Project Closure and
Handover
002402 - Project Closure 1
002402 - Project Closure 2
Project Closure is more than a
milestone… it is a process with
deliverables, to successfully conclude
the project.
002402 - Project Closure 3
This phase is about residual attitudes
toward the project
Client, stakeholders participants
‘taste left in the mouth’
Lessons about:
- what worked
- what did not work
- how to improve
002402 - Project Closure 4
Project Closure
Types of Project Close-out Plan:
Questions to be
Closure Asked
• Normal • What tasks are
required to close the
• Premature project?
• Perpetual • Who will be
responsible for these
• Failed Project tasks?
• Changed Priority • When will closure
begin and end?
• How will the project be
delivered?
002402 - Project Closure 5
14–5
Implementing Closedown
1. Getting delivery acceptance from the
customer
2. Shutting down resources and releasing to
new uses
3. Reassigning project team members
4. Closing accounts and paying all bills
5. Evaluating the project team, project team
members, and the project manager
002402 - Project Closure 6
14–6
002402 - Project Closure 7
002402 - Project Closure 8
Closure phase
Projects enter a downward spiral
Project Closure can be a time of mixed
feelings for the Project Team
People stop engaging with it or taking an
active part.
Worried about what the future will hold
Eager to get on with the next project that
they leave things unfinished
Elongating the project because they don't
want to leave
002402 - Project Closure 9
Drift
Tendency for projects to run on into the
sand
Leaves everyone feeling dissatisfied and
unrewarded for the work
002402 - Project Closure 10
The exit strategy for project staff must be
clear so that they feel adequately
supported whether they are;
- going on to new projects
- returning to routine jobs
- leaving the organisation.
Your aim is that they will feel satisfaction
at a job well done
002402 - Project Closure 11
Project Closure
Project closure ensures
Outcomes match the stated goals of the
project.
Customers and stakeholders are happy
with the results.
Critical knowledge is captured.
The team feels a sense of completion.
Project resources are released for new
projects.
002402 - Project Closure 12
Closure of all financial issues, contracts,
etc.
Collection and completion of all project
records
Archiving of all project records
Documenting the issues faced in the
Project and their resolution. This helps
other projects to plan for such type of
issues in the Project Initiation Phase itself.
002402 - Project Closure 13
Recording lessons learned
Closure for the project team
Celebration of the project completion
Last part of the project lifecycle
002402 - Project Closure 14
Formally closed
To ensure:
The users/customers have formally accepted
all outcomes
Operational procedures are in place
The handover to operational staff has been
completed
Documentation and reference material is in
place
Any further actions and recommendations
are documented and disseminated
The results are disseminated to relevant
people
There are no loose ends
002402 - Project Closure 15
It is important to ensure that a project is
properly closed
There is a tendency for projects to drift on
and become, or develop into, other projects
To ensure that the work of the project team
is acknowledged
The lessons to be learned from the project
are formally investigated and recorded for
use on the next project
002402 - Project Closure 16
Hectic time
Reporting is on a daily basis (or even
more frequent)
High level of detail
Checklists
002402 - Project Closure 17
The Project Manager should produce
confirmation from the
Customer/client or User Group that
the final product or outcome of the
project meets the acceptance criteria
Inform the finance department to
ensure that they are aware that the
project is closed
002402 - Project Closure 18
Post Project Review
Required to check:
outcomes are those expected
projected benefits have occurred
operational working is as planned
costs are as expected
review of what went well with the
project and what went less well
002402 - Project Closure 19
Include all aspects of the project;
objectives review, performance
criteria, financial criteria, resource
utilisation, slips and gains of time,
quality of work, adherence to the
project definition and plan
Every aspect you can think of and the
ones that arise from a group
discussion
002402 - Project Closure 20
Allow the team time to reflect on and
prepare for the review
Keep the meeting positive
Do not dwell on negatives
Ensure that the positive lessons are
brought out from each negative
event
No blame
002402 - Project Closure 21
Project Process Review Questionnaire
1. Were the project objectives and strategic 10. Were communication methods
intent of the project clearly and explicitly appropriate and adequate among all
communicated? stakeholders? Explain.
2. Were the objectives and strategy in 11. Is the customer satisfied with the
alignment? project product?
3. Were the stakeholders identified and 12. Are the customers using the project
included in the planning? deliverables as intended? Are they
4. Were project resources adequate for this satisfied?
project? 13. Were the project objectives met?
5. Were people with the right skill sets 14. Are the stakeholders satisfied their
assigned to this project? strategic intents have been met?
6. Were time estimates reasonable and 15. Has the customer or sponsor accepted
achievable? a formal statement that the terms of the
7. Were the risks for the project project charter and scope have been
appropriately identified and assessed met?
before the project started? 16. Were schedule, budget, and scope
8. Were the processes and practices standards met?
appropriate for this type of project? 17. Is there any one important area that
Should projects of similar size and type needs to be reviewed and improved
use these systems? Why/why not? upon? Can you identify the cause?
9. Did outside contractors perform as
expected? Explain. 002402 - Project Closure 22
Organisational Culture Review Questionnaire
1. Was the organisational culture supportive for this type of project?
2. Was senior management support adequate?
3. Were people with the right skills assigned to this project?
4. Did the project office help or hinder management of the project?
Explain.
5. Did the team have access to organisational resources (people,
funds, equipment)?
6. Was training for this project adequate? Explain.
7. Were lessons learned from earlier projects useful? Why? Where?
8. Did the project have a clear link to organisational objectives?
Explain.
9. Was project staff properly reassigned?
10. Was the Human Resources Office helpful in finding new
assignments? Comment.
002402 - Project Closure 23
Feedback questionnaire
Prepare and distribute a detailed
questionnaire for feedback on the project
2-3 weeks prior to initiating project
closure
Collate the responses to your feedback
questionnaire.
If necessary supplement the
questionnaires with interviews.
002402 - Project Closure 24
Lessons Learned
Forms an integral part of the Project Closure
Phase
Provides the basis to execute the next
projects with much more efficiency and
control.
Did the delivered product / solution meet the
project requirements and objectives?
Was the customer satisfied?
Was project schedule met?
Was the project completed within budget?
Were the risks identified and mitigated?
What could be done to improve the process?
002402 - Project Closure 25
Lessons Learned log
Operated throughout the project
Lessons Learned log needs to be reviewed
and turned into a report
Ensure that the project's documentation is
complete and that it is archived in a
manner so that anyone needing to refer to
it can have access
Identify and define any follow-on actions
002402 - Project Closure 26
Project Report
To provide a complete picture of the
successes and failures (if any) of the
project. Include the following:
Your objective evaluation of the success of
the project
Outline the project accomplishments
Include important project data – good or
bad
Describe significant project changes and
their effect on the project
002402 - Project Closure 27
Describe issues requiring further
work and recommend participation
by team members
Provide a final project accounting
and explain the variances
Provide recommendations for future
projects
002402 - Project Closure 28
Data mining
002402 - Project Closure 29
Data mining
The extraction of hidden predictive
information from large databases
Data mining is the process of analysing data from
different sources and perspectives and
summarizing it into useful information
Data mining software allows users to analyse data
from many different dimensions or angles,
categorise it, and summarise the relationships
identified
Technically, data mining is the process of finding
correlations or patterns among dozens of fields in
large relational databases
002402 - Project Closure 30
Data mining consists of five major
elements:
Extract, transform, and load transaction
data onto the data warehouse system.
Store and manage the data in a
multidimensional database system.
Provide data access to analysts and
professionals.
Analyse the data [by application software]
Present the data in useful formats, such as
a graphs, tables, etc.
002402 - Project Closure 31
Closing event
Always have a closing event to formally
round off the project.
You should always invite the project
accountant and invoice clerk to the closing
event because they are always left out
(unless it’s a new accounting system
project) and you will need their support
for the next project
002402 - Project Closure 32
Make a public announcement
An announcement to the organization is a
good way to highlight the success of the
team, the project and its benefits to the
company
Arrange for an executive to send out an e-
mail message
Publish an article in the company
newspaper
002402 - Project Closure 33
Recognise and reward
Your team members have worked
hard, and now they deserve some
real recognition.
As their project manager, you have
the best understanding of who pulled
the project out of each tight spot,
which members have transformed
themselves with new skills, and who
might be ready for a new level of
responsibility.
002402 - Project Closure 34
Evaluation
Provide each team member with a
performance evaluation
Highlight contributions the member
made
Identify skills the member updated
Recommend new roles the member
might be ready for
Provide a copy of this document to
the member's employer/supervisor
002402 - Project Closure 35
Ensure that the evaluation reaches
all department leads as well as
human resources office
Note: feedback influences annual
evaluations, salary discussions, aid
team members' transitions to new
projects and new responsibilities.
002402 - Project Closure 36
Celebrate!
The team needs and deserves a
celebration
A team dinner, a team outing, gift
certificates, or other rewards are minor
costs that generate a large return in terms
of morale and job satisfaction.
Even if its a wake for the project’s passing
You are not rewarding failure, you are
rewarding effort
Thank the group
002402 - Project Closure 37
Get the sponsor and other executive
stakeholders to make a personal thank-
you to the team
Thank each team member personally
Remind the sponsor and other executive
stakeholders of individual members'
contributions
002402 - Project Closure 38