Aggregate Units Decompose It Disaggregate It
Aggregate Units Decompose It Disaggregate It
Disaggregation
Master Schedule
The result of disaggregation is a master schedule.
The Master Schedule shows quantity and timing of specific products.
It usually covers 6 to 12 weeks.
After preparing a tentative Master Schedule, a planner can do Rough-cut
Capacity Planning.
Rough-cut capacity planning is to check the feasibility of the Master
Schedule with respect to available manpower and machinery capacities,
storage spaces, and vendor capabilities.
It is just a rough check to ensure that the master schedule is achievable.
The master schedule then is used as the basis for short term planning.
Master Schedule
Aggregate plan: 12 months.
Master schedule: 12 weeks.
Master schedule is updated every 2 weeks.
Therefore, it is on a rolling basis, always we
have a disaggregated plan for the next 12
weeks.
Outputs
Master production schedule
Beginning inventory
Forecast
Customer orders
Master
scheduling
Projected inventory
Uncommitted inventory
(Available to Promise)
The key idea is: we have a forecast, but it turns into and actual
order when we receive a customer order.
MPS starts with a preliminary calculation of projected inventory.
This reveals when we need production to get additional inventory.
Beginning
Inventory
June
1
30
33
31
2
30
20
1
3
30
10
41
70
4
30
4
11
5
40
2
41
70
6
40
July
7
40
8
40
31
70
61
70
June
1
30
33
31
11
2
30
20
1
3
30
10
41
70
56
4
30
4
11
5
40
2
41
70
68
6
40
1
July
7
40
8
40
31
70
70
61
70
70
June
1
30
33
31
2
30
20
1
11
64
Forecast
Customer Orders (committed)
Projected on hand inventory
MPS
ATP
3
30
10
41
70
56
4
30
4
11
5
40
2
41
70
68
6
40
1
June
1
30
33
31
11
2
30
20
1
3
30
10
41
70
56
4
30
4
11
5
40
2
41
70
68
6
40
1
July
7
40
8
40
31
70
70
61
70
70
July
7
40
8
40
31
70
70
61
70
70
Updating ATP
Updating MPS
Changing to a master production schedule can be disruptive.
Particularly changes in the immediate periods of the schedule
Aggregate Plan is developed for say 1 year
Master Production Schedule is developed for a period of say 12
weeks.
MPS is updated say every 2 weeks, it is on a rolling basis.
Frozen
6
Firm
9
Full
10
11
Open
12
Assignment
Solution to Problem 1
Solution to Problem 1
Solution to Problem 1
Solution to Problem 1