Lecture 5: Project Scheduling: Networks, Duration Estimation, and Critical Path
Lecture 5: Project Scheduling: Networks, Duration Estimation, and Critical Path
(AON) techniques.
4.Perform activity duration estimation based on the use of
critical path.
9-6
When the nature of the work allows for more than one
activity to be accomplished at the same time, these activities
are called concurrent, and parallel project paths are
constructed through the network.
Copyright ©2016 Pearson Education, Ltd. 9-15
NETWORK DIAGRAM – SERIAL
SEQUENTIAL LOGIC
9-8 (FIGURE 9.2A)
C
Copyright ©2016 Pearson Education, Ltd.
Project Scheduling Terms
9-17
Float: Float, sometimes called slack, is the amount of time an activity, network path,
or project can be delayed from the early start without changing the completion date of
the project.
Critical path: The path through project network with the longest
duration.
Critical Path Method: The Critical Path Method is defined in
the Project Management Body of Knowledge (PMBOK) as follows:
“The Critical Path Method is the sequence of scheduled activities that
determines the duration of the project.” These scheduled activities must be
performed if the project is to be considered a success
Resource-limited schedule: Start and finish dates reflect expected
resource availability.
A Contract signing 3 4 11
B Questionnaire design 2 5 8
C Target market ID 3 6 9
D Survey sample 8 12 20
E Develop presentation 3 5 12
F Analyze results 2 4 7
G Demographic analysis 6 9 14
H Presentation to client 1 2 4