PM Chapter 3
PM Chapter 3
INSTITUTE OF TECHNOLOGY
FACULTY OF MANUFACTURING
Dep’t of Industrial Engineering
Lecture Notes on
Project Management
(Prepared by: Instructor Sitotaw A.)
March 2020
CHAPTER THREE
Network Logic and Construction
Introduction
A network used to represent a project is called a project network. A project network
consists of a number of nodes(typically shown as small circles or rectangles) and a
number of arcs(shown as arrows) that connect two different nodes.
As project becomes larger and more complex, the Gantt chart was found to be lacking
for a planning and control tool, because it could not indicate the logical relationships
between activities. Due to this reason a logical networking diagram is developed.
The two best-known techniques for network analysis are
Programme Evaluation and review Technique (PERT) and
Critical Path Method (CPM).
These two techniques were developed almost simultaneously during 1956-1958.
PERT was developed for US navy for scheduling the research and development
activities for Polaris missiles programme. CPM was developed by E.I. du Pont
de Nemours & Company as an application to construction project.
…cont.
Both CPM and PERT describe the work plan of project where
arrows and circles respectively indicate the activities and events in
the project.
Event : is defined as an instant in time. It marks the initiation of an
activity, and the completion of an activity.
It is represented by a circle ‘o’ in a network which is also known as a node
or connector.
a. Merge event: When more than one activity come and join an event,
b. Burst event: When more than one activity leave an event,
c. Merge and burst event: An activity may be a merge and burst event at
the same time
…cont.
3 D
B
1 A
2 D F
5
C 6
E
4
…cont.
Solution
Activity Times and level of Detail
CPM method of single time estimate
Introduction
CPM was initially set-up to address the time cost trade-off
dilemma, where there is a complex relationship between
project time to complete and cost to complete.
In the critical path method, the critical activities of a
program or a project are identified. These are the activities
that have a direct impact on the completion date of the
project.
Terms in CPM:
An activity time: is a forecast of the time an activity is
expected to take from its starting point to its completion
under normal conditions.
…cont.
Float for each activity, i.e., the amount of time by which the
completion of an activity can be delayed without delaying the
total project completion.
Key Steps in Critical Path Method
Let's have a look at how critical path method is used in practice.
The process of using critical path method in project planning
phase has six steps.
Step 1. Activity specification
We can use the Work Breakdown Structure WBS to identify
the activities involved in the project.
This is the main input for the critical path method. In activity
specification, only the higher-level activities are selected for
critical path method otherwise the critical path method may
become too complex to manage and maintain.
…cont.
Step 2: Activity sequence establishment
In this step, the correct activity sequence is established. For
that, you need to ask three questions for each task of your list.
Which tasks should take place before this task happens.
Which tasks should be completed at the same time as this
task.
Which tasks should happen immediately after this task .
Step 3: Network diagram
Once the activity sequence is correctly identified, the network
diagram can be drawn by putting the estimated duration on the
arrow.
Step 4: Identification of the critical path
Here the path which have longer duration is identified and
termed as critical path.
…cont.
Critical event: the events with zero slack times are called
critical events.
Since the slack of an event is the difference between the
latest and earliest event times. i.e.,
Slack ( i ) L i E i E i L i
2 t - t
2
b- a p o
varience,v
6 6
…cont.