0% found this document useful (0 votes)
50 views26 pages

MRP Scheduling and Inventory Guide

77 83 90 22 10 10 16 19 27 79 Scheduled Receipts Proj. Available Bal. 150 Planned Order Rel.

Uploaded by

ajeng.saraswati
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
50 views26 pages

MRP Scheduling and Inventory Guide

77 83 90 22 10 10 16 19 27 79 Scheduled Receipts Proj. Available Bal. 150 Planned Order Rel.

Uploaded by

ajeng.saraswati
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 26

Example MRP: L-4-L ordering

1
Example MRP: EOQ

2
Lead Time Offsetting

• Gross to net explosion shows how much of


each part is required, but not when
• Timing requires consideration of two factors
– Lead times–how long does it take to obtain the
component or sub-assembly
– Precedent relationships–the order in which parts
must be assembled
• MRP considers both factors when developing
the plan
Scheduling Logic
• Two common approaches to scheduling exist
– Front schedule–schedule each step as early as
possible. This approach is simple, but parts are
scheduled (and finished) earlier than need be, thus
increasing WIP inventory.
– Back schedule–schedule each step as late as
possible. This approach will reduce WIP, minimize
storage (and time) of completed parts, reserve
flexibility (postpone the commitment or raw
materials to specific products), but it requires
accurate BOM data and lead time estimation.
Scheduling Logic and MRP
• MRP combines back scheduling and
performs the gross requirements to net
requirements explosion.
– Reduced inventories
– Minimized storage time
Back Scheduling

Top handle assembly


has the longest
duration of any sub-
assembly
Scoop assembly must
be complete before
final assembly can
begin

Only when all sub-


assemblies and
components are
available can final
assembly begin
Planned order release for
MRP Records top handle assembly
becomes gross requirement
for top handle component
and nail (note 2 nails
required per assembly)

Lot-for-lot order policy


exactly matches supply
to net requirements

Fixed lot size order policy


requires orders in multiples
of lot size
MRP Technical Issues
• Processing frequency–recalculating all records and
requirements is called regeneration
– This is a computationally intensive process so it is often run in
the background and during periods of low system demand
• Net change approach only recalculates those records that
have experienced changes
• Less frequent processing results in an out-of-date
picture
• More frequent processing increases computer costs and
may lead to system nervousness
Safety Stock & Safety Lead Time
Theoretically, MRP systems should not require safety stock
Variability may necessitate the strategic use of safety stock
A bottleneck process or one with varying scrap rates may
cause shortages in downstream operations
Shortages may occur if orders are late or fabrication or
assembly times are longer than expected
When lead times are variable, the concept of safety lead
time is often used
Safety Lead Time (see Fig. 6.9)
– Scheduling orders for arrival or completion
sufficiently ahead of their need that the probability
of shortage is eliminated or significantly reduced
Safety Stock & Safety Lead Time
• Safety stock is buffer stock over and above the
quantity needed to satisfy gross requirements
– Used when quantity uncertainty is the issue
• Safety lead time changes both the release and
due date of shop and/or purchase orders to
provide a margin for error
– Used when timing of orders is the issue
– Safety lead time is not just an inflated lead time
Pegging
• Pegging provides a link between demand
(order releases, customer orders, etc.) and the
gross requirements for parts
– Pegging records include the specific part numbers
associated with a gross requirement
– Pegging information can track the impact of a
problem (e.g. material shortage) back to the
order(s) it will affect
Firm Planned Orders
• Regeneration of the MRP records can lead to
large numbers of planned order changes
• To avoid this, a planned order can be
converted to a firm planned order (FPO)
– An FPO is not the same as a scheduled delivery,
but can’t be changed by the MRP system
– Temporarily overrides the MRP system to provide
stability or to solve problems
Planning Horizon

• Total amount of time included in MRP


calculations
– Longer planning horizon increases computational
requirements
– Shorter planning horizon may result in less-
effective plans if significant future demand is not
visible
– At a minimum, should cover the cumulative lead
time for all finished goods items
Scheduled Receipts vs. Planned Order Releases

• Scheduled receipts represent an actual commitment


(purchase order, production order, etc.)
• Planned orders are only the current plan and can be
changed more easily
• Scheduled receipts for production orders already have
component materials assigned
– Scheduled receipts do not impact gross requirements
• Planned order releases do not have component materials
assigned
– Planned order releases do impact gross requirements
MRP Processing Example

Note: Component D is required by two parents.


MRP Processing Example
MRP Planner Tasks
Release Purchase orders

Shop floor (production) orders


Reschedule ●
Change due dates of existing orders (when desirable)

Analyze and Update Set lot sizes and lead times


Adjust scrap allowances and safety stocks


Reconcile Identify errors and inconsistencies and eliminate their root causes

Identify Problems ●
Take action now to prevent future crises

Solve Shortages Adjust records and system parameters to prevent recurrence


Enhance ●
Identify system enhancements to improve performance
Exception Codes

Separating the vital few from the trivial many

Requirements that
Part numbers with cannot be satisfied
Orders with
planned orders in within system
unsatisfactory
the immediate parameters
timing or quantity
period (management input
needed)
Bottom-Up Replanning
• Using pegging data to guide efforts to solve
material shortages
– Pegging data allows the planner to take action
only when actual customer orders are impacted
MRP System Output
Part number and description MRP system data

MRP planning data

Exception messages
MRP System Dynamics

MRP System Issues

Rescheduling– Complex Procedural


Transactions
moving the transactions– inadequacies–
during a
due date of inventory situations the
period–
an order to an adjustments, system wasn’t
unexpected
earlier or later service parts, designed to
changes
date etc. handle
System Dynamics
An MRP is not a static document
As time goes by
Some orders get completed
Other orders are near completion
New orders will have been entered
Existing orders will have been altered
Quantity changes
Delays
Missed deliveries
– See Figure 6.11,6.12,6.13
Principles

• Effective use of an MRP system allows development of a


forward-looking approach to managing material flows.
• The MRP system provides a coordinated set of linked product
relationships, which permits decentralized decision making for
individual part numbers.
• All decisions made to solve problems must be implemented
within the system, and transactions must be processed to reflect
the resultant changes.
• Effective use of exception messages allows attention to be
focused on the “vital few” rather than the “trivial many.”
10. XYZ Company
Item A; Lot Size = 150; LT = 1, SS = 0. Average Inventory = ?

Period 1 2 3 4 5 6 7 8 9 10

Gross Requirements 71 46 49 55 52 47 51 48 56 51

Scheduled Receipts

Proj. Available Bal. 150

Planned Order Rel.

Item B; Lot Size = 150; LT = 1, SS = 0. Average Inventory = ?

Period 1 2 3 4 5 6 7 8 9 10

Gross Requirements 77 83 90 22 10 10 16 19 27 79

Scheduled Receipts

Proj. Available Bal. 150

Planned Order Rel.


10. XYZ Company
Item A; Lot Size = 3 weeks supply (P=3); LT = 1, SS = 0. Average Inventory = ?
Period 1 2 3 4 5 6 7 8 9 10

Gross Requirements 71 46 49 55 52 47 51 48 56 51

Scheduled Receipts

Proj. Available Bal. 150

Planned Order Rel.

Item B; Lot Size = 3 weeks supply (P=3); LT = 1, SS = 0. Average Inventory = ?

Period 1 2 3 4 5 6 7 8 9 10

Gross Requirements 77 83 90 22 10 10 16 19 27 79

Scheduled Receipts

Proj. Available Bal. 150

Planned Order Rel.


14. ABC Manufacturing Company
a. Component C (Q=40, LT=2, SS=0)

1 2 3 4 5 6

Gross Requirements

Scheduled Receipts

Projected Available Balance

Planned Order Release

b. Component C (Q=40, LT=2, SS=0)

1 2 3 4 5 6

Gross Requirements

Scheduled Receipts

Projected Available Balance

Planned Order Release

You might also like