APC (American Power Conversion)
Motion & Drives
Objective
To Determine Standard Time Of the Model
Cycle time reduction by eliminating NVA Process Improvement
Methodology
Video Study
Report generation
Implementation
Timer pro analysis
Recommendations
Problems Identified
Un availability of hardwares in the work station Un availability of tools in tool box
Waiting & unnecessary movements to bring sub assembly to line
Re work Waiting for Class A,B,C materials from ware house
Searching for cable wire (all wires dumped in same bin )
Searching for bus bar (all bus bar dumped in same box) Manually lifting the heavy weight sub assemblies to fix to unit
Action taken
Implement Auto Screwing machine It avoids Manual work. Accuracy more Easy to handle It is operator friendly Cycle time of assembling dc bank is reduced
Implement bus bar rack
It avoids searching time for bus bars . Part number of Bus Bar will visible clearly. It avoids crosschecking time part number of bus bar with work instructions
Implement kan ban cards
There is no signal system here so material specialist didnt get any signals if bins are empty operator use to him this leads to delay in working and unnecessary waiting.
By implementing this leads to reduce waiting time for Common parts in work station It avoids Operator move to other station to get materials By implementing kanban system operator need not to inform to material specialist to replenish the materials so it avoids waiting time.
Implement lifters Avoid Manually assembling the Bypass assembly Accidents are avoided It is more Safety than doing Manual Operator strain eliminated One person can easily handle
Implemented Cable racks
Avoid the searching for power cables Easily identify the power cables with part number Avoid crosschecking time with wok instructions
Finishing and Packing
Problems Root Cause Actions Taken
Damaged pallet from vendor side Cartons are not able to identify.
Due to transportation and storage Cartons are dump in one place
To improve the Transportation and storage Method. Storage rack provided for carton Storage rack provided for carton
Rework due to carton damage.
High cycle time due to movement
Due to storage.
Strech wrapping m/c is far from carton packing place. It should keep near packing place
Space congested
Cartons and pallets are heavy and bulky.
Increase the work area
Standard Time For Model AIC (ON- 1391)
Present
Process Build Line Sub Assembly Packing and Finishing Testing Total (hrs) Standard Time (hrs)
5.773889 3.920833 0.130278 1.640833 11.466
Proposed
Process Build Line Sub Assembly Standard Time (hrs)
4.5680 3.14611 0.130278
Packing and Finishing
Testing Total (hrs)
1.580
9.475
By reducing the NVA 1.911 hours was reduced
Standard Time For Model S9
Present
Process Build Line Sub Assembly Packing and Finishing Testing Total (hrs) Standard Time (hrs)
4.727222 1.769722 1.462222 4.013333 11.973
Proposed
Process Build Line Sub Assembly Packing and Finishing Testing Total (hrs) Standard Time (hrs)
2.645 1.659 1.022 3.776 9.104
By reducing the NVA 2.869 hours was reduced
Thank You