KRN Phase 3 Power Plant Weekly Report

The weekly project status report summarizes progress from March 12-18, 2021 for the KRN Phase 3 power plant project. Key achievements included underground cable trench work, deck slab installation, coal shed grouting, and coal pit slab work. Planned work for the next period focuses on continued civil works. The report notes some issues with inspection scheduling and coordination of sea water inlet excavation. Attached are tables showing manpower levels of 121-128 direct workers and equipment usage including 4 excavators and 1 crane.

Uploaded by

waode nurainun
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
252 views22 pages

KRN Phase 3 Power Plant Weekly Report

The weekly project status report summarizes progress from March 12-18, 2021 for the KRN Phase 3 power plant project. Key achievements included underground cable trench work, deck slab installation, coal shed grouting, and coal pit slab work. Planned work for the next period focuses on continued civil works. The report notes some issues with inspection scheduling and coordination of sea water inlet excavation. Attached are tables showing manpower levels of 121-128 direct workers and equipment usage including 4 excavators and 1 crane.

Uploaded by

waode nurainun
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 22

WEEKLY PROJECT STATUS

REPORT

KRN Phase 3 (BPN)


2 x 25 MW POWER PLANT

12 Mar. 2021 ~ 18 Mar. 2021

1
EXECUTIVE SUMMARY
Key Achievement of the Last Period (12 Mar.- 19 March 2021) Risk Quality
Project Metrics Budget Schedule
Management Management
• 1. Main Bldg
- UG: Cable Trench (B-C/ 6-10) work and backfilling , Dewatering
- Deck Slab (EL+4.00 B-C/6-10): Installing Rebar & Wiremesh, Embedded Status O O R O
• 2. Coal Shed: Grouting
• 3. Coal Pit : Slab work, installing embedded plate, Dewatering Project Milestone Target Date Expected Status
• 4. Coal Handling : Trench work. dewatering Completion
• 5. WTH : Backfilling, Repairing
• 6. Oil pump FDN : Excavation
• 7. Diesel Generator :Trench, Slab work
• 8. Seawater inlet : Lean Con’c, dewatering Quality Management Issues
Key Planned for the Next Period - Inspection schedule for next week :
• 1. Main Bldg Drawing
- UG: Cable Trench (B-C/ 6-10) work and backfilling . No Date Building Description Remarks
- Deck Slab (EL+4.00 B-C/6-10): Embed, Formwork, Con’c. Number
• 2. Coal Shed: Grouting under base plate.
• 3. Coal Pit : Slab Con’c, Formwork for corridor 1 Monday, March 22, 2021 Oil Pump FDN T0703 Lean Con'c Concrete
• 4. Coal Handling : Trench work.
• 5. WTH : Backfilling and handover 2 Monday, March 22, 2021 Main Building T0205 Deckslab Elv +4 m Part I Concrete
• 6. Oil pump FDN : FDN work
• 7. Diesel Generator : Slab work 3 Monday, March 22, 2021 Coal Shed T0503 Grouting Concrete
• 8. Conveyor#1 : Excavation 4 Thursday, March 25, 2021 Main Building T0205 Cable Trench Wall Concrete
• 9. Seawater inlet : Excavation, Cutting Pile, Lean Con’c, Foundation,
Pedestal, Dewatering. 5 Wednesday, March 24, 2021 Main Building T0205 Short Column Pedestal Concrete
• 10. Outlet Trench : Excavation
Key Risks / Issues / Scope Changes
• 1. Floor Finishing to be confirmed
• 2. 16-area to be Hand Over for Civil construction
Main Transformer-1&2, Electrical House 20kv, Pipe rack at T/G , Workshop, Key Discussion Areas where Management Attention is required 
Sand Unit, Rack of Flu behind Boiler-1&2, Slag Transmission station,
Convert Room, Biomass and corridor, Coal Bulldozer house, Coal slurry pool - Progress Payment
Transfer Station, Coal Handling conveyor-1&2 10th (Feb 2021) : submitted for KRN’s confirmation 12 March 2021
- As the pandemic(COVID-19) is prolonged, it impact to delay progress so that Civil
work can not proceed in time.  
- There are the Road Cross(3 Points) for Sea-water-inlet. It is required the coordination with
the schedule of Piping installing. Excavation in the Road Cross has a very negative impact on
the operation of equipment in the field. =>> the sleeve of Steel Pipe(D1500mm) is required.
- The bedding material for FRP pipe of Sea water inlet is required.

Legend: R Major Issues O Some Issues G Satisfactory Internal Documents not for Distribution
2
WEEKLY PROGRESS STATUS
Main Work
CUM.
WEIGHT PLANNED CUM. DEV.
S.No. DESCRIPTION FACTOR for THIS ACTUAL JUSTIFICATION FOR PROGRESS VARIANCE
% WEEK % %
%

土方开挖 2,346 % 2,377% 0,031% • Chemical Water House, Coal Pit, Diesel
1 Earthwork 1,44% Generator House, Slag Silo, Oil Pump House,
38.000 m3 38.500 m3 500 m3 Limestone Silo
excavation
• Chemical Water House, Diesel Generator House
2 垫层 Cushion 1,14%
0,81 % 0,85 % 0,04%
Limestone Silo
layer 420 m3 439 m3 19 m3
• Pipe Rack-Sea Water Inlet

桩头填芯 0,43 % 0,37 % -0,06% • Chemical Water House, Diesel Generator House
3 Core filling in 1,20%
137 m3 116 m3 -21 m3 Limestone Silo, Slag Silo, Oil Pump House
head of pipe pile

基础、短柱及
• Air Compressor, I.D Fan, Chemical Water House
基础梁 11,53 % 11,43 % -0,10 % • Coal Crusher.
4 Foundation, 15,67%
3.850 m3 3.815 m3 -35 m3 • Oil Pump House
Short Col, • Pipe Rack-Sea Water Inlet
FDN &Beam

• Coal Crusher Top Slab, Column,


框架混凝土 2,40 % 2,25 % -0,15 % • Diesel Generator House Column
5 Reinforced 2,53 %
630 m3 590 m3 -40 m3 • T/G Top Deck
concrete frame • All Above Ground >+- 0.00
• Oil Pump House Top Deck

6 挡煤墙 coal 3,32%


2,94 % 2,72 % -0,22 % • Coal Shed Wall
retaining wall 680 m3 630 m3 -50 m3 • Coal Pit & Corridor

Total Progress for 3


Main Work
ATTACHMENTS
MANPOWER AND EQUIPMET STATISTICAL TABLE
(Cut off period 12 Mar. ~ 19 Mar. 2021)

Manpower Mobilization
Occupation 12/Mar 13/Mar 14/Mar 15/Mar 16/Mar 17/Mar 18/Mar

Direct Manpower (M/D) 121 124 124 123 123 128 128

In-direct Manpower (M/D) 18 18 18 19 17 17 16

Total Manpower (M/D) 139 142 142 142 140 145 144

Equipment Status
Equipment Name 12/Mar 13/Mar 14/Mar 15/Mar 16/Mar 17/Mar 18/Mar

Excavator PS-210 0,8 M3 4 4 4 4 5 5 4


Generator <60 KW 1 1 1 1 1 1 1
Dump Truck 8, 20ton 3 3 3 3 4 4 4
Crane 55 T 1 1 1 1 1 1 1
Total Day Heavy 9 9 9 9 11 11 10
Equipment

4
ATTACHMENTS
MANPOWER AND EQUIPMET STATISTICAL TABLE
(Cut off period 12 Mar. ~ 19 Mar. 2021)

Manpower Mobilization
Occupation 12/Mar 13/Mar 14/Mar 15/Mar 16/Mar 17/Mar 18/Mar

Direct Manpower (M/D) 121 124 124 123 123 128

In-direct Manpower (M/D) 18 18 18 19 17 16

Total Manpower (M/D) 139 142 142 142 140 144

Equipment Status
Equipment Name 12/Mar 13/Mar 14/Mar 15/Mar 16/Mar 17/Mar 18/Mar

Excavator PS-210 0,8 M3 4 4 4 4 5 4


Generator <60 KW 1 1 1 1 1 1
Dump Truck 8, 20ton 3 3 3 3 4 4
Crane 55 T 1 1 1 1 1 1
Total Day Heavy 9 9 9 9 11 10
Equipment

5
PHOTO IN SITE

SITE VIEW
6
PHOTO IN SITE

Main Bldg-Cable Trench work Main Bldg-Cable Trench work

Main Bldg-EL+4. Deck Slab WTH-repairing prior to Hand Over


7
PHOTO IN SITE

Coal Shed – Grouting Coal Pit& Corridor-Formwork for slab

Coal Handling– Cable Trench Disposal Soil


8
PROGRESS ON SITE

Progress Layout - Color Marked


HAND OVER

Hand Over Layout - Color Marked


PROGRESS ON SITE

Coal Pit & Corridor

11
PROGRESS ON SITE
Main

Main Bldg - Cable Trench

12
PROGRESS ON SITE

Main Bldg – Pedestal work

13
PROGRESS ON SITE

Coal Handling - Trench

14
PROGRESS ON SITE

Oil Pump House - FDN

15
PROGRESS ON SITE

Diesel Generator House – Column & FDN.

16
PROGRESS ON SITE

Sea Water Inlet Zone B

17
PROGRESS ON SITE

Sea Water Inlet Zone C

18
PROGRESS ON SITE

E.S.P, ID Fan, Racks of Flue FDN

19
PROGRESS ON SITE

Air Compressor House- Cable Trench & Foundation Equipment

20
PROGRESS ON SITE

Access Road

21
謝謝
(Thank You) !!

22