Basics of Primavera: (Computer-Aided Construction Project Management)
Basics of Primavera: (Computer-Aided Construction Project Management)
PRIMAVERA
(COMPUTER-AIDED CONSTRUCTION
PROJECT MANAGEMENT)
17 18 19 20 21 22 23
24 25 26 27 28 29 30
PERT CPM
3-Times Estimate Single-Time Estimate
PERT/CPM
Program Evaluation & Review Technique / Critical Path Method
1. Parallel Activities
2. Sequential Activities
3. Earliest Expected Completion Time (TE)
4. Latest Allowable Completion Time (TL)
5. Slack or Float
6. Critical Path
7. Dummy
PERT/CPM IN
PRIMAVERA
In PRIMAVERA P6, the following data are the only required to draw a
PERT/CPM:
1. Activity ID or ID No.
2. Activity Name
3. Duration or Time
4. Predecessor
PROJECT MANAGEMENT TEAM
1. Project Manager
2. Project Planner (Recommend)
3. Project Engineer
PROJECT PLANNING PROCESS
Define Goals
Establish Sequences
• Optimistic Time
• Pessimistic Time
• Most-Likely Time
ESTIMATE OF TIME, MANPOWER &
EQUIPEMNT
• OPTIMITISTIC TIME ESTIMATE (A). This is the estimate of the shortest
possible time in which an activity can be computed under ideal conditions. [NO
DELAY]
TE= (A+4C+B)/6
ESTIMATE OF TIME, MANPOWER &
EQUIPEMNT
EXAMPLE : TIME & MANPOWER
Activity = Excavation
Time (days) = __ / __
No. of men = 5
ACTIVITY QUANTITY LABOR REQD. MH MAN-DAY NO. OF MEN TIME (DAYS)
OF WORK PROD. RATE (8HRS/DAY)
EXCAVATION 40 CU.M. 6MH/CU.M. 240 30 5 6
OF FTG.
ESTIMATOR 1: ESTIMATOR 2:
A = No Delay = 6 A = No Delay = 6
B = A + All Possible Delay = 6 + 2 = 8 B = A + All Possible Delay = 6 + 4 = 10
C = A + Most Probable Delay = 6 + 1 = 7 C = A + Most Probable Delay = 6 + 1 = 7
TE = ___ TE = ___
ESTIMATE OF TIME, MANPOWER &
EQUIPEMNT
NOTE: SAME WITH TIME & EQUIPMENT
SUGGESTED REFERENCE:
[1] Estimating Handbook by: Dalmacio Fortuna
[2] Handbook of Construction Estimate by: Reno Velasco
[3] Estimator’s Gen Construction Man-Hour Manual by: John Page
I. PRIMAVERA P6 TERMS
A. Predecessor Relationship
I. PRIMAVERA P6 TERMS
B. Predecessor Lag
II. GETTINGS STARTED WITH PRIMAVERA
P6
TO RUN PRIMAVER P6
DOUBLE CLICK:
II. GETTINGS STARTED WITH PRIMAVERA
P6 TOP BAR
LEFT RIGHT
BAR BAR
II. GETTINGS STARTED WITH PRIMAVERA
P6
III. NEW PROJECT SETUP
A. DEFINE RESPONSIBLE MANAGER
III. NEW PROJECT SETUP
III. NEW PROJECT SETUP
B. DEFINE ENTERPRISE PROJECT STRUCTURE
III. NEW PROJECT SETUP
III. NEW PROJECT SETUP
C. DEFINE CALENDAR
III. NEW PROJECT SETUP
C. DEFINE CALENDAR
III. NEW PROJECT SETUP
III. NEW PROJECT SETUP
D. COPY EXISTING LAYOUT
III. NEW PROJECT SETUP
III. NEW PROJECT SETUP
E. CREATE A NEW PROJECT
III. NEW PROJECT SETUP
E. CREATE A NEW PROJECT
III. NEW PROJECT SETUP
III. NEW PROJECT SETUP
F. AUTOMATING ACTIVITY ID
III. NEW PROJECT SETUP
III. NEW PROJECT SETUP
G. ADDING ACTIVITIES
ADD
III. NEW PROJECT SETUP
III. NEW PROJECT SETUP
H. ADDING PREDECESSORS
III. NEW PROJECT SETUP
III. NEW PROJECT SETUP
I. SCHEDULING/CALCULATING THE PROJECT
III. NEW PROJECT SETUP
III. NEW PROJECT SETUP
J. FOR REVIEW
1. Project Start (Press: F9, Check Data Date, Click: Schedule
2. Original Duration (Compare Input with Data)
3. Predecessors (Review Predecessors at Bottom Layout)
4. Workdays & Holidays (Click: Enterprise>Calendar>Modify)