19/12/2013
TITRE PRESENTATION
TECHNO-ECONOMIC ASPECTS OF POWER SYSTEMS
Ronnie Belmans
Stijn Cole Dirk Van Hertem
2
OVERVIEW
Lesson Lesson Lesson Lesson Lesson Lesson Lesson Lesson Lesson Lesson
1: Liberalization 2: Players, Functions and Tasks 3: Markets 4: Present generation park 5: Future generation park 6: Introduction to power systems 7: Power system analysis and control 8: Power system dynamics and security 9: Future grid technologies: FACTS and HVDC 10: Distributed generation
3
PRESENTATION TITLE
OUTLINE INTRODUCTION TO POWER SYSTEMS
Power systems
Grid structure Grid elements New investments in the grid
Tasks of the TSO Grid operation issues
THE GRID OF TODAY Transmission network
To transport the electric power from the point of generation to the load centers All above a certain voltage
(Subtransmission) Distribution network
To distribute the electric power among the consumers Below a certain voltage
Transmission system Higher voltage (typical at least 110 kV and higher) Power injection by generation and import, large
STRUCTURE OF THE POWER GRID WHATS THE DIFFERENCE?
consumers Interconnected internationally Meshed nature-Redundancy (Subtransmission system) Between transmission system and distribution system Connection of large industrial users and cities Open loop/partly meshed Distribution system 400 V to some ten of kV Industry, commercial and residential areas Radial
INDUSTRIAL NETWORK (HAASRODE)
Transformer: 70 kV/10kV, 20 MVA
UCTE
EXAMPLE: MAP OF THE IBERIAN TRANSMISSION SYSTEM
TRANSPORT OF ELECTRIC POWER
Electric power P [MW]
Alternating current S [MVA] Increase current I
Larger conductor cross-section
P or S = U * I
Two ways to increase the transported power
Increase voltage U
More insulation
Two ways to transport electricity
Alternating current (AC) Direct current (DC)
PROBLEM FACED BY ELECTRICITY PIONEERS AC OR DC?
Direct Current DC
Generator built by W. von Siemens and Z.Gramme
Low line voltage, and consequently limitation to size of the system
Alternating current AC
Introduced by Nikola Tesla and Westinghouse
Transformer invented by Tesla allows increasing the line voltage Allows transmitting large amounts of electricity over long distances
TRANSFORMER
AC TRANSMISSION SYSTEM Frequency of 50 or 60Hz
Current changes direction 100 or 120 times a sec Active AND reactive power in the same line
3 phase system Line voltages can be easily and economically transformed up and down AC current does not use the whole conductor
Skin effect
AC conductors have larger diameters than adequate DC
SWITCHYARD
DC TRANSMISSION SYSTEM
Only active power Current flows in one direction Conductor cross-sections fully used Low transmission losses Requires DC-AC converters to control the voltage level Expensive Switching of higher voltage DC more difficult
AC VS DC
Advantages of AC
Advantages of DC
Cheaper transformation between voltages Easy to switch off Less equipment needed Known and reliable technology More economical in general Rotating field
Long distance transmission
Higher investment costs offset by lower losses
Undersea and underground transmission
on 1000 km line, 5% for DC opposed to 20% for AC
Connection of separate power systems
No reactive power problem
COST OF TRANSMISSION LINE FUNCTION OF VOLTAGE LEVEL
LINES AND CABLES
Overhead transmission lines
Economical
However, visual pollution
Widely used in transmission over large distances
Underground cables
More expensive than lines
5 to 25 times higher capital costs for 380kV
Underground, thus invisible to the public
Ground above the cable can be still used However, maintenance costs are significant
Widely used in urban areas
OVERHEAD LINE
TRANSMISSION CAPACITY UPGRADE
AC overhead
New line Refurbishing New conductor types
Evaluation: different points of view
Technical Economical Regulatory Environmental
AC underground
Conventional cables GILs HTS
OVERHEAD AC TRANSMISSION NEW LINE
Advantages
Widely used in transmission over large distances Most economical (especially in rural areas) Well-known technology
Best choice from techno-economic point of view
Classic approach to network reinforcement
OVERHEAD AC TRANSMISSION NEW LINE
Environmental aspects
Visual impact Vegetation Population Town planning Cultural heritage Natural site and landscape
OVERHEAD AC TRANSMISSION NEW LINE
Social and political issues
Concern about health effects Not popular heavy resistance
NIMBY NIMTO BANANA CAVE NOPE
Regulatory
Permit process up to 15 years
OVERHEAD AC TRANSMISSION NEW LINE
Conclusion
Best from technoeconomic point of view Worst from environmental, social & political point of view Very difficult to construct new lines in industrialized countries
alternatives needed!
OVERHEAD AC TRANSMISSION ADDING/REPLACING CONDUCTORS
Increased ampacity
Without supplementary environmental impact Within existing right-of-way
Equip second circuit
No new towers needed cost effective
Heavier conductors
Tower and foundation modifications may be needed very high cost
new conductor types
OVERHEAD AC TRANSMISSION NEW CONDUCTOR TYPES
Material properties
Composite core Surrounded by aluminium(-zirconium) Increased strenght and reduced weight Increased ampacity
Economics
Significantly higher cost No tower modifications needed Outdated standards state maximum conductor temperature independent of conductor type New technology limited experience e.g.: no data on expected lifetime available Higher operating temp losses increase
Regulatory
Other drawbacks
AC CABLES
AC cables vs. overhead lines
Technical
Almost no maintenance needed Repair more difficult Technical difficulties at high voltages Limited distance
Economical
5 to 25 times higher capital costs (/MVA) Although cost differences have narrowed Repair costs are significant
AC CABLES
AC cables vs. overhead lines
Environmental
Invisibility Dangers: oil spill, poisonous SF6 arcing by-products
Social & political
Less right-of-way needed Permitting takes less time Less concern for health risks (although electromagnetic fields are higher) Ground above the cable can still be used
Widely used in urban areas
AC CABLES
Classic
Paper insulated, oil-filled XLPE
New types
Higher voltages Lower losses More expensive
AC CABLES NEW TYPES
Gas Insulated Cables (SF6)
Higher voltages due to better insulation Suited to bulk transmission C lower suitable for long distances Complex placement (many joints) Arcing by-products hazardous for environment Considered for future tunnel connections (e.g. in the Alps)
Temperature protection
Operating very close to limits Belgium: Tihange - Avernas
AC CABLES NEW TYPES
High Temperature Superconducting
No conduction losses at cryogenic temperatures Cooling losses Cooling and cooling equipment expensive Reduced dimensions Environmentally friendly Could prove economic for specific cases R&D needed
AC CABLES VS DC CABLES
Source: ABB
CABLES
TASKS OF THE TSO
Transmission System Operator TSO Operates the grid
Constant monitoring of system conditions Frequency control (active power) Voltage management (reactive power)
Administrates the settlement of unbalances
Access Responsible Parties (ARP) need to balance their productions and consumption
TSO takes actions if ARP deviates from the schedule TSO charges the ARP for the incurred costs
To keep the lights on
ARP
Production Import/ Export
~
Grids
~
ARP1 ARPN
~
I/E
I/E
Consumer
FREQUENCY CONTROL
TASKS OF THE TSO Frequency control Primary frequency control
Compensate for short-term unbalances at local level Stabilize frequency within acceptable range around set point
Secondary and tertiary frequency control
Control the load-generation balance at the programmed export-import Contribute to bringing the frequency back to its set point Relieve the primary control reserve after an incident
Scheduled (set point) frequency (time control)
Laufenburg control centre in Switzerland To account for the Synchronous Time deviations
50.01 or 49.99 Hz for the whole day
TASKS OF THE TSO
Reactive power management and voltage control Primary voltage control
Excitation of generators Capacitors SVCs (Static Var Compensators)
Secondary voltage control
Zonal coordination of the voltage and reactive power control Maintains the required voltage level at a key node
Tertiary voltage control
Optimization of the reactive power distribution
TASKS OF THE TSO
Constant monitoring of system conditions
State estimation
To get best possible picture of system conditions
Find a best-fit load flow Based on metered values (imperfect measurements)
Contingency analysis
N-1 security rule
One accident cannot bring the system in danger Redundancy
FROM NATIONAL TO INTERNATIONAL GRID
SYNCHRONOUS AREAS IN EUROPE
UCTE
Established in 1951 as UCPTE, 9 control zones, currently 27
23 countries, 33 TSOs, 620 GW installed capacity, 295 TWh exchanges Full synchronous operation of its members in 1958 absorbed many smaller initiatives along the way 450 mln. people, annual electricity consumption 2500 TWh.
CENTREL, SUDEL, COMELEC
Nordel
UK
UKTSOA ATSOI
F,SWE,NO,DK (part)
UPS/IPS
Ireland Ex Commonwealth of Independent States
SYNCHRONOUS AREAS (1) WHY CREATE SYNCHRONOUS AREAS ? Increase grid reliability and mutual support
Improved system frequency control to minimize major disturbances Mutual support in case of emergencies Sharing reserve capacities
Facilitate functioning of the electricity market
non-discriminatory domestic and cross-border access to the grid No need for synchronous area as such, also possible with dc links
Example of direct benefits
Zone of 15 GW production capacity loses its largest unit 1 GW
Isolated: needs to develop 1 GW in less than 5s to avoid collapse As a part of UCTE it needs to develop its share of the two largest UCTE unit, and thus x% of 3GW, in 15-30s.
SYNCHRONOUS AREAS (2) CHALLENGES
Coordination and control of the power flows
Interdependency of power flows Interconnected systems share benefits and problems
Problems on top of the above
Often different standards applied in control zones
TECHNICAL STANDARDS DIFFERENCES
Exact same line can have different capacities
Different interpretation of frequency control Different operational standards
Source: IAEW
SYNCHRONOUS AREAS (3) OPERATIONAL HANDBOOK (UCTE)
Stronger interconnections require common and consistent understanding of grid operation and control and security in terms of fixed technical standards and procedures
Result of discussion between all TSOs involved Successor of past technical and organizational rules and recommendations Unification and formalization of standards To make the best possible use of benefits of interconnected operation To keep the quality standards in the market environment
Operation handbook: http://www.ucte.org/publications/ophandbook/
CROSS-BORDER POWER FLOWS IN EUROPEAN GRID
Typical power flow pattern
Countries structurally exporting or importing
However
Unstable production strongly influences the pattern
Wind generation
Restrictions consist typically of several lines
What matters for the grid are individual lines flows! This differs considerably from the physical border capacity
UCTE PHYSICAL ENERGY EXCHANGES 2004 [GWH]
LEVEL OF CONGESTION BETWEEN EU MEMBER STATES
Source: DG COMP
FRANCO-BELGIAN BORDER 2001
Unexpected flows not just ONE TIME event More like a permanent thing
WIND POWER IS A PROBLEM Large wind parks problematic for the network
Unstable dispatch within a zone
Will there be wind? Not too much?
Unstable loop flows
Benelux case
Positive correlation between loop flows and wind in Germany
Up to 0.4
Loop flows almost entirely through BE and NL
5
3
PHASE SHIFTER INVESTMENTS IN THE BENELUX IN ORDER ALLOW POWER FLOW CONTROL 1. Meeden (Nl) 1 2. Gronau (D) 3. Kinrooi (B) 4. Kinrooi (B) 2 5. Zandvliet (B) 6. Monceau (B)
HOW DANGEROUS CAN UNEXPECTED FLOWS BE?
Unannounced wind power in the north Germany Actual event - Monday 27 Oct. 2003, 18h00 20h00 Very heavily loaded D-NL border 4550 MW total physical flows in the direction of NL
2380 MW more than scheduled
Loss of N-1 security on 2 cross-border lines Loss of N-1 security on phase shifting transformer
UNANNOUNCED WIND POWER IN THE NORTH D
- 980 - 1017
ELIA
- 3068SCHEDULED
POWER EXCHANGES
CENTREL D
RWE
SEPS MVM H
798
NL
TENNET
2169 2150
- 2967
PSE
PSE PL CEPS CZ
South GB
1815
North
+3903
RTE 752
SK
+3126
- 504 - 426
4669 118
+3846
1525
DC link
A
120
APG
575
E
REE
646
CH
+2614 ETRANS +2560
+677
3022
I P
REN
1704
- 5380
TERNA
481
ELES SLO
ELES
BiH
- 452
HEP HR
401
UNANNOUNCED WIND POWER IN THE NORTH D
- 980 - 1017
ELIA
SCHEDULED POWER EXCHANGES VS PHYSICAL - 3068 POWER FLOWS
798 1485
NL
TENNET
2169 4553
CENTREL D
RWE
- 2967
1815
505
North South GB
2150 1421
PSE
PSE PL CEPS CZ
SEPS SK
MVM H
+3903
RTE 752
+3126
- 504 - 426
4669 342 118
+3846
1189
1525
DC link
A
120
APG
575
E
REE
646 846
CH
+2614 ETRANS +2560
+677
28 401 481
ELES SLO
3022
I P
REN
2875
1704 1267
- 5380
TERNA
ELES
BiH
- 452
HEP HR
UNANNOUNCED WIND POWER IN THE NORTH D
B
ELIA
2283
NL
DIFFERENCE BETWEEN PHYSICAL AND PROGRAMMED FLOWS
2384 729
PSE PL CZ
CENTREL
CEPS
North South
2320
TENNET
D
RWE
SEPS SK
MVM H
F
RTE
4327
1307
PSE
A
APG
CH E
REE
1492
ETRANS
92 147
I P
REN
ELES SLO
437
ELES
BiH
TERNA
HEP HR
CUMULATIVE WIND POWER INSTALLED CAPACITY 2005
WIND POWER INSTALLED IN EUROPE BY END OF 2005
SHARE OF DAILY WIND POWER IN RESPECTIVE DAILY PEAK DEMAND IN E.ON-GRID (GERMANY).
CONCLUSIONS
Grid operation becomes more complex Due to the market based flows Caused by wind energy Controlling frequency and voltage by active and reactive power