Lecture#02
Lecture#02
CE-326
Associate Professor
Civil Engineering Department
design,
construction,
operations, and
Benefits:
Similar to DBB projects, owners who choose CMR work
directly with their designers. They also have access to the
builder’s perspective from the outset. If done correctly, this
helps lead to earlier awareness of costs and faster project
delivery. Overall, owners get to lock in on a final construction
cost earlier in the process, and subsequent changes can be
clearly quantified and priced.
CMAR
Drawbacks:
In CMR, the owner is still liable for completeness, accuracy
and details of the design plans. Disagreements with either
the designer or the CMR manager can lead to schedule
delays, increased costs and litigation.
Integrated Project Delivery (IPD)
Integrated project delivery is relatively new delivery method. In
this delivery method the owner selects an A/E and CM prior to
the kickoff of project design. A joint contract is signed between
the three entities after goals and objectives are established
collaboratively. This delivery method incorporates early
participation from the contractor, which can lead to a
streamlined design that is directed specifically towards a
project objectives. Similar to the CMAR process, the owner
must remain highly involved in the project as a crucial member
of the project team. Integrated project delivery provides
opportunities for minimizing project costs and increasing
efficiency through cooperation of the team members.
Integrated Project Delivery (IPD)
It is important to note that the owner, A/E, and CM are legally
bound into a single entity so risk that is normally assigned to
one party is now spread to all parties.
IPD is best suited for projects in the private sector that are
complex, under a tight schedule or may be largely undefined.
Integrated Project Delivery (IPD)
Benefit:
If organized efficiently, all contracted participants in this
process are available to an owner before a construction project
breaks ground. IPD is one of the best ways to increase the
transparency throughout the construction process. Because of
the early stakeholder contracts and discussion, it’s clear to
what the objectives are.
Integrated Project Delivery(IPD)
Drawbacks:
Using IPD won't automatically make team members trust each
other. You still need to work on developing good relationships
between contractors, owners, architects and engineers.
Otherwise, you may find your project slipping back into
traditional methods of project delivery.
Multi-Prime (MP)
In multi-prime, the project is divided into three phases–
design, engineering and construction. When implementing
MP, the owner forms separate contracts with the
professionals heading the separate stages of the project. For
example, one contract likely would include the architecture
firm and its subcontractors for engineering and interior
design. The owner would establish other contracts with the
GC and trade contractors, such as plumbers and electricians.
Each of these categories of contractors may oversee the
work of subcontractors, such as a GC who manages
carpenters and framers. Altogether, the main contractors are
the “primes.”
Multi-Prime (MP)
Benefit:
With MP, owners who are experienced with the design
and construction process gain greater control over their
projects. MP may be the only choice for public sector
projects in some states that require maximum control of
contractors at all levels.
Multi-Prime (MP)
Drawbacks:
It’s tough being your own general contractor, but that’s
what MP requires. Coordination of all the prime contractors
makes it difficult to determine final cost until a project
concludes. Additionally, poor coordination or
communication with so many providers may create
duplication and omission on orders. Finally, in this model,
it’s difficult to direct contractors’ schedules.
Thanks