MAN13 EBM MAN MAINTENANCE Work Identification - Presentation - V0

The document discusses Plant Maintenance EBM Work Identification training which includes understanding the work identification process for maintenance management and EBM variants. The 3 hour training covers topics such as maintenance management processes and tools, work identification, and how to create notifications in SAP. The training also reviews the lifecycle of a notification and reports that can be used for notifications analysis.

Uploaded by

abdou
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
262 views57 pages

MAN13 EBM MAN MAINTENANCE Work Identification - Presentation - V0

The document discusses Plant Maintenance EBM Work Identification training which includes understanding the work identification process for maintenance management and EBM variants. The 3 hour training covers topics such as maintenance management processes and tools, work identification, and how to create notifications in SAP. The training also reviews the lifecycle of a notification and reports that can be used for notifications analysis.

Uploaded by

abdou
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 57

Plant Maintenance

EBM Work Identification training

1
Training Summary
• Description:
Understand the Work Identification process for Maintenance
Management and EBM variants

• Duration:
3 hours

• Target group:
Preventive Maintenance Manager, Mechanical Maintenance
Manager, Electrical Maintenance Manager, Planner, Maintenance
Requester, Maintenance worker

• Topics:
Maintenance Management (Processes and Tool)
» Work Identification

• Tools: SAP PM, TIS


FOR INTERNAL USE ONLY © LafargeHolcim 2015 *
EITS Evacuation plan

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Training Rules

• Be punctual

• Turn off your mobile phone


4 In case you need to attend a call, please go out training room
or use coffee breaks

• Participate actively
4 In case of questions ask

er ? ?
Oth
Any
FOR INTERNAL USE ONLY © LafargeHolcim 2015
Agenda

Objectives
EBM Overview of Work Identification
Maintenance Request and Notification concepts
Notification creation in SAP
Lifecycle of Notifications
Reports
Annex
Background

Plant Maintenance, EBM Manufacturing, EBM Preventive Maintenance FOR INTERNAL USE ONLY © LafargeHolcim 2015
training, 2014-06-04 *
Objectives of the Training

● Understand concepts and reasons why


notifications are created in Plant Maintenance
Management

● Knows what information must be on notifications

● Understand the 4 ways of creating notifications in


SAP

● Understand the lifecycle of a notification

● Knows what reports can be used for notifications


analysis
FOR INTERNAL USE ONLY © LafargeHolcim 2015
Agenda

Objectives
EBM Overview of Work Identification
Maintenance Request and Notification concepts
Notification creation in SAP
Lifecycle of Notifications
Reports
Annex
Background

Plant Maintenance, EBM Manufacturing, EBM Preventive Maintenance FOR INTERNAL USE ONLY © LafargeHolcim 2015
training, 2014-06-04 *
EBM Scope

Cement Manufacturing Scenarios (Level 1) EBM


Maintenance

MAN- 1 Capex Management

MAN-2 Production Planning MAN-3 Production Execution

MAN-4 Maintenance Management

MAN-5 Inventory Management

FOR INTERNAL USE ONLY © LafargeHolcim 2015


8
Cement Manufacturing Business Processes (Level 2)

MAN- 4 Maintenance Management

Major Shutdown

Preventive Work
Work Planning Work Scheduling
Maintenance Identification

RCFA, FMEA,RCM History Analysis History Recording Work Execution

Master Data Update: Technical Structure (Functional Locations, Equipment, BOM)

(*)
RCFA: Root Cause Failure Analysis
FMEA: Failure Mode and Effect Analysis
RCM: Reliability-Centered Maintenance

Short title, Department, Name/Function or Event/Creator, Date yymmdd, FOR INTERNAL USE ONLY © LafargeHolcim 2015
Classification 9
EBM Work Identification Process

FOR INTERNAL USE ONLY © LafargeHolcim 2015


EBM Work Identification Process

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Plant Maintenance, EBM Work Identification, 2014-06-06
EBM Work Identification Process
Process The purpose of the work order system is to plan, schedule, control and monitor maintenance
Objectives activities and to maintain the equipment with an optimum maintenance cost while increasing
availability. It also provides an auditable trail for all the jobs.
The Work identification, planning and scheduling process intends to establish a homogeneous
standard system in LafargeHolcim to assess and evaluate the Work order flow.
The main elements of the assessment are:
• Notifications: identification of the problems or potential problems and malfunctions that may
directly affect the performance of an equipment or system.
• Work Orders: object that shows in detail how a particular maintenance activity is to be executed.
• Total Backlog: list of all the work that has been identified and not yet completed.
• Work Centers: groups of personnel responsible to perform and supervise the maintenance
activities
• Weekly/Daily Plan: definition of the maintenance requirements for the week to be broken down
into daily plans indicating skills needed and hours required.

Key Inputs • Maintenance Work requirements

Key Outputs • Weekly/Daily Maintenance Plan

Process • KPI: Schedule Compliance (K6) and Planning Accuracy (K7)


Indicators • SPI: Aging work request (S7), Scheduled ratio (S4), Overdue (S3), Outstanding work (S2),
Material reservation usage (S9), Call out (S1)
Process Owner • LHGRS Cement Manufacturing Services – Maintenance and Equipment Reliability

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Plant Maintenance, EBM Work Identification, 2014-06-06
EBM Work Identification Process
# Step Name Input Description of Step Output
1 Create • Walk by inspections (Wbi) • Creation of a notification concerning an activity that needs to be performed by • Notification MR
Maintenance • Preventive Maintenance Routines (PMRs) the maintenance department due to a result of a preventive maintenance
Request • Condition Monitoring (CM) activity, a malfunction or failure of an equipment or an exceptional situation.
• Equipment failures
• Requests from all departments
• Root Cause Failure Analyses
2 Shall it break • Maintenance request • Address to maintenance the level of urgency for the requested activity by • Daily meeting review
weekly setting the priority within the MR (Urgent, To plan, no activity)
schedule? • The maintenance department will then know if it is requested to change
daily/weekly plan, to plan the activity and include it in the standard process or
just an information.

3 Daily Meeting • MR with priority • Review all new MR addressed to maintenance and decide how to treat them • Request additional information from
Review (change daily/weekly schedule, include in normal planning process, further the requester
analyze potential issue, request more information or reject the MR) • Reject the MR as non relevant
• Accept the MR

4 Close the MR • Reject MR • Close the MR • Inform the requester

5 Requester • Close MR • Informed the requester on the reasons why the MR was rejected or on the • MR
informed • Request more information need to receive more information / details on the request (initial MR has to be
updated by the requester)

6 Work Order • MR accepted • Check if any work order already in the backlog concern the same request • Close the MR with comments if
Exist? duplicates or assign the MR to the
existing WO
7 Assign to a WO • MR accepted • Assign the MR to the WO • Review Backlog
• WO already existing
8 During • MR accepted • Assess the need to perform the activity during major shutdown • Assign revision number linked to
Shutdown? • No WO already created the shutdown
• Create directly WO
9 Create WO • MR accepted • Create the WO for the activity to be performed. Identification and planning of • Impact on reliability
• Revision assigned required skills, materials, work force, tools and PPEs.
• Major Shutdown Process
10 Assign revision • Activity to be performed during the major • Assign the relevant revision number to the notification • Major Shutdown Process
shutdown FOR INTERNAL USE ONLY © LafargeHolcim 2015
Plant Maintenance, EBM Work Identification, 2014-06-06
EBM Work Identification Process
Preventive Mechanical Electrical
Maintenance
# Step Name Requester Maintenance Maintenance Maintenance Planner
Manager
Manager Supervisor Supervisor
1 Create Maintenance R A
Request

2 Shall it break R A
weekly schedule?

3 Daily Meeting I, C A R R R R
Review

4 Close the MR I, C A R R R R
5 Requester informed I, C A R R R R

6 Work Order Exist? A I I R

7 Assign to a WO I A I I R

8 During Shutdown? C, I A C C R

9 Create WO A C C R

10 Assign revision I A I I R

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Plant Maintenance, EBM Work Identification, 2014-06-06
Agenda

Objectives
EBM Overview of Work Identification
Maintenance Request and Notification concepts
Notification creation in SAP
Lifecycle of Notifications
Reports
Annex
Background

Plant Maintenance, EBM Manufacturing, EBM Preventive Maintenance FOR INTERNAL USE ONLY © LafargeHolcim 2015
training, 2014-06-04 *
Maintenance Notification

The notification contains all important information about the problem


and triggers the maintenance process

What information has


to be on the notification
to be able to execute
the work with full
satisfaction?

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Maintenance Notification
Notification must answer the questions WHAT, WHEN, WHERE, HOW MUCH about the
problem and give the due date

Meaningful Title Notification Title

Location Func. Loc. / Equipment


Object Part
Detailed Description
Subject (Long Text)
Cause Cause Code
Cause Text
Receiver
Planner Group
Requester
Main Work Center
Due Date
Reported By

Required Start / Priority

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Notification Screen

Notification Title

Func. Loc. / Equipment


Object Part

Required Start / Priority

Subject (Long Text)

Planner Group
Main Work Center

Reported By

Cause Code
Cause Text

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Agenda

Objectives
EBM Overview of Work Identification
Maintenance Request and Notification concepts
Notification creation in SAP (4 scenarios)
Lifecycle of Notifications
Reports
Annex
Background

Plant Maintenance, EBM Manufacturing, EBM Preventive Maintenance FOR INTERNAL USE ONLY © LafargeHolcim 2015
training, 2014-06-04 *
Four Scenarios to create Notification in SAP

FOR INTERNAL USE ONLY © LafargeHolcim 2015


SCENARIO 1
Creation of a Notification manually in SAP

Easiest way to create a notification is out of Technical Structure

Transaction
IH01
Select Equipment
(or Functional Location)

GOTO
→ Create notification
→ General

Functional Location and


Equipment automatically
entered in Notification
FOR INTERNAL USE ONLY © LafargeHolcim 2015
SCENARIO 2
Creation of a Notification manually in SAP

Specific Transaction to create Notifications Transaction IW21


Use a Proper Title that describes the problem or request very well

Enter title

Do NOT write an ACTION


(Like: Align belt)

FOR INTERNAL USE ONLY © LafargeHolcim 2015


SCENARIO 2
Creation of a Notification manually in SAP

Use the long text to give all relevant information to the planner

Use the long text to enter all information that could be helpful for the
receiver of the notification to understand the problem.

Use a common structure to write the text


It should be clear who wrote what and when!

FOR INTERNAL USE ONLY © LafargeHolcim 2015


SCENARIO 2
Creation of a Notification manually in SAP

Functional location and equipment gives the location of the problem

As the notification was created


out of the technical structure
nothing has to be added here

FOR INTERNAL USE ONLY © LafargeHolcim 2015


SCENARIO 2
Creation of a Notification manually in SAP
Give the planner the required information to be able to schedule the work and
address it to the right planner

Choose the Required


Start Date according
your priority

Priority U → start date is today!


If the notification is the result of a stoppage of Priority P → normal planning process
the equipment mark the Breakdown check box. Priority 9 → just for information for maint

Enter the Username of the Select the right Planner Group and
requester mainFOR
work center
INTERNAL USE ONLY © LafargeHolcim 2015
SCENARIO 2
Creation of a Notification manually in SAP

Choosing the right Object Part and Cause Code make the analysis of
failures very comfortable

Mandatory at notification’s closure

Choose the correct


object part from the list

Enter a supporting text

Choose the cause code Enter a supporting text


from the list
FOR INTERNAL USE ONLY © LafargeHolcim 2015
SCENARIO 3
Create notification from TIS

TIS allows a direct creation of Notification from the Downtime Log

Indicate if a
Notification needs
to be open
automatically in
SAP ECC6

FOR INTERNAL USE ONLY © LafargeHolcim 2015


SCENARIO 4
Create Notification from Preventive Orders

Create notifications from PM02 work orders Transaction ZPM001

Select the PM02 order(s) from


which notifications should be
created

Click on the work order number


to create a notification from the
work order

FOR INTERNAL USE ONLY © LafargeHolcim 2015


SCENARIO 4
Create Notification from Preventive Orders

Create notifications from PM02 work orders Transaction ZPM001


Fill out all the fields like in any
other notifications then save

Indicate if you want to create a


new notification from the same
inspection

List of notifications create out of


the PM02 work order

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Notification User Status

User status on the notification: CPM and CALL

CPM is automatically
indicated if you generate the
notification from the PM02

CALL is manually set in the


status screen.
CALL means that the notification
result from offshift work

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Agenda

Objectives
EBM Overview of Work Identification
Maintenance Request and Notification concepts
Notification creation in SAP
Lifecycle of Notifications
Reports
Annex
Background

Plant Maintenance, EBM Manufacturing, EBM Preventive Maintenance FOR INTERNAL USE ONLY © LafargeHolcim 2015
training, 2014-06-04 *
Livecycle of a Notification
At every step during the lifecycle of the notification the document gets
another system status

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Agenda

Objectives
EBM Overview of Work Identification
Maintenance Request and Notification concepts
Notification creation in SAP
Lifecycle of Notifications
Reports in SAP
Annex
Background

Plant Maintenance, EBM Manufacturing, EBM Preventive Maintenance FOR INTERNAL USE ONLY © LafargeHolcim 2015
training, 2014-06-04 *
Notification Reports in SAP
Selection Criteria used for for Notification list
Transaction IW28 There are several
selection criteria you
can use when listing
in SAP.

For Notification the


highlighted fields are
the ones usually
used.

You can use any field


available in the list
criteria.
Most utilized are
Maintenance Plant,
Notification Date

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Notification Reports in SAP

Executing the List Transaction


When you completed
entering your selection click
the ‘Execute’ button and
your list will come out based
on your selected layout

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Notification Reports in SAP

Other specific report: Prometheus Notification History


● Transaction
Transaction: /PROGROUP/NHR
/PROGROUP/NHR
○ Select from the “Navigator” or include in your “favorites”
Transaction IW33
● Into the work order
○ in the “Enhancement” tab – activate the notification
history report

This will call the report from the


reference functional location in
the work order

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Notification Reports in SAP

Notification history
Transaction IW69

Report with Work Order information Order cost

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Summary

Scenarios to create a Notification

Notification MUST
contains all important
information about the
problem and triggers
the maintenance
process

FOR INTERNAL USE ONLY © LafargeHolcim 2015


*
Summary

Questions / Doubts

Comments

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Summary

CONGRATULATIONS

THANK YOU FOR YOUR ATTENTION

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Agenda

Objectives
EBM Overview of Work Identification
Maintenance Request and Notification concepts
Notification creation in SAP
Lifecycle of Notifications
Reports
Annex
Background

Plant Maintenance, EBM Manufacturing, EBM Preventive Maintenance FOR INTERNAL USE ONLY © LafargeHolcim 2015
training, 2014-06-04 *
Annex - SAP LAYOUTS

Changing Layout for your list Valid for all SAP list
Click the ‘Get’ to
change the entire
lay out

The current Layout is the one with


the icon
Select a new layout by clicking on
the Layout Name. The system will
bring you back to your list with the
new Layout FOR INTERNAL USE ONLY © LafargeHolcim 2015
Annex - SAP LAYOUTS

Changing the content of your Current Layout 1. Click ‘Current’


2. Click Column
Name to arrange
alphabetically
3. Select the Column
you want to add

4. Click this button to


move the selection
to the Displayed
Column
5. Click this button to
proceed and show
your list with the
added column
6. This is optional, if
you want to save the
changes, click this
FOR INTERNAL USE ONLY
button
© LafargeHolcim 2015
Annex - SAP LAYOUTS

Saving the Layout Changes


7. Do not overwrite
the ‘Default Name’,
put in your preferred
name for this layout
in the ‘Save Layout’
Field. Type in the
description of this
Layout in the ‘Name’
Field. Check the
User Specific and
uncheck the Default
Setting unless you
want it to be your
default
8. Click the ‘Transfer’ button to
save the layout you selected
FOR INTERNAL USE ONLY © LafargeHolcim 2015
Annex - SAP LAYOUTS

Selecting a Default Layout for yourself

To make this as a default


Layout for yourself, click
‘Back’ to get back to the
‘Selection Criteria’ screen
FOR INTERNAL USE ONLY © LafargeHolcim 2015
Annex - SAP LAYOUTS
Selecting a Default Layout for yourself
1. Click the ‘Save’ button

2. Encode:
U_yourusername
in the ‘Variant
Name’ and the
description of the
layout in the
‘Meaning’ field.

Every time you use this


transaction your layout
will be the default layout

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Annex - SAP SELECTION ENTRY
Selecting Multiple Entries that are not in Range

To select multiple selection that


are not in range, click the
‘Multiple Selection’ button

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Agenda

Objectives
EBM Overview of Work Identification
Maintenance Request and Notification concepts
Notification creation in SAP
Lifecycle of Notifications
Reports
Annex
Background

Plant Maintenance, EBM Manufacturing, EBM Preventive Maintenance FOR INTERNAL USE ONLY © LafargeHolcim 2015
training, 2014-06-04 *
Background
New cause code catalogue reduced number of codes by object
part for Maintenance Reliability Analysis

i Indicate the object part and the cause code in


maintenance request

Simplify

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Background

Each object type has its own Object part catalogue

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Background

Cause Code Catalogues and Object Part Codes


• Combine three existing catalogues
1  Object Type
− Code defined in LHAC manual and part of MAC SAP standard
− Code predefined in the equipment master data
2  Object Part
− To be selected from a picking list
3  Cause Code catalog
− To be selected from a picking list, depending on the object part selection

1 2

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Background

Cause Code : Electrical & Instrumentation Group


MTBF 2010 Wear / Tear / Fatigue
2020 Modification / new installation
2030 Lubrication Application/Procedures
2040 Out of operational limits
Idle time
2050 Incorrect Design
2060 Fabrication / Overhaul defect
2070 Planned Maintenance (Prev/Shutdown) ONLY TIS
2320 Corrosion
2330 Misalignment
2340 Improper Installation/Spare/Material
2360 Loose / Missing parts
2380 Negligence
2300 Natural Disaster (Maint. required)
2350 Inappropriate process control settings
FOR INTERNAL USE ONLY © LafargeHolcim 2015
Plant Maintenance, EBM Work Identification, 2014-06-06
Background

Cause Code : Mechanical Group


MTBF 2010 Wear / Tear / Fatigue
2020 Modification / new installation
2030 Lubrication Application/Procedures
2040 Out of operational limits
Idle time
2050 Incorrect Design
2060 Fabrication / Overhaul defect
2070 Planned Maintenance (Prev/Shutdown) ONLY TIS
2320 Corrosion
2330 Misalignment
2340 Improper Installation/Spare/Material
2360 Loose / Missing parts
2380 Negligence
2300 Natural Disaster (Maint. required)

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Plant Maintenance, EBM Work Identification, 2014-06-06
Background

Cause Code : Production and process Group


MTBF
2020 Modification / new installation
2040 Out of operational limits
2070 Planned Maintenance (Prev/Shutdown) ONLY TIS
Idle time 2320 Corrosion
2340 Improper Installation/Spare/Material
2360 Loose / Missing parts
2380 Negligence
2300 Natural Disaster (Maint. required)
2370 Internal Captive Power Plant failure ONLY TIS
2110 Product -Raw Material Quality ONLY TIS
2140 AFR usage ONLY TIS
2150 Refractory / Casting Installation
2310 Lack of Raw Material for Operation ONLY TIS
FOR INTERNAL USE ONLY © LafargeHolcim 2015
Plant Maintenance, EBM Work Identification, 2014-06-06
Background

Cause Code : Others


MTBF 2160 Occupational, Health and Safety

2170 Accident

Idle time 2180 Environment Standards

2200 Sabotage or Theft

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Plant Maintenance, EBM Work Identification, 2014-06-06
Background

Cause Code : Idle time Group – NOT FOR MR

2190 Failure of external Power or Gas Supply


Idle time
2210 Peak Power Non Utiliz. - No Maint.
2230 Natural Disaster - No Maint. required
2240 Lack of Demand
MTBF
2290 External logistical Constraints
2250 Planned Prod. Stop - No Maint.
2260 Change Produced Mat. - No Maint.
2270 Strike

None of these cause codes must be assigned to


a MR notification

FOR INTERNAL USE ONLY © LafargeHolcim 2015


Plant Maintenance, EBM Work Identification, 2014-06-06
FOR INTERNAL USE ONLY © LafargeHolcim 2015