Kansai International Airport
(Phase-I) Foundation Case Study
By
Rajul Teredesai
CE 5333-Foundation Engineering
Spring 2005
Overview
Kansai
International
Airport (KIA)
Key Features
Located on a biggest man-made island in
Osaka Bay, Japan
Constructed cost over $14 billion
The island of 4 X 1 km, constructed in
around 18m of water, entirely from landfill
Project Started in 1986
Opened for flights in 1996
The ASCE named KIA the #2 civil
engineering project of the 20th century,
second only to the Panama Canal
Kansai Airport Aerial View
Construction of Airport
Stage
Activity
Time
Subsurface Investigation
1 year
II
Sea Wall Construction
2 years
III
Landfilling
4 years
IV
Terminal Construction
2 years
Bore Hole Locations
Subsurface of the Kansai Airport
Foundation
Seawall Construction
Up to 40 ft. above sea level
Tripod blocks on seaward side for
dissipation of wave energy
Seawall After Completion
Seawall
Construction
Mechanism of Sand Drains
Advantage of Sand Drains
The weight of the piled sand forces
the water in the clay to move outward
along the sand piles.
Application of One Million Sand
Drain at KIA
Reclamation
Three distinct
grades of sand,
gravel and rock
from nearby
mountains
Four years and 750
million cubic feet of
fill
Transportation on
Ground: Conveyor
Water: Barges
KIA Terminal Building
Architect: Renzo Piano
Settlement Predictions
Lack of experience with construction
on deep deposit of diluvial clay
Expected settlement = 19 to 25 ft
Actual settlement = 27 ft (by the end
of island construction in 1990)
It continued at the rate of 2 in/month
Settlement Calculations
Consolidation Settlement:
c ,ult
vo '
H Cc
log
1 eo
vo '
Time Rate of Consolidation (Terzaghi
1925):
2ue
ue
c v
2
t
z
What Went Wrong in Predictions?
Un-conservative estimation of
consolidation settlement
Wrong estimate of the time required
for completion of consolidation
settlement
Ineffectiveness of the sand drains in
achieving the required success 100%
Incomplete Consolidation
Underestimation of Excess Pore
Water Pressure
Airport
Started
Settlement
Continued
Coping With The Problem of
Continued Settlement
Basement of the terminal was lined
with a quarter of a million tons of iron
ore.
Result: Island sank faster than the
building it is trying to hold
Installation of hydraulic jacks under
the colums
Result: No differential settlement
between the columns of entire building
Learning From Mistakes
Using data actual settlement data
obtained from 1st phase of project
Analysis of 400-m-deep boring
exploration
State-of-the-art soil test methods
Expected Settlement = 18 m
http://
www.kald.co.jp/eindexframe.html
References
A report by Justin Phalen, UC-Davis, 2002
The official website of KIA http://
www.kald.co.jp/eindexframe.html
Questions?