METHOD STATEMEN
TEMPORARY JETTY
BAHODOPI COMBINE CYCLE POWER PLANT
CAPACITY 506 MW
Outline
1 Bathymetry 7 Jetty Plan
2 Setting Out & Surveying 8 Jetty Elevation
3 Land Clearing & Stripping 9 Construction Method
4 Project Plan 10 The End of Jetty
5 Site Location 11 Bollard Work
6 Jetty Head 12 Jetty Condition
1. Bathymetry
Measuring Ocean Depths and Charting the
Shape or Topography of the Ocean Floor
Methodology
a. Mobilization
b. Field Preparation
c. Reference Benchmark and GPS Survey
d. Tide Observation
e. Sea Temperature Measurement
f. Bathymetric Survey
g. Multibeam Calibration
h. Data Processing
• Tide Data Processing
• Current and Temperature Data Processing
• Bathymetric Data Processing
i. Deliverable and Reporting
• Field Daily Report
• Interim Report
• Final Report
j. Coordinate and Communication with Company
2. Setting out & Surveying
GPS Receiver
Total Station
Instruments After construction
calibrated yearly Engineers Level
the position and Survey control
leveling checked Pipe Laser
1 2 Checking 3 4
Calibration of Level
Methodology Stations Checking Position Equipment
Instrument
Base Stations
Survey Stations
Obtain beach marks and local grid Stations checked
monthly
Coordinates.
Setting out of stations by adopting the
transverse & triangulation method. 5
Coordinates and levels of the Application
Site base GPS Station
benchmarks
Survey records
Setting Out & Surveying
Positions, Leveling and
Alignment for Excavation,
Pipelines, Drain and Structures
3. Land Clearing & Stripping
Stripping
The purpose is for clearing
the are from organics.
Excavating
Levelling
Cut to crossfill or spoil
(side long cut)
borrow
Hauling
The transportation of
material (soil) by
means of conveyance is
carried out using a
Dumping dump truck.
The unloading
(dumping) and
spreading of the soil
should always start at
the point furthest away
from the loading place.
Returning
4. Project Plan
Temporary Jetty
For landing the heavy cargo to project site. The sketch had been distributed related to a proposed
materials associated with the proposed jetty.
A planning application for the project shall be submitted to PP under Project Bahodopi Combine Cycle
Power Plant Capacity 506 MW. The operation of the jetty will require an integrated cooperation and
coordination with PT Medco Energi, and local authorization.
The material jetty will include the construction 60 meter long access jetty to temporary quay for the
delivery of materials by LCT or barge. The construction of the jetty will involve works on the near the
foreshore.
The general arrangement of the proposed jetty and the general gas engine stowage plan on the trailer is
shown on the attachments. Nothing the final design of the final design of the jetty construction or the
dimension of gas engines has yet to be completed.
Proposed Material Jetty
The delivery of construction via trucking (land transportation) may require the construction of material
handling at jetty i.e excavator and dozer to compact and leveling the jetty.
5. Site Location
Location Address:
Bahodopi, Morowali, Central Sulawesi
Coordinate:
Longitude : 122.1086 Degrees
Latitude : -2.7953 Degrees
Access road type & condition:
intra-province roads (great)
sub urban roads with limited wight due to limited bridge
capacity (medium - poor)
6. Jetty Head
The jetty head will be 16 meter long and width about 16 meter
area, and it will be supported with bollard using coconut
diameter 12 inch x 4,5 meter piled about 4 meter.
The pavement shall support load bearing capacity up to 6 ton
per m2.
To level the jetty with barge deck if needed would be used FOB
(Fly over bridge) supported with sand bags and wooden
dunnage.
7. Jetty Plan
The details of temporary jetty is available in these following sections:
8. Jetty Elevation
9. Construction Method
The following is an assessment of the means of
construction of the proposed jetty at the time of
application for a barge landing and beaching. Before
construction commences, a more detailed construction
method statement will be prepared and submitted for
approval in advance of any works taking place
Construction of road Transport and Laying of Boulder The excavator sets the boulder rock
access Material material sideways as the
embankment and forward.
10. The End of Jetty
At the end of the jetty (widening) is
carried out with a typical trapezoid as
access to dump trucks and excavators
to transport boulder material and is
done in stages.
11. Bollard Work
To facilitate bollard installation work, the foundation and
bollard piles are precast on land. Laying boulder for access to
the bollard installation area. Meanwhile, on the side for access
to bollard foundation work, the boulder piling is carried out in
stages. To access the work, the bollard is made on a slope or
with a ladder.
12. Jetty Condition
The Temporary Jetty Has Been Done