CRDB TestingPlan

The document outlines a 15 week testing plan with activities scheduled each week. It includes test analysis and planning, test design preparation, test execution planning, and activities scheduled for week 5 such as circulating test cases for review and preparing customization test cases.

Uploaded by

msvinu
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views

CRDB TestingPlan

The document outlines a 15 week testing plan with activities scheduled each week. It includes test analysis and planning, test design preparation, test execution planning, and activities scheduled for week 5 such as circulating test cases for review and preparing customization test cases.

Uploaded by

msvinu
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Testing Plan

Wk0 Wk1 Wk2 Wk3 Wk4 Wk5 Wk6 Wk7 Wk8 Wk9 Wk10 Wk11 Wk12 Wk13 Wk14 Wk15
                               

Test Analysis and


Completed Automation Tool Test Execution Plan
Planning

 Test cases review
Basic set up – done
Test Design Preparation  Sample test – done  Test cases for customisations
 Sample extraction –  Parameterisation testing

.
.

tested  Smoke & sanity testing


 Sorting of automation  Functional testing
 Test Strategy and Test Plan
test cases  Customisation testing
 Receipt of BRDs/FSDs – mostly received  Trial run with T24  Integration testing
 Query & Resolution tracking mechanism (dependent on env)  Interface testing
 (Bank to provide Mantis details)
 SIT and UAT support
 Preparation of Test cases – done
 Test cases for customisations – In progress

Activities for the week 5th Aug, 2022
Test cases review by SMEs – in progress
 High priority test cases – Bank to provide  Circulation of test cases with SMEs for review
 RTM – available  Preparation of customisation test cases
 Environments – in progress  Review of test cases and sign off by SMEs
 Environment check if ready

ITSS S.A.R.L
WWW.ITSSGLOBAL.COM
Bank’s support required

1) Drafting and review of bank process specific test cases


2) Execute typical end to end test cases
3) Provide all supporting documents for deltas under development
4)

.
.

ITSS S.A.R.L
WWW.ITSSGLOBAL.COM