Proposal On Construction of Laboratory Building For Agricultural 1
Proposal On Construction of Laboratory Building For Agricultural 1
In Chitwan
Presented By:
Rashmi Pahari
19124 MBA fall 2019
Project Overview
Project name Construction of laboratory
building for agricultural
knowledge center
Location Chitwan
Beneficiaries Exporters, Importers, Domestic
consumers, farmers, government
4
Introduction to the
project The project is to build a facility that ease
international trade through quality testing such as
SPS and plant quarantine.
Present laboratory facilities: The facility includes construction of lab building
Check posts only and installation of testing machineries.
1. Insufficient capacity The projects result into a laboratory building with
2. Insufficient instrument the international standard lab testing and
certifications.
3. Insufficient expertise
6
Human resources (skilled and unskilled):
engineers, contractors, lab technicians and
specialist,
Building construction materials
Lab instruments, special Lab furniture
Project input capital
Project budget
The number and amount construction of the lab building
of input will depend upon $350 to $500 per gross square foot
the phases of the project
proposed lab covers an area of 3000 Square feet
mentioned in the
following sections 12.75 crore Nepali rupees
7
Finance
source
8
Phases Work breakdown Time
estimate
Phase I (Pre- Develop decision making process and establish lines of communication. 3 months
design Phase)
Review of various documents of the facilities and prepare a report of
Project facility evaluation, facility program, preliminary design alternatives, and
activities preliminary construction cost estimates. The area recce, along with
various soil testing, compression tests, load bearing limits etc. to be
done.
Phase II (Design This phase requires completion of documents necessary for the 6 months
and
construction of the lab along with the provision of the inputs required for
Documentation
Phase) the construction
Detailed 2D (site plan, floor plan, building sections) and 3D Design of
the lab structure
Structural analysis and detailed report of the same
Document confirming government approval of the design
9
Phase III The construction phase includes the actual construction on the site. It 2.5 years
(construction
Phase) also requires to constantly check the progress of the construction and
Phase IV (Post Here we check lab facility is consistent with the construction documents 6 months
construction and
machines and initial expectations.
installation Installation of the available lab machineries.
phase)