Wilkins, A Zurn
Company:
Material
Requirements
Planning
PRESENTED BY:
SPANDAN, NINAD, NAYYER, NISHANT,
NIRANJAN,
Introduction & Background
Wilkins
Regulator General
Plumbing
Company Commercial
Building
1998
1971 Merger with
Jacuzzi Agricultural Municipal
Acquired Irrigation Water Works
1906 Brands, Inc.
by Zurn
Started Industries
Operations
Product Brief
720 Product:
Backflow preventer. Belongs to pressure
vacuum breaker (PVB) valve family
Protects the quality of water when
installed in potable water lines
Available in 6 different models based on
dimension of in-feed pipes
Model examples: 34-720 – PVB valve
with a ¾-inch diameter in-feed pipe
720 Repair Kit:
Sold directly to customers
Consists of additional eight parts
Organization structure – Materials
Department
Chris
Connors
General Manager
Jim Bernie
Gerpheide Barge
Materials Manager Inventory Manager
Cyd lane
Purchasing Manager
Tammi Vivian
Keyes Matthews
Purchasing Agent Purchasing Agent
Problems faced by Wilkins in MRP
Repeated physical verification of
Production department mistakenly uses the
inventory leading loss of revenue due
wrong part number
to production shut down
Relieving inventory based on what is
Continuous new product designs and
perceived to be built, and not what is
customization is not aligned with system
actually produced (makeshift type of
adaptability and inventory management
production techniques used)
Current inventory system is not completely
Component changes not adequately
accurate and hinders correct working of
reported in the production reports
MRP system
Bill of material is not always correct. Rippling affect caused by the inventory
Inventory level is always high. inaccuracy
Stated Reasons for Inventory
discrepancy by Wilkins employees
Part commonality: Creates confusion in the
Timing of transactions; data is not
real quantity of parts needed by
entered in to the computer until that
production
night or next morning
Use of wrong components not recorded.
Product modifications; product was
Wrong components used as right ones
redesigned but the BOM was not
were not found.
updated
Custom product requested by
customer, but was not noted during
the production.
Product Tree Structure
Recommended Solutions
MRP update – accommodate safety stock, proper lead times, and
proper product tree structure
Safety stock streamlining
Resolving discrepancies in Lead Time
Providing unique part numbers for individual products and repair kits
Proper change management during production of customized
product should be adopted i.e. integration between production
planning and materials planning
Analysis and MRP