HAMAD BIN KHALIFA MEDICAL CITY
AGENDA:
Hamad Bin Khalifa Medical City Hospital Introduction
Basic Electrical Services
Generator System
Electrical Power System and Sequence of Operation
HAMAD BIN KHALIFA MEDICAL CITY
The new hospitals the Qatar Rehabilitation
Institute ,an Ambulatory Care Center, and the
Womens Wellness and Research Center will
create more than 500 additional beds for patients
It has been overseeing the development of the
250,000-square-meter space site in Rumailah in
central Doha with a cost of QR2.4 billion, which
has been led by Korean-based Hyundai
Engineering and Construction Co.
HAMAD BIN KHALIFA MEDICAL CITY
The project also includes the main kitchen for
the new medical city, with a capacity for
delivering 8,000 meals a day and a robotic
pharmacy.
The facilities incorporate 21 operating theatres,
designed for long-term flexibility, safe
operations and optimized construction space.
The design also responds to the objective of
lowering risk of injury to patients.
QATAR REHABILITATION INSTITUTE
The Qatar Rehabilitation Institute will offer a range of specialized
services including physiotherapy, occupational and speech
therapy, prosthetics and orthotics.
The institute will have approximately 200 beds as well as an
adult hydrotherapy suite. Additionally, there will be outpatient
clinics for occupational therapy, prosthesis, organ
transplantation and inpatient therapy support.
The outpatient physical therapy facilities include:
12 treatment rooms;
4 gyms;
A group therapy room; and
A suite for education and support services.
AMBULATORY CARE CENTER
The Ambulatory Care Center will provide outpatient care
and minor surgery for adults who do not require an
overnight stay.
This center has 116 beds and 14 operating theatres with
recovery rooms and support.
It also includes radiology and examination suites, as well
as treatment rooms and 12 examination rooms for ENT
(ear, nose and throat) audiology.
The Qatar National Diabetes Center will also be housed in
the building. It will have more than 30 examination rooms
and more than 50 short-stay room.
WOMENS WELLNESS ANS RESEARCH CENTER
The Womens Wellness and Research Center will create
much-needed additional provision for pregnant women in
Qatar.
The hospital will have approximately 200 beds and 53
neonatal intensive care cots.
It include 7 operating theatres, 21 delivery rooms and 60
outpatient rooms.
It will have a full accident and emergency department with
a series of rooms for Caesarean section deliveries, triage,
ultrasound, treatment rooms and rooms for emergency
deliveries.
It previously said that the hospital will have capacity
for 15,000 births a year.
AGENDA:
Hamad Bin Khalifa Medical City Hospital Introduction
Basic Electrical Services
Generator System
Electrical Power System and Sequence of Operation
LV System Equipment
Hamad Bin Khalifa Medical City Hospital are
consists of the following Electrical Equipment;
EQUIPMENT QRI ACC WWRC
TRANSFORMER 7 5 8
GENERATOR 2 2 2
MDB 7 5 8
EMDB 6 4 6
ATS 6 4 6
*Hospital Substation at Lower Level
ELECTRICAL PANELS
EQUIPMENT
S/N PMR AH WH LL TOTAL
DESCRIPTION
1 SMDB 14 23 41 29 107
2 ESMDB 16 39 38 22 115
3 DB/EDB/UPS 193 212 278 183 866
4 UPS-HICT 18 20 28 11 77
5 CBS 18 20 25 13 76
6 MCP 63 87 336 88 574
TOTAL PANELS 322 401 746 346 1815
Building Automation System
S/N Description Qty
1 Fan Coil Unit (FCU) 1,045
2 VAV(EAB,FAB,SAB) 947
3 DDC panel 175
4 Air Handle Unit (AHU) , Outdoor Air Unit (OAU) 314
5 FAN 374
6 Point 54,500
UPS System
QRI WWRC ACC HIS
UPS Capacity / CEP
(Lower (Lower (Lower (Lower Total
Models Rating Building
Level) Level) Level) Level)
MGE 60 KVA 4 nos. 2 nos. 6 nos.
Galaxy
5000 80 KVA 4 nos. 4 nos.
160 KVA 2 nos. 2 nos.
200 KVA 4 nos. 4 nos. 8 nos.
MGE
Galaxy 250KVA 2 nos. 2 nos.
7000
300 KVA 2 nos 2 nos.
500 KVA 6nos. 6 nos.
IPS System
TOTAL
S/N DESCRIPTION ACC WWRC 10
5kVA
kVA
Isolation Panel with 17
1 17
10 branch circuit, 5kva nos.
Isolation Panel with 18 15
2 15
branch circuit , 10kva nos.
Isolation Panel with 10
3 32 nos. 32
branch circuit, 5kva
Isolation Panel with 16
4 8 nos. 8
branch circuit , 10kva
Isolation Panel with 18
5 7 nos. 7
branch circuit , 10kva
TOTAL 32 47 79
BHU/PENDANT SYSTEM
Building BHU Type Quantity BuildingBHU Type Quantity Building Pendant Type Quantity
A2-1 4 Flu - B 176 J6-1A 2
B1 10 Flu - C(Q) 24 J6-1B 6
Flu - A 210 Flu - C(R) 24 J6-1C 2
M1 0 M1 93 J6-1D 2
PMR
QRI AH
ACC
M1-1 1 M1-1 2 J6-1G 1
M1-2 1 M1-6 1 J6-2A 2
M1-3 18 N-1 7 J6-2B 1
P-2 6
WWRC
WH
N-2 9 J7-1A 2
TOTAL 250 N-3 2 TOTAL 18
O 6
Building BHU Type Quantity Building
Pendant Type Quantity
O1-1 32
B2 32 J6-1E 1
P 13
Flu - A 64 P1(SABS) 21 J6-1F 4
M1 125 PMP 3 J6-4 1
M1-1 1 TOTAL 413 J7-1 1
WH
WWRC
M1-4 2 J7-2 2
ACC
AH M1-5 2 Building BHU Type Quantity J7-2A 14
O 2 A2 3 J7-3A 19
LL
P 42 M1-1 7 J7-4 4
P-1 20 TOTAL 10 TOTAL 46
P1(SABS/SRS) 2
P1-1 2
TOTAL 294 TOTAL BHU 967 UNITS TOTAL PENDANT64 UNITS
ELEVATOR SYSTEM
No of No. of No. of
Elevator Capacity Speed Elevator Capacity Speed Elevator Capacity Speed
Stops Stops Stops
105 mpm 105 mpm
PMR-31 10 2500 kg 60pm CHL-3 13 2500 kg
(1.75m/s) POD-1 5 2500 kg (1.75m/s)
(1m/s)
105 mpm 105 mpm
PMR-33 10 2500 kg 60pm CHL-4 13 2500 kg
(1.75m/s) POD-2 6 2500 kg (1.75m/s)
(1m/s)
105 mpm 105 mpm
PMR-34 10 2500 kg 60pm CHL-5 13 2500 kg
(1.75m/s) POD-15 5 2500 kg (1.75m/s)
(1m/s)
105 mpm 105 mpm
PMR-32 11 2500 kg 60pm CHL-6 13 2500 kg
(1.75m/s) POD-16 5 2500 kg (1.75m/s)
(1m/s)
105 mpm 105 mpm
PMR-35 11 2500 kg 105 mpm CHL-7 13 2500 kg
(1.75m/s) ORT-20 12 2500 kg (1.75m/s)
(1.75m/s)
105 mpm 105 mpm
PMR-28 10 2500 kg 105 mpm CHL-8 13 2500 kg
(1.75m/s) ORT-22 11 2500 kg (1.75m/s)
(1.75m/s)
105 mpm 105 mpm
PMR-29 10 2500 kg 105 mpm CHL-9 14 2500 kg
(1.75m/s) ORT-21 11 2500 kg (1.75m/s)
105 mpm
(1.75m/s)
PMR-30 10 2500 kg 105 mpm
105 mpm CHL-10 14 2500 kg
(1.75m/s) ORT-23 11 2500 kg (1.75m/s)
60 mpm (1.75m/s)
PMR-40 3 2500 kg 60 mpm
105 mpm POD-11 3 2500 kg
(1m/s) ORT-24 11 2500 kg (1m/s)
105 mpm (1.75m/s)
PMR-25 4 2500 kg 60 mpm
(1.75m/s) 105 mpm POD-12 3 2500 kg
ORT-17 11 2500 kg (1m/s)
105 mpm (1.75m/s)
PMR-26 4 2500 kg 60 mpm
(1.75m/s) 105 mpm POD-13 4 2500 kg
ORT-18 11 2500 kg (1m/s)
105 mpm (1.75m/s)
PMR-27 4 2500 kg 105 mpm
(1.75m/s) ORT-19 11 2500 kg
(1.75m/s)
60 mpm
*Fireman Lift POD-14 2 2500 kg
(1m/s)
QRI 12 ELEVATOR ACC 13 ELEVATOR WWRC 11 ELEVATOR
LIGHTING SYSTEM
NORMAL LIGHT
(KAHRAMAA POWER)
SELF CONTAINED BATTERY LIGHT
(BATTERY PACKS-NORMAL POWER)
EMERGENCY LIGHT
(CENTRAL BATTERY SYSTEM-
EMERGENCY POWER)
EXIT LIGHT
(BATTERY PACKS-EMERGENCY POWER)
AGENDA:
Hamad Bin Khalifa Medical City Hospital Introduction
Basic Electrical Services
Generator System
Electrical Power System and Sequence of Operation
GENERATOR SYSTEM
POWERED BY:
CUMMINS
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
Part 1 Part 2
GENERATOR SYSTEM
Part 1 Part 2
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR SYSTEM
GENERATOR TESTING
1. No-Load TEST
2. On-Load TEST
No-Load TEST Flowchart
START
KIND OF NO LOAD START
TESTING TEST CHECKLIST
YES NO
CHECKLIST
WITH LOAD TROUBLESHOOT
A COMPLIED?
TEST
YES
PROBLEM
LOG-IN TO DMC
RESOLVED?
START THE NO
GENERATOR PUT TAGGING
NOT TO OPERATE
RECORD
PARAMETERS
CONTACT SERVICE
CHECK THE
PROVIDER
GENERATOR FOR ANY
ABNORMALITIES
SHUTDOWN THE CHECK THE
GENERATOR FOR END
GENERATOR ANY LEAK
On-Load TEST Flowchart
START
A
CHECKLIST
YES CHECKLIST NO
TROUBLESHOOT B
COMPLIED?
LOG-IN TO DMC YES PROBLEM
RESOLVED?
TURN-OFF THE
ATS BREAKER NO
FROM THE MDB PUT TAGGING
NOT TO OPERATE
GENERATOR NO
B
START?
CONTACT SERVICE
YES PROVIDER
RECORD
PARAMETERS
CHECK THE CHECK THE
SHUTDOWN THE
GENERATOR FOR ANY GENERATOR FOR END
ABNORMALITIES GENERATOR ANY LEAK
AGENDA:
Hamad Bin Khalifa Medical City Hospital Introduction
Basic Electrical Services
Generator System
Electrical Power System and Sequence of Operation
HIGH VOLTAGE LAYOUT
11kV/.415kV
Hosp. Substation
11kV/.415kV
QRI Substation
66kV/11kV
KM Substation
ELECTRICAL SYSTEM
66kV/11kV
11kV
HV Switchgear
ELECTRICAL
6.6kV SWGR
6.6kV ROOMS
& MCP Panel
TX 11kV/.415kV
ELECTRICAL Transformer
ROOMS
UPS
MDB
PANEL
ATS EMDB
PANEL
ELECTRICAL SYSTEM
ELECTRICAL
ROOMS
UPS
ATS EMDB
PANEL
ELECTRICAL SYSTEM
ELECTRICAL
ROOMS
UPS
2000 kVA
Generator
GCP ATS EMDB
PANEL
ELECTRICAL SYSTEM
66kV/11kV
11kV
HV Switchgear
ELECTRICAL
6.6kV ROOMS
TX 11kV/.415kV
ELECTRICAL Transformer
ROOMS
UPS
MDB
2000 kVA PANEL
Generator
GCP ATS EMDB
PANEL
SUBSTATION LAYOUT AND NORMAL OPERATION
11kV HOSPITAL SUBSTATION
GENERATOR
ROOM
MDB-3
TR-3 ATS-3
G1
G2
G3 G4
11kV/.415V WWRC MDB 11kV/.415V ACC MDB
TX ROOM ROOM TX ROOM ROOM
G1
A-EMDB-3 G2
UPS PANEL GCP ROOM
G3
G4
SUBSTATION LAYOUT AND EMERGENCY OPERATION
11kV HOSPITAL SUBSTATION
GENERATOR
ROOM
G1
G2
MDB-3
TR-3 ATS-3
G3
G4
11kV/.415V WWRC MDB 11kV/.415V ACC MDB
TX ROOM ROOM TX ROOM ROOM
G1
A-EMDB-3 G2
UPS PANEL GCP ROOM
G3
G4
Normal Power Operation
DMC
LOADS
Emergency Power Operation
DMC
LOADS
G G
HAMAD BIN KHALIFA MEDICAL CITY
BASIC LOCATION
(QRI)
QRI BUILDING Ground Floor
- Elevator
- Elec/Comm Room
- Fireman Elevator
Elec. Room
Comm. Room
Elevator
Fire Control Room
Fireman Lift
Security Room
Comm. Room Elec. Room
HAMAD BIN KHALIFA MEDICAL CITY
BASIC LOCATION
(ACC)
ACC BUILDING Ground Floor
- Elevator *POD-1
- Elec/Comm Room POD-2
- Fireman Elevator POD-14
POD-15
Elec. Cabinet POD-16
Room
Comm. Room
Elevator
Fireman Lift Elec. Room
Comm. Room
Elec. Room
Fire Control Room
Elec. Cabinet Room
Security Room
HAMAD BIN KHALIFA MEDICAL CITY
BASIC LOCATION
(WWRC)
WWRC BUILDING Ground Floor
- Elevator
*POD-11
- Elec/Comm Room
- Fireman Elevator Elevator
Fireman Lift
Elec. Room
Comm. Room
Elec. Room
Comm. Room
Security Room Fire Control
Room
The End
Thank you!