Atm.
CONSTRUCTION
GIS is assembly of standard equipment modules to match SLD Modules are joined bolted flanges with O ring seals for enclosures and sliding plug -in contacts for conductor. Internal parts are supported by cast epoxy insulators. Up to 170kV, all 3 phases are often in one enclosure, above that 3-ph enclosure becomes very large, so 1-ph design is used Estimated Service life 30 years
INSTALLATION
GIS is mostly installed on a monolithic concrete pad or floor of building Rigidly attached by bolting/welding GIS support frames to embedded steel plates
HVDC Sub-stations
HVDC converters convert AC power to DC power and vice versa. They terminate DC transmission lines or form back to back asynchronous AC system coupling
BAY COMPONENTS
TRANSFORMERS CIRCUIT BREAKERS ISOLATORS INSTRUMENT TRANSFORMERS ( CT / PT ) LIGHTNING ARRESTORS INSULATORS CONDUCTORS CARRIER COMPONENTS (WAVE TRAP, CVT) STRUCTURES
STATION EQUIPMENT
STATION TRANSFORMERS REACTIVE COMPENSATION EQUIPMENT CONTROL PANELS
ACTIVE MEASURES Automatic fire protection measures designed to extinguish or control fire at early stage Automatic separation system consists of extinguishing agent supply, control valves, delivery system, fire detection and control equipment MANUAL MEASURES Manual measures include manually operated fire extinguisher, fire hydrant etc by staff
ILLUMINATION SYSTEM,
Objective of Illumination System
Quality lighting is an important factor that ensures efficiency productivity and employees comfort at work place. All vision requires light and the quality, direction and diffusion of the light are all important in determining how well one sees.
Illumination design should be based on the achievement of desired illumination level concept with minimum glare. Also, the concept of aesthetics in lighting should also be taken into consideration. Illumination should be uniform and free from dark patches. Illumination design must be energy efficient and reasonably decorative.
SUBSTATION GROUNDING
The Substation Grounding System is an Essential part of the overall Electrical System. Proper Grounding is Essential for following two reasons It provides a means for dissipating Electric Current into Earth without exceeding the operating limits of the Equipment. Provides a Safe Environment to protect personnel in the vicinity of grounded facilities from the danger Electric Shock under fault condition IMPEDENCE TO GROUND SHOULD BE AS LOW AS POSSIBLE WITHIN 1 OHM FOR LARGE SUBSTATION & 5 OHM FOR SMALL SUBSTATIONS
CABLING : TRENCHES AND CABLE DUCTS POWER CABLES IN FIRST RACK, LOWER RACK CONTAIN CONTROL CABLES, UN-ARMOURED CABLES IN BOTTOM MOST RACK CRANE FACILITY: LARGE S/S HAVE REPAIR BAY ALONGWITH CRANE PROVISION OF RAIL TRACK FOR MOVEMENT OF T/F TO REPAIR BAY
SAFETY CLEARANCES
Highest System Voltage BIL Minimum Clearance Sectional Clearance Ph Earth Ph - Ph
36 72.5
170 325
32 63
40 75
300 350
SWITCHYARD AUTOMATION
Sub-station integration & automation can be broken down into 3 levels or layers Level 1 Field Devices Level 2 Substation Data Concentrator Level 3 SCADA System
COMMUNITY CONCERNS
NOISE: INDUSTRIAL ZONE <75dBA, Commercial Zone <65dBA, Residential Zone <55dBA ELECTRIC FIELDS: Dependent on Voltage, independent of Current, Magnitude varies is a function of operating voltage and decreases with square of distance from source. Could easily be Shielded MAGNETIC FIELDS: Dependent on Current, independent of voltage, decreases inversely with distance; Factors affecting current magnitude, phase spacing, bus height, phase configuration, distance from source, phase unbalance; Difficult to Shield- special enclosures required AESTHATICS